Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland Pozzolana Cement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, PO Burudih, Dist. Saraikela-Kharsawan, Jahrkhand Form – I / Appendix I 1 APPENDIX I (See paragraph – 6) FORM 1 (I) Basic Information S. No. Item Details 1. Name of the project/s Integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland Pozzolana Cement: 180000 TPA and Power Plant:20 MW, was proposed along with captive railway siding near village Hansda, PO Burudih, Dist. Saraikela- Kharsawan, Jahrkhand by Jupiter Cement Industries (unit of SKJ Coke Industries Ltd.). Environment Clearance was granted by the MoE&Fvide letter no. J- 11011/692/2008-IA II (I) dated 30/08/2010. Now, the site of above proposed project has been taken-over by M/s. Shree Cement Ltd. The Business Transfer Agreement has been issued on 24/06/2016 between M/s. Shree Cement Ltd. and M/s. SKJ Coke Industries Ltd. and M/s Sri Ganesh Cement Private Limited 2. S. No. in the schedule As per EIA Notification, 2006 the project falls under S. No. ‘3’ (Cement Plant), Project Activity ‘3 (b)’. 3. Proposed capacity / area / length /tonnage to be handled / command area / lease area / number of wells to be drilled Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland Pozzolana Cement: 180000 TPA, Power Plant:20 MW and Captive Railway Siding. 4. New/Expansion/Modernization New (Corrigendum) 5. Existing Capacity/Area etc. Not Applicable 6. Category of Project i.e. 'A' or 'B' As per EIA Notification, 2006 the project falls under S. No. ‘3’ (Cement Plant), Project Activity ‘3 (b)’. 7. Does it attract the general condition? If yes, please specify. No 8. Does it attract the specific No

Upload: others

Post on 29-Jan-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

1

APPENDIX I(See paragraph – 6)

FORM 1(I) Basic Information

S. No. Item Details1. Name of the project/s Integrated cement plant, capacity Clinker:540000 TPA, Portland Slag Cement: 937500TPA, Portland Pozzolana Cement: 180000TPA and Power Plant:20 MW, was proposedalong with captive railway siding nearvillage Hansda, PO Burudih, Dist. Saraikela-Kharsawan, Jahrkhand by Jupiter CementIndustries (unit of SKJ Coke IndustriesLtd.). Environment Clearance was grantedby the MoE&Fvide letter no. J-11011/692/2008-IA II (I) dated30/08/2010.Now, the site of above proposed project hasbeen taken-over by M/s. Shree Cement Ltd.The Business Transfer Agreement has beenissued on 24/06/2016 between M/s. ShreeCement Ltd. and M/s. SKJ Coke IndustriesLtd. and M/s Sri Ganesh Cement PrivateLimited2. S. No. in the schedule As per EIA Notification, 2006 the projectfalls under S. No. ‘3’ (Cement Plant), ProjectActivity ‘3 (b)’.3. Proposed capacity / area / length/tonnage to be handled /command area / lease area /number of wells to be drilledClinker: 540000 TPA, Portland SlagCement: 937500 TPA, Portland PozzolanaCement: 180000 TPA, Power Plant:20 MWand Captive Railway Siding.4. New/Expansion/Modernization New (Corrigendum)5. Existing Capacity/Area etc. Not Applicable6. Category of Project i.e. 'A' or 'B' As per EIA Notification, 2006 the projectfalls under S. No. ‘3’ (Cement Plant), ProjectActivity ‘3 (b)’.7. Does it attract the generalcondition? If yes, please specify. No

8. Does it attract the specific No

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

2

condition? If yes, please specify.9. LocationPlot/Survey/Khasra No. Khasra details is enclosed as annexure 1Village Near village HansdaDistrict Saraikela-KharsawanState Jahrkhand10. Nearest railway station/airportalong with distance in kms. Nearest Railway Station: MahaliMarupStation 1.8 kms in E directionNearest Airport: Ranchi Airport (~82 km inNW direction)11. Nearest Town, city, DistrictHeadquarters along with distancein kms.Raj Kharswan- 5.0 km in SW directionKharswan- 5.0 km in NW direction

