Bushwick Inlet Park Motiva Parcel bounded by Franklin Street/ Kent Avenue, East River and Quay Street, in Bushwick Inlet Park in the Borough of Brooklyn. CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio - $9.8 M FY19 Project Size: 1.90 ac

Upload: others

Post on 25-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

Bushwick Inlet ParkMotiva Parcelbounded by Franklin Street/ Kent Avenue, East River and Quay Street,in Bushwick Inlet Parkin the Borough of Brooklyn.

CB1 - Parks Committee Meeting, Schematic Design PresentationJune 03, 2020Abel Bainnson Butz, LLP

Total Budget: $9,818,000 Mayor, Bill de Blasio - $9.8 M FY19

Project Size: 1.90 ac

Page 2: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

Goals• Reconnect the community with the waterfront by providing a passive park that remediates environmental site conditions, restores native plant habitat and increases wildlife biodiversity.

• Coordinate design vocabulary with adjacent Bushwick Inlet Park parcels to create a cohesive plan which aligns with the vision of the 2009 Greenpoint Williamsburg Open Space Master Plan and allows for a connection to the future build out of Bushwick Inlet Park.

2Bushwick Inlet Park, Motiva Parcel | Project Goals

Page 3: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

Neighborhood Site

City NTS

NTS NTS

Brooklyn

ManhattanQueens

Site

East River

GreenpointEast

Village

Bushwick Inlet ParkMotiva Parcel

3Bushwick Inlet Park, Motiva Parcel | Project Location

N

Page 4: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

Site

EAST RIVER

NTS N

Land Use Categories

Commercial

Multi-Family Residential

Institutional

Mixed Use

Industrial

Transportation / Utilities

Open Space And Outdoor Recreation

Parking

Vacant Lots

1 And 2 Family Residential

Site Boundary

| Surrounding Land Use4

| Bushwick Inlet Park, Motiva Parcel

Page 5: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

NTS

N

McCarren ParkAthletic FieldsFitness EquipmentOutdoor PoolsSpray ShowersRecreation CentersPlaygroundTennis CourtsHandball Courts

North 5th Street Pier

Bushwick Inlet ParkPlaygroundsAthletic FieldsSpray Showers

American PlaygroundPlaygroundsBasketball CourtsHandball CourtsSpray Showers

Transmitter ParkPlaygroundSpray Showers

Project Site

East River

Msgr. McGolrick ParkSpray ShowersPlaygroundsDog-Friendly Areas

5 min (1/4 mile)

walk radius

10 m

in-(1/2

mile)

walk ra

dius

| Neighborhood Context5

| Bushwick Inlet Park, Motiva Parcel

Page 6: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

Project Site

6Bushwick Inlet Park, Motiva Parcel | Concept from 2009 Greenpoint Williamsburg Open Space Master Plan

NTS N

Page 7: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

LegendProject Limit

Existing Bicycle Circulation

Proposed Pathway

Future Bicycle Circulation

Future Phase

Future Pedestrian Connection

KEN

T

AVE

.

N. 14TH ST.

N. 15TH ST.

GEM ST.

WYT

HE

AVE.

N. 13TH ST.

N. 12TH ST.

N. 11TH ST.

N. 10TH ST.

N. 9TH ST.

FRANKLIN ST.

QUAY ST.

NTS

| Site Plan (Future Integration with Master Plan)

N

7 | Bushwick Inlet Park, Motiva Parcel

Page 8: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

| Existing Conditions

NTS

N

8 | Bushwick Inlet Park, Motiva Parcel

Page 9: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

1 2

1 - Looking north at Bushwick Inlet with MTA facility in background 2 - Bushwick Inlet

