Capital Planning Tool
Sharon De Sykes, Principal Estates Advisor
Craig Marriott, Assistant Director of Finance
September 2014
2 2
Background
Overview of System
Extracts from System
National Prioritisation
Capital Planning Tool
3 3
Since 2009……
Benefits of System
Review of Potential Systems
Pilots : D&G, Lanarkshire & Tayside Imported data
Modelled future lifecycles
General reporting and analysis
Investment
Background
4 4
The property condition is assessed using the
Facility Condition Index (FCI) measurement
The output from VFA.facility can automatically
generate an accurate capital plan, for lifecycle
modelling and future capital funding projections
VFA.facility can highlight the areas of capital
investment required to achieve and maintain
Condition ‘B’
Overview of System
5 5
Capital Scenario plans
Detailed Lifecycle Profile
Budget Prioritisation
Benchmarking requests
Reports using NHS ranking protocol
Details of Maintenance Backlog
VFA can generate
6 6
VFA appointed in 2013
Transfer of Data
Lifecycle Models
Board Training
Future Surveys
Programme Since Appointment
7
1. What do we own?
3. How much money do we need?
4. What is most important?
2. What is the condition & what
does the condition need to be?
Ensuring Success – VFA.facility
8
Facility Condition Index (“FCI”)
‘Current Replacement Cost FCI =
Capital & major maintenance cost to achieve ‘Condition A’
8
A standards-based common performance metric:
Measure and compare performance on facility condition using a
Facility Condition Index (“FCI”) for the 4 constituent parts:
A B C D
0% 5% 11% 30% 50% 100% 50% 100%
1. The building envelope;
2. Engineering services;
3. Internal elements;
4. External area.
9
Condition Definition Classification FCI
Excellent/as new condition (generally less than 2 years old).
Expected to perform as intended over its expected useful
service life. A ≤ 5%
Satisfactory condition with evidence of only minor deterioration.
Element/Sub-Element is operational and performing as
intended. B 6 - 11%
Poor condition with evidence of major defects.
Elements/Sub-Element remains operational but is currently in
need of major repair or replacement. C 12 – 30%
Unacceptable condition.
Non-operational or about to fail.
Has reached the end of its useful life.
D 31 – 59%
Supplementary rating added to D only to indicate that it is
impossible to improve without replacement. X >60%
NHS Ranking Protocol Ranking Protocol
FCI can be linked to the NHS Ranking Protocol for Physical Condition
9
10 10
Backlog Maintenance
• Physical Condition
• Statutory Compliance
• Environmental Management
NHS Scotland Property
Appraisal Guidance
• Space Utilisation
• Functional Suitability
• Quality
Standard Functionality of VFA .facility
Future Functionality / Integration with NHS Scotland Property Appraisal
Guidance
The Six Facet Approach
11
=
11
Maintenance Backlog Detail
MB / Typical Peak Year Requirement List
12
Cost Estimating Access to external databases
BCIS, or Own Cost Information
12
13
Modeled system lifecycle data to be added
Based on building use lifecycle models
13
Example:
System Detail
View: System level record
BCIS coding
Location
Quantity
Estimated
replacement value
Associated
requirements
Documents
Photos
System Lifecycle Added
14
Adjusting Lifecycle based on Observed Conditions
Tailor “normal” data to…
Be contract specific
Reflect maintenance
strategies
Example: System Detail
View:
Tailor “observed”
years remaining
Tailor “% Renew”
14
15
Facility Condition Index is an industry standard
measure used to compare relative building
conditions across regions or portfolios.
Constant insufficient funding
Maintain current condition.
