centerville middle school conversion · • (2) locker rooms at 1,964 sf ea • 772 day use lockers...

13
FREMONT UNIFIED SCHOOL DISTRICT Centerville Middle School Conversion Drama Program Performance Space January 22, 2020

Upload: others

Post on 27-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

FREMONT UNIFIED S C H O O L D I S T R I C T

Centerville Middle School ConversionDrama Program Performance Space

January 22, 2020

Page 2: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Site Plan

2

Approved by the Board on June 26, 2019

Page 3: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Drama Classroom - Existing

3

Drama Classroom:• 1580sf; 450sf

performance area• Storage shared with

backstage area • Existing raised stage

and seating configuration not in DSA approved plans

• Light and sound table within seating area

• Curtain separates stage and seating area

Page 4: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

4

Option 1 – Original Schematic Design Presented to the Board 11/20/19Highlights:

• Acoustic improvements to MPR for larger performances

• Locker rooms expanded in Bldg G

• Art room in Bldg D

• Drama room moves to Bldg D

Page 5: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

5

Option 1 - Drama Classroom and Lockers Presented to the Board 11/20/19

Drama Classroom:• 1200sf; 430sf performance area; and 45-55 seat

capacity• 165sf of usable storage• No backstage area• No curtain

Locker Room Expansion:• (2) Locker Rooms at 1968 sf ea:

• 772 Day Use Lockers ea• 255 PE Use Lockers ea

• (2) Offices at 248 sf ea• (2) Storage at 255 sf ea• (2) Multi Occupant Restrooms and (2) Single

Occupant/Gender Neutral Restrooms

MPR:• Acoustic improvements and portable lighting for

larger drama performances

Design for drama meets approved Middle School Educational Specifications

Scope of work is within current project budget

Page 6: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Option 2 – Site Plan

6

Highlights:• Hardcourt space

extended • Square footage added to

Bldg G• Drama remains in Bldg G• Locker rooms expanded

in Bldg G• No improvements to

MPR

Page 7: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

7

Option 2 – Building Floor PlansDrama Classroom:• 1580sf; 450 sf performance area; 50-60 seating capacity• 418 sf for backstage and storage• Curtain location in approximately same location as existing

Locker Room Expansion:• (2) Locker Rooms at 1,702 sf ea:

• 772 Day Use Lockers ea• 255 PE Use Lockers ea

• (2) Offices at 320 sf ea• (2) Storage at 265 sf ea• (2) Multi Occupant Restrooms and (2) Single Occupant/Gender Neutral

Restrooms

MPR:• No improvements

Hardcourts:• Expansion to account for addition to Bldg G

Additional Cost: $3M

Items to note:• Drama remains in current space• Smaller square footage for lockers than in SD option, no impact to locker

count• Creates additional flex lab in Bldg D

Page 8: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Option 3 – Site Plan

8

Highlights:• Locker rooms

expanded in Bldg G• Drama moves to Bldg

D with larger sf• Art moves from Bldg D

to new modular • No improvements to

MPR

Page 9: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

9

Option 3 – Building Floor PlansDrama Classroom:• In Bldg D, D2 and D3 combined to create larger space• 2,360 sf; 653 sf performance area; 85-95 seating capacity• Curtain locations to be developed• 240 sf for side stage• 318 sf for storage

Locker Room Expansion:• (2) Locker Rooms at 1,964 sf ea

• 772 Day Use Lockers ea• 255 PE Use Lockers ea

• (2) Offices at 250 sf ea• (2) Storage at 255 sf ea• (2) Multi Occupant Restrooms and (2) Single Occupant/Gender Neutral Restrooms

Art Room:• Moves to new modular• 1,440 sf

MPR:• No improvements

Additional Cost: $3.9M

Items to note:• Drama room will have low ceiling and suboptimal sight lines• Drama program does not have history in this type of space

Page 10: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

10

Option 3 – Side View

Page 11: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Next Steps

11

• Complete Design Development phase

• Develop phasing plan with Contractor, Construction Manager, and Site

• Continue coordination of schedule, phasing, cost and constructability

Page 12: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Reference Slides

12

Page 13: Centerville Middle School Conversion · • (2) Locker Rooms at 1,964 sf ea • 772 Day Use Lockers ea • 255 PE Use Lockers ea • (2) Offices at 250 sf ea • (2) Storage at 255

Centerville MS CampusOriginal Design Direction/Goals for Conversion Project:• Student centric spaces for 6-8• 2 story Development• Update Centerville presence in community• Minimize Portables• Safe Student Drop-off• Outdoor learning spaces

Community/Board Input at 10/24/18 Meeting:• Expansion of Playfields• Space for Emergency Supplies• 2 story Development• Classrooms in New Construction• Minimize New Portables• Safe Student Drop-off

Updated Input from the District since then:• Old Enrollment Projections: 1822 • Updated Enrollment Projections: 1545*

*Based on Jan 2019 Report to 2024/2025• Incorporation of Ed Specs 13