bsbpmg402a apply time management techniques 1 apply time management techniques week 6 project time...

27
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 Certificate IV in Project Management 17871 Qualification Code BSB41507 Unit Code BSBPMG402A

Upload: rodger-austin

Post on 27-Dec-2015

219 views

Category:

Documents


0 download

TRANSCRIPT

BSBPMG402A Apply Time Management Techniques1

Apply TimeManagement Techniques

Week 6Project Time Processes – Part 2

Certificate IV in Project Management 17871Qualification Code BSB41507

Unit Code BSBPMG402A

BSBPMG402A Apply Time Management Techniques2

Project Time Processes – Part 2

• PMBOK Project Time Management Processes - 6.1 Define Activities

6.2 Sequence Activities

6.3 Estimate Activity Resources

6.4 Estimate Activity Duration

6.5 Develop Schedule

6.6 Control Schedule

• Related processes from Project Integration Management –

4.1 Develop Project Charter

4.2 Develop Project Management Plan

BSBPMG402A Apply Time Management Techniques3

6.3 Estimate Activity Resources

• The process of estimating the type and quantities of material, people, equipment or supplies required to perform each activity

• Closely related to the Estimate Costs process (7.1) and normally done simultaneously

• Sometimes the resources are captured in project management software, most particularly human resources

• Supplementary registers are often maintained for non human resources

• Occurs during the Planning Phase

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques4

6.3 Estimate Activity Resources

• Inputs to Estimate Activity Resources

Activity list and attributes

Resource Calendars

Resource availability and skills

Staffing policies and procedures

Procurement policies and procedures

• Tools and techniques to Estimate Activity Resources

Adapted from PMBOK 4th Edition

Bottom-UpEstimating

ExpertJudgement

AlternativesAnalysis

PublishedEstimating

Data

ProjectManagement

Software

BSBPMG402A Apply Time Management Techniques5

6.3 Estimate Activity Resources

• Published Estimating Data

Many industries (eg Construction) have standard production rates and unit costs for common activities

• Bottom-Up Estimating

Decomposing activities into more detail to assist with estimation

• Project Management Software

Can assist with planning, organising and managing resources

Different levels of sophistication Initiation Planning Execution Close

Monitor

Control

Adapted from PMBOK 4th Edition

BSBPMG402A Apply Time Management Techniques6

6.3 Estimate Activity Resources

• Outputs of this process include –

Activity Resource Requirements

– Captured in project management software or supplementary registers

Resource Breakdown Structure

– Hierarchical chart of resources required

– Commonly depicted as the project organisation structure for human resources

Revised Activity List and Attributes

Revised Resource Calendar

– Resources marked as unavailable

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques7

6.4 Estimate Activity Duration

• The process of approximating the number of work periods needed to complete individual activities with the assigned or estimated resources

• Previous experience in the type of project and activities being estimated greatly helps with the accuracy of duration estimates

• Duration is a function of work effort and resources

• Most project management software can perform this function

• Occurs during the Planning Phase

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques8

6.4 Estimate Activity Duration

• Inputs to Estimate Activity Duration

Activity list and attributes

Activity Resource requirements and estimates

Resource Calendars

Project Scope Statement

Productivity metrics and estimating data

• Tools and techniques to Estimate Activity Duration

Adapted from PMBOK 4th Edition

Three-PointEstimating

ExpertJudgement

AnalogousEstimating Parametric

Estimating

ReserveAnalysis

BSBPMG402A Apply Time Management Techniques9

6.4 Estimate Activity Duration

• Analogous EstimatingDevelops duration estimates based on previous projects with

similar size, risk and complexity

Relies heavily of expert judgement and previous experience

Less costly and less time consuming than other methods

Least accurate

Most common form of duration estimating

• Parametric EstimatingDuration is quantified by multiplying the quantity of work by

the labour hours required

Relies on published estimating data

Common in Construction

Initiation Planning Execution Close

Monitor

Control

Adapted from PMBOK 4th Edition

BSBPMG402A Apply Time Management Techniques10

6.4 Estimate Activity Duration

• Three-Point Estimates - PERT

Calculates the Expected activity duration based on the weighted average of the Most Likely, Optimistic and Pessimistic estimates

Often more accurate than other methods and quantified range of uncertainty

• Reserve Analysis

Inclusion of contingency

Can be calculated for each activity

Can be calculated for entire project

Often a percentage based on risk or complexity

Initiation Planning Execution Close

Monitor

Control

Adapted from PMBOK 4th Edition

BSBPMG402A Apply Time Management Techniques11

6.4 Estimate Activity Duration

• The major output of this process

Activity Duration Estimates

Draft or High Level Project Duration Estimate

• Often include some form of range of possible results

• Most common form of range is plus or minus - eg

2 weeks +/- 2 days – the activity could take between 8 and 12 days

3 weeks +/- 30% - the activity could take between 2 weeks and 4 weeks

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques12

6.5 Develop Schedule

• The process of analysing activity sequences, durations, resource requirements and schedule constraints to create the project schedule

• All this data is entered into a project scheduling tool which generates a schedule with planned dates for completing project activities

• An iterative process with several cycles of refinement

• Baseline Schedule developed in Planning Phase

• Simultaneous with 6.1, 6.2, 6.3 & 6.4

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques13

6.5 Develop Schedule

• Inputs to Develop Schedule

Activity list and attributes

Project Schedule Network Diagrams – relationships and dependencies

Activity Resource Requirements

Resource Calendars

Activity Duration Estimates

Project Scope Statement

Project Scheduling Tool

Scheduling Methodology and Standards

Overall Project Calendar and PrioritiesAdapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques14

6.5 Develop Schedule

• Tools and techniques to Develop Schedule

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

Critical ChainMethod

SchedulingTool

ScheduleNetworkAnalysis Critical Path

Method

ResourceLevelling

ScheduleCompression

ApplyingLeads &

Lags

What-ifScenarioAnalysis

BSBPMG402A Apply Time Management Techniques15

• Critical Path MethodWas developed in the 1950s by the Dupont Corporation The Critical Path Method, abbreviated CPM, or Critical Path

Analysis, is a mathematically based algorithm for scheduling a set of project activities.

