c. t. s. no. 27(a) of siddhartha nagar, at … because of new crz notification 2011, ... siddhartha...

29
EXECUTIVE SUMMARY REDEVELOPMENT OF RESIDENTIAL CUM NON RESIDENTIAL PROJECT AT C. T. S. NO. 27(A) OF SIDDHARTHA NAGAR, AT MHADA LAYOUT, GOREGAON (W), MUMBAI BY M/S MARWIN CONSTRUCTION COMPANY

Upload: ngobao

Post on 02-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

EXECUTIVE SUMMARY

REDEVELOPMENT OF RESIDENTIAL CUM NON RESIDENTIAL PROJECT

AT

C. T. S. NO. 27(A) OF SIDDHARTHA NAGAR, AT MHADA LAYOUT, GOREGAON (W),

MUMBAI

BY

M/S MARWIN CONSTRUCTION COMPANY

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 1

Mumbai the capital of Maharashtra is also the financial capital and the most populated city of India.

Mumbai has grown in recent decades for many residential and commercial developments.

Diminishing of Industrial zones and development of corporate offices, mall culture in very short

period is one of the features of today’s Mumbai.

The Mumbai has many old, dilapidated structures. They are very unsafe to retain. Many of them are

in CRZ zones. Development of those by rehabilitant those tenants along with development of new

flats to compensate the development charges will not be possible if extra FSI is not used. Because of

CRZ conditions the FSI restriction makes those structures unattended.

But because of New CRZ notification 2011, it is possible to compensate development charges by

developing these structures. The one of such project of unsafe, dilapidated building of residential use

as declared dilapidated structure by office of P Ward is discussed here.

1.

Proposed redevelopment of plot bearing C.T.S. No. 27(A) of Siddhartha Nagar, at MHADA Layout,

Goregaon (W), Mumbai and thereby obtain Environmental Clearance as per clause 33(6) of DCR –

1991 in force as on 6

INTRODUCTION TO THE REPORT

th

As per MoEF Notification dated 6/1/2011, redevelopment of dilapidated, CESSED and unsafe

buildings in CRZ areas are permitted with special advantages, in which the project is planned as per

DCR’s in force as on 6/1/2011 and staircase/ lobby/ lift area is claimed free of FSI, as per clause

35(2)c of DCR 1991. The proposal is submitted for prior CRZ clearance, as per the requirement of

January 2011. The scheme for the same is approved by MCGM under DCR

33(6). The Plot is occupied by existing one building structures of Ground + 3 upper floors structure,

occupying 32 existing tenants/ occupants. The structure was declared as dangerous by the office of

Executive Engineer, Housing, Bandra Division, Mumbai Board, of MHADA, dated 03.09.2010

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 2

amended CRZ notification-2011 and the check list finalised by MCZMA vide Office Memorandum

dated 02/07/2011.

Current development thus will help the existing tenants/ occupants to get permanent, safe structure.

They were residing in unsafe building. Photos of the same are attached in annexure.

These old dilapidated structure is now proposed to be developed into one building, comprising of One

Basement + Stilt + 1st to 20th

2.

upper floors for residential and commercial use including refuge area and

car parking.

2.1 NATURE OF THE PROJECT

This is a proposal for development of residential building situated at C.T.S. No. 27(A) of

Siddhartha Nagar, at MHADA Layout, Goregaon (W), Mumbai in CRZ-II belt, as the same is

situated within 50 meters wide CRZ-II belt of Oshiwarah Nallah. The proposal is for redevelopment

of dilapidated residential building, which is situated on the landward side of existing Link Road in

existance prior to 19/2/1991, as may be seen from CZMP of Mumbai as well as old 1967 DP of

Mumbai.

DESCRIPTION OF THE PROJECT

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 3

2.2 SIZE OF THE PROJECT

Area of the plot is 1198.01sq mtr. Cost of the Project is Rs. 59,13,46,682/- ( Rupees Fifty Nine Crore

Thirteen Lakh Forty Six Thousand Six hundred and Eighty Two Only)

2.3 LOCATION

The C.T.S. No. 27(A) of Siddhartha Nagar, at MHADA Layout, Goregaon (W), Mumbai, is in the

suburban part of the Mumbai city.

