caissons new
TRANSCRIPT
CAISSONS
GROUP 06
CONTENTS What is caisson? Materials used for construct a caisson Design aspects of caisson Types of caisson Open caisson Pneumatic caisson Box caisson Comparison between the types of caissons Failures of caissons Applications of caisson Illustrative example
WHAT IS CAISSON ?
A caisson is a structure used in construction and engineering, particularly underwater projects. Its purpose is to provide a dry, protected environment for workers and construction materials.
It’s a form of deep foundation which are constructed above ground level, then sunk to the required level by excavating or dredging material from within the caisson as a single unit.
1
2
MATERIALS USED FOR CONSTRUCT A CAISSONS
Depending upon the importance and magnitude of the job there are three types of materials which are used to construct a caisson. 1.Timber - Timber is much less used these days than steel and
reinforced Concrete & comparatively high cost.
2.Steel - It provides the necessary weight to aid in the sinking process, which is more continuous, and relatively faster when compared with Caissons built of reinforced Concrete.
3.Reinforced concrete - It utilizes concrete for the dual purpose of providing the necessary
strength and the dead weight for sinking. It is more economical. 3
DESIGN ASPECTS OF CAISSON
1. Shape & size
2. Design loads
3. Allowable bearing pressure
4. Skin friction & sinking effort
5. Concrete seal
6. Cutting edge
4
1. Shape & size Caissons are constructed with practically straight and
vertical sides from top to bottom. The shape of a Caisson in plan may be Circular, Square, Rectangular, Octagonal, Twin-Circular, Twin-Rectangular, Twin-Hexagonal, Twin- Octagonal, or Double-D
5
Sometimes, the choice of shape of a Caisson is influenced by its size and by the shape of the superstructures.
Twin-Circular, Twin-Rectangular, Twin-Hexagonal, Twin-Octogonal, and the Double-D types are used to support heavy loads from large bridge piers.
The size of a Caisson is governed by the following factors:
Size of Base Bearing Pressure Practical Minimum Size
6
2. Design loads A Caisson must be designed to resist all kinds of
loads which may act at different times during service Dead Loads Live Loads Impact Loads Wind Loads Water Pressure Longitudinal Force Earth Pressure Centrifugal Force Seismic Forces Resultant Force
7
3. Allowable bearing pressure Caissons are carried to a hard stratum, such as
compact sand, hard clay, gravel, or rock and never to a soft stratum or weathered rock. The Net allowable bearing pressure, Qnet, for a Caisson in cohesionless soil may be obtained from the following equation;
Where;
B = Smaller dimension of the Caisson, m
Df = Depth of Foundation below scour level, m
N = Standard penetration number (corrected)
Rγ and Rq = Correction Factors for Water Table
Qnet = 0.22N2BRγ + 0.67(100 + N2) Df · Rq
8
9
The factor of safety is 3 and Qnet will be got in kN/m2. In the case of pure clays, undisturbed samples should be tested to determine the value of cohesion, C. The ultimate bearing capacity Qult is obtained from;
Where;
Qult = Ultimate bearing capacity, kN/m2
C = Unit Cohesion, kN/m2
Nc = Bearing capacity factor
The allowable bearing pressure of Caissons resting on Rock should not exceed that for the concrete seal. Since the seal is in water or in adverse working conditions, the allowable bearing pressure is usually limited to 3,500 kN/m2
Qult = C.Nc
10
4. Skin friction & sinking effort
Skin Friction is the shearing resistance between the soil and the exterior surface of the caisson, encountered during the process of sinking.
Caissons are usually designed to have sufficient weight in each lift to overcome skin friction to facilitate the sinking process.
Occasionally, the use of water jets on the sides tends to reduce the skin friction. Even the injection of bentonite solution on to the exterior of the well has been found to reduce skin friction.
11
Values of the skin friction vary within a wide range for each type of soil. Terzaghi and Peck (1948) give the following values
If it is desired to proportion a circular Caisson such that no ballast is required for sinking, the self-weight should be at least equal to the force due to Skin Friction.
12
This leads us to the Equation
where ;
De and Di = External and Internal diameters of the Caisson
D = Depth of Penetration
γc = Unit weight of the Caisson Material
f = Unit Skin Friction.13
5. Concrete seal After the Caisson is placed in its final position a
thick concrete layer is placed at the bottom to plug it. This is known as ‘Concrete Seal’ or ‘Plug’, and forms the permanent base for the Caisson.
The thickness of the seal should be sufficient to withstand the upward hydrostatic pressure after dewatering is complete and before concreting of the Caisson shaft is done.
The seal may be designed as a thick plate subjected to uniform pressure due to maximum vertical loads from the Caisson.
14
The thickness of the concrete seal, t, may be obtained from the following equations:
These are for simply supported conditions.
