cemex redwood city cement terminal equipment upgrade & modification project
TRANSCRIPT
![Page 1: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/1.jpg)
CEMEXCEMEXREDWOOD CITY CEMENT TERMINALREDWOOD CITY CEMENT TERMINAL
EQUIPMENT UPGRADE & MODIFICATION PROJECTEQUIPMENT UPGRADE & MODIFICATION PROJECT
![Page 2: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/2.jpg)
CEMEXCEMEXREDWOOD CITY CEMENT TERMINALREDWOOD CITY CEMENT TERMINAL
EQUIPMENT UPGRADE & MODIFICATION PROJECTEQUIPMENT UPGRADE & MODIFICATION PROJECT
RMC Pacific Materials Purchased The Terminal From Ideal Cement
March 1, 2005 – CEMEX Officially Purchased RMC Standard Procedure During An Acquisition Includes
Formation Of A Post Merger Integration (PMI) Team• Evaluation Of Facility Operations And Procedures &
• Recommendations To Bring Facility In Compliance With CEMEX Standards
Improve Operations, Safety, Environmental And Community Service Improve Customer Service.
![Page 3: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/3.jpg)
CEMEXCEMEXREDWOOD CITY CEMENT TERMINAL REDWOOD CITY CEMENT TERMINAL
UPGRADE OBJECTIVESUPGRADE OBJECTIVES
Convert Storage Silo Dedicated For Fly Ash To Cement Truck Load-Out System Upgrade And Improvement
• Upgrade Existing Truck Loading System With Up To Date Equipment And Add An Additional Load-out Spout That Will Expedite Load Times By Half;
• Install A Second Two Spout Truck Loading System; &
• Centralize Nearly All Of The Cement Storage And Loading To One Vicinity Of The Terminal That Is Away From The Pacific Shores Complex.
![Page 4: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/4.jpg)
CURRENT TERMINAL ENTERANCE CURRENT TERMINAL ENTERANCE & TRAFFIC PATTERN& TRAFFIC PATTERN
![Page 5: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/5.jpg)
Stockhouse D
Current Loadout
Phase 1 Loadout System
Phase 2 Loadout System
PROJECT OVERVIEW
![Page 6: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/6.jpg)
PROPOSED TRAFFIC PATTERN PROPOSED TRAFFIC PATTERN & LOADING SYSTEM LOCATIONS& LOADING SYSTEM LOCATIONS
New Traffic Pattern
Phase 2 Loadout System
Phase 1 Loadout System
![Page 7: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/7.jpg)
Artist conception of Phase 1 ModificationModern 2 Nozzle Loadout System Replaces Single Nozzle system
PROPOSED IMPROVEMENTPROPOSED IMPROVEMENT
![Page 8: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/8.jpg)
PROPOSED IMPROVEMENTPROPOSED IMPROVEMENT
Artist conception of Phase 1 & 2 ModificationsViewed Facing The New Phase 2 Loadout System
Phase 2
Phase 1
![Page 9: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/9.jpg)
PROPOSED IMPROVEMENT (cont.)PROPOSED IMPROVEMENT (cont.)
Move Truck Loading From The Small Bulk Tanks To Stock House – D;
Utilize Four Storage Silos In Stock House – D As Both Storage And Load-Out;
Replacing Inventory From Adjacent Silos Reduces Time Required To Re-fill System;
Reduce Energy Consumption And Operating Cost; Reduce Truck Loading And Waiting Time; Installation Of Modern Equipment Minimizes Emissions;
![Page 10: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/10.jpg)
PROPOSED IMPROVEMENTS (cont.)PROPOSED IMPROVEMENTS (cont.)
Minimizes The Number Of Trucks Waiting On Seaport Blvd. Which Would Move Cement Trucks Inside The Terminal;
Moves A Majority Of The Truck Loading Operations Away From Property Line Adjacent To Pacific Shores;
Centralize Cement Storage – Minimize Transfer Of Cement From Stock House – D To Small Bulk Tanks
Pave Roads • Minimize Fugitive Dust During The Dry Season• Minimize Mud Track Out During Wet Weather Season
![Page 11: CEMEX REDWOOD CITY CEMENT TERMINAL EQUIPMENT UPGRADE & MODIFICATION PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022062221/56649cb95503460f9497ffed/html5/thumbnails/11.jpg)
Any Questions?