budget balances
DESCRIPTION
Budget Balances. Cash Flow . The June balance after $3M funding will be either $383k ($538k behind the original schedule) or $-155k (depending on timing of RF progress payment 3 ) This has largely solved our cash flow problem for 2011, but a similar problem remains in 2012. - PowerPoint PPT PresentationTRANSCRIPT
Budget Balances
Diag - Automation
Diag Enhanced
Diag Upgrade
Control Room
Equip Replacement
Data Infrastructure
Management
MDF
Power Supplies
Vaccum Enh.
RF antennas
RF Power
MNRF carryover
0 1000000 2000000 3000000
Jun-11Allocation
Cash Flow The June balance after $3M funding will be either
$383k ($538k behind the original schedule) or $-155k (depending on timing of RF progress payment 3 )This has largely solved our cash flow problem for 2011, but a similar problem
remains in 2012.Expenditure of the final $2M instalment in 9 months to June 2013 will be a
challenge.
10Q210Q3
10Q41-Se
p11Q1
11Q211Q3
11Q4
Jun2011adj
12Q112Q2
12Q312Q4
13Q113Q2
13Q313Q4
-1000
-500
500
1000
1500
2000
Position by FY Quarter
Position
Milestones for the coming Fiscal Year20 First plasma produced in satellite prototype 31 March 2011
Proposed Milestones to 30 June 201115 Create a database of Magnetic Configurations (magnetic coordinate
transformation) 30 June 2011
18 Decommission radio frequency source and begin installation of the upgraded sources
30 June 2011
19 Commission Spectral Line Monitors dedicated to monitoring specific impurities (e.g. C, O)
30 June 2011
Submit Milestone Report 6 30 June 2011
Proposed Milestones to 30 September 201132 Demonstration of initial diagnostics on Satellite Device 30 September 2011
Submit Annual Report 2 (including Milestone Report 7) 30 September 2011
Proposed Milestones to 31 December 201121 Commission new Radio Frequency Heating Antenna 31 December 2011
16 Upgrade multi-channel interferometer - Phase I complete 31 December 2011
23 Demonstrate operation of new Radio Frequency Heating System (source and antenna)
31 December 2011
Submit Milestone Report 8 31 December 2011
Proposed Milestones to 31 March 201224 Extend the Magnetic Database to include plasma effects 31 March 2012
25 Coherence Imaging Camera upgrade complete 31 March 2012
26 Remote operation from Sydney University 31 March 2012
Submit Annual Business Plan 3 (Including Milestone Report 9 31 March 2012
Proposed Milestones to 30 June 201227 Milestones by March 2012 which is the number to that date in the original contract
Fusion Reactors – the route to ITER and DEMO
H-1 1m3
H-1 Heliac – a type of stellarator, an advanced plasma configuration more stable and more suitable for continuous operation than a tokamak. W7X (helias) operational in 2016
A Stellarator may be the preferred configuration for “DEMO”
Australian Plasma Fusion Research Facility• Australia’s leading fusion-relevant facility• $30 million (ANU contribution ~$20 million) • Facility funding extended to 2013.
Infrastructure upgrade to
Mission:• Study physics of hot plasma in a helical magnetic container• Host development of advanced plasma measurement systems• Contribute to global research, maintain Australian presence in fusion
Improve suitability as a testbed for ITER diagnostics
Improve plasma production/reliability/cleanliness
Improving opportunities for collaboration
Improve data analysis + provide computational support
Improve diagnostics
New Initiative: Materials Diagnostic Test Facility Prototype• Explore effects of plasma on
advanced refractory materials• Joint ANU-ANSTO + USyd, UNew.++• Directly related to Gen 4 nuclear,
high temperature coal, solar• Uses H-1 power systems, diagnostics
• We are a world leader in plasma measurement science and technology
• Diagnostics are largely stand-alone modular systems well defined Australian contribution in scale & budget.
Courtesy: Alan Costley, ITER organisation
Why focus on diagnostics for ITER?
• ITER diagnostics are modular : components installed in multiple port-plugs
• Earlier discussions with ITER suggests integrated package:Erosion monitor (physics)Dust diagnostic (safety)Tritium analyser (licensing)
Budgetary Estimates
Operations $ 0.7M/yearResearch Support (internal+external) $ 2M/yearFacility Upgrades (funded component) $ 7MFacility Upgrades (unfunded component) $ 5MNew Initiatives (incl fusion materials) $ 2MITER Diagnostic Initiative $ 20M
Blackwell, Infrastructure Presentation, Future Technologies 2011
(Capability-wide – includes ITER forum strategic plan 2007: revised version being compiled)