ADVANCED COATINGS TECHNOLOGY Case History Manhaan Bridge New York, New York INTRODUCTION If traffic polluon can cause corrosion on your car, image what a steady stream of cars driving in and out of the busiest city in America does to the Manhaan Bridge. The size and scope of this project covers everything from the main structure and towers to the main and suspender cables. They have to enclose the bridge to blast off old coangs making way for the proven technology of Wasser. Short downmes, excellent corrosion resistance and long life are the reasons we are on the job, just ask George Campbell. OWNER New York City Department of Transportaon PROJECT Manhaan Bridge Rehabilitaon (North Span) CONTRACTORS Koch-Skanska George Campbell Painng Corp. SYSTEM Surface preparaon SSPC-SP10 Near White Blast Cleaning Power Wash and Hand Tool Clean BRIDGE STRUCTURE AND TOWER Primer MC-Zinc 3-5mils DFT Intermediate MC-Prepbond 1.2-2.5 mils DFT MC-Ferrox B 3.0-5.0 mils DFT Top-coat MC-Luster 2-4 mils DFT MAIN CABLE AND SUSPENDER CABLES Primer MC-MioAluminum 1.5-2.0mils DFT Intermediate MC-Ferromasc 3.0-5.0 mils DFT Top-coat MC-Luster 2-4 mils DFT PROJECT DATE 2003 SUBSTRATE Steel

Upload: truongkhue

Post on 29-Mar-2018

220 views

Category:

Documents


1 download

TRANSCRIPT

ADVANCED COATINGS TECHNOLOGY

Case History

Manhattan BridgeNew York, New York

INTRODUCTION

If traffic pollution can cause corrosion on your car, image

what a steady stream of cars driving in and

out of the busiest city in America does to the Manhattan

Bridge. The size and scope of this project covers

everything from the main structure and towers to the

main and suspender cables. They have to enclose

the bridge to blast off old coatings making way for the

proven technology of Wasser. Short downtimes,

excellent corrosion resistance and long life are the

reasons we are on the job, just ask George Campbell.

OWNERNew York CityDepartment ofTransportation

PROJECTManhattan Bridge

Rehabilitation(North Span)

CONTRACTORSKoch-Skanska

George CampbellPainting Corp.

SYSTEMSurface preparation

SSPC-SP10 Near White Blast Cleaning

Power Wash andHand Tool Clean

BRIDGE STRUCTURE AND TOWERPrimer

MC-Zinc 3-5mils DFTIntermediateMC-Prepbond

1.2-2.5 mils DFT MC-Ferrox B

3.0-5.0 mils DFT Top-coat

MC-Luster 2-4 mils DFT

MAIN CABLE AND SUSPENDER CABLES

PrimerMC-MioAluminum

1.5-2.0mils DFTIntermediate

MC-Ferromastic3.0-5.0 mils DFT

Top-coatMC-Luster

2-4 mils DFT

PROJECT DATE2003

SUBSTRATESteel