Building the Future

Page 2: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  Design-Build Team hired to construct Business 40

•  Timeline to complete project

•  Schedule for Construction Segments A-D

•  Other off-site improvements

•  Bridge designs

•  Transportation Management Plan

•  Incident Management

•  Other mobility options

•  Communication and contact information

Building the Future

Today’sPresentation

Page 3: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

Business 40 Visualization

Visualization

Page 4: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

Flatiron Constructors, Inc./Blythe Development Company Joint Venture and HDR Engineering Inc. •  Rebuild the 1.2-mile section of Business 40, which includes

reconstruction of the roadway, 9 vehicular bridges and 2 pedestrian bridges.

•  Build a major section of the Multi-Use Path from Peters Creek Parkway to Liberty Street (remaining section from Peters Creek to Lockland will be built afterwards)

•  Increase speed limit to 55mph.

Design-BuildTeamHired

Page 5: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Timeline

Project

Completed

Late 2020

9

CONSTRUCTION/CLOSURE TIMELINE

Business 40 Improvements

NCDOT hires Design-Build Team of Flatiron/Blythe/HDR

Preliminary Soil Testing

Construction Segment A begins – 4th St. Bridge, Peters Creek Parkway and other local improvements

All of Business 40 Reopens

Fall

2017

4

3Dec 2016

Jan 2017

NCDOT announces that Business 40 will be renamed Salem Parkway in 20202

October 21

2016September

2016

Business 40 closes while construction Segments B and C begin

62017Fall

2018

ONLY the section of Business 40 from Main St. east to U.S. 52 reopens

72017Fall

2019

Construction Segment D begins – MLK Jr. Blvd. and Academy St. Improvements

5Summer

2018

8Summer

2020

1 PUBLIC MEETING AUG/SEP

2017

Page 6: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ConstructionSegmentsA-D

Fall 2019 – Summer 2020

Page 7: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ConstructionSegmentAFall2017toFall2018

PETERS CREEK PKWY.

FOURTH STREET

BUSINESS 40

APPLE & GREGORY STREETS

Page 8: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ConstructionSegmentD*Summer2018toFall2018

MLK, Jr. Blvd./Eighth St.

Page 9: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Peter’s Creek Pkwy. and Silas Creek Pkwy.

Off-SiteImprovements

Page 10: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  PetersCreekParkway/SecondStreetatFirstStreetProvideasecondleftturnlaneeastboundandathirdleftturnlanewestbound•  BroadStreetatSecondStreetConverttheleftmosteastboundthroughlanetoasharedleft/throughlane•  BroadStreetatFifthStreetProvideaseparateleftturnlanewestbound•  BroadStreetatSixthStreetProvideaseparateleftturnlanewestbound•  MarshallStreetatAcademyStreetProvideaseparateleftturnlanesouthbound•  ThirdStreetatLibertyStreetProvideaseparateleftturnlanewestbound

Off-SiteImprovements

Page 11: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  MartinLutherKingJr.DriveatMarshallStreet&CherryStreetProvideasecondleftturnlanesouthbound•  FirstStreetatNorthwestBoulevardProvideaseparaterightturnlanewestbound•  FirstStreetatHawthorneRoadProvideaseparaterightturnlanenorthbound•  NorthwestBoulevardatBroadStreet/ThurmondRoadProvideaseparateleftturnlaneeastbound•  PetersCreekParkwayatSilasCreekParkwayProvideasecondleftturnlanesouthbound;converttherightmosteastboundleftturnlanetoathroughlaneandconverttherightmosteastboundthroughlanetoasecondrightturnlane.

Off-SiteImprovements

Page 12: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ConstructionSegmentCFall2018toFall2019

THE STROLLWAY

LIBERTY ST.

MAIN ST.

CHURCH ST.

Page 13: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ConstructionSegmentBFall2019–Summer2020

BROOKSTOWN AVE.

BROAD STREET

GREEN ST. PED BRIDGE

BUSINESS 40

MARSHALL & CHERRY STREETS

Fall 2019 – Summer 2020

Page 14: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

Business40ClosurePeriodBusiness 40 Closure Period

Segment C Bridges*Bridges will be closed while under Construction:

Fall 2018 – Fall 2019

*OTHER NOTES

Section of Business 40 from Main Street to U.S. 52 will Re-Open: Fall 2019

BUSINESS 40 CLOSED

Segment B Bridges*Bridges will be closed while under Construction:

Fall 2019 – Summer 2020

FALL2018

FALL2019

SUMMER2020

• When a bridge is completed, it will re-open to traffic.• When Segment C is completed in Fall 2019, ONLY the section of Business 40 between Main Street and U.S. 52 will re-open to traffic.• The remaining sections of Business 40 will open in Summer 2020.

Bus 40 (pavement and ramps) under construction during both Bridge Segment B & Segment C: Fall 2018 – Summer 2020

Green StreetPedestrian Bridge

Broad Street

Business 40

Brookstown Ave.