N

9Bushwick Inlet Park, Motiva Parcel | Site Photos

Page 10: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

1 - Bushwick Inlet from Franklin Street 2 - Looking north along Franklin Street

12

N

10Bushwick Inlet Park, Motiva Parcel | Site Photos

Page 11: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

1 - Panoramic View of Existing Conditions

N

1

11Bushwick Inlet Park, Motiva Parcel | Site Photos

Page 12: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

COMMUNITY VISIONING SESSION | JANUARY 24, 2019

WHAT WE HEARD:Canoeing/ Kayaking

PassiveRecreation

Educational/HistoricalElements

Other

Viewsheds

Storm Resiliency& SustainableMaterials

Pathways& Seating

Signage

Native Planting & Habitat

OtherSecurity Lighting

Physical Accessto the Water

- Movie/Game Night- Kiosks- Billion Oyster Project

- Boulders/Rocks- Zipline- Art/ Sculpture- Water Features

- Soft Edges

SITE PROGRAM SUMMARYPhysical Access to the Water Canoeing/ KayakingEducation/ Historical ElementsPassive RecreationOther

31%21%18%15%15%

SITE FEATURES SUMMARYPathways and Seating Native Planting & HabitatOtherSignageStorm Resiliency & Sustainable MaterialsViewshedsSecurity Lighting

29%21%16%13%10% 6% 5%

SITE PROGRAM

SITE FEATURES

12Bushwick Inlet Park, Motiva Parcel | Community Visioning Session

Page 13: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

40 QUAY ST.[MTA FACILITY]

BAYSIDE PARCEL

MONITOR MUSEUM PARCEL

BUSHWICK INLET

N 14TH ST.

N 15TH ST.

MESEROLE AVE.

LegendProject Limit

Mean High Water Line (+1.81’)

Mean Low Water Line (-2.42’)Designated Bike Lane

Vegetative Screeningrecommended

Vehicular TrafficChain Link Fence

Future Physical Connection to adjacent propertyFuture upland Connection & Visual Corridor per Zoning

Deteriorated FormerWood Bulkhead

Timber Piles

Potential Park Entry(Identified in MasterPlan)*Views to

Manhattan

Revetment Stone, Typ.(unless otherwise Indicated)

*

Slight Slope (0-5% Slope)

Moderate Slope (6-10% Slope)

Severe Slopes (11%+ Slope)

Approximate Extent of WaterFRAN

KLIN

ST.

/ KE

NT A

VE.

| Site Analysis

N

NTS

13 | Bushwick Inlet Park, Motiva Parcel

Page 14: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

N 14TH ST.

Legend

Native, Non-Invasive10% of Total Trees

Ailanthus altissima Tree of Heaven (57.0%)Corylus colurna Turkish Hazelnut (1%)Elaeagnus umbellata Japanese Silverberry (1%)Morus alba White Mulberry (9.0%)Paulownia tomentosa Royal Empress Tree (4%)Ulmus pumila Siberian Elm (1%)

Notes:1. Trees 4”+ caliper inventoried by NYC Parks.2. Canopy size indicated calculated from DBH.3. Percentages rounded to the nearest %.4. All trees to be removed due to soil contamination & environmental soil cap requirements except street trees which are to remain.

Prunus sp. Unknown Cherry (9%)Pyrus calleryana Callery Pear (1%)Zelkova serrata Japanese Zelkova (7%)

Chamaecyparis thyoides Atlantic White Cedar (1.0%)Populus deltoides Eastern Cottonwood (1.0%)Prunus serotina Black Cherry (4.0%)Quercus palustris Pin Oak (4.0%)

Non-Native, Invasive Species73% of Total Trees

Non-Native, Non-Invasive Species17% of Total Trees

Project Limit

N 15TH ST.

MESEROLE AVE.

FRAN

KLIN

ST.

/ KE

NT A

VE.

| Tree Inventory + Analysis

N

NTS

14 | Bushwick Inlet Park, Motiva Parcel

Page 15: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

15 | Bushwick Inlet Park, Motiva Parcel | Schematic Design Plan (Disapproved by CB#1)

BAYSIDE PARCEL

MONITOR PARCEL

BUSHWICK INLET

FRA

NK

LIN

ST.

/K

ENT

AVE.

