cable details and grid connection statement - forewind - · pdf file4.3 inter-array subsea...
TRANSCRIPT
August 2013
Cable Details and Grid
Connection Statement
Pursuant to Regulation 6(1)(b)(i) of the Infrastructure Planning
(Applications: Prescribed Forms and Procedure) Regulations 2009
Application reference: 7.2
DOGGER BANK CREYKE BECK
This page is intentionally blank
DOGGER BANK CREYKE BECK
Title:
Cable Details and Grid Connection Statement
Contract No. (if applicable)
Onshore / Offshore
Document Number:
F-ELC-SP-001
Issue No:
3
Issue Date:
11-08-13
Status:
Issued for 1st. Technical Review
Issued for 2nd. Technical Review
Issued for PEI3
Issued for Application
Prepared by: Fabio Spinato
Checked by: Melissa Read
Approved by:
David Flood
Signature / Approval meeting
David Flood
Approval Date:
13/01/2013
Revision History
Date Issue No. Remarks / Reason for Issue Author Checked Approved
25/07/13 1 Internal review MR FS 08/08/13
08/08/13 2 Final for approval MR DF 11/08/13
13/08/13 3 SMT sign off MR SMT 13/08/13
DOGGER BANK CREYKE BECK
Contents
1 Introduction and summary ............................................................................................. 1
2 Project overview ............................................................................................................ 3
2.1 Background ......................................................................................................... 3
2.2 Project description .............................................................................................. 3
2.3 Site selection ....................................................................................................... 3
2.4 Operation ............................................................................................................ 4
3 Proposed cable routes .................................................................................................. 5
3.1 Cable route ......................................................................................................... 5
3.2 Onshore converter station and substation location ............................................. 7
4 Offshore electrical system ............................................................................................. 9
4.1 Overview ............................................................................................................. 9
4.2 Wind turbine generators .................................................................................... 10
4.3 Inter-array subsea cables ................................................................................. 10
4.4 Offshore collector platform ................................................................................ 11
4.5 Inter-platform subsea cables ............................................................................. 12
4.6 Offshore converter platform .............................................................................. 13
4.7 Export system HVDC subsea cables ................................................................ 13
5 Offshore cable installation ........................................................................................... 15
5.1 Pre-installation works ........................................................................................ 15
5.2 Offshore cable installation methods .................................................................. 15
5.3 Crossing of existing infrastructures ................................................................... 17
6 Onshore electrical system ........................................................................................... 18
6.1 Overview ........................................................................................................... 18
6.2 Landfall transition joint bay................................................................................ 18
6.3 Export system HVDC underground cables........................................................ 18
6.4 Onshore converter substation ........................................................................... 19
6.5 Export system HVAC cables ............................................................................. 20
6.6 Connection works at Creyke Beck substation ................................................... 21
7 Onshore electrical system installation ......................................................................... 23
7.1 Onshore HVDC cable corridor .......................................................................... 23
7.2 Onshore cable installation methods .................................................................. 25
7.3 Onshore crossings ............................................................................................ 26
7.4 Onshore construction compounds .................................................................... 26
8 Conclusion .................................................................................................................. 28
DOGGER BANK CREYKE BECK
Table of Figures
Figure 1: The offshore export cable corridor ................................................................. 5
Figure 2: The onshore export cable corridor ................................................................. 7
Figure 3: Visualisation of proposed converter station siting .......................................... 8
Figure 4: A representation of the offshore electrical system ......................................... 9
Figure 5: An example inter-array layout connecting the collector substation .............. 10
Figure 6: Example of 33kV, three-core, XLPE insulated, armoured subsea cable ...... 11
Figure 7: Typical offshore collector platform design. .................................................. 12
Figure 8: Example of 245kV, three-core, XLPE insulated, armoured, subsea cable ... 13
Figure 9: Example of a subsea HVDC cable ............................................................... 14
Figure 10: Typical HVDC, underground cable. ............................................................ 19
Figure 11: An illustrative converter substation layout ................................................. 20
Figure 12: A 400kV XLPE insulated underground copper conductor cable ................. 21
Figure 13: Indicative onshore cable route working widths based on two illustrative
construction options for an HVDC section ................................................................... 24
Figure 14: Indicative HDD construction compound (launch pit) .................................. 27
Figure 15: Indicative HDD construction compound (receiving pit) ............................... 28
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 1 © 2013 Forewind
1 Introduction and summary
1.1 Introduction
1.1.1 This Cable Details and Grid Connection statement is provided by Forewind Limited in
relation to the Dogger Bank Creyke Beck offshore wind farms.
