cdr joseph thomas

36
From, 1 st March 2011 Joseph Thomas Verghis, 1/11 Gipps Street, Wollongong, NSW 2500 Ph: 0411 646 085 Email: [email protected] To, Overseas Qualification Assessment, Education & Assessment, Engineers Australia 11 National Circuits Barton ACT 2600 Australia. Subject: Application for the assessment of the Bachelor of Engineering Degree in Industrial & Production Engineering. Dear Sir/Madam, I, Joseph Thomas Verghis completed my Bachelor of Engineering degree in Industrial & Production Engineering from Malnad College of Engineering (MCE) Hassan, affiliated to The University of Mysore, India, in January 1992. Worked in related field up until 2008, and then came to Australia to pursue my Master in Science (Logistics) and MBA from University of Wollongong, Australia, both of which I began in March 2009 and completed in November 2010. I now would request you to assess my Bachelors degree in Industrial & Production Engineering through your institution for the purpose of migration and in this regard sending you the following documents as per your requirements.

Upload: raj-changra

Post on 07-Mar-2015

1.296 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CDR Joseph Thomas

From, 1st March 2011

Joseph Thomas Verghis,

1/11 Gipps Street,

Wollongong, NSW 2500

Ph: 0411 646 085

Email: [email protected]

To,

Overseas Qualification Assessment,

Education & Assessment,

Engineers Australia

11 National Circuits

Barton ACT 2600

Australia.

Subject: Application for the assessment of the Bachelor of Engineering Degree in

Industrial & Production Engineering.

Dear Sir/Madam,

I, Joseph Thomas Verghis completed my Bachelor of Engineering degree in

Industrial & Production Engineering from Malnad College of Engineering (MCE) –

Hassan, affiliated to The University of Mysore, India, in January 1992. Worked in

related field up until 2008, and then came to Australia to pursue my Master in Science

(Logistics) and MBA from University of Wollongong, Australia, both of which I

began in March 2009 and completed in November 2010.

I now would request you to assess my Bachelors degree in Industrial & Production

Engineering through your institution for the purpose of migration and in this regard

sending you the following documents as per your requirements.

Page 2: CDR Joseph Thomas

Completed application form

CDR Cover page with full name, passport style photo and signed declaration.

Continuing professional development(CPD)

Curriculum Vitae

Certified true copies of all academic certificates and transcripts.

Certified true copy of Master of Logistics ( University of Wollongong)

Certified true copy of Master of Business Administration ( University of

Wollongong)

Certified true copies of passport

I hope the above information and documentation will suffice to do the needful,

and in case you need any further clarifications, please do not hesitate contact me

on my mobile no. 0411 646 085 or mail me at [email protected]

Looking forward to your positive and early response.

Thanks & Regards

Joseph Thomas

Page 3: CDR Joseph Thomas

CONTINUING PROFESSIONAL DEVELOPMENT

I obtained my undergraduate degree in Industrial & Production Engineering in 1992

from the Malnad College of Engineering – Hassan, University of Mysore, India. The

Project work undertaken, which was part of my course was on “Value Engineering”

We did this project with one of India‟s premier motor manufacturer – Kirloskar Motors.

Our task was to essentially enhance the value of one of their best selling induction

motors, by either decreasing the cost of manufacture or keeping the cost at its present

price and enhancing its features, thereby increasing the value of the product. This was

achieved by basically stripping the motor of its parts, and identifying each and every

part for its primary and secondary functions, the material used and the ease and cost of

its manufacture and whether or not it could be standardized, basically an exercise of

where the costs lie, and ways to replace or reduce it. This project work was successful

and its recommendations were being considered to be implemented with some fine

tuning.

After graduation, I took up a job as a Sales Engineer in a company by the name

Schenck Avery Pv t Ltd., a technical and commercial collaboration between Carl

Schenck AG, Darmstadt and Avery India Ltd., India. Their main products were Dynamic

Balancing Machines, Vibration Monitoring Systems and Dynamometers. As a Sales

Engineer, I was responsible for the Sales & Service of my region, which included,

presentation of my company and its products to potential buyers, presentation of its

operation and its benefits, commercial and technical discussions, closing sales and post

sales activities. For the 4 ½ years I worked here, I met all my quarterly and yearly

targets.

From an exposure of the commercial aspects of business, I was curious and keen to

learn how products were manufactured and the activities therein, this led me to switch

my career to Production & Operations and put to use the knowledge I gained in college.

Page 4: CDR Joseph Thomas

I joined the Apparel Manufacturing and Exporting Industry, with a focus on Production

as the Asst. Production Manager of an apparel manufacturer. During my tenure in this

role I was exposed to all aspects and activities of Production and Industrial Engineering

such as Lean Management, Increasing Efficiencies, Production Planning and Control,

Inventory Management, Preparing Bill of Materials and Procurement, Scheduling Man

and Materials for different activities, Preventive and Breakdown maintenance of

machines meeting delivery deadlines and quality control.

After several months in this role, I was given the additional responsibility of managing

the entire factory which included Administration, HR, Compliance, Payroll, and Profit

Centre Head. It was at this stage that I was introduced to the practical world of my

studies i.e. Improving Productivity and Efficiency, with a view of cutting down

operational expenses.

I have during my working experience, also initiated, designed, coordinated the

execution of a 300 machine apparel making facility with a in house laundry and

embroidery that could turn out a million pieces annually.

Also, was part of a team that started a buying office with a marketing collaboration with

a firm in the USA. This office which I was heading was responsible for business

development and execution of the orders through various associated manufacturing

facilities in the area.