STD. & ADA ACCESSIBLE PICNIC TABLES

PLANTED BERM

SAND ‘GET-DOWN’BACKLESS BENCHES

MULTI-PURPOSE LAWN

EX. 60” DIA. SEWER LINEORNAMENTAL GRASSES

TRASH COLLECTIONADA ACCESSIBLE ‘GET-DOWN’

OVERLOOK W/ BACKED BENCHES

ADA BINOCULARS

REVETMENT STONE/ SLOPE STABILIZATION

FUTURE CONNECTION TO MONITOR PARCEL

OSPREY STAND

CHAISE LOUNGES

ADA BINOCULARS

CONCRETE SIDEWALKPARK ENTRY

PARK ENTRY

BICYCLE RACKS

REVETMENT STONE/ SLOPE STABILIZATION

PLANTED AREA, TYP.

NEW CROSSWALK STRIPING& PEDESTRIAN RAMPESPLANADE PATHWAY (10’-0” WD.)REVETMENT PLANTERS

N

NTS

Page 16: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

16 | Bushwick Inlet Park, Motiva Parcel | Schematic Design - Summary of Revisions

1. Shoreline Treatment:• CB Comment: Provide a softer, more naturalistic shoreline.

• Reduced amount of revetment.• Incorporated tidal wetlands along waterfront edge.• Varied shoreline geometries.• Provided additional planting at waterfront edge.

2. Waterfront Access:• CB Comment: Provide direct access to the water.

• Relocated a larger sand kayak launch to the center of the site off the main pathway.• Enlarged kayak launch and added stone boulder seating.• Incorporated ADA access directly down to the water.• Provided a pathway which brings users right along the waterfront’s edge.

3. Circulation:• CB Comment: Rethink pathways; softer, more naturalistic, fewer.

• Reduced the number of pathways and total quantity of hardscape.• Reconfigured pathway geometries to have smooth, sweeping curves.

4. Ecology:• CB Comment: Provide more ecologically immersive planting.

• Introduced tidal wetlands along the waterfront (low & high marsh planting).• Provided a planting palette with year-round seasonal interest.

5. Program• CB Comment: Reduce program, more naturalistic.

• Removed the lawn, picnic tables & chaise lounges.• Provided a program which is more passive in experience.

Page 17: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

BAYSIDE PARCEL

MONITOR PARCEL

BUSHWICK INLET

FRA

NK

LIN

ST.

/K

ENT

AVE.

PLANTED BERM

EX. 66” DIA. SEWER LINE & EASEMENT: 38’-0”

ADA ACCESSIBLE ‘GET-DOWN’

TIDAL WETLANDS, TYP.(HIGH + LOW MARSHPLANTINGS)

FUTURE CONNECTION TO MONITOR PARCEL

OSPREY STAND

17 | Bushwick Inlet Park, Motiva Parcel | Schematic Design Plan

PUBLIC SIDEWALK

ADA BINOCULARS

RECONFIGURED STRIPING & BICYCLE LANES (BY DOT)

REVETMENT STONE/ SLOPE STABILIZATION

PLANTED AREA, TYP.

NEW CROSSWALK STRIPING, PEDESTRIAN RAMP & PARK ENTRY

ESPLANADE PATHWAY

N

NTS

SAND BEACH/ KAYAK LAUNCH WITH BOULDER SEATING

Page 18: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

MONITOR PARCEL

MTA- 40 QUAY STREET

BUSHWICK INLET

18 | Bushwick Inlet Park, Motiva Parcel | Schematic Design - Enlargement Plan 1 - North

Page 19: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

| Axonometric 1 - North19

| Bushwick Inlet Park, Motiva Parcel

A

A

B

B CC

D

D

E

E

F

G

F

G

BUSHWICK INLETREVETMENT STONE

ESPLANADE PATHWAY OSPREY STAND

CHAIN LINK FENCE

TIDAL WETLANDS/ HIGH MARSHTIDAL WETLANDS/ LOW MARSH

Page 20: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

20 | Bushwick Inlet Park, Motiva Parcel | Schematic Design - Enlargement Plan 2 - Central

BUSHWICK INLET

FRA

NK

LIN

ST.