Here; Di = Internal diameter of caisson
α = Bi/Li
Li , Bi = Internal length and breadth of caisson
q = Net upward pressure on the seal
σc = Allowable flexural stress for concrete (≤ 3,500 kN/m2)
For Circular Caissonst = 0.59Di q
σc
For Rectangular Caissons
t = 0 866.Bi q σc ( 1+ 1.61α )
√
√
15
6. Cutting edge The Cutting Edge protects the walls of the Caisson
against impact and obstacles encountered during penetration.
A cutting edge is usually made of angles and plates of structural steel or reinforced concrete and steel. Since sharp edges are easily damaged, blunt edges are more commonly used.
To avoid tearing off the cutting edge, the shell concrete must be anchored to the cutting edge.
16
TYPES OF CAISSONS
Open caisson Pneumatic caisson Box caisson
17
OPEN CAISSONS The top & bottom of the
caisson is open during construction.
They may have any shape in plan as round, oblong, oval,rectangular, etc.
Open Caissons are normally used on sandy soils or soft bearing stratum and where no firm bed is available at a higher depth. 18
Components of open caisson Topping
Covering provided over the
caisson is called as topping.
Sand is filled in between
topping and bottom plug.
Topping also acts as a part
of shuttering for laying the
well cap.
Bottom plug
The lower portion of caisson
is sealed by the concrete is
called as bottom plug 19
Steining
Steining is constructed in concrete or masonry work. Use of steining is to provide dead load during sinking operation
Well curbs
It is a transition member between the sharp cutting edge and the thick steining. It is thus tapering in shape. It is usually made of reinforced concrete as it is subjected to severe stresses during the sinking process
Well caps
R.C.C Slab covering provided over the top of well is termed as well cap
Sand filling
The portion between top and bottom plug is filled with sand so as to increase the self weight of the well and makes safe during earthquake. 20
Construction method of open caisson
The open-end caisson usually has a cutting edge. It is first fabricated at the site & the first segment of the shaft is built on it.
Then the soil inside the shaft is removed by grab buckets & the segment sunk vertically.
Another segment is added to the top & the process of sinking is continued by excavating the soil inside.
After the required depth is reached, concrete is placed under water on the open bottom as seal to a depth that will contain the hydrostatic uplift pressure.
Finally the concrete seal is completely cured, the water in the caisson can be pumped out.
21
22
Advantages & disadvantages of open caisson
Advantages Disadvantages
The caisson can be constructed to greater depths.
The clearing and the inspection of the bottom of the caisson cannot be done
The construction cost is relatively low
Concrete seal placed in water will not be satisfactory
The rate of progress will be slowed down if boulders are met during construction
The help of divers may be required for excavation near haunches at the cutting edges
23
PNEUMATIC CAISSONS This type of caisson is
open at the bottom and close at the top & it is used at the place where it is not possible to construct the well.
The working chamber at the bottom of the caisson is kept dry by forcing out water under air pressure.
Pneumatic Caissons are suitable in soft soils with danger of scour and erosion
24
Components of pneumatic caisson Working Chamber
This is made of structural steel,
about 3 m high, with a strong roof,
and is absolutely air tight. It helps to
prevent entry of water and soil into
it.
Air Shaft
This is a vertical passage which
connects the working chamber with
an airlock. It is provide access to the
working chamber for workmen &
also used to transport the excavated
material to the ground surface. 25
Air Lock
This is a steel chamber provided at the upper end of the air shaft above the water level. Its function is to permit the workmen to go in or come out of the caisson without releasing the air pressure in the working chamber.
Miscellaneous Equipment
It is the equipment such as motors, pressure pumps, and compressors are usually located outside at bed level. Pressure in the working chamber is maintained through an air pipe connected to a compressor.
26
Construction method of pneumatic caisson The cutting edge is carefully positioned & compressed
air is introduced into the working chamber to keep off mud and water.
After dewatering the working chamber keep it to dry. As workmen carry out the excavation in the dry, the
caisson gradually sinks. After the caisson has reached the desired depth, the
working chamber is filled with concrete. The air pressure in the chamber is kept constant till the
concrete has hardened up to the roof level. The shaft tubes are then dismantled, and finally, the shaft
itself is filled with lean concrete.27
Advantages & disadvantages of pneumatic caisson
Advantages Disadvantages
Control over the work & preparation of foundation for the sinking of caisson are better since the work is done in dry
Extreme care is required for the proper working of the system
The caisson can be sunk vertically as careful supervision is possible
The depth of penetration below water is limited to about 35m (3.5 kg/cm3).
The bottom of the chamber can be sealed effectively with concrete as it can be placed dry.
A lot of inconvenience is caused to the workmen while working under compressed air pressure, and they may be afflicted with caisson disease.
Obstruction to sinking, such as boulders can be removed easily.
Construction cost is quite high.
28
BOX CAISSONS In here the bottom is
closed. This type of caissons is
first cast on land & then towed to the site & then sunk on to a previously leveled foundation base. It is sunk by filling inside with sand, gavel, concrete or water.