As I was advancing in my career, I felt the need to further strengthen my knowledge in

by combining elements of technical and management studies and this led me to take up

a Masters in Logistics and a Masters in Business Administration.

I am now looking for employment in the field of Strategic Planning, Change

Management, Productivity Improvement and Efficiency enhancement especially in the

manufacturing or Process Industries.

Page 5: CDR Joseph Thomas

DECLARATION

„All statements of fact in this report are true and correct and I have made claims of

acquired competencies in good faith. The report is all my own work and is a true

representation of my personal competence in written English. I confirm that I understand

that members of the engineering team in Australia are required to display a commitment

to exercising professional and ethical responsibility in all aspects of their work. I also

understand that documentation submitted in support of my application may be referred

to the Department of Immigration and Citizenship (DIAC) for integrity checking.‟

Printed Name: Joseph Thomas Verghis

Signature:

Date:

Page 6: CDR Joseph Thomas

COMPETENCY DEMONSTRATION REPORT

CAREER EPISODE 1

CE 1.1 INTRODUCTION

Chronology: Feb 1991 – July 1991

Name of Company: Kirloskar Motors Pvt. Ltd.,

Location: Bangalore, Karnataka, India

Nature of Project: Enhancing the Value of a 280KW LD 280 Induction Motor by Value

Engineering Techniques.

Title: Final Year Engineering Student

This project work was part of my Engineering degree course and it was essential to

undertake this project to graduate. One of the many important aspects of Industrial &

Production Engineering was to improve efficiency and productivity of products or

process such that it could value to the product and for the organization.

C.E. 1.2 BACKGROUND

Being an integral part of the course and essential for award of the degree, it was

imperative that all students do a project work. Taking this opportunity to get an insight of

the commercial world and manufacturing activity coupled with an aim to implement what

we had studied in theory and experience the outcome of our work.

C.E. 1.2.1 Objective of this Project

The objective of this project was to enhance the value of the selected product – a 280

KW induction motor, by either keeping the cost at the same level or increasing the

features of this product, or by reducing the cost of its manufacture, thereby enhancing

the value of the product.

Page 7: CDR Joseph Thomas

C.E. 1.2.2 Hierarchy of the Project Team

C.E.1.2.3 My Duties in the Project

Take a complete Bill of Materials for the Motor

Segregate each and every component into that which are outsourced and that

which is made in house

Note down the prices of the bought out items and estimate the prices of the

components that are made in house.

Observe and map the process of all the components made in house

Observe and map the process of the final assembly.

Work study and Time study each and every activity

Tabulate and document all findings – cost, time, and process in its existing

method of manufacture

C.E.1.3 PERSONAL ENGINEERING ACTIVITY

First and foremost I am very indebted to my Guide and Professor, Mr. Mohan Babu to

have got me this opportunity to work with India‟s leading Motor Manufacture – Kirloskar

Motors. I was clearly briefed by my guide on the aim and objective of this project, the

Professor & Guide

Mr. Mohan Babu

Value Engineering

Manager

I.E. Department

Mr. Ganesh Bhatt

Team Member

Joseph Thomas

(Myself)

Page 8: CDR Joseph Thomas

methodology to be followed, the tools and techniques to be used, and when where and

how to use them. I was also given the utmost cooperation by the Value Engineering

Manager, Mr. Ganesh Bhatt and his staff on this exercise, and they were delighted and

welcomed the idea as this exercise, which they felt was important and useful, but were

rarely done as it did not find time in their busy day to day schedules. This whole

experience was of immense value to me, as it not only gave me the opportunity to see

and feel my theoretical studies being put to practical use, but it taught me the

importance of personal interaction, team work, presentation of my work, and a general

picture how industries run.

C.E. 1.3.1 The first couple of days I was oriented by the staff of the company as to the

various aspects of their products, process, personnel‟s, departments, design shop, shop

floor, stores and inventory and the finance / accounts department. All these

departments and functions played an integral part for the success of the project. The

staff at Kirloskar along with me narrowed down to one particular product, their best

selling 280 KW induction motor. Since an exercise of this nature was never performed

on existing products, everybody was curious and keen to know the outcome, and if

tangible and implementable, wanted to apply the same to every product of theirs.

C.E.1.3.2 In the first stage, I carefully studied the Motor, its functions, its expectations,

its performance with reference to the standards set, its reliability, serviceability, the cost

of manufacture and its selling price. The next step was to take the complete bill of

materials for this product and even the consumables that is used to finish and ready the

product for delivery.

C.E. 1.3.3 My next task was to identify the primary and secondary function of each and

every component that went into making this motor, by asking myself straight forward

questions as what is its primary role / function, and if it serves any other purpose what

was its secondary role. This exercise gave an in-depth technical and functional

knowledge for the true purpose of every component that led me into the next step of

brainstorming along with the design, sourcing and production departments as to

Page 9: CDR Joseph Thomas

whether or not certain components is actually required to be there, can it be replaced

with substitute materials (cheaper or dearer) either to enhance the functionality or

reliability or reduce cost. These findings were tabulated as follows:-

Main

Assembly

------------------

Sub

Components

-------------------

Primary

Function

------------------

Secondary

Function

------------------

Cost

------------------

Remarks

-------------------

This exercise was performed on both, bought out items, and in house items. A similar

exercise was performed on the processing activities of those components that were

made in house, and an estimated cost of manufacture of bought out items. A separate

study was conducted on all bought out items, as to see the feasibility of doing the same

in house, given the existing resources and discussions with suppliers as to what would

be the cost of outsourcing components that were made in house. Components that

were not critical enough to be made in house and was cheaper to outsource was

marked and compared.