The nearest station is Jogeshwari Railway Station which is about 2.0 km away from the site. The

nearest bus stop is Ram Mandir Bus Stop, which is 150 meters away from the site. The Sahara

International Airport is about 9.0 km from the site under reference.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 4

Google Earth Image of the site

SITE UNDER REFERENCE

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 5

SITE UNDER REFERENCE

CZMP Plan showing location of reference Plot

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 6

2.4 SITE DESCRIPTION

The site under reference is affected by CRZ-II zone and the property fall landward side of the existing

Link Road which is reflected in CZMP plan. Thus property attracts the CRZ legislation as per CRZ

2011.

The development site does not fall or contain the environmentally sensitive areas as specified in the

coastal Regulation zone notification. Total plot Area in CRZ is 1198.01 sq. mtrs. and the same area

will be used for construction activity.

Town / Tehsil : Mumbai

District : Mumbai Suburban

State : Maharashtra

Latitude : 19° 09' 03.00"N

Longitude : 72° 50' 36.43"E

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 7

2.5 PROPOSED DEVELOPMENT

2.5.1 AREA

Description Area

1 Area of Plot 1198.01 Sq. mtrs.

2 Deductions for

a) Road set back area 0.00 Sq. mtrs.

b) Proposed Area 0.00 Sq. mtrs.

c)Any Reservations 0.00 Sq. mtrs.

c)__% Amenity space as per DCR 56/57 0.00 Sq. mtrs.

Total (a+b+c)

3 Balance area of plot (3-4) 1198.01 Sq. mtrs.

4 Deduction for

15% Recreation ground on Balance Plot Area 0.00 Sq. mtrs.

5 Net area of plot (1-2) 1198.01 Sq. mtrs.

6 Additions for F.S.I purpose 0.00 Sq. mtrs.

2(a )100% for DP Road (restricted to 40% or 80% of

“3” above) 0.00 Sq. mtrs.

2(b) 100% for set-back (restricted to 40% or 80% of

“3” above) 0.00 Sq. mtrs.

7 Total area ( 5+6 ) 1198.01 Sq. mtrs.

8 F.S.I Permissible 3.50

9 Floor space index credit available by 00.00 Sq. mtrs.

9a) As per MHADA NOC No. 0.00 Sq. mtrs.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 8

9b) BUA to be allotted by MHADA 0.00 Sq. mtrs.

9c) 0.33 FSI as per DCR 32 0.00 Sq. mtrs.

9d) 0.67 FSI by development rights 0.00 Sq. mtrs.

10 Permissible floor area (7 x 8+9) 4193.04 Sq. mtrs.

11 Total Proposed Built up Area 4193.04 Sq. mtrs.

12 Gross Built Up Area 7580.00 Sq. mtrs.

13 FSI consumed on net holding 3.50

Parking Statement

Required Parking 56 Nos

Provided Parking 57 Nos

Building Structure

Basement + Ground Floor + 1st to 20th Floor

Height of Building 66.90 meters

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 9

PROJECT DEVELOPMENT DETAILS

Proposed development

1 Existing Structure Existing one building structures of Ground + 3

upper floors occupying 32 existing tenants/

occupants

2 Structure of Building Basement + Ground Floor + 1st to 20th upper

residential and non residential floors including

refuge and parking area.

3 Tenements existing 32 nos.

4 Tenements proposed 87 nos. Residential tenements and 14 Non

Residential tenements ( Sale and Rehab)

5 Height of Building from Ground

level

66.90 mtr

6 Parking required as per MCGM 56 nos.

7 Parking provided 57 nos.

8 Emergency Power supply (D.G.

Nos. x KVa

1 no. 35 KVa

9 Area required for D.G sets 5 sq. mt

10 Salient features of the project

• Earthquake Resistance Building structure

• Rain water Harvesting System in the complex

• Energy Conservation; Provision of Solar water heating system.

• Eco-Friendly Measures

• Optimum use of Timber

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 10

2.5.2 UTILITIES

The Utilities required during the construction phase area water, power, fuel and Labour.

i) WATER : (Expected Consumption – total 35 cum/day)

For Construction activities: 30 cum/day & For Domestic use: 5 cum/day

Water Balance (Construction Phase)

Sr.

No.

