Capacity Building Workshop
Stuart Anderson, PhD, PETexas A&M University
Minneapolis, MinnesotaAugust 11, 2010
NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going?
Outline• History
• Advances
• Current Environment
• Wrap Up
• Discussion
State Highway Agencies face a major challenge is controlling project budgets over the time span between the initiation of a project and the completion of construction.
The Problem
Consistency and Accuracy
Strategic Focus Definitions
• Strategy: “a plan of action intended on accomplishing a specific goal.”
• Method: “a means or manner of procedure, especially a regular and systematic way of accomplishing something [action].”
• Tool: “something used in the performance of an operation [method].”
• Phase 1 – State of Practice Review– Comprehensive literature review– Detailed agency interviews– Potential Strategies, Methods, and
Tools (SMTs)
• Phase 2 – Guidance Document– Guidance development around SMTs– Guidance testing and validation– Implementation
DevelopmentTwo-Phase Approach
NCHRP 8-49Guidebook Results
• 18 primary cost escalation factors• 8 Strategies to address cost escalation factors• 30 implementation Methods• 90 Tool applications• 1 agency level process map• 3 generic CE/CM process maps for project development phases
1. Bias2. Delivery/Procurement Approach3. Project Schedule Changes4. Engineering and Construction Complexities5. Scope Changes6. Scope Creep7. Poor Estimating 8. Inconsistent Application of Contingencies9. Faulty Execution10. Ambiguous Contract Provisions11. Contract Document Conflicts1. Local Concerns and Requirements2. Effects of Inflation3. Scope Changes4. Scope Creep5. Market Conditions6. Unforeseen Events7. Unforeseen Conditions
Inte
rnal
Exte
rnal Cost Escalation
Factors
1. Management2. Scope/Schedule3. Off Prism4. Risk5. Project Delivery/Procurement6. Document Quality7. Estimate Quality8. Integrity
NCHRP 8-49Guidebook Results
Example Strategy
Estimate Quality Strategy
Use Qualified Personnel and UniformApproaches to Achieve Improved
Estimate Accuracy
Cost Escalation Factors
Engineering and Construction ComplexitiesPoor Estimating
Example Methods in Programming (aka Scoping)
• Consistency• Document Estimate Assumptions and
Basis• Creation of a Project Baseline
NCHRP 8-49Guidebook Results
Why?
Project Complexity
Tips for Success
Tool
s
NCHRP 8-49Guidebook Results
Illustration
Creation of Project Baseline Method in Programming
Why – Need a cost performance benchmark
Project Complexity – Required for every project
Tips for Success – Major project elements must be defined
Tools – Project BaselineCost Containment TableScope Change Form
NCHRP 8-49Guidebook Results
Example Tools in Programming• Standardized Estimating and Cost
Management Procedures• Project Estimate File• Project Baseline
Tips Resources
What is it?Why What does it do?When Examples
NCHRP 8-49Guidebook Results - Illustration
Project Baseline in Programming
What is it? – Sets basis for controlling costs
Why? – Cost management cannot be performed effectivelywithout a baseline budget
What does it do? – Provides management with a tool for makingdecisions when changes occur
When – Project is programmed
Examples – WSDOT Scoping Process
Tips – Need certain level of detail to track changes
Resources – Principled Based Project Management - Chapman
Basic Process StepsDefine Scope (Input)Estimating Process
– Determine Estimate Basis– Prepare Base Estimate– Determine Risk/Set
Contingency– Review Estimate
Basic Process StepsEstimate Management
– Obtain Approvals– Communicate– Monitor for Change– Evaluate Change– Adjust Baseline
Estimate
Cost EstimatingAnd Cost EstimateManagementduring Programming
NCHRP 8-49Guidebook Results
Advances
• Minnesota DOT – Technical Reference Manual• NCHRP Report 625 – Right of Way Cost
Estimation and Management• NCHRP Report 658 – Risk Management• Texas A&M MS Thesis – Sliding Scale
Contingency Assessment• TxDOT Synthesis – Construction Unit Cost
Development• NCHRP 20-7, Task 278 – Practical Guide to
Estimating
Moving From Theory to Practice:Can We Avoid These Situations?
Image003.jpg
“Theory to Practice”
• Framework – NCHRP Report 574 and Mn/DOT Scoping Process
• Methodology with rigor• Industry involvement –
Mn/DOT Professionals• Academics with right
industry experience• Know user expectations• Deliverable – “How to”
Manual
How?
Development
Conversion
Process Model
23
Total Project Cost ComponentsTOTAL PROJECT COST ESTIMATE
ITEM
CATEGORY
ELEMENT
Project Development; State Share of Letting; Utilities; Railroads; and so on
Related Work (e.g. Excavation; Paving; Bridges; etc)
Specific Work with Unique Number (e.g. 2105607/00021: Excavation-Common
2105607/00025: Excavation-Subgrade)
GROUP
DIVISION
RAW TOTAL Total Before Inflation
Engineering, Construction and Right-of-Way
Engineering; Internal; Primary Construction; Letting; and so on.