1.1.2 Dogger Bank Creyke Beck comprises two proposed offshore wind farms to be
located within the Dogger Bank Zone in the North Sea. As the proposal is an offshore
generating station of more than 100 megawatts, under the Planning Act 2008 it is
classed as a Nationally Significant Infrastructure Project. Therefore, in order to gain
development consent and a deemed Marine Licence to construct and operate the
wind farms it is necessary to apply to the Major Applications and Plans Directorate of
the Planning Inspectorate for a Development Consent Order (DCO).
1.1.3 This statement accompanies the final application and is submitted alongside a draft
DCO, an Environmental Statement, a Consultation Report and other statutory and
non-statutory documents.
1.2 The scope of this document
1.1.4 This Cable Details and Grid Connection Statement provides details of the electrical
system which connects the wind turbines to the national electricity export system.
This comprises an offshore electrical system and an onshore electrical system. The
offshore system extends from each individual wind turbine generator, via collector
and converter platforms, to the cable landfall where the offshore cables are jointed to
the onshore cables in a landfall transition joint bay. The onshore electrical system
extends from this bay to the connection point at the existing National Grid Electricity
Transmission (NGET) 400kV Creyke Beck substation near Cottingham in the East
Riding of Yorkshire (hereafter referred to as the „Creyke Beck substation‟). The
entirety of the onshore cable route is provided through underground cables with no
overhead lines required.
1.1.5 The export system will be realised through high voltage direct current (HVDC)
technology, which requires a converter station at both ends of the export system for
the conversion between HVDC and high voltage alternating current (HVAC). The
converter modules will be mounted on specific platforms for offshore locations and in
dedicated converter buildings (converter substations) for onshore locations.
1.1.6 The application for development consent contains all of the above electrical grid
connection works required for Dogger Bank Creyke Beck. A requirement under
Regulation 6(1)(b)(i) of the Infrastructure Planning (Applications: Prescribed Forms
and Procedures) Regulations 2009 (the APFP Regulations) is that an application for
an offshore generating station must provide details of the proposed route and method
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 2 © 2013 Forewind
of installation of any cable with the application. In addition Regulation 5(2)(q) allows
for the submission of any other documents which are considered necessary to
support the application; it is considered the grid connection details fall within this
category.
1.1.7 This statement sets out the location, type and proposed installation methods for the
electrical system. Further detail on the project description and cable installation
methods can be found in Chapter 5 of the Environmental Statement.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 3 © 2013 Forewind
2 Project overview
2.1 Background
2.1.1 In January 2010, following a competitive tender process, The Crown Estate awarded
Forewind Limited (Forewind) the exclusive development rights for „Zone 3 Dogger
Bank‟; the largest of the Round 3 offshore wind farm zones. The Dogger Bank Zone
comprises an area of 8,660km2, and is located in the North Sea between 125km and
290km off the coast of Yorkshire. Forewind is a consortium comprising four leading
international energy companies (RWE, SSE, Statkraft and Statoil).
2.1.2 Dogger Bank Creyke Beck is the first application within the zone to be submitted to
the Planning Inspectorate for consent. The application comprises two offshore wind
farms; Dogger Bank Creyke Beck A and Dogger Bank Creyke Beck B, along with the
associated development necessary to enable connection to the national grid.
2.2 Project description
2.2.1 Dogger Bank Creyke Beck is located within Tranche A of the Dogger Bank Zone,
which lies over 125 kilometres (km) off the coast of Yorkshire. The connection point
to the electricity transmission network is proposed to be the existing Creyke Beck
substation. Further information on the location and design of the wind farms, the
cable corridor and substation is set out in the Environmental Statement. In addition
Part 1 of Schedule 1 of the draft Development Consent Order (DCO) describes the
works for which development consent is being sought.
2.2.2 The total maximum installed power of Dogger Bank Creyke Beck is proposed to be
2,400 megawatts (MW) (2.4 gigawatts (GW)). However, the electrical system is
designed to deliver up to 1,000 MW per project at the connection point. The purpose
of providing a higher installed capacity is to take account of several factors that
reduce the actual power being delivered to the network. These may include: wake
effect, wind turbine and electrical system availability, electrical losses and the
average expected capacity factor. The total connected power (also known as
transmission entry capacity) for the two projects is therefore 2,000 MW which will not
be exceeded.
2.3 Site selection
2.3.1 The selection of the cable corridor, connection point and landfall has been subject to
wide-ranging consultation with National Grid, statutory consultees and the local
community over the past few years. In addition, rigorous environmental assessment
has been undertaken and any likely significant effects on the environment have been
taken into account in the final site selection.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 4 © 2013 Forewind
2.3.2 Therefore, the route presented at this stage is the result of an iterative process taking
into account and balancing many constraints.
2.4 Operation
2.4.1 Generators have a choice around how the electrical assets to connect to the
transmission network are constructed. Generators can either construct the network
themselves or can instead opt for an Offshore Transmission Owner (OFTO) to do so.
