Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University Minneapolis, Minnesota August 11, 2010 NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going?

Upload: others

Post on 04-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Capacity Building Workshop

Stuart Anderson, PhD, PETexas A&M University

Minneapolis, MinnesotaAugust 11, 2010

NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going?

Page 2: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Outline• History

• Advances

• Current Environment

• Wrap Up

• Discussion

Page 3: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

State Highway Agencies face a major challenge is controlling project budgets over the time span between the initiation of a project and the completion of construction.

The Problem

Page 4: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Consistency and Accuracy

Page 5: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report
Page 6: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Strategic Focus Definitions

• Strategy: “a plan of action intended on accomplishing a specific goal.”

• Method: “a means or manner of procedure, especially a regular and systematic way of accomplishing something [action].”

• Tool: “something used in the performance of an operation [method].”

Page 7: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

• Phase 1 – State of Practice Review– Comprehensive literature review– Detailed agency interviews– Potential Strategies, Methods, and

Tools (SMTs)

• Phase 2 – Guidance Document– Guidance development around SMTs– Guidance testing and validation– Implementation

DevelopmentTwo-Phase Approach

Page 8: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 8-49Guidebook Results

• 18 primary cost escalation factors• 8 Strategies to address cost escalation factors• 30 implementation Methods• 90 Tool applications• 1 agency level process map• 3 generic CE/CM process maps for project development phases

Page 9: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

1. Bias2. Delivery/Procurement Approach3. Project Schedule Changes4. Engineering and Construction Complexities5. Scope Changes6. Scope Creep7. Poor Estimating 8. Inconsistent Application of Contingencies9. Faulty Execution10. Ambiguous Contract Provisions11. Contract Document Conflicts1. Local Concerns and Requirements2. Effects of Inflation3. Scope Changes4. Scope Creep5. Market Conditions6. Unforeseen Events7. Unforeseen Conditions

Inte

rnal

Exte

rnal Cost Escalation

Factors

Page 10: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

1. Management2. Scope/Schedule3. Off Prism4. Risk5. Project Delivery/Procurement6. Document Quality7. Estimate Quality8. Integrity

Page 11: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 8-49Guidebook Results

Example Strategy

Estimate Quality Strategy

Use Qualified Personnel and UniformApproaches to Achieve Improved

Estimate Accuracy

Cost Escalation Factors

Engineering and Construction ComplexitiesPoor Estimating

Page 12: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Example Methods in Programming (aka Scoping)

• Consistency• Document Estimate Assumptions and

Basis• Creation of a Project Baseline

NCHRP 8-49Guidebook Results

Why?

Project Complexity

Tips for Success

Tool

s

Page 13: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 8-49Guidebook Results

Illustration

Creation of Project Baseline Method in Programming

Why – Need a cost performance benchmark

Project Complexity – Required for every project

Tips for Success – Major project elements must be defined

Tools – Project BaselineCost Containment TableScope Change Form

Page 14: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 8-49Guidebook Results

Example Tools in Programming• Standardized Estimating and Cost

Management Procedures• Project Estimate File• Project Baseline

Tips Resources

What is it?Why What does it do?When Examples

Page 15: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 8-49Guidebook Results - Illustration

Project Baseline in Programming

What is it? – Sets basis for controlling costs

Why? – Cost management cannot be performed effectivelywithout a baseline budget

What does it do? – Provides management with a tool for makingdecisions when changes occur

When – Project is programmed

Examples – WSDOT Scoping Process

Tips – Need certain level of detail to track changes

Resources – Principled Based Project Management - Chapman

Page 16: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Basic Process StepsDefine Scope (Input)Estimating Process

– Determine Estimate Basis– Prepare Base Estimate– Determine Risk/Set

Contingency– Review Estimate

Page 17: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Basic Process StepsEstimate Management

– Obtain Approvals– Communicate– Monitor for Change– Evaluate Change– Adjust Baseline

Estimate

Page 18: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Cost EstimatingAnd Cost EstimateManagementduring Programming

NCHRP 8-49Guidebook Results

Page 19: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Advances

• Minnesota DOT – Technical Reference Manual• NCHRP Report 625 – Right of Way Cost

Estimation and Management• NCHRP Report 658 – Risk Management• Texas A&M MS Thesis – Sliding Scale

Contingency Assessment• TxDOT Synthesis – Construction Unit Cost

Development• NCHRP 20-7, Task 278 – Practical Guide to

Estimating

Page 20: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Moving From Theory to Practice:Can We Avoid These Situations?

Image003.jpg

Page 21: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

“Theory to Practice”

• Framework – NCHRP Report 574 and Mn/DOT Scoping Process

• Methodology with rigor• Industry involvement –

Mn/DOT Professionals• Academics with right

industry experience• Know user expectations• Deliverable – “How to”

Manual

How?

Page 22: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Development

Conversion

Process Model

Page 23: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

23

Total Project Cost ComponentsTOTAL PROJECT COST ESTIMATE

ITEM

CATEGORY

ELEMENT

Project Development; State Share of Letting; Utilities; Railroads; and so on

Related Work (e.g. Excavation; Paving; Bridges; etc)

Specific Work with Unique Number (e.g. 2105607/00021: Excavation-Common

2105607/00025: Excavation-Subgrade)

GROUP

DIVISION

RAW TOTAL Total Before Inflation

Engineering, Construction and Right-of-Way

Engineering; Internal; Primary Construction; Letting; and so on.

