PURPOSE : To identify and evaluate the aspects and impacts of the activities, products
and services.
SCOPE : The activities on which HF have direct control and influence.
RESPONSIBILITY : EMR and Core Team Members.
Sr
.
INPUT ACTIVITY OUTPUT RESP.
1 - Organisation Chart
- Process Flow chart- List of Activities &
services
Identification of activities,
products and services
List of activities in
Format No. F/EMR/03
Concern.
HOD/Teammember
2 List of activities in
Format No.F/EMR/03
Identify Environmental
Aspects associated with theactivities, processes & services
Identification &
Evaluation of Environmental Aspect
& Impact (Format No.F/EMR/03)
Concern
Core TeamMember
3 Experience,Judgment & Past
Record
Identify actual & potentialEnvironmental Impacts
associated with each identified
aspect
Identification of Environmental Aspect
& Impact
ConcernCore team
member
4 Evaluation of
Environmental
Aspect & Impact
(Annexure ‘E’)
Do ranking of each and every
Aspect to find out significant
Environmental aspect
Evaluation of
Environmental Aspect
& Impact
Concern
Core team
member
5 Criteria’s for significance:
1.Legal Compliance,
2.EmergencyCondition
3.Cut Of Score≥16
4.Positive Aspects
Decide significantEnvironmental aspects based
on the criteria.
SignificantEnvironmental Aspect
& Impact
ConcernCore team
member
6 Identification &
Evaluation of
Environmental
Aspect & Impact
Plan corrective action / EMS
Management Program
depending upon the feasibility
Reference documents
to Identification &
Evaluation of
Environmental Aspect& Impact (Format No.
F/EMR/03)
Concern
Core team
member
Prepared By Reviewed & Approved By
Designation EMR Designation Managing Director
7/28/2019 C - Procd for Environmental Aspect
http://slidepdf.com/reader/full/c-procd-for-environmental-aspect 2/2
DEPARTMENT- EMS
HARDROCK FABRICATION PVT. LTD.
Phase-VI, Industrial Area, Gamharia.
Jamahedpur
TITLE
PROCEDURE FOR
ENVIRONMENTAL
ASPECTS
Doc No. HF/EMS/PRO/01
Issue No. / Date 01 / 16.08.10
Rev. No. / Date 00 / 09.08.10
Page Page 2 of 2
Sr.
INPUT ACTIVITY OUTPUT RESP.
7 - SignificantEnvironmental
Aspect &
Impacts- Process change
need
- Process approval
Update / review theEnvironmental Aspect -Impact
Study in following cases -
- Objective is implemented- Change in the process
- New Facility is installed
on annual basis
- Revision of document- Occurrence of emergency
- Implementation of CA or PA
Revised documentsof Environmental
Aspect & Impact
Study
ConcernCore team
member
8 Revision of
‘Identification &
Evaluation of Environmental
Aspect & Impact’
Send the revised Environmental
Aspect -Impact Study to EMR
Office for approval
Approved Document
By EMR
EMR
9 - Agenda of MRM
- Performance sheet
of Environmental
Aspect & Impact
Discuss the latest results of
Environmental Aspect-Impacts
Study in Management Review
Meeting for the norms of significant aspects
MOM & Approved
Document
EMR &
Core Team
Members
Prepared By Reviewed & Approved By
Designation EMR Designation Managing Director