If they construct the assets themselves, then the generator must transfer the assets
to an OFTO post-construction and installation. OFTOs are selected on a competitive
basis through a tender process run by Ofgem, the GB energy regulator.
2.4.2 At this application stage it has not yet been decided on how the electrical assets will
be constructed, so details of ownership cannot be provided within this document.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 5 © 2013 Forewind
3 Proposed cable routes
3.1 Cable route
3.1.1 The offshore export cables for Dogger Creyke Beck will be installed within one 2km
wide corridor as shown in Figure 1. A 2km wide corridor is considered necessary to
accommodate the maximum number of cables for both projects and provide flexibility
to microsite around any obstacles (such as wrecks) or features (such as biogenic
reef) that require avoidance. The Order Limits also includes an area 750 metres
either side of this cable corridor in which temporary construction activities may take
place, such as the use of anchor spreads for installation vessels. The export cable
corridor will extend predominantly approximately south-west from the south-western
corner of the development zone, to come ashore at the cable landfall zone on the
Holderness coastline, in the East Riding of Yorkshire. Each project will have two
HVDC power cables in a pair. The maximum total export cable length for high voltage
direct current (HVDC) cables, from the offshore platform to the landfall, is 420km for
Dogger Bank Creyke Beck A and 378km for Dogger Bank Creyke Beck B.
Figure 1: The offshore export cable corridor
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 6 © 2013 Forewind
3.1.2 In relation to Dogger Bank Creyke Beck B, the final exit point of the HVDC export
cable from the array areas has yet to be determined, so two options are presented in
the DCO; Work No. 2BA exits to the west and Work No. 2BC exits to the south
passing through Dogger Bank Creyke Beck A. Although considerable work has been
carried out on each of the routes presented in the Environmental Statement, flexibility
is needed as a balance between environmental and technical considerations will
need to be struck in choosing the most appropriate exit point once post-consent
design optimisation work has been carried out and the location of the converter
substation established. There is a provision in the draft Development Consent Order
that only one of these options can be constructed, not both.
3.1.3 The landfall for the offshore export cables is along the northern section of the
Holderness coastline, between Skipsea and Fraisthorpe, and the location is an area
approximately 1km wide located to the north of the village of Ulrome. At the landfall
the offshore HVDC export cables from both Dogger Bank Creyke Beck A and B will
be connected to the onshore HVDC cables within a landfall transition joint bay.
3.1.4 The onshore export cable route will consist of an approximately 30km long HVDC
section from the landfall transition joint bay to the onshore converter substation,
followed by an approximately 2km long HVAC section of cable to the Creyke Beck
substation which provides the connection point to the UK transmission network.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 7 © 2013 Forewind
Figure 2: The onshore export cable corridor
3.2 Onshore converter station and substation location
3.2.1 The development consent order includes a provision for two onshore converter
stations, one for each of the Creyke Beck projects, along with the works required to
connect to the existing National Grid substation at Creyke Beck.
3.2.2 Having determined the connection point would be the Creyke Beck substation, the
most appropriate location for the converter stations was subsequently determined. A
key factor in the site selection process was proximity to the connection point in order
to minimise the landscape and visual effects associated with introducing new
electricity infrastructure to the environment. The area selected is an agricultural area
located approximately 3km north-north west of the substation on the northern side of
the A1079. The indicative layout and expected dimensions of the converter
substations are illustrated in Figure 3.
3.2.3 Each converter station will convert HVDC export power to 400kV HVAC prior to
connection to the Creyke Beck substation.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 8 © 2013 Forewind
Figure 3: Visualisation of proposed converter station siting
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 9 © 2013 Forewind
4 Offshore electrical system
4.1 Overview
4.1.1 The offshore electrical system is comprised of the following elements:
wind turbine generators positioned in arrays;
inter-array subsea cables, connecting the wind turbines to the offshore collector
platform(s). The inter-array cable system is rated at nominal voltage in the
range of 33kV to 72.5kV;
HVAC offshore collector platforms, where step-up transformers increase the
voltage to between 132kV and 400kV;
the inter-platform subsea cables transferring the generated power from the
collector platforms to the offshore converter platforms;
the offshore converter platforms for the conversion of the generated power to
HVDC. The nominal HVDC voltage will be up to ± 550kV; and,
the offshore HVDC export system, comprised of HVDC subsea cables.
4.1.2 An indicative connection schematic for the offshore electrical system can be found in
Figure 4. The development consent order provides for up to 400 wind turbines, up to
eight offshore collector platforms and up to two offshore converter platforms in total,
with the final number pending detailed electrical design.