12. Village Panchayats, Zila Parishad,Municipal Corporation, Localbody (complete postal addresseswith telephone nos. to be given)Village Panchayat: HansdaZila Parishad: Saraikela-Kharsawan

13. Name of the applicant M/s. Shree Cement Limited14. Registered Address Shree Cement Ltd.Post Box No. 33, Bangur Nagar,Andheri Deori, Beawar,Distt. Ajmer (Raj.)15. Address for correspondence : Shree Cement Limited (Applicant)Name Rakesh BhargavaDesignation(Owner/Partner/CEO) Vice President - Environment

Address M/s Shree Cement Ltd.Post Box No. 33, Bangur Nagar,Andheri Deori, Beawar,Distt. Ajmer (Raj.)Pin Code 305 901E-mail [email protected] No. 01462-228101-6Fax No. 01462-228117/ 22811916. Details of Alternative Sitesexamined, if any. Location of these The proposed site for cement plant meetsthe siting criteria guidelines.

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

3

sites should be shown on a toposheet.17. Interlinked Projects Existing Cement Plants of Shree CementLtd. at Ras, Pali (Rajasthan), Beawar, Ajmer(Raj), Balodabazar (Chhattisgarh) andother clinker units; EnvironmentalClearance has already been obtained.18. Whether separate application ofinterlinked project has beensubmitted?

Not Applicble

19. If yes, date of submission Not Applicble20. If no, reason Not Applicable21. Whether the proposal involvesapproval/clearance under: if yes,details of the same and their statusto be given.(a) The Forest (Conservation) Act,1980 ?(b) The Wildlife (Protection) Act,1972 ?(c) The CRZNotification, 1991

No

No

No22. Whether there is any GovernmentOrder/Policy relevant/relating tothe site? Not Applicble

23. Forest land involved (hectares) None24. Whether there is any litigationpending against the project and/orland in which the project ispropose to be set up?(a) Name of the Court(b) Case No.(c) Orders/directions of theCourt, if any and its relevancewith the proposed project.

No litigation pending against theproject

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

4

(II) Activity1. Construction, operation or decommissioning of the Project involving actions,

which will cause physical changes in the locality (topography, land use, changes

in water bodies, etc.)

S. No. Information/Checklistconfirmation

Yes/No Details thereof (with approximatequantities / rates, wherever possible)with source of information data1.1 Permanent or temporarychange in land use, landcover or topographyincluding increase inintensity of land use (withrespect to local land useplan)

Yes The proposed cement plan will be set upin the area of 110 acres.

Land is not primarily suitable foragriculture purpose. It is classified asfellow land which is more suitable forindustry.

The setting up of cement plant will resultin change of land use pattern toindustrial land.1.2 Clearance of existing land,vegetation and buildings? No No land and building present on the site

1.3 Creation of new land uses? Yes New land use will be created.1.4 Pre-constructioninvestigations e.g. borehouses, soil testing? Yes Soil testing shall be done to know thelithology and estimate load bearingcapacity. Borehole shall be dug toestimate draw down recovery test.1.5 Construction works? Yes Construction will be done for variousplant installations and set up. It isproposed to construct of clinker unit,cement grinding, CPP, Captive RailwaySiding and colony1.6 Demolition works? No No demolition work is proposed.1.7 Temporary sites used forconstruction works orhousing of constructionworkers?

Yes Temporary sites will be developed forconstruction workers. Proper sanitaryfacility will be provided.

1.8 Above ground buildings,structures or earthworks Yes Administrative building, CCR, Store,

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

5

including linear structures,cut and fill or excavations. workshop, canteen, dispensary,substation, weighbridge, colony alongwith plant buildings will be constructed.1.9 Underground worksincluding mining ortunneling? No -

1.10 Reclamation works? No Not applicable1.11 Dredging? No Not applicable1.12 Offshore structures? No Not applicable1.13 Production andmanufacturing processes? Yes The cement plant processes involvescrushing, blending, grinding and pyro-processing is done for clinkermanufacturing.

Clinker along with fly ash, slag andgypsum will be ground in closed circuitball mill to manufacture OPC and PPCcement.

