Caythorpe Gas Storage ProjectLiaison Committee Meeting28th September 2009

Page 2: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20092

Agenda

• Project Status Report – September 2009

• Archaeological site investigation

• Bridge design

• Seismic survey

• Traffic management plan

• Ongoing community liaison

• Environmental support fund

• Activities on site within coming weeks / months

• Questions

Page 3: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20093

Health, Safety & Environment

• No on or off site complaints (to date)

• No on or off environmental impacts (to date)

• No accidents, incidents or near misses to report (to date)

• Project working under the “Construction Design & Management

Regulations” regulated by the Health & Safety Executive

• Site visit by HSE Construction Division 27th August. No issues of

concern raised

• Baseline noise survey completed August 2009 and issued to ERYC

• Noise, Vibration, Dust Management and Monitoring Scheme submitted

to ERYC (in accordance with planning conditions)

Page 4: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20094

Current Status

• Demolition of existing equipment completed in June

• Archaeological site investigation ongoing

• Geotechnical site investigations

Page 5: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20095

Archaeological Site Investigation

• Located on the margins of a settlement occupied in the late Iron Age,

Roman and early Anglo-Saxon periods (about 200BC to AD700)

Page 6: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20096

Archaeological Site Investigation

Page 7: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20097

Archaeological Site Investigation

Page 8: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20098

Invitation to an Archaeological Site Visit

• Liaison Committee Saturday 10th October

• Boynton School w/c 12th October

Page 9: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 20099

Bridge Crossing of Gypsey Race

• Would like to install October/November 2009 but may delay until Spring

2010

• Design approved by the Environment Agency

• Ecological surveys on river ongoing

Page 10: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200910

Bridge Crossing of Gypsey Race – Existing View

Page 11: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200911

Bridge Crossing of Gypsey Race – Proposed View

Page 12: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200912

Water Voles

• Water Vole is a protected species and

present on the Gypsey Race including

location of bridge crossing

• Ongoing daily surveys on the river

• Habitat management to encourage

voles to move along the river

• Fallback option is to move the voles

under licence from Natural England

• Ecological Mitigation & Monitoring

Strategy submitted to ERYC (in

accordance with planning condition)

Page 13: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200913

Seismic Survey

• Seismic survey underway, due to

complete mid November

• 7 day/week operation.

• Mitigation measures in place to avoid

damage to land and protect

archaeology and ecology

• Vibration monitoring at residential

properties

Page 14: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200914

Seismic Survey – Notification to Residents

Page 15: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200915

Seismic Survey – Notification to Residents

Page 16: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200916

Construction Traffic Management Plan

Page 17: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200917

Construction Traffic Management Plan

Page 18: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200918

Environmental Support Fund

The Fund will be structured into two elements:

• An initial one-off sum of £150,000 which is available up until the completion of construction of the project (2012); and

• An ongoing annual budget of £5,000 as per the Warwick Energy agreement with ERYC (over the 24 year lifespan of the planning permission this equates to £120,000)

• The allocation of monies will be subject to applications to the Liaison Committee in accordance with published guidelines

Page 19: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200919

Future Activity October-December 2009

• Completion of seismic survey by mid November

• Completion of archaeological site works for this season (with remainder of work to be done in spring)

• Moving of water voles if habitat management unsuccessful

• Construction of bridge and access road (although may be delayed until spring)

Page 20: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200920

Point of contact for seismic survey

IMC Geophysics International Ltd

c/o Garland Total Vehicle SolutionsLancaster RoadCarnaby Industrial EstateCarnabyBridlingtonYO15 3QY

Tel: 07810 855318

Page 21: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200921

Points of contact for project

Paul Dacombe

Consents & Licencing Manager

Caythorpe Gas Storage Project

Centrica plc

Millstream West

Maidenhead Road

Windsor

Berkshire

SL4 5GD

Mobile 07789 570416

[email protected]

Justin Kenyon

Site HSE Manager

Caythorpe Gas Storage Limited

Caythorpe Well Site

Rudston

Driffield

YO25 4JD

Site Office 01262 420177

Mobile 07904200995

[email protected]

• Project Website

Page 22: Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009

Caythorpe Liaison Committee 28th September 200922

Questions?