Figure 4: A representation of the offshore electrical system
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 10 © 2013 Forewind
4.2 Wind turbine generators
4.2.1 Up to 400 three-bladed, horizontal axis wind turbine generators will be installed at
Dogger Bank Creyke Beck. Through the movement of turbine blades in the wind, a
generator is turned which transforms kinetic energy into AC electricity.
4.2.2 Offshore wind turbine technology is evolving rapidly and it is anticipated that turbines
rated at approximately 4MW to 10MW will be available within the timescales of
construction.
4.3 Inter-array subsea cables
4.3.1 The inter-array electrical system connects the wind turbines to the collector platforms.
The wind turbines are connected in arrays depending on the turbine size and wind
farm layout.
4.3.2 Figure 5 shows an indicative inter-array layout.
Figure 5: An example inter-array layout connecting the collector substation (shown as a rectangle at the centre)
4.3.3 The inter-array electrical system will likely be made of three-core conductor, XLPE
insulated armoured cables suitable for submarine installation. An example of such a
cable is shown in Figure 6.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 11 © 2013 Forewind
Figure 6: Example of 33kV, three-core, XLPE insulated, armoured subsea cable
4.3.4 It is anticipated that, in order to optimise the economy of the system, cables of
different sizes will be used throughout the system.
4.3.5 The use of copper conductor cables is the industry standard for submarine
application. Copper is more resilient to the marine environment and a heavier weight
allows an easier installation. Submarine cables are protected against mechanical
damage by one or more armour layers, which are typically made of stranded steel
wires. The XLPE insulation is also industry standard practice, as XLPE is a
substantially inert compound that minimises the environmental impact of the cable.
4.4 Offshore collector platform
4.4.1 Up to eight offshore collector platforms (four each for Dogger Bank Creyke Beck A
and B) will be constructed, which will receive power from the wind turbines via the
inter-array cable systems. Transformers will be located on the collector platforms to
increase the voltage of the AC power received from the wind turbine generators. This
aims to minimise transmission losses so that the electricity can be efficiently
transmitted to the offshore converter platform.
4.4.2 Figure 7 shows an example of an offshore collector platform. Converter platforms
(see below) are of similar design, albeit with larger dimensions.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 12 © 2013 Forewind
Figure 7: Typical offshore collector platform design. Source: Seagreen Wind Energy
4.5 Inter-platform subsea cables
4.5.1 The power is transferred from the collector platforms to the converter platforms
through inter-platform cables which operate at a higher voltage than the inter-array
cables. The structure of the inter-platform subsea cables is substantially similar to the
structure of inter-array cables, however one major difference is the thickness of the
insulating layer required as a result of the higher voltage. Single core cables in trefoil
could also be considered for the inter-platform circuits.
4.5.2 The inter-platform cables will therefore typically be HVAC, one- or three-core, XLPE
insulated, armoured subsea cable. Figure 8 shows an example of a three-core cable.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 13 © 2013 Forewind
Figure 8: Example of 245kV, three-core, XLPE insulated, armoured, subsea cable
4.6 Offshore converter platform
4.6.1 The electricity generated will be transmitted to shore using HVDC technology, which
provides significant technical advantages and power loss reduction over long
distance when compared to HVAC transmission.
4.6.2 Therefore an offshore converter platform is required for each project to convert the
power generated by the wind farm and collected by the offshore collector platforms
from Alternating Current (AC) to Direct Current (DC). This power is then exported to
the landfall via the HVDC subsea cables.
4.7 Export system HVDC subsea cables
4.7.1 The offshore HVDC export cables provide for the transmission of electricity between
the offshore converter platform and the transition bays at the onshore landfall point.
The purpose of the transition bays is to connect the offshore HVDC export cables to
the onshore HVDC cables.
4.7.2 The cables of the offshore export system are likely to be copper conductor, single-
core, XLPE insulated, armoured cables, suitable for submarine installation. The
structure of a XLPE insulated HVDC cable is very similar to the structure of more
conventional HVAC cables. The main difference concerns the XLPE compound
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 14 © 2013 Forewind
which is specific for HVDC applications. Mass impregnated cables could also be
considered, pending detail design.
Figure 9: Example of a subsea HVDC cable
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 15 © 2013 Forewind
5 Offshore cable installation
5.1 Pre-installation works
5.1.1 The preferred installation method for all the offshore cables is through direct burial
into the seabed. The objective is the protection of the cable by installing it at a
sufficient depth, which must be compatible with the risks anticipated for each stretch
of cable route. Where the cable burial is unfeasible or inadequate, additional and/or
alternative protective measures will be considered.
5.1.2 The preferred cable routes, as identified within the limits of the development consent
order, would be surveyed via pre-construction geophysical and geotechnical surveys.
This would also locate any obstacles that may obstruct cable laying (e.g. rocks,
wrecks, metal objects, unexploded ordnance) and inform the installation method to
be used.