In the Captive power plant, coal will befed in the boiler, where steam will begenerated which will move turbine toproduce electrical energy.1.14 Facilities for storage of goodsor materials? Yes Covered storage shed for gypsum.

Silos for clinker, cement and fly ashstorage.1.15 Facilities for treatment ordisposal of solid waste orliquid effluents? Yes In proposed Cement Plant, dustparticles will be collected in variouspollution control equipment &recycled back to the system.

In the CPP, entire fly ash generatedwill be utilized in cementmanufacturing process.

Domestic wastewater generated willbe treated in STP and reused forgreen belt development.

RO reject water will be used for mill

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

6

spray.1.16 Facilities for long termhousing of operationalworkers? Yes Residential colony will be establishedfor staff.

1.17 New road, rail or sea trafficduring construction oroperation? Yes Site will be connected with nearestrailway line for transportation of rawmaterial and products (clinker andcement) along with road1.18 New road, rail, airwaterborne or othertransport infrastructureincluding new or alteredroutes and stations, ports,airports etc?

Yes Existing road will be strengthen.

Captive railway line will be constructedwith in the plant area.

1.19 Closure or diversion ofexisting transport routes orinfrastructure leading tochanges in trafficmovements?No No diversion of existing roads.

1.20 New or divertedtransmission lines orpipelines? No No diversion of transmission lines

1.21 Impoundment, damming,culverting, realignment orother changes to thehydrology of watercoursesor aquifers?Yes Harvesting pond will be developed in the

project area to collect the rain water foruse in process.

1.22 Stream crossings? Yes One minor stream is passing through theproject site and will be diverted as andwhen required1.23 Abstraction or transfers ofwater from ground orsurface waters? Yes The water requirement will be 546 KLDand will be sourced from ground/sonariver. The water balance is given below:

Description (KLD)Clinker andCement Section

300

Captive PowerPlant

200

Drinking and 46

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

7

DomesticTotal 5461.24 Changes in water bodies orthe land surface affectingdrainage or run-off? No No impact will be envisaged.

1.25 Transport of personnel ormaterials for construction,operation ordecommissioning?Yes Staff vehicles will be provided for

workers.

1.26 Long-term dismantling ordecommissioning orrestoration works? No No dismantling work proposed

1.27 Ongoing activity duringdecommissioning whichcould have an impact on theenvironment? No No such activity proposed

1.28 Influx of people to an area ineither temporarily orpermanently? Yes The influx of people will be permanentlyfor job opportunity.

1.29 Introduction of alien species? No Not envisaged1.30 Loss of native species orgenetic diversity? No Not envisaged

1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of Project (such as land,water, materials or energy, especially any resources which are non-renewableor in short supply).

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data2.1 Land speciallyundeveloped oragricultural land (ha) Yes The proposed project site is fellow land(primarily not suitable for agriculture).Total area for the proposed cement plantwill be 110 acres.2.2 Water (expected source &competing users) unitKLD Yes The water requirement will be 546 KLDand will be sourced from ground/sonariver. The water balance is given below:

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

8

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data

Description (KLD)Clinker andCement Section

300

Captive PowerPlant

200

Drinking andDomestic

46

Total 5462.3 Minerals (MT) Yes Mineral gypsum will be procured fromRajasthan and limestone will be sourcedfrom Mines in West Singhbhum andSaraikela-Kharsawan.

2.4 Construction material –stone, aggregates, and/soil (expected source-MT) Yes Construction material available locallywill be used for construction work ofproposed plant.2.5 Forests and timber(source-MT) No Not Applicable

2.6 Energy includingelectricity and fuels(source, competing users)Unit: fuel (MT), energy(MW)Yes The estimated power requirement for

the proposed project will be about 18MW which will be sourced fromJSEB/proposed CPP and D.G sets of 3.0MWfor power back up.2.7 Any other naturalresources (useappropriate standardunits)

No

Not envisaged

3.0 Use, storage, transport, handling or production of substances or materials,

which could be harmful to human health or the environment or raise concerns

about actual or perceived risks to human health

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data3.1 Use of substances ormaterials, which arehazardous (as per MSIHC Yes Coal will be used as fuel in cement andpower plant.