C.E. 1.3.4 The next step was to study the work flow and the map the process of how the

components arrive to the final assembly stage, how they were assembled, doing a

thorough work, method and time study of each and every activity. This meant that the

present methods of each activity and was observed and noted down and the time taken

from start to finish that activity was recorded by use of stop clocks. Here again a

meeting of all concerned people was convened and a brainstorming session held as to

whether or not the current methods adopted could be improved not only in terms of

time, but also ease and ergonomics that could reduce strain on the worker. Discussions

were held whether certain process could be eliminated totally, or coupled with another

Page 10: CDR Joseph Thomas

by the same worker, or whether certain tools, fixtures or aids could be applied to ease

and speed up the operation and the study was recorded as follows :-

Activity

----------------

Functionality

----------------

Method

Adopted

---------------

No. of

workers

involved

---------------

Tools /

Aids

Utilized

---------------

Time

Taken

---------------

Remarks

---------------

C.E.1.3.5 With all these data‟s in hand, a meeting was held amongst all members of the

team, mine and that of the factory‟s and a brainstorming session was held on every

component of the product stage and on every process at the assembly stage. Several

ideas were thrown in to mark an improvement, and every idea, however good or

unpractical it may have seemed, was recorded. Once the brainstorming session was

exhausted with ideas, every idea was considered and segregated into feasible or

practical vs. not feasible or practical. This narrowing down stage, was to zero down to

the best few ideas that suited every component or process activity that was practical

and feasible given the available resources.

C.E.1.3.6 These ideas were then put to a hypothesis testing to see its practicality of

implementation, the cost involved, and the savings derived from the replacement of

existing components and methods. The best idea was then decided upon taking into

account the ease of change, the cost saving, the availability of substitute product, the

design, its overall functionality in reference to the desired standards.

Page 11: CDR Joseph Thomas

C.E.1.3.7 Findings & Recommendations

Too many fasteners, nuts and bolts of various sizes – We proposed the standardization

of all nuts and bolts, which was design friendly and made no difference to the

performance of the motor. This simple act, saved a lot of time in assembly and ease of

maintenance on site, and more importantly eased the inventory and brought down the

cost tremendously. The next important proposal was to shave off the wall thickness of

the casing which reduced the weight of the motor by around 7%, easing the handling

and onsite maintenance and reducing the material cost. Overall our study and the

recommendations we proposed brought down the cost of this motor by 12%, with no

extra investment.

C.E.1.4 SUMMARY

The overall objective of my course in Industrial & Production Engineering is to

constantly find ways of improving the way things are done, thereby reducing the cost of

the product or service, or by increasing its features or functions, thereby enhancing its

value. This project work was my first peep into the real world of business and an

opportunity to see and experience how theoretical knowledge can be transformed into

practicality and experience its outcome.

This project gave me a real life experience of my Engineering studies and set the tone

for my future endeavors in the job market. It taught me the step by step method on how

to conduct a Value Engineering study, and the use of tools and techniques to be

applied. It taught me the importance of team work, developed my interpersonal skills,

showed me the importance of brainstorming sessions and the outcome from it, and

gave me the confidence to make a difference. The detailed study of the motor, gave me

the technical knowledge on the products.

Page 12: CDR Joseph Thomas

COMPETENCY DEMONSTRATION REPORT

CAREER EPISODE 2

CE 2.1 INTRODUCTION

Chronology: Jan 1999 – May 2003

Name of Company: Hope & Glory Ltd.,

Location: Mumbai, Maharashtra, India

Nature of Project: Greenfield Project: Setting up a 300 machine apparel manufacturing

Facility for one of my Suppliers

Title: Branch Manager

Hope & Glory is a buying house, for popular US brand Tommy Hilfiger, Guess, Limited

and UK brand Pepe. This company‟s role was mainly to facilitate in the procurement of

various merchandise, especially apparels, for these brands. This meant that once the

design was received from these brands, this company‟s role was to source suppliers,

merchandising, control quality, production planning and control reporting and logistic

activities.

I was in charge of all the suppliers in the southern region of India for execution of

sample and production orders placed on them. Responsibility also included Quality

control, Production planning and follow-up, Development of the line for every season,

Compliance, Shipping

C.E.2.2 BACKGROUND

One of our most resourceful suppliers was keen to expand, and we encouraged this as

we needed more capacities as business grew. This required a brand new manufacturing

facility complying with all SA8000 standards and other government regulations like

OH&S. The Director of this company along with the General Manager of my company,

taking into account my experience in Production and Plant Layout and my knowledge

on Lean Management, assigned this task to me.

Page 13: CDR Joseph Thomas

C.E.2.2.1 Objective of this Project

To design, build and put into operation a 300 machine facility that meets all Compliance,

Buyer‟s and Government‟s standards and regulations, with an inbuilt laundry and

embroidery unit To design the layout and work flow of Man, Machine and Materials in a

manner that gives the maximum efficiency with the available resources.

C.E.2.2.2 Hierarchy of the team

C.E.2.2.3 My Duties in the Project

Design the complete layout of the Factory

Map out the responsibility and Accountability of all concerned and delegate the

job, and get regular feedback on the progress.

