BURNHAMTHORPE ROAD EAST

RECONSTRUCTION

INFORMATION SESSION

November 9, 2017

What Is This Project?

The City of Mississauga will be working in your

neighbourhood to reconstruct Burnhamthorpe Road

East from approximately 200 m east of Dixie Road to

the East City Limit.

This project will include:

Reconstruction of Burnhamthorpe Road East

(approximately 2 km);

The extension of the multi-use trail along the north

side of the road, including lighting and connecting

with the Etobicoke Creek Trail;

Catch basin lead replacements;

Management of stormwater runoff using Low

Impact Development; and,

Intersection improvements including, traffic signal

replacements, bus stop/queue jump lanes

constructed at Bough Beeches

Boulevard/Havenwood Drive, Fieldgate Drive and

Ponytrail Drive intersections.

The construction cost is approximately $8.5 million.

To find out more about the project,

please see the Design Plan.

This Information Session has been arranged to

present the following:

The Project Schedule;

The Design Plan; and

Next Steps.

Representatives of the Project Team are

available to discuss the project with you.

Project Schedule

Construction Tender Project Finalize Detail Design

Plans

Procurement Process

The Project will be following the City’s High Value Acquisition Process / Formal

Competitive Bid Process.

The Project will be Publicly Advertised – Biddingo.com.

All submitted Proposals will be evaluated based on cost and accuracy of form

of tender and will be reviewed and approved by the City’s Finance, Materiel

Management and Legal sections.

The lowest priced qualified bidder is awarded the Project.

A completion date will be specified in the Contract Tender Document.

Liquidated damages will be assessed if the project is not completed by the

specified completion date.

Construction Management Plan

Advanced digital signage will be displayed along Burnhamthorpe Road to

allow drivers to better understand their commute time based on construction

delays.

During construction, there will always be inspectors on site to answer any

questions residents may have.

The City will be working with the Region of Peel and other agencies (utility

companies) to coordinate projects in the area:

The Region of Peel will be completing sanitary and watermain works

on Ponytrail Drive and Rathburn Road. The project is expected to

commence December 2017/January 2018 weather permitting and will

take approximately 52 weeks to complete. For more information,

contact the Region of Peel Project Manager:

Derek Gorzynski, P. Eng.

[email protected]

905.791.7800 x5013

Cycling Facilities

Multi-use Trails are paved trails separated from the road and shared by cyclists and

pedestrians. These trails are denoted by “Shared Path” signage.

General traffic principles apply on multi-use trails – keep to the right as appropriate for a

two-way transportation facility, and slower users should keep as far to the right as practical.

Courteous use of the trail is encouraged. Faster moving users should clearly communicate

to other users of their approach using a bell, horn or audible call; slower moving users

should move to the right to allow them to pass.

Cycling Facilities

A crosswalk is intended for pedestrians

and/or dismounted cyclists to walk through an

intersection.

Riding beside (“along”) a crosswalk is

specifically permitted and called a crossride.

In order to allow cyclists to cross the

intersection, a bicycle signal is provided.

The cycling crossride will be provided

using “elephant’s feet” markings beside the

pedestrian crosswalk.

CROSSWALK CROSSRIDE

Next Steps

If you have any questions please contact the City’s Project Manager:

Domenic Galati, C.E.T., L.E.L.,

City of Mississauga Project Manager

City of Mississauga

201 City Centre Drive, Suite 800

Mississauga, ON L5B 2T4

Tel: 905-615-3200 ext. 5792

Email: [email protected]

Following this Information Session the Project Team will:

Finalize the detail design plans;

Tender the project for construction; and,

Commence construction in April 2018 with anticipated completion in December

2018.