Building the Future
• Design-Build Team hired to construct Business 40
• Timeline to complete project
• Schedule for Construction Segments A-D
• Other off-site improvements
• Bridge designs
• Transportation Management Plan
• Incident Management
• Other mobility options
• Communication and contact information
Building the Future
Today’sPresentation
Building the Future
Business 40 Visualization
Visualization
Building the Future
Flatiron Constructors, Inc./Blythe Development Company Joint Venture and HDR Engineering Inc. • Rebuild the 1.2-mile section of Business 40, which includes
reconstruction of the roadway, 9 vehicular bridges and 2 pedestrian bridges.
• Build a major section of the Multi-Use Path from Peters Creek Parkway to Liberty Street (remaining section from Peters Creek to Lockland will be built afterwards)
• Increase speed limit to 55mph.
Design-BuildTeamHired
Timeline
Project
Completed
Late 2020
9
CONSTRUCTION/CLOSURE TIMELINE
Business 40 Improvements
NCDOT hires Design-Build Team of Flatiron/Blythe/HDR
Preliminary Soil Testing
Construction Segment A begins – 4th St. Bridge, Peters Creek Parkway and other local improvements
All of Business 40 Reopens
Fall
2017
4
3Dec 2016
Jan 2017
NCDOT announces that Business 40 will be renamed Salem Parkway in 20202
October 21
2016September
2016
Business 40 closes while construction Segments B and C begin
62017Fall
2018
ONLY the section of Business 40 from Main St. east to U.S. 52 reopens
72017Fall
2019
Construction Segment D begins – MLK Jr. Blvd. and Academy St. Improvements
5Summer
2018
8Summer
2020
1 PUBLIC MEETING AUG/SEP
2017
Building the Future
ConstructionSegmentsA-D
Fall 2019 – Summer 2020
Building the Future
ConstructionSegmentAFall2017toFall2018
PETERS CREEK PKWY.
FOURTH STREET
BUSINESS 40
APPLE & GREGORY STREETS
Building the Future
ConstructionSegmentD*Summer2018toFall2018
MLK, Jr. Blvd./Eighth St.
Peter’s Creek Pkwy. and Silas Creek Pkwy.
Off-SiteImprovements
• PetersCreekParkway/SecondStreetatFirstStreetProvideasecondleftturnlaneeastboundandathirdleftturnlanewestbound• BroadStreetatSecondStreetConverttheleftmosteastboundthroughlanetoasharedleft/throughlane• BroadStreetatFifthStreetProvideaseparateleftturnlanewestbound• BroadStreetatSixthStreetProvideaseparateleftturnlanewestbound• MarshallStreetatAcademyStreetProvideaseparateleftturnlanesouthbound• ThirdStreetatLibertyStreetProvideaseparateleftturnlanewestbound
Off-SiteImprovements
• MartinLutherKingJr.DriveatMarshallStreet&CherryStreetProvideasecondleftturnlanesouthbound• FirstStreetatNorthwestBoulevardProvideaseparaterightturnlanewestbound• FirstStreetatHawthorneRoadProvideaseparaterightturnlanenorthbound• NorthwestBoulevardatBroadStreet/ThurmondRoadProvideaseparateleftturnlaneeastbound• PetersCreekParkwayatSilasCreekParkwayProvideasecondleftturnlanesouthbound;converttherightmosteastboundleftturnlanetoathroughlaneandconverttherightmosteastboundthroughlanetoasecondrightturnlane.
Off-SiteImprovements
Building the Future
ConstructionSegmentCFall2018toFall2019
THE STROLLWAY
LIBERTY ST.
MAIN ST.
CHURCH ST.
Building the Future
ConstructionSegmentBFall2019–Summer2020
BROOKSTOWN AVE.
BROAD STREET
GREEN ST. PED BRIDGE
BUSINESS 40
MARSHALL & CHERRY STREETS
Fall 2019 – Summer 2020
Building the Future
Business40ClosurePeriodBusiness 40 Closure Period
Segment C Bridges*Bridges will be closed while under Construction:
Fall 2018 – Fall 2019
*OTHER NOTES
Section of Business 40 from Main Street to U.S. 52 will Re-Open: Fall 2019
BUSINESS 40 CLOSED
Segment B Bridges*Bridges will be closed while under Construction:
Fall 2019 – Summer 2020
FALL2018
FALL2019
SUMMER2020
• When a bridge is completed, it will re-open to traffic.• When Segment C is completed in Fall 2019, ONLY the section of Business 40 between Main Street and U.S. 52 will re-open to traffic.• The remaining sections of Business 40 will open in Summer 2020.
Bus 40 (pavement and ramps) under construction during both Bridge Segment B & Segment C: Fall 2018 – Summer 2020
Green StreetPedestrian Bridge
Broad Street
Business 40
Brookstown Ave.