Page 24: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

24

Gated Process

Gn GATES

PREPARE PLANNING REPORT

APPROVED PLANNING REPORT

PERIODIC HIP PROJECT COST

UPDATES

ENTER AND CONTINUE IN

HIP

ENTER STIP

PREPARE SCOPING REPORT

APPROVED SCOPING REPORT

ANNUAL STIP PROJECT COST AMENDMENT(S)

PREPARE DESIGN

APPROVED FINAL

DESIGN PS&E

SOLICIT/ APPROVE BID PRICE

APPROVED DISTRICT DESIGN

SUBMITTAL LETTER

LETTING PHASE

CONSTRUCTION PHASE

G1

G2A

G2B

G3

G4

G5

G6

G7

G1: To Enter HIPG2: To Proceed to ScopingG3: To Enter STIPG4: To Remain in STIP/ Proceed to DesignG5: To Proceed to LettingG6: To Solicit/ Approve Bid Price

G7: To Proceed to Construction

Planning Phase HIP (Program) Scoping Phase STIP (Program) Design Phase Letting Phase Post-Letting

Page 25: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

“Theory to Practice”Right of Way

• Framework – NCHRP Report 574

• Developing a “How To” Guide

• Interviews with ROW Experts

• Adapted CE/CM Process for ROW

• Expended ROW Tools

How?

Page 26: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

ROWResearchResults

ProceduresGuide

Development

Page 27: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

“Theory to Practice”Risk Management

• Framework – NCHRP Report 574 and the MnDOT TRM

• Developed “How To” Guide

• Case Studies in Risk Management

• Guidebook Format Similar to ROW Guide

• Expand Risk Management Tools

How?

Project Development Phases

Project Complexity

Page 28: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Cost Estimate at Any Phase

Total Project Estimate = Base + Contingency (plus inflation)

Reflects Estimated Dollars Associated with Uncertainty

Page 29: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Risk Management Process Framework

Assess/AnalyzeAllocate

Monitor and

ControlIdentify

MitigateandPlan

Risk Management

Process

Scalable for Project ComplexityAdaptable to Project Development Phases

Estimating

Contingency

Cost Management

Update Contingency

Page 30: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Pro

ject

Cos

t

Project Development Process

Planning Preliminary Design

FinalDesign

Cost Range

Programming

Contingency

Base Estimate

Contingency

Base Estimate

Contingency

Base Estimate

Base Estimate

Baseline Estimate & Total Project Cost Estimate

Cost Estimates and Contingency(w/Total Project Cost Estimate = Baseline Estimate)

Page 31: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

“Theory to Practice”Risk Management

• NCHRP Report 658 Tool

• Test Ohio Sliding Scale Contingency Concept

• Delphi Technique• Develop Sliding Scales

for Three Levels of Project Complexity

• Tie to Risk Management Process

Idea?

Ohio DOT

Project Complexity

Page 32: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

The Delphi Technique

Round 1 Group Response AnalysisControlled Feedback in round 2Round 2 Group Response AnalysisControlled Feedback in subsequent rounds

Page 33: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Moderately Complex Projects

0

10

20

30

40

50

60

70

80

1 1.5 2 2.5 3 3.5 4 4.5 5

Perc

ent C

ontin

genc

y

Phase of Project Development

Sliding Contingency Scale

Low MLEHigh

Planning Programming Design 1 Design 2 Design 3

Page 34: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Construction Unit CostsDatabase

Idea?

• Framework – NCHRP Report 574 CE Process Flowchart

• Tie Historic Database toEstimating Base Costs

• Survey and Interviews• Compile Results• Illustrate Different

Requirements• Proposed Unit Cost

Development Framework

Project Development Phases

Page 35: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Construction Unit CostsDatabase

Submitted Bids

Acquiring Unit Cost- Information Systems

- Type of Historical Bid Data

Storing Unit Cost- Information Systems- Calendar Duration

- Listing of Historical Data- Categories of Historical Data

Historical database

Accessing Unit Cost- Information Systems

Applying Unit Cost- Calendar Duration

- Statistical Technique- Number of Bids

- Factors influencing Unit Prices

General- Estimating Techniques & Tools

- Innovative Approach

Prepare Base Estimates

Determine Risk/Contingency

Unit Cost Development Framework

Page 36: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

NCHRP 20-7, Task 278Cost Estimating Guide

• Create a National Standard Approved by AASHTO• Sponsor – AASHTO Subcommittee on Design, Technical

Committee on Cost Estimating• Focus on Key Estimating Techniques• Tie to Generic Estimating Process (Report 574)• Content

– Parametric– Risk Based– Bid Based– Cost Based

• Under Development

Page 37: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Current Environment

• Economic Downturn

• ARRA Projects

• Resource Constraints

• Market Conditions

Page 38: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Ten Key Principles

• Complete every step in the cost estimate process

• Document estimate basis• Identify risks• Anticipate external cost influences• Perform estimate reviews

Cost Estimating Practice

Page 39: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Ten Key Principles

• Make estimating a priority• Set a project baseline cost estimate• Create cost control mechanisms• Create estimate transparency• Protect estimators

Cost Estimate Management

Page 40: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Issues and Challenges

Page 41: Capacity Building Workshop NCHRP Report 574 and Beyond ...Capacity Building Workshop Stuart Anderson, PhD, PE Texas A&M University. Minneapolis, Minnesota. August 11, 2010. NCHRP Report

Questions, Answers, and Discussion!