Consumption Input

m3

Loss

m/Day 3

Effluent m

/Day

3/Day

1. Construction Activities 30 30 (Tanker

consumption)

Nil

2. Domestic (50 Site Workers) 5 1 4

Total 35 31 4

Anticipated Impacts-

• Increased water demand during construction phase for site preparation, water spraying for dust

suppression, for construction activities, curing, domestic and other water requirements for labour and

staff onsite

• Waste water disposal by construction labour and staff can lead to pollution.

• Water logging creates unsanitary conditions and mosquito breeding at site

Mitigation Measures –

• Wastage of water used for construction curing shall be avoided

• Proper management of channelization of water to avoid water logging at site.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 11

Water Balance (Operation Phase)

Sr.

No.

Component/ Head Occupants Water Requirement Remarks

Domestic Flushing

1 Total residential

population 609 54.81 27.405 @ 90/45 lpcd

2 Total floating

population* 113 2.26 2.825 @ 20/25 lpcd

3 Car washing 57 0.57 CMD 28 cars (@10L per car)

4 Total Quantity of Water Required 87.30 CMD

For a total population of 722 person.(Excluding car washing requirement)

5 Total Fresh Water Requirement 57.07 CMD

6

Total Grey Water generation

45.65 CMD

44.97 CMD to Sewage Treatment plant (capacity 57 CMD) after 20% use loss and 1.5% evaporation losses

7 Sludge generated 0.90 CMD -

8 Grey Water Treatment Plant treated recycled water

44.88 CMD -

* - Floating population consists of drivers, servants, security personnel, etc.

1] Source: - Water will be available from Mumbai (MCGM) for domestic use and from Tanker

for construction purpose

2] Storage: - Water for construction will be stored in open tank.

Drinking water will be stored in HDPE tank.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 12

Anticipated Impacts

• Lowering the infiltration capacity and increased run off

• Increased run off, Water logging in the low lying areas

• Stress on existing water supply & generation of waste water.

Mitigation Measures

• Provision of storm water drainage system with adequate capacity & proper maintenance of storm

water drainage

• Use of water efficient technologies to reduce water consumption

• Treatment of waste water in Grey Water Treatment Plant and recycling of treated water from grey

water treatment plant for flushing, car washing, gardening, etc.

i) POWER

DURING CONSTRUCTION

(Expected Consumption- about 0.3 MW)

1] An Electricity supply of 0.3 MW will be available from BEST. It is mainly required for some

construction equipments, general lighting etc.

2] All Fire & Safety measures will be taken as appropriate and will be supervised by the

Authority.

DURING OPERATION

Total Energy consumption: 0.59 MW

The electricity supply will be available from BEST/ TATA Undertaking.

ENERGY SAVING MEASURES

The following Energy Conservation Methods are proposed in the project:

• Solar & LED Lights for common area use.

• Use of Solar System for Hot water Requirement.

• DG sets will be kept 6m or more away from Buildings.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 13

ii) FUEL

DURING CONSTRUCTION PHASE

Diesel (5 L/day during excavation & 10 L/day post excavation).

All the equipment are electrically driven except JCB, poclain, and concrete mixers.

DURING OPERATION PHASE

Diesel will be required to run the D. G. Set in case of power failure. Hence the quantity of diesel

consumed will vary depending upon the usage of D. G set.

1. Storage: Diesel and oil will be stored in drums / tins with proper identification mark/labels

in identified areas only.

2. Fire and safety measures will be taken as per the guidelines from concerned authority.

3. All Safety and fire precautions will be followed.

iv) MANPOWER

DURING CONSTRUCTION PHASE

(Expected Manpower – about 50)

Approximately 50 persons will be working during the peak time of construction phase. These

persons will be on the project site during 0900 hrs. Except Security Personnel, who will be on

the field round the clock for twenty – four hours.

DURING OPERATION PHASE

POPULATION

There will be about 609 persons residing in the building and 113 will be non residential office

staff including drivers, security, visitors, etc.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 14

3.

Sr. No.

CONSTRUCTION PHASE

The type of Construction Materials, Equipments used during the construction phase and

persons involved in various activities on the field affect the status of environment to a great

extent. The impact of construction Activities on various components of environment on the on

the project site and surrounding area is predicated in this section.

3.1 LIST OF MATERIALS

The Construction material required for the proposed redevelopment is given below.

