    CONCRETE FLAT ROOF

    DONE BY : ABDALLAH M. KREEM 20122221096

    ABDALLAH ABO AWAD 20120221032

    INSTRUCTOR : ARCH.SANAA RGEBAT

  • 8/11/2019 Building Constraction 2

    2/22

    The first step of the concrete flat roofconstruction :

    Before starting with the contractions these

    things should be done :1-the out walls should be raised to the level ofthe roof with services such as plumping systemsand electricity in it

    2-columns should be raised with steel bars

    higher than the level of the roof for 600 mm atleast

    3- now we are reedy to start with the first step

  • 8/11/2019 Building Constraction 2

    3/22

    The first step is applying a wooden frame and this is done with

    the following steps :

    a- a wooden grid supported by steel jacks

    Steel jacks

    Wooden grid

  • 8/11/2019 Building Constraction 2

    4/22

    b- the grid is coveredwith a layer o wood

    which makes it flatand we make sure theits flat using the level

    machine

  • 8/11/2019 Building Constraction 2

    5/22

  • 8/11/2019 Building Constraction 2

    6/22

    The next step is tobuild one row of stone

    to hold the concretewhen its bumped

  • 8/11/2019 Building Constraction 2

    7/22

    Now our wooden frame is

    ready and we can move to the

    next step which is putting

    blocks (rips) in rows

  • 8/11/2019 Building Constraction 2

    8/22

    bars with the following steps:

    the beams that connects thecolumns with each other should be

    applied and its length and widthdepends on the structural designand calculations

    The relation between the steel bars in

    columns and beams

  • 8/11/2019 Building Constraction 2

    9/22

    Note : the beams can also bee tiltedthats depends on the structural destoo

    Tilted beam

  • 8/11/2019 Building Constraction 2

    10/22

    the reinforcement steel bars

    are being connected witheach other by steel ringswhich called kanat in Arabicand then applied to the roofbetween the blocks rows in

    different diameters accordingto the plans

  • 8/11/2019 Building Constraction 2

    11/22

    Note : the reinforcement steel should not touch the wood below it there must be at least 50 mm bet

    putting the steel on small pieces of broken block of 50mm height

  • 8/11/2019 Building Constraction 2

    12/22

    When all the beams

    and steal cages are

    done we add a gridof 8mm steel bars

    above the blocks

  • 8/11/2019 Building Constraction 2

    13/22

    A cantileveris a beam anchored at only one end. The beamcarries the load to the support where it is forced againstby moment and shear stress. Cantilever construction allows overhanging structures without external bracing. Cantileversalso be constructed with trusses or slabs.

    This is in contrast to a simply supported beam such as thosefound in a post and lintel system. A simply supported beam isupported at both ends with loads applied between the supp

    If h il i h fl h h l b

  • 8/11/2019 Building Constraction 2

    14/22

    If there were a cantilever in the concrete flat then the steel barsconnects it with the rest of the roof must be increased with a ladiameter

    When we are done of the reinforcement

  • 8/11/2019 Building Constraction 2

    15/22

    When we are done of the reinforcementsteel there is some services are appliedin the steel cages and above it likeelectricity and plumping systems

    Drainage system

    lighting system

    Wires pathes

    Finally the roof is ready and we can add

  • 8/11/2019 Building Constraction 2

    16/22

    Finally the roof is ready and we can addthe concrete :

    First of all the roof should be moisturized with water in order to

    better movement for the row concrete

  • 8/11/2019 Building Constraction 2

    17/22

    The bump arrival :

  • 8/11/2019 Building Constraction 2

    18/22

    The beams are the first elements that we add the concrete to and then we move on to cover the who

    A worker holds the end of the bump to guide th

    Whil ddi th t th

  • 8/11/2019 Building Constraction 2

    19/22

    While adding the row concrete there mua Vibrate to make sure thats there is nospaces between the aggregates

  • 8/11/2019 Building Constraction 2

    20/22

    When the beams are done w continue the rest of the roof and making the concrete flat usin

    flat surface

  • 8/11/2019 Building Constraction 2

    21/22

    Finally the roof is done now we have to add water to the roof for three days tell the concrete gets t

    strength

  • 8/11/2019 Building Constraction 2

    22/22