Improve condition
Line represents condition (FCI)
Bars represent funding profile
Replace
Scenario Planning – From tactical to strategic
16
Prioritisation of Required Actions
Based on criteria
specified by the user
16
17
Budgeting based on Prioritised Actions
17
18
Bespoke Reporting
Dozens of
standard
reports
Flexible
selection
criteria
Project,
Building,
System level
Custom
reports
18
19
Report distribution
19
Web-access
Select from
list
Share
favorites
PDF, HTML,
Excel, CSV
Automated
reporting via
20
Creation of additional ad-hoc reports
20
Drag and
drop
Customize
titles, notes,
instructions
Create
calculation
fields
“Pro” tool
available
21
21
Project Bundling
22
VFA FacilityView
Graphically view the Estate
Drill down from Region, Board to Hospital
No additional data entry required
22
Governance •Project Board Remit :
Provides overall strategic direction and leadership for the Capital Planning System
•Development Group Remit : Agree and recommend priorities to the Project Board
Testing the lifecycle models Potential future work focusing the Health and Social Care
Integration and the 2020 vision
•User Group Remit Provides a forum for the operational users of the System Can raise and discuss operational issues that require
clarification, change or further development Enables best practice to be shared between Boards
Proposed National Priorities
Triple Aim Quality Ambitions12 Priority Areas
for Improvement
Capital Planning
Tool
Prioritisation
Example
Score (0,1,2,3)NHS Grampians Examples of Projects that may generate a
score
1Person-centred Health and Care Collaborative
implemented
2Information and support to enable people at
home and during times of transition
3 Further increase in safety in Scottish hospitals
4 New broader measure of safety developed (SPSI)
5
Maternity, mental health and primary care
components of the Scottish Patient Safety
Programme implemented with measureable
improvements
6 Implementation of new GP contract
7 2020 Vision for expanded primary care
8 New models of ‘place-based’ primary care
9 Out of hospital care action plan
10 Sustainable performance on 4-hour A&E waits
11 Increase flow through the system
12 New Bill
13
Preparatory work with NHS Boards, local
authorities, third and independent sector and
the building of effective Integrated Health and
Social Care Partnerships
14
Key pressure points in the entire patient
pathway for most common multiple illnesses
will be identified and actions agreed
15
Through more detailed analysis of existing
data, people will be identified as ‘at risk’ and
anticipatory plans will be agreed
Early Years 16
The world’s first national multi-agency quality
improvement programme will be implemented
across partner organisations
Child development programme, leasing new accommodation
to provide services for Children in their communities.
17 New focus on most deprived areas
18‘Deep-end’ GP practices approach rolled out
more widely across relevant areas
19 Early detection of cancer
20 New restrictions on tobacco advertising
21 2020 Vision for NHSScotland workforce
22Detailed action plan agreed to deliver 2020
Workforce Vision
23A new fund to provide pump-priming for
innovative approaches in healthcare
24
A new procurement portal will be
established to encourage working with
SMEs and third sector
Efficiency and
Productivity25 Recommendations to increase shared services
IT solution - introduction of Hospital Electronic Prescribing
and Medicine Administration System (HEPMA)
Development of the "one stop" ambulatory care process,
Implementing the Electronic Patient Record system and
introducing the Clinical Guidance Intranet (CGI) for Clinicians,
and health care workers.
Provision of new primary care premises in Grampians more
deprived areas such a the new dental unit in Fraserburgh and
new GP premises in Woodside, Aberdeen.
Provision of new diagnostic and radiography services in the
acute and community setting and increased MRI Capacity
25 Key Deliverables for 2013/14
Person-centredPerson-centred
Care0
0
He
alt
h I
mp
rov
em
en
t
Quality of
Care
Health of the
Population
Prevention
Effective
Unscheduled
and Emergency
Care
Integrated Care
Care for
Multiple
and Chronic
Illnesses
Health
Inequalities
Introduction of "Smarter offices" to improve the working
environment and efficiency of our staff and the provision of
quality affordable accommodation to health care workers.
Innovative solutions for Healthcare provision have already
been introduced to NHSG such as local community owned
Maud Resource Centre, the new Crimmond Health and
Community Centre provided by a local benefactor.
Workforce
Innovation
IT solutions - IT for community based Staff, Patient Portal,
"No Delays" and improved Quality of Physical Environment
Improving Statutory Standards Compliance, Improving SCART
scores and Reduction in Backlog Maintenance
Implementation of Primary Care Premises 10 year Plan
New Build Emergency Care Centre and increased use of Tele-
medicine centre for unscheduled care.
Introduction of Health and Social Care agenda, partnership
working projects such as Health Village, Maud Resource
Centre, Whinhill and Maggies Centre.
Value and
Sustainability
Safe Safe Care
Primary Care
Person-centred
Safe
Effective Quality
of Care
Health of the
Population
Value and
Sustainability
Eff
icie
ncy
HEAT TARGETS
Acc
ess
Tre
atm
en
t
0
0
0
Proposed National Prioritisation Criteria
• Person Centred • Safe • Effective Quality of Care • Health of Population • Value and Sustainability
Pairwise Ranking
Profile of Scoring
Workshop Questions
1. What are your views on the weightings of the national priorities proposed?
2. How will you use this tool as part of your local prioritisation for formula capital investment?
3. What issues do you need to consider when implementing this approach?
Allow 25 mins discussion and 15mins for all tables to feedback.