/KEN

T AV

E.

Page 21: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

| Axonometric 2 - Central21

| Bushwick Inlet Park, Motiva Parcel

A

A

B

B

B C

C

DD

E

E

F

F

G

H

H

G

SAND BEACH/ KAYAK LAUNCHTIDAL WETLANDS/ LOW MARSH

BOULDER SEATINGESPLANADE PATHWAY

TIDAL WETLANDS/ HIGH MARSHEXIST. 66” DIA. SEWER

CHAIN LINK FENCE

ADA ACCESSIBLE GET-DOWN

Page 22: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

22 | Bushwick Inlet Park, Motiva Parcel | Schematic Design - Enlargement Plan 3 - South

BAYSIDEPARCEL

BUSHWICK INLET

FRA

NK

LIN

ST.

/ KEN

T AV

E.

Page 23: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

23 | Bushwick Inlet Park, Motiva Parcel

A

A

B

B C

C

D

D

E

E

F

F

G

G

BUSHWICK INLETREVETMENT STONE

LOWER ESPLANADE (5-FT WD.)BACKED BENCHES

SLOPED PLANTED AREAPUBLIC SIDEWALK

FRANKLIN STREET/ KENT AVE.

| Axonometric 3 - South

Page 24: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

BAYSIDE PARCEL

MONITOR PARCEL

BUSHWICK INLET

FRA

NK

LIN

ST.

/K

ENT

AVE.

HP 2+

13 12

11 10

9

9

8

9

1011

1213

1415

8

8

7654

4

5

6

7

788

7

7

6

6

6

6

5

555

4

44

3

3 3

2

2

2

1

1

1

0

00

0

0

0

0

-1-2

-2

-2

4.5%4.5%3.2%

1-1/2:1

1-1/2:1

1-1/2:1

2

4.5%

2%2%2%1.25%

1.25%

33%

16.6%

33%

FLAT

2%

+10.00

+9.85

+9.23

+9.66

+9.63

+9.52

+9.31

+9.11

+8.93

+8.81

+8.71

+8.52

+8.42

+

++

++

++

+

+

++

+++

++

++++

TW 10.5TW 9.5

TW 11.5TW 10.5

TW 13.5TW 12.5

TW 13.5TW 12.5TW 12.5

TW 11.5TW 11.5TW 10.5TW 9.5

TW 8.5TW 8.5

TW 10.5TW 9.5

TW 13.5

TW 12.5TW 11.5

+8.44

+TW10.44

+HP

| Schematic Grading Plan

N

NTS

Legend

Spot Elevation

Major ContourMinor Contour

Top of Wall Elev.

High PointDirection of Slope

24 | Bushwick Inlet Park, Motiva Parcel

Page 25: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

25 | Bushwick Inlet Park, Motiva Parcel | Perspective View

Page 26: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

LEGEND

| Fence Diagram

x

x*

x*

* = TEMPORARY FENCE UNTIL ADJACENT PARCEL IS COMPLETED

8’-0”*

7’-0

” *

8’-0”

8’-0”

MEDIUM FENCES(x= HEIGHT)

CLF

CLF

STEEL BAR

GATEG

FRAN

KLIN

ST.

/ KE

NT A

VE.

BAYSIDE PARCEL

MONITOR PARCEL

BUSHWICK INLET

G4’-0”

G

26Bushwick Inlet Park, Motiva Parcel

Page 27: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

LEGEND

| Site Furnishings

1964 World’s Fair Bench, 8’-0” Longw/ Back

Boulder SeatingBicycle Rack

Drinking FountainSecurity LightOsprey Stand

ADA Binoculars

+

+

=

=

Trash/ Recycling Receptacle

FRAN

KLIN

ST.

/ KE

NT A

VE.

BAYSIDE PARCEL

MONITOR PARCEL

BUSHWICK INLET

27Bushwick Inlet Park, Motiva Parcel

Page 28: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

BIKE RACK, FLO BY LANDSCAPE FORMS, STAINLESS STEEL, POLISHED [MASTERPLAN STD.]