It takes the activities in the Work Breakdown Structure, the durations and the interdependencies, and calculates the longest path through the project.

It is the longest total duration of all the activities required to complete a project

Advanced techniques and calculations (such as early start and early finish dates, and late start and late finish dates) are now carried out using project scheduling tools

Does a forward and backward pass through the schedule with no regard for resource limitations

Critical Path & Critical Chain

Adapted from PMBOK 4th Edition

BSBPMG402A Apply Time Management Techniques16

• Critical Chain MethodUndertakes the same form of analysis and calculations, but

takes into consideration the resource availability and constraints

Takes the Critical Path and resource availability to produce a resource constrained critical path OR Critical Chain

It is the longest total duration of all the activities required to complete a project, considering resource availability and limitations

Often done simultaneously with Critical Path

Critical Path and Critical Chain

Adapted from PMBOK 4th Edition

Critical Chain = Resource Constrained Critical Path

BSBPMG402A Apply Time Management Techniques17

Schedule Compression

Shortens the project schedule without changing project scope

1. Crashing

Only works for activities where additional resources will shorten duration

Does not always produce a viable schedule

Always results in increased cost

Sometimes results in increase risk

Cost

RiskCrashing leads to

increased

increased

BSBPMG402A Apply Time Management Techniques18

Schedule Compression

Shortens the project schedule without changing project scope

2. Fast Tracking

Phases or activities normally performed sequentially are performed in parallel

Only works if activities can be overlapped to shorten duration

May result in rework and increased risk

Can result in decreased costCost

Risk

Fast Tracking leads to

decreased

increased

Reworkincreased

BSBPMG402A Apply Time Management Techniques19

6.5 Develop Schedule

• The major outputs of this process

Project Schedule

– Milestone charts

– Bar chart – GANTT charts

– Project Schedule Network Diagrams – PERT Charts

Schedule Baseline

Revised Activity Resource Requirements

Revised Activity Attributes

Project Calendar

Revised Risk register

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques20

What is a GANTT chart?

• Gantt charts are named after their creator, an American engineer Henry Laurence Gantt, who created the first bar charts in the early 1910’s.

• It converts the Work Breakdown Structure into a graphical display of a project schedule

• It displays the durations of all scheduled activities including the interdependencies

• Often also includes information on project milestones and resource allocation to activities

• It has become one of the most widespread project management tools due to the prevalence of MS project

BSBPMG402A Apply Time Management Techniques21

Sample GANTT Charts

BSBPMG402A Apply Time Management Techniques22

What is a PERT chart?

• PERT stands for Programme Evaluation and Review Technique

• It was created by a Naval scientist, Frederick Taylor, in the 1950’s

• It is a project management technique for determining how much time a project needs before it can be completed.

• Each activity is assigned a best, worst and most probably completion time estimate.

• These estimates are then used to determine the average completion time and are represented graphically in a network diagram

BSBPMG402A Apply Time Management Techniques23

Sample PERT Charts

BSBPMG402A Apply Time Management Techniques24

6.6 Control Schedule

• The process of monitoring the status of the project in order to update progress and manage any changes to the baseline project schedule

• Includes –

Determining the current status of the project schedule

Influencing the factors that create the schedule changes

Determining that the project schedule has changed

Managing changes as they occur

• Occurs during Monitoring & Controlling

• Is part of Perform Integrated Change Control (4.5) Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques25

6.6 Control Schedule

• Inputs to Control Schedule

Project Management Plan

Project Schedule

Performance data

Project Reporting standards

• Tools and techniques to Control Schedule

Adapted from PMBOK 4th Edition

VarianceAnalysis

StatusReports

PerformanceReviews

ProjectManagement

Software

SchedulingTool

ResourceLevelling

ScheduleCompression

ApplyingLeads &

Lags

What-ifScenarioAnalysis

BSBPMG402A Apply Time Management Techniques26

6.6 Control Schedule

• The major outputs of this processWork Performance measurement

Costs and impacts of variance and corrective actions

Lesson learned

Change Requests

Project Management Plan updates– Schedule baseline

– Schedule management plan

– Cost baseline

Project Schedule updates

Status Reports

Adapted from PMBOK 4th Edition

Initiation Planning Execution Close

Monitor

Control

BSBPMG402A Apply Time Management Techniques27

Team Assignment Criteria

Team AssignmentComponents

Marks Basic Competency Higher Competency

Work Breakdown Structure including deliverable/activity duration (start and end dates) and interdependencies

5 Basic WBS presented in Excel or a tableHigh level deliverables and activities includedSome interdependencies are indicated

Detailed WBS in MS ProjectPhases broken down into detailed deliverables and activities with appropriate indentationInterdependencies on all activities

Baselined Gantt chart indicating the critical path

5 Basic Gantt chart Report showing critical path

Detailed Gantt chartReport showing critical path and the duration

Explanation of the tools and techniques used to estimate the activity durations and timelines

10 Basic understanding of tools and techniquesAt least two estimating methods used

Advanced understanding of tools and techniques More than two methods used and experts consulted

Total 20 13 to 16 17 to 20