5.1.3 If an obstruction is located it would be assessed and an appropriate strategy would
be established to remove or avoid the obstruction. Typically a Pre Lay Grapnel Run
(PLGR) and Remote Operated Vehicle (ROV) survey would be conducted to clear
the obstruction. Where the obstacle is suspected to be unexploded ordinance,
specialist mitigation would be employed to either avoid or make safe the obstruction.
The geophysical surveys would also serve to identify the location of sand waves
along the cable route so that an assessment can be made as to whether such
features can be avoided or, if not, what level of seabed preparation (such as pre-lay
sweeping) is required to ensure an appropriate burial depth is achieved in stable (i.e.
non mobile) seabed conditions.
5.1.4 Prior to cable installation, cable burial trials may be conducted in advance of the main
installation programme to ensure that the chosen equipment would be suitable for the
ground conditions encountered and that an appropriate burial depth can be achieved.
If undertaken, any such trial may involve trials of lengths of up to 1km in each of the
soil types likely to be encountered along the export cable route.
5.2 Offshore cable installation methods
5.2.1 There are several different methods available for the installation of submarine cables,
the most common of which are:
simultaneous lay and burial using, for example, a cable plough;
post lay burial using, for example, a jetting Remote Operated Vehicle (ROV);
and,
simultaneous lay burial / post lay burial with a combination of plough, jet
trencher and/or mechanical trencher.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 16 © 2013 Forewind
5.2.2 The final decision on installation method would be made on completion of the pre-
construction geotechnical site investigation surveys. However, it is likely that for the
inter-array cables of Dogger Bank Creyke Beck a combination of ploughing, jetting
and trenching will be considered. This approach is considered to take into account
the inevitable variation in sedimentary conditions along the cable routes.
5.2.3 Cable burial ploughs cut through the seabed, lifting the soil from the trench. Cable
ploughs are designed to cut a narrow trench, with a slot of material temporarily
supported before falling back over the trenched cable. The advantage of this method
is that burial can be achieved as the cable is laid, thus minimising risk to the cable
before the completion of the installation works. However, the number of vessels
which can carry out this method and that have the required cable carrying capacity
for “heavy” power cable is limited. The performance of a plough and the depth of
burial which can be achieved are a function of plough geometry and seabed
conditions, with dense or stiff sediments providing the greatest challenge.
5.2.4 Where seabed conditions are predominantly soft sediment material it may be
considered appropriate to bury the array cables with a Directionally Positioned (DP)
vessel post installation. Under this process the cable would be laid on the seabed
first and a Remote Operated Vehicle (ROV) fitted with high-pressure water jets would
be subsequently positioned above the cable. The jets fluidise a narrow trench into
which the cable sinks under its own weight. The jetted sediments settle back into the
trench and with typical tidal conditions the trench coverage would be reinstated over
several tidal cycles.
5.2.5 In locations where seabed conditions comprise very stiff soils (typically over 100kPa)
and/or bedrock, ploughing and jetting techniques may not be appropriate for cable
burial. One approach for installing cables in very stiff or hard seabeds would be to
use mechanical trenchers which can either be used to simultaneously bury the cable
as it is laid or in a “post lay” mode where the cable is laid by one vessel and burial is
achieved by another vessel following on behind. Simultaneous lay and burial of the
cable tends to be preferred since this reduces risk to the cable from exposure.
However, if a post lay burial solution is used then typically the length of time of
exposure would only be a few hours (depending on the exact arrangements). During
this time any unburied lengths of cable would probably be protected using a guard
vessel.
5.2.6 It should be noted that simultaneous lay and burial can also be achieved by
ploughing in stiff materials to 140KPa and above (e.g. chalk) by use of specially
designed “rock ripping” ploughs as well as certain types of “standard” subsea plough
or mechanical trencher.
5.2.7 Full details of the cable installation works and vessels used are set out in Chapter 5
of the Environmental Statement.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 17 © 2013 Forewind
5.3 Crossing of existing infrastructures
5.3.1 Where existing subsea services cross the offshore cable routes alternative and/or
additional protection and installation methods will be required. The draft DCO
provides the power to carry out cable crossings of existing cables and pipelines
within the Order Limits. The number of crossings associated with the inter-array
cabling will be determined following the confirmation of the final layout post-consent.
However, discussions with the relevant cable and pipeline operators are underway. It
is currently anticipated crossing agreements will be needed with:
Tata Communications – in relation to the TATA North Europe
telecommunications cable;
BT Subsea / Cable and Wireless Worldwide – in relation to the UK-Germany 6
telecommunications cable
BT – in relation to the UK-Denmark 4 telecommunications cable
Gassco – in relation to the Langeled gas pipeline; and,
Shell UK – in relation to the Shearwater to Bacton (SEAL) gas pipeline.