The box type of casing is also called as floating caisson
29
Components of box caisson Concrete cap
It is for received the loads from the superstructure
Rip rap
To prevent scour, rip rap is placed around the base
Sand or gravel
It is invariably used as the ballast inside the caisson to aid the sinking process. Concrete is seldom used to fill a box caisson. 30
Construction method of box caisson Preparation & paving construction Bottom rebar binding (rebar fabrication) Bottom formwork erection (formwork fabrication) Bottom concrete casting after concrete testing Bottom Formwork Removal and Curing Upper Rebar Cage Installation (Rebar Cage Binding) Upper Formwork Upper Concrete Casting Upper Formwork Removal Inspection and Mark Launching of a casted caisson (Heavy duty marine air
bags were used to move a caisson on yard premises) Placing of Caissons
31
Advantages & disadvantages of box caisson
Advantages Disadvantages
Since floating caissons are precast, good quality can be ensured
The foundation bed has to be leveled before installing the caisson
The installation of a floating caisson is quick and convenient
Deep excavation for seating the caissons at the required depth is very difficult below water level
Floating caissons are less expensive than other types; they may also be transported at a low cost by floating
Due care has to be taken to protect the foundation from scour
The bearing capacity of the base should be assessed in advance 32
COMPARISON BETWEEN THE TYPES OF CAISSONSOpen of monolith Pneumatic Box or floating
Relatively low cost High construction cost due to use of compressed air in working chamber
Construction cost is low
Can extend to great depths
Depth is limited to a maximum of 35 m below the outer side water level
Shallow depth of excavation
Bottom of caisson cannot be easily inspected ,cleaned and tested physically
Bottom of the caisson can be easily inspected, cleaned and tested as the working chamber is kept dry
Bottom of caisson can only be inspected by divers with difficulty
Concrete placed under water is of doubtful quality
Concrete placed in dry condition is good & reliable
Construction of caisson in control condition & of known quality
Relatively difficult to control plumbness
Easier to control plumbness than open caisson
Plumbness requires preparation of level seating surface. Provision for protecting against scour must be made.
Slow construction if boulders or logs are encountered
Obstructions like boulders or logs can be easily removed
Only less compacted material is removed & bearing layer is not well compacted
33
FAILURES OF CAISSONSThere are two types of failures of caissons. They are;
1. Tilting
2. Shifting
The well should be sunk straight and vertical at the correct position. Sometimes the well tilts onto one side or it shifts away from the desired position.
The following precautions may be taken to avoid tilts and shifts: The outer surface of the well curb and steining should be smooth. The curb diameter should be kept 40 to 80 mm larger than the outer
diameter of the steining, and the well should be symmetrically placed.
The cutting edge should be uniformly thick and sharp. Dredging should be done uniformly on all sides and in all the
pockets.34
Remedial Measures for Rectification of Tilts and Shifts
Remedial measure Figure Description
Regulation of Excavation
The higher side is grabbed more be regulating the dredging. If it is not initial stage, the caisson may be dewatered if possible & open excavation may be carried out on the higher side.
Eccentric Loading
Eccentric placing of the kentledge may be resorted to provide greater sinking effort on the higher side. depth of sinking increases, with heavier kentledge
35
Water Jetting
If water jets are applied on the outer face of the well on the higher side, the friction is reduced on that side, and the tilt may get rectified.
Pulling the caisson
Pulling the well to the higher side by placing one or more steel ropes round the well, with vertical sleepers packed in between to distribute pressure over larger areas of well steining, is effective.
36
Pushing the Well with Jacks
Tilt can be rectified by pushing the well by suitably arranging mechanical or hydraulic jacks. In actual practice, a combination of two or more of these approaches may be applied successfully
Strutting the caisson
The well is strutted on its tilted side with suitable logs of wood to prevent further tilt. The well steining is provided with sleepers to distribute the load from the strut. The other end of the logs rest against a firm base having driven piles
37
APPLICATIONS OF CAISSON
Foundation for bridge piers and abutments in lakes, rivers, and seas, breakwaters and other shore protection works
38
large water-front structures such as pump houses, subjected to huge vertical and horizontal forces.
Occasionally caissons, especially Pneumatic Caissons, have been used as foundations for large and tall multi-storey buildings and other structures.
39
Illustrative example
40
37
the table given under the concrete seal
41
SUMMARY
A Caisson is a type of foundation, built above ground level and sunk to the required depth as a single unit.
Caissons are broadly classified as Open Caissons, Pneumatic Caissons, and Floating or Box Caissons.
Caissons are mostly used as foundations for bridge piers and abutments, and water-front structures, as also for multi-storey buildings occasionally.
How to solve a small problem to find out the parameters of the caisson according to the design aspects.
42
ANY QUESTIONS…….?
THANK YOU
57
58