Coordinate with the Architect and his team

Invite Tenders for Machine Supplies

Negotiate Technical & Commercial details with all Suppliers

Managing

Director

Executive

Director

Project In

charge

(Myself)

HR Manager Other

Suppliers

Architect Machine

Supplier

Interior

designer

Building

Contractor

Electrical

&

Plumbing

Contractor

Page 14: CDR Joseph Thomas

Draw Timelines, set deadlines and follow-up

Coordinate with HR for Recruitment of Staff and Workers

Supervise for quality, quantity, adherence to design specifications and time.

C.E.2.3 Personal Engineering Activity

I was very fortunate to have been assigned this great opportunity, as it enabled me to

put into live action all my theoretical studies and the experience I gained from my work

experience as a Production and Factory Manager. I was also honored to have been

given a free hand and the trust bestowed on me for this approximately 2 million dollar

project which was a serious amount of money in the year 2000. The project was a

Greenfield project wherein this project had to start from a barren land of approximately

2000 sq. meters. The target for this factory was to make approximately a million pieces

annually. The various departments required for the production were as follows:-

The Raw material stores – Fabric, Trims, and accessories.

Cutting Department – Where the fabric is cut and numbered and prepared for

sewing

The sewing department

The Finishing department – Trimming, Quality checking, Ironing, Packing &

Carton Boxing

The Embroidery unit – Two 12 head automatic embroidery machines and a 4

head machines for samples

The Laundry – Three 50 kg washing machines and dryer and a 10 kg machine

and dryer for samples.

Sampling Department, Showrooms, Office, Meeting Rooms, Reception, Electrical

& Machine maintenance room & Generator Room.

Dining Area, First Aid room & Crèche

C.E.2.3.1 My first step was to survey the land for its dimensions, and then draw out the

initial plan of the departments and machine layout. This was done taking into account

Page 15: CDR Joseph Thomas

the number of sewing machines required to meet the target number of pieces,

supplementary machines, its placement in an assembly line system, taking into account

the dimension of the machine, no. of machines and work stations required in a line to

make products like men‟s and women‟s tops and bottoms, the space between them,

aisle space, the design of material handling aids to move the WIP (Work in progress)

from one station to the next. I designed the layout in a manner that there was a smooth

flow and shortest route from raw material stage to finished products. Every department

and the machines and Man in them were designed to produce approximately 3500-4000

pieces a day depending on the style and complexity.

C.E.2.3.2 The next step was to take this drawing and discuss with the Architect and his

team as to how to build the structure around this layout. Given the size of the land, and

how much of it could be utilized giving room for driveway, fire escapes, and frontage.

After various discussions, permutations and combinations we froze on the design as

follows:-

The structure would be a 4 storey building each floor measuring 1200 sq. meters

totaling up to 4800 sq.meters.

The Ground floor consisted of the Office, Meeting Rooms, Reception, and

Showroom (2) (one for apparels and one for fabric swatches). It also housed the

laundry, the embroidery unit, a 30 machine sampling unit, Raw material store, a

dining area for staff and the Generator Room.

The first floor was the Finishing area – Trimming, Checking, Ironing, Quality

Inspections area, Packing, Carton Box Area and area for storage of ready to ship

cartons. This floor also housed the Cutting section area and one sewing line of

56 work stations of which 42 were sewing machines.

The second floor consisted of six sewing assembly lines – 4 with 42 work

stations and 2 with 56 work stations.

The third floor was mainly a dining area for the workers with provision for having

a Canteen, and resting area.

Page 16: CDR Joseph Thomas

The final drawings were drawn and firmed and submitted for budget and plan approval

to the M.D. and Government authorities.

On getting the approval, my next step was to draw timelines, for all activities and

phases that went into building the structure and supervise and follow up to see things

went according to plan. The deadline for this project was 15 months.

C.E.2.3.3 The next step was to list down all that had to be done and bought in executing

the project namely

Re-search on machine suppliers and inviting quotes and technical details from

them.

The same exercise on items such as furniture, lighting fixtures, tools and working

aids.

Coordination with the HR department on the no. of workers and staff required,

and setting standards for their qualifications.

All these activities were listed down in an Activity chart, and the lead times for its

execution noted down. With these dates in hand, we planned backwards to see what

activity needed to be taken up first, what needed to wait till the previous was completed,

what could be done independently which wouldn‟t affect other activities. These were all

put onto a PERT chart and the CPM decided. The aim was to see to that all came

together by the end of 15 months. We also had to take care to see that purchased items

did not come in too early for lack of storage and financial implications, neither did it

come too late which would delay the project and end up with cost overruns.

C.E. 2.3.4 The next phase was to go through all the quotations we received from

suppliers (3 suppliers minimum for every item) to see if they met technical, cost and

delivery standards. Technical and commercial discussions were held and negotiations

on price and features were made. Once I froze on these, P.O. were raised for all items

required and delivery schedules recorded for follow up. In addition to that I had to

calculate the energy requirements for the complete factory which included machines,

Page 17: CDR Joseph Thomas

lights and other power points so as to discuss with the electrical contractors as to the

power required and the size of the generator to be purchased. I had arranged for a bi-

weekly meeting of all concerned at the site for any additions or alterations that had to be

made in terms of layout, lighting and all other aspects for finishing the building.

Discussions were held with the interior designer for design of showrooms and the office

area.

In the meantime hiring of workers and staff had to begin such that I could fill up the

factory with the right people so as to fill up the vacancies and be ready to start the

operation in the 16th month, after completion and testing of the structure and the

electrical circuits and machines.

On completing of the building and before the machines or furniture arrived, I marked the

placement of every machine, furniture and work aids, and aisles to make it easy for the

machine suppliers to erect and place their machines. While this was going on, I was

following all the compliance, government and OH&S standards for fire extinguishers and

exits, outfits that certain workers needed for certain operations, drinking water facilities,

toilet facilities, resting and first aid areas.