5.3.2 Alternative protection measures include concrete mattressing, fronded concrete
mattressing, rock dumping, bridging or the positioning of gravel bags.
5.3.3 There is no single universally accepted crossing design that would be applicable in all
situations. Designs would vary with the seabed properties at the particular location.
Each crossing would have a range of features possibly unique to that location, based
on:
the physical properties of the crossing, for example the cable size and weight,
bend radius and armouring;
protection requirements relative to the hazard profile, including depth of burial or
extent of mattress/rock cover;
the physical properties and protection status of the crossed product;
seabed properties at the crossing point, for example substrate type, morphology
and stability (presence of mobile bedforms); and,
any constraints placed by the crossed party, for instance location and burial
determination standards, maintenance clearance zone, plough approach limits
and notification zone.
The components most commonly used to protect telecommunication cables
would be flexible mattresses and graded rock. These components may be used
exclusively or in combination.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 18 © 2013 Forewind
6 Onshore electrical system
6.1 Overview
The onshore electrical system is comprised of the following elements:
landfall transition joint bay;
the onshore HVDC cables;
the onshore converter substations;
the onshore HVAC export system connecting the converter substation to the
connection works at the Creyke Beck substation; and,
the connection works required at the existing Creyke Beck substation.
6.2 Landfall transition joint bay
6.2.1 Offshore HVDC cables will end at the landfall transition joint bay, where they are
connected to the onshore HVDC cables. The transition bay location has been
carefully chosen to be a convenient distance inland from shore, in particular taking
into account local coastal erosion which is a feature of the selected landfall area.
6.2.2 The landfall transition joint bay is buried underground and provides the following
functions:
providing a suitable environment to the cable joint elements;
providing a reliable anchoring point to the offshore cables;
allowing the landfall directional drilling operations a suitable angle of attack;
and,
creating a pulling ramp for the offshore cable installation (if not separated from
the transition bay).
6.2.3 The pit will have a concrete plinth on the bottom to provide the cable joints with an
anchoring point. Approximate maximum pit dimensions are 1.5m deep, 4m wide and
up to 12m long but dimensions may vary depending on the final electrical design.
6.3 Export system HVDC underground cables
6.3.1 The cables of the onshore export system will likely be single-core, XLPE or mass
impregnated insulation cables, suitable for underground installation. Either copper or
aluminium conductors can be used for the onshore HVDC cable, pending the final
electrical design. It is likely aluminium cable will be the preferred option due to them
being lighter and allowing easier installation and handling. An example of
underground, HVDC cable is illustrated in Figure 10.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 19 © 2013 Forewind
Figure 10: Typical HVDC, underground cable.
6.3.2 Since the risk of mechanical damage to underground cables onshore is lower than
for submarine cables, it is industry practice to install unarmoured cables.
6.4 Onshore converter substation
6.4.1 The development consent order includes provision for up to two 1,000MW onshore
converter substations, with a total rating of 2,000MW, for the conversion of the wind
farm output from HVDC to HVAC at the connection nominal voltage (400kV). The
HVDC cables which transmit electricity along the onshore cable route terminate at
the converter substation. The connection to the onshore connection point at the
Creyke Beck substation is made through HVAC underground cables.
6.4.2 Each converter station will include:
a valve hall – a large building housing electronic and electro-mechanical
equipment to convert the power from DC to AC;
an ancillary building containing a control room, equipment rooms, operator
facilities and storerooms;
outdoor equipment areas containing rigid aluminium DC and AC current
connectors, transformers, filtering systems, switchgear, measuring and ancillary
electrical systems, cable sealing ends and air-conditioning equipment; and
areas for car parking and internal roads.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 20 © 2013 Forewind
Figure 11 illustrates a converter substation like those proposed for Dogger Bank
Creyke Beck.
Figure 11: An illustrative converter substation layout (Courtesy of Siemens)
6.4.3 The footprint of such a design based on data from the major suppliers and allowing
for roads, drainage and construction area is approximately 2 ha per converter station.
An area of up to 1 ha adjacent to each station would be required for construction and
laydown areas. Landscaping would be undertaken as required and it is envisaged
that this may require an additional area of up to 2 ha. The converter stations would
be serviced by a tarmac road of up to 6m in width. Therefore, the total land take for
the two converter stations including permanent landscaping and temporary
construction areas is approximately 10 ha.