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

9

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information datarules) to human health orthe environment (flora,fauna, and watersupplies)3.2 Changes in occurrence ofdisease or affect diseasevectors (e.g. insect orwater borne diseases)

No N.A

3.3 Affect the welfare ofpeople e.g. by changingliving conditions? Yes Better employment opportunities willenhance the living standards of the localpeople.3.4 Vulnerable groups ofpeople who could beaffected by the project e.g.hospital patients,children, the elderly etc.,

No Vulnerable targets like hospital orschool are not present in the vicinity ofproject site

3.5 Any other causes No -

4.0 Production of solid wastes during construction or operation or decommissioning

(MT/month)

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data4.1 Spoil, overburden ormine wastes No Not Applicable

4.2 Municipal waste(domestic and orcommercial wastes) Yes Kitchen waste (biodegradable)generated will be converted in compost.

4.3 Hazardous wastes (asper hazardous wastemanagement rules) Yes Used oil generated from the plantmachineries will be sold to CPCB / SPCBauthorized recycler.4.4 Other industrial processwastes No Not Applicable

4.5 Surplus product No No surplus product will be generated.4.6 Sewage sludge or othersludge from effluenttreatment Yes STP Sludge will be used for green beltdevelopment.

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

10

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data4.7 Construction ordemolition wastes Yes Construction wastes will be reused atthe site4.8 Redundant machinery orequipment No Not envisaged

4.9 Contaminated soils orother materials No No contaminated soil will be generated.

4.10 Agricultural wastes No No agricultural waste will be generated.4.11 Other solid wastes No No other waste will be generated.

5.0 Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Sr.No

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data5.1 Emissions fromcombustion of fossil fuelsfrom stationary or mobilesources

Yes In the CPP, SO2 will be neutralizedwith lime to minimize the SO2emission. Low NOx burner will beused & PM emissions will becontrolled by using high efficiencyESP.

ESP and bag filters will be providedin the cement plant

Silo for fly ash, clinker and cementstorage.

Covered shed for gypsum storage Concreting roads with vacuum

sweeping5.2 Emission from productionprocesses Yes Particulate matter will be emittedfrom the cement making process.

As mentioned above all measureswill be taken to control theemission.5.3 Emissions from materialshandling includingstorage or transport Yes In the cement plant and CPP, thefugitive emission of dust particlesresulting in increase in SPM / RSPMwill be there due to the materialstorage, handling andtransportation activity also due tovehicular movements.

ESP and bag filters will be providedin the cement plant and CPP forcontrol of dust emission.

Bag filters will be installed at all

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

11

Sr.No

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data

material transfer points. Silo for fly ash, clinker and cement,

gypsum in covered shed, watersprinkling arrangement in lime andcoal storage and concreting roadswill be provided to maintain fugitivedust emission.5.4 Emissions fromconstruction activitiesincluding plant andequipment

Yes Fugitive dust emissions may begenerated from construction activities.These emissions will be temporary andwill be controlled.5.5 Dust or odours fromhandling of materialsincluding constructionmaterials, sewage andwaste

Yes/No The construction activities may causeincrease in SPM levels locally. No odourgenerating substance will be handled inthe premises.

5.6 Emissions fromincineration of waste No There will be no incineration of waste.5.7 Emissions from burningof waste in open air (e.g.slash materials,construction debris)No There will be no burning of waste in

open air.

5.8 Emissions from any othersources No There will be no emissions from anyother sources.

6.0 Generation of Noise and vibration, and emissions of Light and heat

Sr.No

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data6.1 From operation ofequipment e.g. engines,ventilation plant,crushers

Yes In the cement plant and CPP, noisepollution will be generated fromturbine, fans, compressors, motors,crusher and grinding mills.Adequate measures include closed

buildings for turbine & compressorand proper maintenance of plantmachineries will maintain noise levelbelow the permissible level.Proper noise abatement measures

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

12

Sr.No

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data

will be taken. Persons working closeto machine will be providedpersonal protective equipment suchas Ear plugs / Ear muffs etc.6.2 From industrial or similarprocesses Yes In the cement plant and CPP, there will

be noise generation due to the runningof the machinery. Adequate measuresincludes closed buildings for turbineand compressor and propermaintenance of plant machineries willmaintain noise level below thepermissible level

The workers will be provided withpersonal protective equipment.6.3 From construction ordemolition Yes Noise during construction activitieswill be temporary & will be resolved.