C.E. 2.4 SUMMARY

The project was finished right on time, 15 months as estimated and planned. The

factory was certified by all Government bodies and the buyers compliance teams. The

workers and staff were all hired and ready to start, the raw materials for the orders

planned in this facility had arrived, and with a week of trial runs, the facility was ready to

execute the orders placed on them.

This was truly a wonderful and fulfilling experience for me as it taught me all the

essence of a project work, multi-tasking, negotiating, planning and control, interpersonal

relationships. This project furthered my knowledge on many technical aspects like civil,

electrical, plumbing and mechanical.

Page 18: CDR Joseph Thomas

COMPETENCY DEMONSTRATION REPORT

CAREER EPISODE 3

CE 3.1 INTRODUCTION

Chronology: September 2006 – September 2008

Name of Company: Bachi Shoes (India) Pvt. Ltd.,

Location: Ranipet, Tamilnadu, India.

Nature of Project: Certification of the company for ISO 9000, SA 80000, Enhancing

Productivity and Efficiency

Title: Consultant

C.E.3.2 BACKGROUND

Bachi shoes is one of India‟s more popular children shoe manufacturer exporting their

merchandise to popular European brands like Ecco, Start rite and Stones & Bones. This

company started off as a shoe upper manufacturer and then diversified into making the

complete shoes. This diversification led to a flood of orders that needed expansion and

streamlining to service the order as per requirements. It was around this time that I was

hired, mainly to streamline all production activities, and assist in the setting up of 3 new

facilities.

C.E.3.2.1 Objective of this Project

To streamline all pre-production, production and post production activities and get the

company certified for ISO 9000, and thereafter to focus on the manufacturing area and

get the facility certified for SA 800000. The next major area was then to improve the

productivity and increase the overall efficiency of this company..

Page 19: CDR Joseph Thomas

C.E.3.2.2 Hierarchy of the team

C.E.3.2.3 My Duties in the Project

Streamline all activities and get the company certified for ISO 9000

Meet all the Buyer‟s and Government regulations for manufacturing and get the

facility certified for SA 800000

Improve the Productivity of the manufacturing facility

Improve the efficiency of the complete chain and the overall company.

Map out the responsibility and Accountability of all concerned and delegate the

job, and get regular feedback on the progress.

C.E.3.3 Personal Engineering Activity

With adequate experience from the apparel manufacturing industry and the wealth of

knowledge I had gained over the years, I was confident to take up this assignment,

even though it was a different trade, with a host of similarities with regard to the

assignment I was entrusted with. By this time I had learnt that before embarking on a

project like this, it was critical to first have a holistic view of the entire functioning of the

company, before any one area is targeted for improvement, as this causes a ripple

effect, maybe positive or negative to other areas as well. Hence it was all the more

important for the balance to be maintained.

Managing

Director

Finance & Admn

Director

Consultant

(Myself)

Accounts Production I.T. Administration HR Merchandising

Page 20: CDR Joseph Thomas

C.E. 3.3.1 The first step I took was to observe and record how the present system is

functioning. The findings were recorded in a flow chart. This flow chart was then added

with more information like the resources utilized for every activity, such as Man, material

and money and the time it took to complete it. These were then carefully analyzed and

studied, along with the top Management and concerned department heads, for true

functions, and activities such as duplication of work, unnecessary work, activities that

are necessary but missing in the process, activities that were utilizing more than the

required resources, and similarly activities that lacked enough resources. This exercise

was a two pronged effort, one to comply with the ISO standards and the other to make it

more lean and efficient.

C.E. 3.3.2 The complete process was broken into three main parts: (1) Pre-Production,

such as Processing buyers enquiries, Costing, Sales Samples, Prototypes, Approvals of

colors, styles, raw materials, Production Planning and Scheduling (2) Production: Listing

the bill of materials, sourcing, negotiating prices, specifications and delivery schedules,

generating Purchase Orders, receiving the same at the raw material stores and

maintaining inventory, Trial runs, Actual Production and Quality control. (3) Post

Production: Shipping, Logistics, Commercial Activities and Receipt of Payments. I then

started to work on them one by one and began to make necessary changes that were

conducive to all other activities or departments. During this exercise I began to try out

various Permutations and Combinations that delivers the required output at a much

lesser cost. One of the best streamlining efforts was to computerize the entire operation

that not only speeded up the work, but also needed lesser people and was transparent

as to the exact status of the order, for everyone concerned, both internal and external to

see. This saved a lot of time on want of information at the right time and waiting for

information for actioning. More importantly it also met the ISO requirement of

documentation. This exercise alone saved the company approximately 20% of its

resources.

Page 21: CDR Joseph Thomas

C.E.3.3.3 My next step was to address the Production area. Firstly in terms of the work

flow and documentation, such that it had a smooth continuous flow from the

Merchandising and Sampling departments, this was an ISO 9000 requirement which we

met. Here again, it was lack of information, lack of proper documentation and

coordination that caused the delays and this was set right by educating the Production

staff on how the new process is beneficial and mandatory. One of the greatest cost

savers in this area was to try and bring closer to the JIT concept of inventory control,

and an exercise which was never done before, and that is to prepare all raw materials

required in the right quantities to process an order / style in advance, rather than

retrieving it when the order just begins, which proves to be risky as there may not be

enough time for an item that is required or mismatch quantities. This also gave the

Production time to inspect the raw materials for specifications, quantities and quality

before it went into the production line. The documentation that was mainly required here

was designed for back tracking of any quality problems, and its causes, that may arise

when the merchandise arrives at the buyer‟s end. It also revealed information on the

resources utilized, which was critical information when applying Lean Management

principles.