6.5 Export system HVAC cables
6.5.1 HVAC cables will transmit electricity at 400kV between the converter station and the
point of connection. Underground HVAC cables are likely to be conventional XLPE
aluminium or copper cables rated at 400kV nominal voltage; the construction and
installation of such cables are industry consolidated practices. As it can be seen in
Figure 12, illustrating the split view of a 400kV, the structure of HVAC cables is not
dissimilar from the structure of conventional medium voltage cables.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 21 © 2013 Forewind
Figure 12: A 400kV XLPE insulated underground copper conductor cable
6.5.2 The HVAC cables installation is expected to be through direct burial in open
trenching. For both ordinary installation and obstacle crossing the techniques used
are identical to the ones considered for the HVDC cables.
6.6 Connection works at Creyke Beck substation
6.6.1 Creyke Beck 400kV substation was initially identified by National Grid as the onshore
connection point for the projects as part of the Grid Connection Application process,
following initial option assessment work carried out jointly by National Grid and
Forewind.
6.6.2 Following acceptance of the grid connection offer and in parallel with the
development phase, National Grid and Forewind have jointly undertaken further
detailed assessment of options to identify the optimum onshore interface point(s) for
the projects. When developing options to connect new generation to the
Transmission System, National Grid must ensure that the Transmission System
continues to comply with relevant obligations in respect of security and quality of
supply. Also, National Grid must ensure that the connection offered meets the
requirements of Forewind where applicable. The assessment of options has
therefore included environmental considerations, land availability, technical
requirements, economic considerations, and programme and timing requirements.
6.6.3 The detailed option assessment work has confirmed the initial conclusion that Creyke
Beck was and remains the optimum onshore connection point for the projects
6.6.4 Works will be required at the National Grid substation at Creyke Beck, part of which
is leased to Northern Power Grid, to allow connection of Dogger Bank Creyke Beck
offshore wind farm. Consenting, constructing, operating and maintenance and
decommissioning of some of these works will be the responsibility of National Grid,
with the balance being the responsibility of Forewind.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 22 © 2013 Forewind
6.6.5 The works within Creyke Beck substation will require new switchgear connection
bays comprising typically new busbars and busbar supports, circuit breakers,
disconnectors and earth switches, measuring transformers and associated ancillary
equipment. These works are referred to as „works to connect actions‟ and have been
considered in the environmental impact assessment work for Dogger Bank Creyke
Beck.
6.6.6 The preferred areas for connection works are identified within Work No. 9A and 9B
on the Works Plans (application reference: 2.4.2). However, as the precise location is
uncertain, Work No. 9C is also included within the Order Limits as an alternative
connection point.
6.6.7 The National Grid connection may require consent under the provisions of the Town
and Country Planning Act (TCPA) 1990, for which the determining authority is East
Riding of Yorkshire Council. Should planning permission be required, it is anticipated
that the application will be lodged by National Grid in 2014 or 2015.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 23 © 2013 Forewind
7 Onshore electrical system installation
7.1 Onshore HVDC cable corridor
7.1.1 The majority of the proposed onshore cable route passes through agricultural land,
which at the time of the surveys was primarily being used for arable purposes. For
the two projects Dogger Bank Creyke Beck, the maximum total width for two adjacent
cable systems during installation is 36m for the HVDC cables over a distance of
approximately 30km and 38m for the HVAC cables over a distance of approximately
2km, including cable trench, haul roads, fencing and temporary topsoil and subsoil
storage areas.
7.1.2 The 36m corridor swathe is based on the following indicative working widths,
although other breakdowns of the working width are possible following detailed
design:
two cable trenches of nominal width 1m;
a 2m zone on either side of the trench to allow for battering of the trench and
maintaining a safe distance between the edge of the trench and the stored
subsoil or haul road;
a 0.5m wide French drain to one side of each haul road (included within the 2m
separation zone from the trench);
two 6m wide haul roads (one per contract), each to allow two-way construction
traffic flows;
a 6.5m zone for each circuit trench for topsoil and subsoil storage; and
a 1m separation between each haul road.
7.1.3 The corridor swathe is identified in Figure 13.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 24 © 2013 Forewind
Figure 13: Indicative onshore cable route working widths based on two illustrative construction options for an
HVDC section (courtesy of Ramboll)
7.1.4 Where major horizontal directional drilling (HDD) is necessary, for example to bury
underneath key features such as the River Hull, the railway line or main roads, the
below ground sections of the cable route may be up to 53m wide for a major HDD, up
to 70m in the case of the HDD below Figham Pastures, or up to 250m wide for the
landfall HDD, due to the varying depth and distances of the HDDs.
7.1.5 Due to the nature of the ground conditions along the length of the cable route and the
potential issues surrounding surface water run-off and groundwater, it is envisaged
that a haul road will be required for a significant portion of the cable route. The haul
road will be formed using methodologies such as hardcore material or proprietary
bog mats.