1964 WORLD’S FAIR BENCH W/ ARMSGALV. STEEL FRAME W/ ‘CEDAR’ RPL

TYPE F HI-LO DRINKING FTN. & BOTTLE FILLER, COLOR: BLACK

DUAL BINOCULARSMFG: HI-SPYVIEWINGFREE & ADA ACCESSIBLE

TRASH / RECYCLING RECEPTACLESGREY BODY W/ BLACK, BLUE & GREEN LIDS

WATERFRONT PATHWAY TIDAL WETLANDS / LOW MARSH PLANTED SLOPES/ HIGH MARSH SECURITY LIGHTING- FLUSHING MEADOWS LUMINAIRE & POLE [GREENPOINT-WILLIAMSBURG MASTERPLAN STD.,12’-0” HT. ‘B-POLE’ AND ‘RIVERSIDE PARK LUMINAIRE’ COLOR: SILVER

28Bushwick Inlet Park, Motiva Parcel | Site Materials & Furnishings

Page 29: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

OSPREY STANDS NATIVE PLANTINGS & HABITAT RESTORATION

| Ecological Enhancements29

| Bushwick Inlet Park, Motiva Parcel

Page 30: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

BAYSIDE PARCEL

MONITOR PARCEL

TIDAL WETLAND:LOW MARSH PLANTINGS

PATHWAY: SHRUBS, PERENNIALS GROUNDCOVERS

HIGH MARSH PLANTING

FRA

NK

LIN

ST.

/K

ENT

AVE.

| Planting Typology Identification Plan

N

NTS

LEGEND

GRASSES/ MEADOW MIX

30 | Bushwick Inlet Park, Motiva Parcel

Page 31: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

31 | Bushwick Inlet Park, Motiva Parcel

Common Hackberry / Celtis occidentalis Blackgum / Nyssa sylvatica Pitch Pine / Pinus rigida Northern Red Oak / Quercus rubra Black Oak / Quercus velutina

Eastern Redbud / Cercis canadensisEastern Red Cedar /juniperus virginiana

Black Cherry / Prunus serotina Staghorn Sumac / Rhus typhinaQuercus palustris / Pin Oak

| Plant Palette - Major & Minor Trees (Sampling)

Page 32: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

32 | Bushwick Inlet Park, Motiva Parcel

Bayberry / Morella pensylvanicaCarolina Rose / Rosa carolina Eastern Baccharis / Baccharis halimifolia

High-tide Bush / Iva frutescensSweet Pepperbush / Clethra alnifolia

| Plant Palette - Shrubs (Sampling)

Page 33: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

33 | Bushwick Inlet Park, Motiva Parcel

Seacoast bulrush /Bolboschoenus robustus

Saltmeadow Rush / Juncus gerardii Pennsylvania smartweed /Persicaria pensylvanica

Virginia glasswort /Salicornia depressa

Coastal little bluestem /schizachyrium littorale

Seaside Goldenrod /Solidago sempervirens

Smooth Cordgrass/ Spartina alterniflora Saltmeadow cordgrass /Spartina patens

New York Aster /Symphyotrichum novi-belgii

Switchgrass / Panicum virgatum

| Plant Palette - High Marsh & Low Marsh (Sampling)

Page 34: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

TIDAL WETLAND

HIGH MARSH

MEADOW

PATHWAY: SHRUBS, PERENNIALS GROUNDCOVERS

01 0704 1002 0805 1103 0906 12

34 | Bushwick Inlet Park, Motiva Parcel | Plant Palette - Seasonal Interest

Page 35: Bushwick Inlet Park Motiva Parcel · CB1 - Parks Committee Meeting, Schematic Design Presentation June 03, 2020 Abel Bainnson Butz, LLP Total Budget: $9,818,000 Mayor, Bill de Blasio

N

NTS

35Bushwick Inlet Park, Motiva Parcel | Schematic Design