Item Unit Quantity Source Process

1. Sand CUM 2945 River bed Nil

2. Aggregate CUM 6552 Quarry Crushing

3. Standard

Bricks

Nos. 2371 Red Soil Heating, Moulding

4. Timber M.T 108 Forest Cutting &

Trimming

5. Construction

Waste

Kg/

Day

202 - -

The basic engineering materials like aggregate, cement, sand and bricks/blocks will be purchased

locally. However, finishing materials will be purchased keeping in mind the energy conservation

aspect.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 15

3.2 LIST OF EQUIPMENTS

The construction equipments required for the residential building is given below.

Sr. No. Equipments Numbers Operation Duration

1. JCB, Poclain 1 Diesel Short

2. Dumpers 2 Diesel Short

3. Goods lifts / Personal

lifts

1 Electric Total

4. Vibrators 4 Electric Total

5. Dewatering Pumps 1 Electric Total

6. Concrete Mixers 1 Electric Total

7. Wood Cutting

Machine

1 Electric Total

8. Drill Machine 1 Electric Total

3.3 CONSTRUCTION PROCEDURES

The outline of the construction procedure is described below schematically.

Note:

1] The project is expected to be completed within three years (Maximum) period.

Construction Parameters and Quality will be strictly adhered to as per the approved

architectural design data/map. All the regulations of government authorities will be

followed.

Site Clearing

Excavation Foundation Plinth Super structure

Finishing

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 16

2] All the safely precaution will be observed as per the guidelines during the construction

phase. Personal Protective Equipments (PPE) will be provided to all the personnel involved

in the construction activities.

3] Site barricading by corrugated tin sheets up to height of 5.0 mtr will be done to protect the

surrounding area of the project site from nuisance /dusting.

4] All electrical connections & cables will be checked by authorized persons to ensure the

safety of workers on field.

5] Water sprinkling will be done, wherever required to reduce the dusting in atmosphere. Jute

barricading along building / plot boundary shall be provided to minimize noise level from

construction activities.

6] The safety and security officers shall supervise the site.

7] Safety helmets will be mandatory to all the persons present on the site during the

construction activities.

8] Hand gloves and dust masks will be provided to persons handing construction materials

during the operation.

9] Safety belts will be provided to the persons working at height during the operation.

10] Safety nets will be arranged at a height at about 5.0mtr.when the structures get raised

above the required height from the ground.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 17

3.4 SEISMICITY:

Seismic zone map was initially based on the amount of damage suffered by the different regions of

India because of earthquakes. Following are the varied seismic zones of the nation,

• Zone - II: This is said to be the least active seismic zone.

• Zone - III: It is included in the moderate seismic zone.

• Zone - IV: This is considered to be the high seismic zone.

• Zone - V: It is the highest seismic zone.

Proposed project and Study Area comes under Seismic Zone III.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 18

4.

Parameter

ENVIRONMENTAL CONCERNS

4.1 AIR POLLUTION

1] Source: - The source of Air Emissions is from the use of some equipment like concrete pumps,

mixers, etc. These equipments consume Diesel as fuel during their operation. Carbon Monoxide,

Hydrocarbons, Oxides of Nitrogen and Particulate Matter etc. will be the major pollutants.

Fugitive Emissions i.e. Emissions from construction activities will mainly consist of dust. Movement

of Heavy & light vehicles, for loading and unloading of Construction Materials, transporting people,

will also add on to source of emissions.

Permissible

Range

CPCB Limits AVG Range

Before Activity

During Activity

SPM (µg/m3 100 ~ 200 ) 200 80-100 150-200

RSPM (µg/m3 50 ~ 100 ) 100 20-30 50-100

SO2 (µg/m3 50 ~ 80 ) 80 10-15 10-15

NOx (µg/m3 40 ~ 80 ) 80 5-10 5-10

Ref : 24 Hourly values as per Central Pollution Control Board, National Ambient Air Quality

Monitoring, Notification 11th

April, 1994, Schedule 1.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 19

4.2 AIR POLLUTION MITIGATION

Sr. No. Source Mitigation

1. Vehicle i] All the vehicles coming to the site will be ensured to be

in good condition having PUC.

ii] Public awareness to use Green Fuel will be done.

2. Solid Waste i] Proper segregation and collection of waste will be

ensured.

ii] Location of loading and unloading will be fixed.

Iii] Good Housekeeping practices will be ensured at the

premises.

3. Construction

Activities

i] Noise / Dust nuisance preventions by barricading site

up to 5.0 meter height by GI Sheets

ii] Water sprinkling on dry site, sand.