C.E.3.3.4 The next area we focused upon was all the post shipping activities, such that

not only was the documentation process right to avoid any discrepancies, but this would

also mean receipt of payments quicker and with more ease. This involved the

participation and cooperation of the Logistics provider and the Shipping lines.

C.E.3.3.5 I, in the meantime also simultaneously began all the work that was required to

get the SA 8000 certification. This included workers regular and overtime hours and

compensation, working environment standards like the No. of toilets per worker,

drinking water, canteen and resting areas, OH&S, facilities like First Aid room, Crèche,

signs and boards for safe work, educating the workers of their rights and

responsibilities, adequate space for aisles, and movement of goods and marking the

same. Documentation of preventive maintenance and consumables used and its

frequency were recorded.

Page 22: CDR Joseph Thomas

C.E.3.3.6 These exercises got the company the ISO 9000 & the SA 8000 certification

and more importantly paved the way to apply the principles of Lean Management with

the objective to increase productivity and enhance total efficiency. The exercise that

went into the certification had many similarities to the initial jobs of Lean Management.

From all the information I gathered, my first task was to identify the weakest links in the

chain right from the pre-production activity all the way till receipt of payment. Most of the

work that went into the pre and post production activities were mainly information

gathering and sharing, eliminating unnecessary and duplicating activities, streamlining

information and delegating the right people for given tasks. Due to the limitation of this

report, I shall focus more on the Production activity where we applied most of our Lean

Management Principles.

C.E. 3.3.7 After the initial work of process mapping and work flows, I along with the

Production team took a very out of the ordinary approach to the existing method of line

production wherein the raw materials in batches of 10 would enter the line and go

through the line of 40 machines before the final product comes out from the other end.

The approach we took was to make smaller batches/line entering the production line

one piece at a time, and the line was re-arranged from straight lines to circular, leading

to lesser and shorter movement of WIP and the first finished piece coming out much

faster. This also was advantageous to correct any quality problems immediately rather

than wait for 10 pieces to come out at a time at a much delayed time. This arrangement

had another great advantage of producing smaller SKU‟s at a much faster rate. After

many trial runs and fine tuning, we timed the whole operation and came to realize that it

took close to 15-20% much lesser time than the traditional method, thereby increasing

productivity by the same amount.

C.E. 3.3.8 The same exercise was carried on to the sole fixing and finishing section,

and we incorporated the packing section into this area. This also increased the

productivity by around the same amount, and one of the good things amongst many

other things, that came out was the floor space savings, which was big enough to

Page 23: CDR Joseph Thomas

accommodate another line. This was a trial exercise carried out in one line in one

factory, and its success was to be duplicated on to other lines and other units too.

C.E. 3.4 SUMMARY

One of the greatest advantages of applying Lean Management is that the investments

Vis-a vis the outcome is tremendous, and the improvement continuous. This exercise in

itself improved the productivity by around 20% with much more scope to improve, it

saves space which can be utilized for other purposes saving real estate investments,

less tiresome for workers as movements reduced by close to 30-40% which in turn

minimized handling.

This project helped me to realize the potential of taking a holistic approach to problems

and targeting the weakest link, strengthening it, and moving onto to the next weakest

link, and in the process improving the overall efficiency of a facility. It also taught me

that waste reduction is in itself a great tool to improve bottom lines rather than just

focusing on getting more business. This facility also saved a lot of dollars by adherence

to delivery schedules which otherwise needed to be aired to the client rather than it

being shipped.

Page 24: CDR Joseph Thomas

PROFESSIONAL ENGINEER

Summary Statement

Competency Element A brief summary of how you

have applied the element

Paragraph in the career episode(s)

where the element is addressed

PE1 KNOWLEDGE BASE

PE1.1

Knowledge of science and

engineering fundamentals

I have utilized my

theoretical knowledge and

applied those concepts in

the various projects I have

been involved with during

my undergraduate degree

and work experience.

I have gained a lot of

knowledge in the

fundamental principles of

Industrial Engineering while

working towards my Project

work at University and at

work involving Value Engg,

Project Management and

Lean Management

CE 1.3.2, CE 1.3.3 CE 1.3.4, CE 1.3.7, CE 2.3, CE 2.3.1, CE 2.3.2, CE 2.3.3, CE 2.3.4, CE 3.3.1, CE 3.3.2, CE 3.3.6 CE 3.3.7 CE 1.3.3, CE 1.3.4 CE 1.3.5, CE 1.3.6 2.3.3, CE 3.3.3, CE 3.3.4

Page 25: CDR Joseph Thomas

PE1.2

In-depth technical competence

in at least one engineering

discipline

I have been able to

achieve in-depth technical

competence in Value

Analysis and its application

on products and design of

systems and layouts for

maximising productivity

and efficiency.

I also gained in-depth

knowledge in handling

projects through my

experience in a green field

project, my lean

management experiment

and through my studies in

Project Management and

Supply Chain

Management in my post

graduate studies.

CE 1.3.2, CE 1.3.3, CE 1.3.4, CE 2.3.1, CE 2.3.3, CE 2.3.7, CE 3.3.1, CE 3.3.2, CE 3.3.3, CE 3.3.7, CE 2.2.1, CE 2.3.3, CE 2.3.4, CE 2.3.5, CE 3.3.2, CE 3.3.3

PE 1.3

Techniques and resources

I have done extensive

literature reviews for my

projects and in the work

place by critically

reviewing journals,

textbooks and catalogues

including the internet in

general to learn more

about the different aspects

of the projects as well as

look for possible

improvements in the

particular field of research.