6.4 From blasting or piling No Not applicable6.5 From construction oroperational traffic Yes Noise during construction activitieswill be temporary & will be resolved.6.6 From lighting or coolingsystems No No

6.7 From any other sources No No

7.0 Risks of contamination of land or water from releases of pollutants into the ground

or into sewers, surface waters, groundwater, coastal wasters or the sea.

S.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible)with source of information data

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

13

7.1 From handling, storage,use or spillage ofhazardous materialsNo In the cement plant and CPP, there is

no use / handling of hazardousmaterial except used oil generationwhich shall be handled in closedcontainers.

7.2 From discharge ofsewage or othereffluents to water or theland (expected modeand place of discharge)No No effluent will be generated during

the cement making process. Domesticwastewater from plant and colony willbe treated in STP and treated waterwill be used in green belt development.The STP sludge will be used as manurefor green belt development within thepremises. RO reject water will be usedin mill spray.

7.3 By deposition ofpollutants emitted to airinto the land or intowaterYes Increase in Particulate matter will

deposit on land and water.

Adequate pollution controlequipment’s will be installed tomaintain the emission level<30mg/Nm3.

Besides this, other mitigationmeasures followed for control of airpollution are mentioned below:

Bag filters at all material transferpoints

Covered unloading hoppers

Concreted roads and vacuumsweeping.7.4 From any other sources No No7.5 Is there a risk of longterm build-up ofpollutants in theenvironment from thesesources?

No No

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

14

8.0Risk of accidents during construction or operation of the project, which could affect

human health or the environment

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible) withsource of information data8.1 From explosions,spillages, fires etc andfrom storage, handling,use or production ofhazardous substances

No There is no chance of accident on account ofspillages, fire or hazardous substances etc.Proper maintenance, operation and leakageproof condition of machinery eliminatespossibilities of fire.Fire extinguishers will be made availablenear all machines and all persons would beproperly trained to quench the fire atsource itself. No other major risks will beinvolved.8.2 From any other causes No Not envisaged8.3 Could the project beaffected by naturaldisasters causingenvironmental damage(e.g. floods, earthquakes,landslides, could burstetc)?

No Seismic Zone-II as per IS 1893 (Part-I)-2002.

9.0 Factors which should be considered (such as consequential development) whichcould lead to environmental effects or the potential for cumulative impacts withother existing or planned activities in the locality

Sr.No.

Information/ChecklistConfirmation

Yes/No Details thereof (with approximatequantities/ rates, wherever possible) withsource of information data9.1 Lead to development ofsupporting, facilities,ancillary development ordevelopment stimulated bythe project which could have

Yes Around the project site, there will bedevelopment of few small shops and smallmarket.

Employment opportunities will increase

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

15

impact on the environmente.g.:Supporting infrastructure(roads, power supply, wasteor waste water treatment,etc) Housing development Extractive industries Supply industries Other

due to the requirement of workers for theproposed project. Local people will bepreferred for employment. This willcontribute in raising the socio-economicstatus and standard of living of the nearbyvillagers.

9.2 Lead to after use of the site,which could have an impacton the environment No -

9.3 Set a precedent for laterdevelopments Yes The proposed project will makeemployment opportunity for the localpeople and will improve the economy ofthe area.9.4 Have cumulative effects dueto proximity to other existingor planned projects withsimilar effects

No -

(III) Environmental Sensitivity

Sr.No.