Marshall StreetCherry Street

Liberty Street

The Strollway

Main StreetChurch Street

Page 15: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  Initial construction work DOES NOT mean closure. •  Peters Creek Parkway interchange and local road work

will begin in Fall 2017 and finish in Fall 2018. •  Business 40 will be closed beginning in Fall 2018 and

ending in Summer 2020. •  Liberty/Main and Cherry/Marshall one-way pairs WILL

NOT be closed at the same time. •  Detours and bridge closures must be noticed 30 days in

advance. •  Incident Management Plan is underway to better manage

and clear accidents.

Building the Future

AFewReminders

Page 16: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

A Transportation Management Plan (TMP) is currently being

reviewed by the City and NCDOT.

The TMP includes detours for vehicles and pedestrians.

Page 17: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

•  Currently, NO vehicular detours are planned on First or Second Streets between Broad and Marshall Streets.

•  Pedestrian detours are planned for First Street between Broad and Marshall Streets.

•  A capacity analysis is being conducted on the proposed detours - results are anticipated this summer.

WhatwecanSharewithyouNOW

Page 18: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

DowntownRoadsthatprovide“through”accessduringClosure

Bridges to reopen once complete – detours for each bridge closure.

First and Second streets in Holly Avenue Neighborhood will NOT be

signed as detour routes.

Page 19: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ArearoadsprovidingaccesstoDowntown

Page 20: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

•  Incorporate new design features; visually attractive. •  Created through the combined efforts of:

•  NCDOT •  Business 40 Bridge & Design Working Group •  City of Winston-Salem •  Creative Corridors Coalition

NewBridgeDesigns

Page 21: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

PetersCreekPkwy.Bridge

Page 22: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

ChurchStreetBridge

Page 23: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

MarshallStreetBridge

Page 24: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

GreenSt.PedestrianBridge

Page 25: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

GreenSt.PedestrianBridge(lightedatnight)

Page 26: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

StrollwayLandBridge

Page 27: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  Managing accidents will be critical during closure. •  NCDOT is coordinating with City and County services,

including Police, Fire, EMS, to remove/clear accidents quickly.

•  Will install mobile message boards to alert drivers. •  Will contract with towing company to ensure quick

removal of vehicles. •  Will add one more driver to IMAP routes, add routes and

mobilize equipment at specific locations.

Building the Future

ManagingAccidentsduringClosure(IncidentManagement)

Page 28: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

•  Free Park and Ride/Shuttle locations •  Employer-based incentives for FREE RIDES •  Additional cameras and signage for Incident Management •  Centralized Regional Call Center •  Interactive transit maps for real time info. •  “Dynamic” carpool and vanpool rides •  Expanded marketing and outreach program to

provide citizens alternative mobility options

www.partnc.org

APlantoEnhanceMobilityOptionsPiedmontAuthorityforRegionalTransportation(PART)

Page 29: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

•  Telecommuting •  4-day, 10-hour/day work week •  Flextime, staggered work hours •  Vanpool/carpool incentives •  Webinars, conference calls, on-line sharing in lieu of

meetings

Building the Future

Employer’sCanHelp:

Page 30: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

•  Name was announced on October 21 at Groundbreaking Ceremony.

•  New name for all of US 421/Business 40 (from I-40/US 421 split near Clemmons to I-40 in Guilford County).

Incaseyoudidn’tknow:Business40gotanewname!

Page 31: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

OutreachandCommunication•  Social media:

•  Web site: www.business40nc.com •  Twitter: @NCDOT_Triad #Biz40NC

•  Email: •  [email protected]

•  Mail: •  Business 40 Project, NCDOT - Division 9 375 Silas Creek Pkwy., Winston-Salem, NC 27127

PUBLIC MEETINGS – AUGUST/SEPTEMBER 2017

Page 32: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

•  Mobile Navigational Apps. •  NCDOT communicates with all navigational companies to provide

traffic/travel information. •  Currently reviewing an agreement with WAZE about “HOW” to share

data.

•  Presentations like the one today.

•  Newsletters – next one is this Summer.

•  Small Business Liaison, SPECIFICALLY for this project.

•  Downtown Partnership, Chamber and City - marketing

campaign to let people know that:

DOWNTOWN IS OPEN FOR BUSINESS!

OutreachandCommunication

Page 33: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

MiracleKing,NCDOTCommunicationsOfdicer,Div.7&[email protected]

CassandraHerndon,NCDOT

[email protected]

ConnieJames,P.E.,CityofWinston-Salem

[email protected]

KarenSimon,Pres.,SimonResources

StakeholderPresentations 336-749-1411 [email protected]

PatIvey,P.E.,[email protected]

MichaelPenney,NCDOT

[email protected]

JamilleRobbins,[email protected]

JasonMroz,[email protected]

YourBusiness40TeamNCDOT,Design-BuildContractor,Consultant

Page 34: Building the Future - Historic West End Holiday …historicwestend.org/wea-minutes/2017/2017_05_I40...4th St. Bridge, Peters Creek Parkway and other local improvements All of Business

Building the Future

Concerns,QuestionsandComments