case study vincent square, westminster - mgf · case study mgf designed a scheme suitable for the...
TRANSCRIPT
CustomerFairpoint Properties
Main ContractorJ Reddington Ltd
Date2005
Commitment Innovation Sustainability
Case Study
MGF designed a scheme suitable for the complex construction sequence using a mixture of modular 120Te hydraulic and mechanical cross struts spanning up to 23m across the capping beam. Where other spans were too great, 54Te mechanical struts were utilised as raking struts, and knee braces were used in the corners of the excavation. Bespoke items were also developed, manufactured and supplied byMGF including special connection details to allow knee braces to articulate through two planes and non-standard shaped waler beams.
MGF’s products and detailed design provided J Reddington with a made to measure system that was easy to install and remove, whilst providing optimum working space. The considerable safety buffer built into the scheme design gave the customer additional peace of mind and successfully prevented any damage to or movement of the surrounding structures.
MGF were asked to design and supply temporary support to the basement of a development of 50 luxury apartments in the heart of Westminster. Support was required against the capping beam of the contiguous piled wall that would later form the basement car park. Temporary support to the face of the contiguous piles was also required at lower levels to allow construction of the basement slabs and columns. The biggest concerns on the project were supporting, and not causing any damage to, the fragile listed buildings surrounding the site, as well as the earth wall below the adjacent live road.
The Problem
The Solution
The Verdict
www.mgf.ltd.uk
Vincent Square, Westminster
Head Office: 01942 402700 North East: 0191 378 2100 Yorkshire: 01977 521930 North West: 01942 896282 Midlands: 01889 574777 South West: 01179 820706 London North: 01296 663250 London City: 01322 344520