building commissioning: cx 101 brock graham, gilbane building co. michael gannon, bvh integrated...
TRANSCRIPT
![Page 1: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/1.jpg)
Building Commissioning:
Cx 101
Brock Graham, Gilbane Building Co.Brock Graham, Gilbane Building Co.
Michael Gannon, BVH Integrated Michael Gannon, BVH Integrated ServicesServices
November 15, 2010
![Page 2: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/2.jpg)
ASHRAE ?
LEED ? Federal Gov’t ?
USGBC ? ASME/ANSI ?
Building Commissioning…
Where did it come from ?
![Page 3: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/3.jpg)
The United States Navy …
U.S.S. Theodore Roosevelt (CVN 71)
Commissioned October 1986
![Page 4: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/4.jpg)
Retro-commissioning (existing buildings)
Re-commissioning (existing buildings)
Commissioning (new construction)
Building Commissioning…
What is it?
![Page 5: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/5.jpg)
The short answer:
Building commissioning (new construction) is
construction quality assurance
Building Commissioning…
What is it?
![Page 6: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/6.jpg)
Different ‘levels’ of Cx (and cost)…
Minimal: Start-up & troubleshooting
Typical: LEED
Cx on Steroids: HPB
& ASHRAE Guideline 0
Building Commissioning…
![Page 7: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/7.jpg)
Commissioning: Why do it?
•High performance building standards require…buildings to perform.
•Commissioning provides the assurance that buildings are built and perform as intended.
![Page 8: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/8.jpg)
Commissioning Process Overview:
•Design Phase
•Construction Phase
•Acceptance Phase
•Occupancy Phase
![Page 9: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/9.jpg)
Design Phase:•Review or assist in development of
OPR and BOD
•Peer reviewSometimes at many stages (SD, DD, CDs)
•Initial schedule development (CM)
•Commissioning Specification
Very important!
![Page 10: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/10.jpg)
Construction Phase:
•Submittal reviews
•Develop Cx Plan
•Kick-off with installing contractors
•Installation observation
•Contractors fill out pre-functional checklists
![Page 11: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/11.jpg)
Construction Phase (cont.):
•Further develop schedule with GC / CM
•Pre-balancing meeting
•Proactive Field Quality Control
Installation observation
Witness some testing
•O&Ms submitted and reviewed
![Page 12: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/12.jpg)
Construction Phase (cont.):
•Prefunctional checklists – developed by CxA, filled out by contractors
•Not to be confused with functional test sheets
•Manufacturer’s start-up of equipment
![Page 13: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/13.jpg)
Acceptance Phase:
•Functional testing begins (when systems are complete!)
•A ‘test case’ system can be commissioned to let contractors know what to expect
•This should be coordinated and witnessed by CxA, not installing contractors.
•Deficiencies recorded and tracked by CxA
![Page 14: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/14.jpg)
Acceptance Phase (cont.):
•Contractors correct deficiencies and notify CxA of correction
•CxA retests and records results
•Contractor-provided Owner training is organized and verified
•Validation (if called for) follows functional testing
![Page 15: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/15.jpg)
Occupancy Phase:
•Functional testing continues (realistically)
•CxA develops Systems Training Manual (aka the Recommissioning Manual)
•Owner personnel trained by CxA
•Final commissioning report produced
![Page 16: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/16.jpg)
Occupancy Phase:
•Deferred (seasonal) testing
•End-of-Warranty Review
•Post-occupancy performance verification
Needs to be addressed in design phase (e.g. are enough ATC points and / or energy meters specified to capture all usage)
![Page 17: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/17.jpg)
Commissioning Scoping•Identify Cx Scope clearly
•Typical systems include:•All HVAC (some sampling possible)•Plumbing (DHW, CA, Pumps, etc)•Electrical (lighting controls, E-power and E-lighting, etc)
•Other systems:•Fire alarm, fire protection•Security, data, PA, envelope, elevators…
![Page 18: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/18.jpg)
Commissioning Scoping
•Peer Reviews
•Early docs (SD, DD) don’t have as much to review
•Allow time in schedule for reviews and doc updates by EOR
![Page 19: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/19.jpg)
Commissioning Scoping
How much should you expect to pay?
0.5% to 3% of total construction cost
3 to 5% of total operating cost (retro) to 5% of total construction cost (validation)
2 to 3% of mechanical systems cost + 1 to 2% of electrical systems cost
It Depends on the CxA scope, as defined by the Owner
![Page 20: Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010](https://reader036.vdocuments.mx/reader036/viewer/2022082505/56649eec5503460f94bfda07/html5/thumbnails/20.jpg)
QuestionQuestions?s?