CE 1.3.2, CE 1.3.3, CE 1.3.4, CE 2.3.1, CE 2.3.2, CE 2.3.3 CE 2.3.4, CE 3.3.6, CE 3.3.7, CE 3.3.8

Page 26: CDR Joseph Thomas

I am proficient with various

Industrial and Production

engineering tools and

techniques like process

mapping, Problem

identifications, Method,

Time and Work study,

PERT and CPM charts

I have an extensive

knowledge base in using

the different packages in

MS office including MS

Word, MS PowerPoint and

advanced usage of MS

Excel including using

macros for calculations as

well as MS Project for

project management.

CE 1.3.3, CE 1.3.4, CE 1.3.5, CE 2.3.1, CE 2.3.3, CE 3.2.1, CE 3.3.6, CE 3.3.7, CE 3.3.8, CE 3.3.2, CE 3.3.3, CE 1.3.7, CE 1.3.8,

PE 1.4

General Knowledge

I have used my general

knowledge in identifying

problems in the different

projects and solved them

with appropriate

measures.

I successfully completed

my projects which was

approved by various

institutions and are even

today operational, which

CE 1.1, CE 1.2, CE 1.3. CE 2.1, CE 2.2 CE 2.3, CE 3.1, CE 3.2, CE 3.3

CE 1.4, CE 2.4, CE 3.4

Page 27: CDR Joseph Thomas

requires general

knowledge of engineering

and science.

PE2 ENGINEERING ABILITY

PE 2.1

Ability to undertake problem

identification, formulation, and

solution

I first thoroughly examine

the objectives of my

project or client and the

problems and obstacles

before finding the solutions

to them. I have always

worked to meet the

demand and the

requirements of my

projects and my client. I

have improved

professionally with every

project that I was involved

in.

Detailed Process mapping

gives me an idea to

identify the weakest links

in the chain, and to focus

on a solution to strengthen

it, and then move on to the

next weakest link and so

on until the whole chain

works in tandem with each

other supporting one

another.

CE 1.1, CE 1.2, CE 1.2.1, CE 1.2.3, CE 1.3.1, CE 1.3.2, CE 1.4, CE 2.2, CE 2.2.1, CE 2.3.2, CE 2.3.4, CE 3.1, CE 3.2.1, CE 3.3.2, CE 3.3.3

CE 3.3.1, CE 3.3.2, CE 3.3.3, CE 3.3.6 CE 3.3.7, CE 3.3.8

Page 28: CDR Joseph Thomas

PE 2.2

Understanding of social,

cultural, global, and

environmental responsibilities

and the need to employ

principles of sustainable

development

I have interacted with

various departments

during my project work and

all through my working

career and the specified

projects undertaken and at

different levels to ensure

successful project

implementation.

I have worked in both

western and eastern

cultural environments due

to the nature of my work

and understand the

differences in their

procedures and

requirements.

All the projects that I have

worked are focussed

towards the improvement

of society and aspects of

sustainable development

are entwined with

improvements made to the

community at large.

CE 2.3.3, CE 2.3.4, CE 3.3.2, CE 3.3.3 CE 1.3.1, CE 1.3.2, CE 1.3.6, CE 1.3.7, CE 1.3.8, CE 2.3.3, CE 2.3.4, CE 2.3.8, CE 1.4, CE 3.3.2, CE 3.3.9, CE 3.3.10 CE 1.1, CE 1.2, CE 1.3.8, CE 1.4, CE 2.2, CE 2.3.8, CE 3.1, CE 3.2

PE 2.3

Ability to utilize a systems

approach to complex problems

and to design and operational

performance

I used different techniques

to accomplish the task of

designing in my projects

by systematically

producing various

solutions and selecting the

CE 1.2.3, CE 1.3.2, CE 1.3.3, CE 1.3.4, CE 2.2, CE 2.3.3, CE 2.3.5, CE 2.3.8, CE 3.2.1

Page 29: CDR Joseph Thomas

best alternative for the

different constraints

involved

I have made schedules for

my activities and prepare

project schedule outlines

to identify responsibilities

of all the people involved

in the project

I have always consulted

and researched with

various experts in this field

and demand for

continuous feedback from

the senior management on

my project during its

implementation

CE 1.2.2, CE 1.2.3, CE 1.3.1, CE 1.3.5, CE 1.3.6, CE 1.3.7, CE 1.3.8

CE 1.3.1, 1.3.2, CE 2.2.2, CE 2.3.1, CE 2.3.8, CE 3.3.2, CE 3.3.9

PE 2.4

Proficiency in engineering design

The project in my

Bachelor‟s degree was a

re-design of a motor which

involved the re-design and

standardization of several

components which

involved implementation of

design techniques and

technical knowledge

The opportunity to be

involved in a Greenfield

project, wherein I utilized a

lot of aspects of Industrial

Engineering to set up this

CE 1.2, CE 1.2.1, CE 1.2.3, CE 1.3.3, CE 1.3.4, CE 1.3.5

CE 2.3.3, CE 2.3.4, CE 2.3.5

Page 30: CDR Joseph Thomas

manufacturing facility to

ensure maximum

efficiency and productivity.

I have designed systems

and applied them to get

the ISO 9000 and SA

800000 certification which

greatly improved the pre-

production and post

production activities and

cut down tremendous time

in paper work and

improved the filing system

which made backtracking

very easy.