Marshall StreetCherry Street
Liberty Street
The Strollway
Main StreetChurch Street
• Initial construction work DOES NOT mean closure. • Peters Creek Parkway interchange and local road work
will begin in Fall 2017 and finish in Fall 2018. • Business 40 will be closed beginning in Fall 2018 and
ending in Summer 2020. • Liberty/Main and Cherry/Marshall one-way pairs WILL
NOT be closed at the same time. • Detours and bridge closures must be noticed 30 days in
advance. • Incident Management Plan is underway to better manage
and clear accidents.
Building the Future
AFewReminders
Building the Future
A Transportation Management Plan (TMP) is currently being
reviewed by the City and NCDOT.
The TMP includes detours for vehicles and pedestrians.
Building the Future
• Currently, NO vehicular detours are planned on First or Second Streets between Broad and Marshall Streets.
• Pedestrian detours are planned for First Street between Broad and Marshall Streets.
• A capacity analysis is being conducted on the proposed detours - results are anticipated this summer.
WhatwecanSharewithyouNOW
Building the Future
DowntownRoadsthatprovide“through”accessduringClosure
Bridges to reopen once complete – detours for each bridge closure.
First and Second streets in Holly Avenue Neighborhood will NOT be
signed as detour routes.
Building the Future
ArearoadsprovidingaccesstoDowntown
Building the Future
• Incorporate new design features; visually attractive. • Created through the combined efforts of:
• NCDOT • Business 40 Bridge & Design Working Group • City of Winston-Salem • Creative Corridors Coalition
NewBridgeDesigns
Building the Future
PetersCreekPkwy.Bridge
Building the Future
ChurchStreetBridge
Building the Future
MarshallStreetBridge
Building the Future
GreenSt.PedestrianBridge
Building the Future
GreenSt.PedestrianBridge(lightedatnight)
Building the Future
StrollwayLandBridge
• Managing accidents will be critical during closure. • NCDOT is coordinating with City and County services,
including Police, Fire, EMS, to remove/clear accidents quickly.
• Will install mobile message boards to alert drivers. • Will contract with towing company to ensure quick
removal of vehicles. • Will add one more driver to IMAP routes, add routes and
mobilize equipment at specific locations.
Building the Future
ManagingAccidentsduringClosure(IncidentManagement)
Building the Future
• Free Park and Ride/Shuttle locations • Employer-based incentives for FREE RIDES • Additional cameras and signage for Incident Management • Centralized Regional Call Center • Interactive transit maps for real time info. • “Dynamic” carpool and vanpool rides • Expanded marketing and outreach program to
provide citizens alternative mobility options
www.partnc.org
APlantoEnhanceMobilityOptionsPiedmontAuthorityforRegionalTransportation(PART)
• Telecommuting • 4-day, 10-hour/day work week • Flextime, staggered work hours • Vanpool/carpool incentives • Webinars, conference calls, on-line sharing in lieu of
meetings
Building the Future
Employer’sCanHelp:
Building the Future
• Name was announced on October 21 at Groundbreaking Ceremony.
• New name for all of US 421/Business 40 (from I-40/US 421 split near Clemmons to I-40 in Guilford County).
Incaseyoudidn’tknow:Business40gotanewname!
Building the Future
OutreachandCommunication• Social media:
• Web site: www.business40nc.com • Twitter: @NCDOT_Triad #Biz40NC
• Email: • [email protected]
• Mail: • Business 40 Project, NCDOT - Division 9 375 Silas Creek Pkwy., Winston-Salem, NC 27127
PUBLIC MEETINGS – AUGUST/SEPTEMBER 2017
Building the Future
• Mobile Navigational Apps. • NCDOT communicates with all navigational companies to provide
traffic/travel information. • Currently reviewing an agreement with WAZE about “HOW” to share
data.
• Presentations like the one today.
• Newsletters – next one is this Summer.
• Small Business Liaison, SPECIFICALLY for this project.
• Downtown Partnership, Chamber and City - marketing
campaign to let people know that:
DOWNTOWN IS OPEN FOR BUSINESS!
OutreachandCommunication
Building the Future
MiracleKing,NCDOTCommunicationsOfdicer,Div.7&[email protected]
CassandraHerndon,NCDOT
ConnieJames,P.E.,CityofWinston-Salem
KarenSimon,Pres.,SimonResources
StakeholderPresentations 336-749-1411 [email protected]
PatIvey,P.E.,[email protected]
MichaelPenney,NCDOT
JamilleRobbins,[email protected]
JasonMroz,[email protected]
YourBusiness40TeamNCDOT,Design-BuildContractor,Consultant
Building the Future
Concerns,QuestionsandComments