24
Gated Process
Gn GATES
PREPARE PLANNING REPORT
APPROVED PLANNING REPORT
PERIODIC HIP PROJECT COST
UPDATES
ENTER AND CONTINUE IN
HIP
ENTER STIP
PREPARE SCOPING REPORT
APPROVED SCOPING REPORT
ANNUAL STIP PROJECT COST AMENDMENT(S)
PREPARE DESIGN
APPROVED FINAL
DESIGN PS&E
SOLICIT/ APPROVE BID PRICE
APPROVED DISTRICT DESIGN
SUBMITTAL LETTER
LETTING PHASE
CONSTRUCTION PHASE
G1
G2A
G2B
G3
G4
G5
G6
G7
G1: To Enter HIPG2: To Proceed to ScopingG3: To Enter STIPG4: To Remain in STIP/ Proceed to DesignG5: To Proceed to LettingG6: To Solicit/ Approve Bid Price
G7: To Proceed to Construction
Planning Phase HIP (Program) Scoping Phase STIP (Program) Design Phase Letting Phase Post-Letting
“Theory to Practice”Right of Way
• Framework – NCHRP Report 574
• Developing a “How To” Guide
• Interviews with ROW Experts
• Adapted CE/CM Process for ROW
• Expended ROW Tools
How?
ROWResearchResults
ProceduresGuide
Development
“Theory to Practice”Risk Management
• Framework – NCHRP Report 574 and the MnDOT TRM
• Developed “How To” Guide
• Case Studies in Risk Management
• Guidebook Format Similar to ROW Guide
• Expand Risk Management Tools
How?
Project Development Phases
Project Complexity
Cost Estimate at Any Phase
Total Project Estimate = Base + Contingency (plus inflation)
Reflects Estimated Dollars Associated with Uncertainty
Risk Management Process Framework
Assess/AnalyzeAllocate
Monitor and
ControlIdentify
MitigateandPlan
Risk Management
Process
Scalable for Project ComplexityAdaptable to Project Development Phases
Estimating
Contingency
Cost Management
Update Contingency
Pro
ject
Cos
t
Project Development Process
Planning Preliminary Design
FinalDesign
Cost Range
Programming
Contingency
Base Estimate
Contingency
Base Estimate
Contingency
Base Estimate
Base Estimate
Baseline Estimate & Total Project Cost Estimate
Cost Estimates and Contingency(w/Total Project Cost Estimate = Baseline Estimate)
“Theory to Practice”Risk Management
• NCHRP Report 658 Tool
• Test Ohio Sliding Scale Contingency Concept
• Delphi Technique• Develop Sliding Scales
for Three Levels of Project Complexity
• Tie to Risk Management Process
Idea?
Ohio DOT
Project Complexity
The Delphi Technique
Round 1 Group Response AnalysisControlled Feedback in round 2Round 2 Group Response AnalysisControlled Feedback in subsequent rounds
Moderately Complex Projects
0
10
20
30
40
50
60
70
80
1 1.5 2 2.5 3 3.5 4 4.5 5
Perc
ent C
ontin
genc
y
Phase of Project Development
Sliding Contingency Scale
Low MLEHigh
Planning Programming Design 1 Design 2 Design 3
Construction Unit CostsDatabase
Idea?
• Framework – NCHRP Report 574 CE Process Flowchart
• Tie Historic Database toEstimating Base Costs
• Survey and Interviews• Compile Results• Illustrate Different
Requirements• Proposed Unit Cost
Development Framework
Project Development Phases
Construction Unit CostsDatabase
Submitted Bids
Acquiring Unit Cost- Information Systems
- Type of Historical Bid Data
Storing Unit Cost- Information Systems- Calendar Duration
- Listing of Historical Data- Categories of Historical Data
Historical database
Accessing Unit Cost- Information Systems
Applying Unit Cost- Calendar Duration
- Statistical Technique- Number of Bids
- Factors influencing Unit Prices
General- Estimating Techniques & Tools
- Innovative Approach
Prepare Base Estimates
Determine Risk/Contingency
Unit Cost Development Framework
NCHRP 20-7, Task 278Cost Estimating Guide
• Create a National Standard Approved by AASHTO• Sponsor – AASHTO Subcommittee on Design, Technical
Committee on Cost Estimating• Focus on Key Estimating Techniques• Tie to Generic Estimating Process (Report 574)• Content
– Parametric– Risk Based– Bid Based– Cost Based
• Under Development
Current Environment
• Economic Downturn
• ARRA Projects
• Resource Constraints
• Market Conditions
Ten Key Principles
• Complete every step in the cost estimate process
• Document estimate basis• Identify risks• Anticipate external cost influences• Perform estimate reviews
Cost Estimating Practice
Ten Key Principles
• Make estimating a priority• Set a project baseline cost estimate• Create cost control mechanisms• Create estimate transparency• Protect estimators
Cost Estimate Management
Issues and Challenges
Questions, Answers, and Discussion!