7.1.6 The exact requirements for the built-up haul road will be dependent on a number of
factors such as the time of year that the works are being undertaken and the detailed
knowledge of subsoil and groundwater regime obtained from the ground
investigation.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 25 © 2013 Forewind
7.2 Onshore cable installation methods
7.2.1 The onshore underground cables will be installed in one of the following ways:
laid directly in to the ground via open trenches and backfilled;
laid into ducts in the ground and backfilled; or
laid by Horizontal Directional Drilling (HDD).
Open trench installation
7.2.2 The onshore route for Dogger Bank Creyke Beck stretches for a considerable portion
over farmland. The open trench installation is therefore the preferred installation
method.
7.2.3 An ordinary two cables trench is about 1.5m deep and about 1m wide at the trench
base (1.5m for the HVAC sections). For arable land installation it is practice to install
the cables at no less than 1.2m underneath the surface to prevent damage from third
parties, in particular, deep ploughing and drain excavation.
7.2.4 The trench bottom must be smooth so rocks, boulders and any other item that may
mechanically damage the cables are removed. Power cable trenches are backfilled
with stabilised material to provide adequate thermal conductivity and drainage. The
trench top layer, i.e. the top 200-300mm, is backfilled with native material and the
original surface reinstated as required.
7.2.5 Warning tapes and protective concrete or hard plastic tiles are placed in the ground
above the cables.
Ducted installation
7.2.6 For some of the cable route sections the cable could be installed in ducts. Ducts
increase the cable mechanical protection and/or increase the installation flexibility.
The use of ducts on the project will be dependent on the phasing of the projects,
whether two circuits are being installed together, the availability of cables and the
strategy adopted by the installation contractor(s) for the projects.
7.2.7 Ducts can be installed with all the associated civil works, prior to the installation of the
cables, which can reduce the footprint and length of time required for construction for
each section. However ducting can increase the thermal resistivity, therefore
reducing the cable rating. CBS or other stabilised material can be used in duct
installation in order to increase the rate of heat dissipation and increase the cable
rating. Ducting requires that the cables would have to be installed through regular
jointing bays by nose pull methods.
7.2.8 There are constraints associated with siting of jointing bays (e.g. they cannot be
placed in floodplains) and there is a limit to cable pulling tension and therefore a limit
to the length of cable and cable bending radius that can be pulled.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 26 © 2013 Forewind
7.2.9 Where the cable route crosses roads and some watercourses and utilities, ducting is
the preferred method of installation in order to decrease the disruption to these routes
during construction and for maintenance during the operational phase.
7.3 Onshore crossings
7.3.1 Where the route crosses significant obstacles such as large watercourses, utilities,
railways or major roads where open trenching is not practical, the preferred method
of cable installation will be by horizontal directional drilling (HDD). HDD is a
steerable, trenchless method of installing underground pipes, ducts and cables in a
shallow arc along a prescribed bore path by using a surface launched drilling rig.
HDD is a well-established method for cable installation where the more conventional
trench installation is either unfeasible, or undesirable for environmental reasons.
7.3.2 Minor crossings will be realised by alternative methods including hand or digger
excavation, if required. Each case will be addressed by considering the most suitable
crossing technique.
7.4 Onshore construction compounds
7.4.1 Temporary construction compounds will be required at various points and stages of
the onshore works, in particular:
one landfall works construction compound for each project;
up to three primary compounds for cable installation for each project;
up to six intermediate compounds for cable installation for each project; and
HDD construction compounds.
7.4.2 The compounds will typically be comprised of the following main elements:
cable laydown area;
portakabin with offices and comfort rooms;
lock-up storage area;
car park;
machinery and lifting equipment area; and,
utility area.
7.4.3 Landfall and HDD construction compounds will also include an HDD equipment area
and the area for the launch pit. Figure 14 illustrates an example of an HDD
construction compound, which also requires a compound at the receiving end.
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 27 © 2013 Forewind
7.4.4 The transition bay at the landfall should be included in the landfall construction
compound.
Figure 14: Indicative HDD construction compound (launch pit)
DOGGER BANK CREYKE BECK
F-ELC-SP-001 Page 28 © 2013 Forewind
Figure 15: Indicative HDD construction compound (receiving pit)
7.4.5 Primary compounds will be located in the proximity of junctions, usually „A‟ roads for
ease of access, whereas secondary compounds will be distributed along the cable
route, as required by the installation plan.
8 Conclusion
8.1.1 This document provides an overview of the electrical grid connection works which will
be required for Dogger Bank Creyke Beck, as included within the application for a
development consent order. A requirement under Regulation 6(1)(b)(i) of the
Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations
2009 (the APFP Regulations) is that an application for an offshore generating station
must provide details of the proposed route and method of installation of any cable
with the application. This statement has provided details on both the offshore and
onshore electrical system, providing details of the location, type and proposed
installation methods. Additional detail can also be found in Chapter 5 of the
Environmental Statement submitted with the application.