Areas Name/Identity

Aerial distance (within 15 km) Proposedproject location boundary1 Areas protected underinternational conventions,national or local legislationfor their ecological,landscape, cultural or otherrelated value

None No National Parks, Wild Life Sanctuarieswithin 10km radiusPF in 6.5 kms in E DirectionPF in 9.0 kms in E DirectionPF in 9.5 kms in E DirectionOpen Jungalmainly Sal in S, N, NE &NWdirection2 Areas which are importantor sensitive of ecologicalreasons – wetlands, watercourses or other waterbodies, coastal zone,biospheres, mountains,forests

None No

3 Areas used by protected,important or sensitivespecies of flora or fauna forbreeding, nesting, foraging,resting, over wintering,None No

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near village Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form – I /Appendix I

16

Sr.No.

Areas Name/Identity

Aerial distance (within 15 km) Proposedproject location boundarymigration4 Inland, coastal, marine orunderground waters None No5 State, national boundaries None No6 Routes or facilities used bythe public for access torecreation or other tourist,pilgrim areas

Yes Kandra-Saraikela – Chaibasa Highway-5.5 km and and 11 km from Tata Nagar -Chaibasa Highway7 Defence installations None No8 Densely populated or built-up area None No

9 Areas occupied by sensitiveman made land uses(hospitals, schools, places ofworship, communityfacilities)

Yes Schools, dispensaries, small hospitals,places of worship of general natureexists within 15 km from the project site.

Raj Kharswan- 5.0 km in SW directionKharswan- 5.0 km in NW direction10 Areas containingimportant, high quality orscarce resources

(ground water resource,surface resources, forestry,agriculture, fisheries,tourism, minerals)

None No

11 Areas already subjected topollution or environmentaldamage. (those whereexisting legal environmentalstandards are exceeded)

None No

12 Areas susceptible tonatural hazard which couldcause the project to presentenvironmental problems(earthquakes, subsidence,landslides, erosion, floodingor extreme or adverseclimatic conditions)

None The site is located in seismically stablezone i.e. Seismic Zone-II as per IS 1893(Part-I)-2002.

(IV) Proposed Terms of Reference for EIA studies :Environment Clearance was granted by the MoE&Fvide letter no. J-11011/692/2008-IA II (I) dated 30/08/2010.

Proposed integrated cement plant, capacity Clinker: 540000 TPA, Portland Slag Cement: 937500 TPA, Portland PozzolanaCement: 180000 TPA and Power Plant:20 MW, along with captive railway sideing was proposed near vii/age Hansda, POBurudih, Dist. Saraikela-Kharsawan, Jahrkhand

Form - 1/Appendix I

UNDERTAKING

"I hereby given undertaking that the data and information given in the applicationand enclosures are true to the best of my knowledge and belief and I am aware that ifany part of the data and information submitted is found to be false or misleading atany stage, the project will be rejected and clearance giVj!,J!..a.w::. to the roject will berevoked at our risk and cost. I:UJ" ~hree m nt Ltd

Date: 04/08/2016Place: Beawar

Autb- Signat rv(Rakesh Bharga a)

Vice President (Environment)(Authorized Signatory)

For, M/s Shree Cement Limited,Bangur Nagar, Post Box. No.- 33,

Beawar-30S 901, Rajasthan, IndiaNote:1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall

submit with the application a C.R.Z.map duly demarcated by one of the authorizedagencies, showing the project activities, W.r.t. c.R.Z. (at the stage of ToR) and therecommendations of the State Coastal Zone Management Authority (at the stage of EC).Simultaneous action shall also be taken to obtain the requisite clearance under theprovisions of the c.R.Z. Notification, 1991 for the activities to be located in the CRZ.

2. The projects to be located within 10 km of the National Parks, Sanctuaries, BiosphereReserves, Migratory Corridors of Wild Animals, the project proponent shall submit themap duly authenticated by Chief Wildlife Warden showing these features vis-a-vis theproject location and the recommendations or comments of the Chief Wildlife Wardenthereon (at the stage of EC).

3. All correspondence with the Ministry of Environment & Forests including submission ofapplication for ToR/Environmental Clearance, subsequent clarifications, as may berequired from time to time, participation in the EAC Meeting on behalf of the projectproponent shall be made by the authorized signatory only. The authorized signatoryshould also submit a document in support of his claim of being an authorized signatoryfor the specific project.

17