CE 3.3.3, CE 3.3.4, CE 3.3.5, CE 3.3.6, CE 3.3.7, CE 3.3.8

PE 2.5

Ability to conduct an engineering

project

I have extensive

capabilities of conducting

and managing projects

evidenced by the project in

my Bachelor‟s degree.

I further improved my skills

in setting up a 300

machine apparel

manufacturing facility and

setting up systems to

improve the efficiency of a

shoe manufacturing

facility.

Whole of CE1 Whole of CE2 Whole of CE 3

PE 2.6

Understanding of the business

environment

I have a good

understanding of the

hierarchy of organizations

and the inter-relationship

Whole of CE1

Page 31: CDR Joseph Thomas

between the different

departments during my

project work at for my

Bachelor‟s

I have dealt effectively with

all departments, my

clients‟ suppliers and

company executives for all

kinds of business

transactions during my

working career. Working

as a Profit centre head

gave me an immense

understanding of the

business world.

Whole of CE 2 Whole of CE 3

PE 3 PROFESSIONAL ATTRIBUTES

PE 3.1

Ability to communicate

effectively, with the engineering

team and with the community at

large

I have excellent

communications skills

proven by my role as

Merchandiser and

Production Manager

wherein I had to

communicate with my

buyers based overseas

and at all levels of my

office and production staff.

Communication with

suppliers and all external

bodies during my projects

was another clear

evidence of the same.

I have presented my

project to the management

CE 1.2.2, CE 1.3.1, CE 1.3.5, CE 1.3.6, CE 2.1, CE 2.2, CE 2.3.1, CE 2.3.2, CE 2.3.3, CE 2.3.4 and CE 3 CE 2.

Page 32: CDR Joseph Thomas

for budget approvals and

communicated well with

industry partners for

equipment and materials

I have given presentations

and submitted several

assignments on various

subjects during my post

graduation course in

Logistics and Business

Administration at the

University of Wollongong.

Curriculum Vitae

PE 3.2

Ability to manage information

and documentation

A key function during my

project work for my

Bachelor‟s was to collect

as much data as possible

and file them in a manner

that it can be easily

retrieved and acted upon.

During the execution of the

Greenfield project and the

ISO 900 and SA 80000

certification projects, large

amounts of various data‟s

such as technical,

commercial, social and

cultural, and general

data‟s, had to collected

and documented, upon

which critical decisions

need to be made.

CE 1.3.1, CE 1.3.2

CE 2

CE 3

Page 33: CDR Joseph Thomas

My post graduate studies

required a lot of

assignments and reports

to be submitted on various

subjects, companies, and

projects. This required a

lot of information gathering

and compiling and

choosing the appropriate

ones.

PE 3.3

Capacity for creativity and

innovation

My project in my

Bachelor‟s degree shows

that I have a flair for

creative thinking and

innovative ideas.

Continuous improvement

and adjustments during

the execution and

application of my projects

from the drawing board to

the site was essential and

delivered.

Recommendations and

solutions for all my

research during my post

graduate studies was a

result of my creativity and

innovative ideas.

CE 1.1, CE 1.2, CE 1.3.3 CE 2, CE 3

PE 3.4

Understanding of

professional and ethical

responsibilities, and commitment

I have ensured to keep my

supervisor and team

members well informed of

CE 1.3.1, CE 1.3.5, CE 1.3.6, CE 2.3.1, CE 3.3.2, CE 3.3.9

Page 34: CDR Joseph Thomas

to them the status of the project on

a regular basis.

I have managed to

incorporate changing

requirements in a project

without any hesitation

incorporating all agreed

upon suggestions from all

concerned.

Factory Compliance which

includes, workers

compensations, high

standard of working

environment, OH&S,

Waste management,

Water and air pollutions

was my responsibility and

a key part of my job during

the management of

factories or sourcing

factories.

C.E. 1.3.6

The whole of CE 2

The whole of CE 3

PE 3.5

Ability to function effectively as

an individual and in

multidisciplinary and multicultural

teams, as a team leader or

manager as well as an effective

team member

I have handled projects

individually as well as a

part of a team.

I have coped well to the

change in work cultures

and understand the

importance of team work

and contributions to the

team as an individual.

CE 1, CE 2 & CE 3

CE 1, CE 2 & CE 3

Page 35: CDR Joseph Thomas

I have interacted in various

levels and departments in

the organization.

I have led a team during

my project work for

Bachelor‟s and during my

work experiences in

several occasions.

Whole of CE 1, CE 2 & CE 3

PE 3.6

Capacity for lifelong learning

and professional development

I have shown keen interest

in learning new aspects of

Industrial & Production

engineering, especially in

areas of minimizing waste

and improving

sustainability

I have learnt and applied

several tools and

techniques in order to

keep myself updated with

latest technology.

I have strengthened my

knowledge and skills in

this field with a Master‟s

degree in Logistics and

Business Administration,

and will continue to pursue

a career path wherein I

can contribute my skills

and knowledge to

Industries in a more

Whole of CE 1, CE 2 & CE 3 Whole of CE 1, CE 2 & CE 3

Page 36: CDR Joseph Thomas

economical and

sustainable approach to

business.

PE 3.7

Professional Attitudes

I have always performed

professionally during my

work and study; interacting

with technicians, industry

personnel, engineers and

the management alike.

I have been able to

achieve a high level of

knowledge in the

engineering discipline and

have also been

commended for my

dedication and success in

all the projects I undertook.

CE 1, CE 2, CE 3 CE 1, CE 2, CE 3