Iii] Maximum use of electrical driven construction

equipments with regular maintenance.

4.3 WATER POLLUTION

1] Use : - The MCGM water will be used for domestic purpose i.e. drinking water for staff and

laborers working on the field whereas bore well water/Tanker water will be used for various

constructions activities like, Concreting, Plastering , Flooring & Finishing etc.

2] Effluent : - There will be no generation of effluent from construction activities as the water used

for concreting; Plastering, Flooring and Finishing etc. will get evaporated during drying or curing

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 20

time. All the construction activities are physical in nature. The Domestic Effluent will be generated

due to the persons working on the site who will require water for drinking, cleaning, bathing etc.

Sullage generated during operation phase will amount to 44.97 CMD which will be treated in the

Grey Water Treatment Plant. The treated water will be used for non domestic purposes such as

gardening, car washing, flushing etc.

3] Treatment & Disposal:-The Domestic Effluent generated in construction phase will be disposed

off in existing MCGM Sewer.

4] Rain Water Harvesting: The plot is already covered with dilapidated existing one building

structures of Ground + 3 upper floors structure occupying 32 existing tenants/ occupants. The same

will be developed in Basement + Ground + 1st to 20th

• Percolation Pits: 4no. (0.5 * 0.5 * 2m)

Upper Floor for Residential Building. The plot

area is 1198.01 sq mtrs. Roof top rain water harvesting is proposed in the project. The permeable

paver blocks are proposed along with 4 Recharge pit to increase the percolation of rain water into the

soil rather than flowing to the drain.

* (AS PER MOEF GUIDELINES)

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 21

5] Storm Water Discharge:

Storm water drains will be constructed for proposed facility as per the norms. The Rain water

recharge pits will help to reduce the runoff and reduce the load on external storm water drain.

4.4 NOISE POLLUTION

Location Range dB

(A)

Day Time

National Ambient Air Quality Standards (For Residential Zone) 55

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 22

4.5 NOISE LEVEL MITIGATION

Sr.

No.

Source Mitigation

1. Near

Residential

Areas

i] Site Barricading by corrugated tin sheets will be done to

protect the surrounding area.

ii) Construction Activity will be carried out during

daytime only.

2. Nearby

Traffic

i] All the vehicles coming to the site will be ensured in

good condition, having Pollution Under Check (PUC).

ii] Smooth Roads will be maintained in a project site.

3. Construction

Equipments

i] All the equipments will be run during daytime only.

ii] Lubricants will be applied to all the equipments at

proper interval.

Iii] Acoustic Enclosure will be provided for all the

Equipments

2] It is evident from the nature of operation (i.e. construction) that the Concentration of suspended

particulate matter would be higher than the other two parameters.

3] Control of Emission: - Proper precaution will be taken to reduce the particulate matter by water

sprinkling on the dry site area, barricading the periphery by corrugated tin Sheets of 5.0 mtrs height to

protect the surrounding area from dusting. The pollution generated will be controlled by, allowing

vehicles that will comply to mass Emission Standard (Bharat Stage –II) stipulated by Central

Pollution Control Board (CPCB)–Ministry of Environment & forest (MoEF), New Delhi. Also it will

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 23

be ensured that the vehicles will carry PUC certificate. To minimize air pollution efforts shall be

made by use of equipments, which area electric power driven.

4.6 SOLID WASTE MANANGMENT DURING OPERATIONAL PHASE

1] The project proponents have proposed provision for segregation and collection of biodegradable

& non-biodegradable waste within the premises.

2] Solid transfer stations have been proposed for collection, sorting, segregation, storage &

transportation of biodegradable and non-biodegradable waste.

CALCULATION FOR QUANTUM OF SOLID WASTE TO BE GENERATED IN THE

BUILDING DURING OPERTAIONAL PHASE:

• Total no of persons = 722 persons

• Generation of Total waste per person = 500 grams/day (as per Solid waste management study

– Year - 2005 conducted by NEERI)

• Total solid waste generation will be 722 x 500 gms/person/day = 361.00 Kg

• Generation of organic waste = 30.84% of total waste (ref. Table 2 in next page)

• So total organic waste generated by the occupants = 361 x 0.3084 grams = 111.33 kg by all

occupants of the building.

• We will provide one bins of each capacity 5 kg at every landing.

• Dry waste will be collected separately in wheeled bins as required as per MCGM guideline

and transported to common collection area by MCGM.

• E-waste :Shall be stored separately and disposed of to the recyclers authorized by MPCB

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 24

Source: Municipal Solid Waste Management in India: Present Practices and Future Challenge, Sunil Kumar,

http://www.cd3wd.com/CD3WD_40/ASDB_SMARTSAN/Kumar.pdf

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 25

A sample waste collection bin to be Bins recommended by BMC to be used

Kept in lobby area for shifting the waste from building to common area

We will be using organic waste converter to create manure from the organic waste. Manure generated will used for plantation and gardening purpose.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 26

5.7 CONSTRUCTION WASTE MANAGEMENT PLAN

Sr. no. Item Reuse/Recycle

1. Excavated Soil Formation and Filling of Road and garden top soil - within plot (RG area)

2. Steel Metal Scrap steel use for small size slab, pathway etc and balance will be sold as scrap for re-use.

3. Red Bricks Waterproofing at floor level for wet areas – terrace, toilets, etc

5. PROJECT SCHEDULE AND COST ESTIMATES

The Proposed Project is Redevelopment project and will be started as soon as all government NOC’s

and CRZ Clearance is received to start the work. The projected Date of Start is June 2017while the

Date of completion will be Jan 2020 if everything went as per planning.

6.

• Storage and Godown area will be properly identified.

TRAFFIC MANAGEMENT

6.1 CONSTRUCTION PHASE

• There will be about adequate wider space for movements of vehicles and parking.

• The area for loading and unloading will be located at proper demarcated location in the

premises.

• Thus the traffic management on the project site will be easily and smoothly monitored without

any hindrance to the regular flow of traffic on the main road.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 27

6.2 OPERATIONAL PHASE

• About 57 cars per day are expected to be accommodated in the premises. The parking space

will be provided in basement and under stilt / parking floors. There is ample car parking space

in the building on all sides; there will be smooth movements of cars.

• There will be 6.0 mtrs wide approach road to the building from municipal road for movements

of vehicles and parking.

• Traffic Management Plan system will be approved from concern MCGM Authority.

• Thus the traffic management will be easily and smoothly monitored without any hindrance to

the regular flow of traffic on the main road.

7. ENVIRONMENTAL, HEALTH AND SAFETY

All the safety and security measures shall be observed at constructions site. Safety precautions will be

observed as per the guidelines during the construction phase. Personal Protective Equipments (PPE)

will be provided to all the personnel involved in the construction activities. The project authorities

will ensure use of safety equipments for workers during execution process. The safety and security

officers shall supervise the site. Proper training will be given to workers and authorities to handle the

hazard situation.

7.1 SAFETY MEASURES ON SITE

1] Parameters and Quality will be strictly adhered to as per the approved architectural design

data/map. All the regulations of government authorities will be followed.

2] All the safely precaution will be observed as per the guidelines during the construction phase.

Personal Protective Equipments (PPE) will be provided to all the personnel involved in the

construction activities.

Application for CRZ clearance Project name: C. T. S. No. 27(A)of Siddhartha Nagar, Goregaon (W), Mumbai

Developers: M/s Marwin Construction Company 28

3] Site barricading by corrugated tin sheets up to height of 5.0 mtr will be done to protect the

surrounding area of the project site from nuisance /dusting.

4] All electrical connections & cables will be checked by authorized persons to ensure the safety of

workers on field.

5] Water sprinkling will be done, wherever required to reduce the dusting in atmosphere. Jute

barricading along building / plot boundary shall be provided to minimize noise level from

construction activities.

6] The safety and security officers shall supervise the site.

7] Safety helmets will be mandatory to all the persons present on the site during the construction

activities

8] Hand gloves and dust masks will be provided to persons handling construction materials during the

operation.

9] Safety belts will be provided to the persons working at height during the operation.

10] Safety nets will be arranged at a height at about 5.0 mtrs when the structures get raised above the

required height from the ground.

8.

• The proposed redevelopment will initiate redevelopment of surrounding old building.

BENEFITS OF THE PROJECT

• The surrounding area will also be developed from residential point of view.

• It will provide employment opportunities to the local people in terms of labour during

construction and services personnel during operational phase.

• Modern sanitation and infrastructure facilities will have minimal impact on living condition of

local people.

• The project will improve living standard and welfare of the area and local people.