brookland & turkey thicket community meeting (03 23-13)

16
BROOKLAND COMMUNITY MEETING MARCH 23, 2013 Turkey Thicket “Play DC Initiative” and the new Brookland Middle School Community Meeting March 23, 2013

Upload: dc-department-of-general-services

Post on 22-May-2015

1.524 views

Category:

News & Politics


1 download

DESCRIPTION

We enjoyed our meeting today with the Ward 5 residents. If you happened to have missed the meeting or simply wish to share the update and new design concepts with your neighbors, friends and family feel free to share! Thanks. Get Social With Us on Facebook & Twitter Today! http://facebook.com/dcdgs & http://twitter.com/dcdgs

TRANSCRIPT

Page 1: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Turkey Thicket “Play DC Initiative”

and the new

Brookland Middle School

Community Meeting

March 23, 2013

Page 2: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

AGENDA

• Introductions

• Rules of the Road

• Meeting Goals

• Project History

• What We Considered

• Current Project Status

• Site Options

• Next Steps

Page 3: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

COMMUNITY MEETING GOALS

• Where is the school situated on the site

• What is the status of the playground construction project

• What is the timeline for the school and playground initiatives

• What is the budget for the school and playground initiatives

• How is the school and recreation center parking going to be

addressed

• Who makes the final decisions

• How will information regarding the projects be communicated

more effectively

Page 4: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

PROJECT HISTORY

Turkey Thicket Park

• Included in DPR “Play-DC” Initiative for outdoor space upgrades

during 2013.

• Design concept by Studio 39 developed in December 2012 based

on community input.

Brookland Middle School

• Site selected for arts-focused middle school through efforts of DCPS

and Ward 5 Council on Education.

• SIT created to guide school development and share information.

• Educational Specifications developed in mid-2012 – Program

includes 23 classrooms, performance space and gymnasium.

• Hartman-Cox/Grimm+Parker architectural team selected in

December 2012 to begin concept designs.

Page 5: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

WHAT WE HAVE CONSIDERED

• Achieving a World Class Middle School

• Playground Development Plan and Timeline

• Stand-Alone or Co-Located School and Recreation Center

• Tennis Courts and Exterior Park Amenities

• Park Site Access

• Recreation Center and School Facility Access

• Pick-up and Drop-off

• Traffic

• Parking

Page 6: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CURRENT PROJECT STATUS

• MISSION CRITICAL: Find the Solution that Best Balances the

Needs, Wants, Logistics, Budget & Timelines of All Parties

• DGS, DPR, DCPS and the Community Working Together to Best

Address the Neighborhood’s Needs

• A Collaborative Effort to Create the Most Efficient and Useful Space

for Both Turkey Thicket and Brookland Middle School

• Brookland Middle School Budget = $50 million

• Turkey Thicket Budget = Determined Based on Final Concept

• DGS Will Oversee Project and Lead Communications Effort with

Community Once Designs and Timeline are Finalized

• DCPS and DPR are DGS’ Clients

• Consistent Interaction with SIT Team, ANC, Playground Group,

Community Groups and Neighborhood Residents

Page 7: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

N

Aerial View of Current School Site

Page 8: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

N

CONS:

• DPR 2013 “Play DC” park upgrades delayed until 2014

• Potential increase in traffic along 10th St

• Park areas will be closed at times for school building construction

• Secure access point required between school population and rec center population

• Increased project budget due to demolition and rebuild of interior and exterior rec center amenities

• Areas within rec center will require temporary closure to construct reconfiguration & connection to school

PROS: • Potentially more space for surface parking

• School has closer and easier access to playing fields

• Shifting of park amenities provides a more flexible design

• School has proper classroom orientation for natural light and energy efficiency

• Shared school facilities provides for “expansion” of recreation center through shared use of amenities

CO-LOCATION OPTION WITH RECREATION CENTER

Page 9: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

N

STAND ALONE SCHOOL AT 10th Street PROS:

• School in close proximity to rec center to provide access to amenities

• Provides physical separation between school and rec center

• Students have easy access to playing fields

• School has better access to light and views

• School entrance on less active street

CONS:

• Less green space available for park use

• Additional exterior park facilities are involved in large construction project requiring extensive periods of closure for construction

• Project budget must be increased to demolish and rebuild outdoor rec areas and address site topography

Page 10: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

N

STAND-ALONE SCHOOL AT SOUTH POINT OF PARK PROS:

• School located at civic end of site

• School has ideal classroom orientation for natural light and energy efficiency

• Parking lots centrally located for possible shared use during non-school hours

• Provides physical separation between school and rec center

• School location is closer to Metro

CONS:

• Outdoor park space is reduced with less flexibility for outdoor space design and layout

• North end of site has topography changes which poses issues and additional costs for constructing playing fields

• All exterior park facilities are involved in the construction project, requiring extensive periods of closure for construction

• Project budget must be increased to demolish and rebuild outdoor rec areas and address site topography

Page 11: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

N

STAND-ALONE SCHOOL ON EXPANDED EXISTING SCHOOL SITE PROS:

• Additional open space added between school and tennis courts

• Provides physical separation between school and rec center

• Additional space available for parking or play-space

• Minimal impact to 2013 “Play-DC” upgrades

• School has civic presence on Michigan Ave

CONS:

• No Drop-off to offset street traffic on Mich. Ave.

• School constructed in close proximity to smaller scale houses

• Potentially reduces tennis courts and delays Play-DC upgrades

• Accessing fields from school requires crossing drive aisle and moderate walk

• Classroom orientation is not optimal for natural light and energy efficiency

Page 12: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONS:

• Limited site area available for surface parking

• School building abuts tennis courts and enclosure fence

• School constructed in close proximity to smaller scale houses

• Accessing fields from school requires crossing drive aisle and moderate walk

• Classroom orientation is not optimal for natural light and energy efficiency

STAND-ALONE SCHOOL ON EXISTING SCHOOL SITE PROS: • DPR 2013 “Play-DC” upgrades can continue for 2013 completion

• School pickup and drop off drive helps alleviate traffic problems on streets

• Rec center would not experience any construction related closures

• School construction will have little impact on park and rec center

• Provides separation between school and rec center

• School has civic presence on Michigan Ave

• School can be built with budgeted funds

N

Page 13: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Next Steps

• Posting of the presentation on the DGS website

• Collect additional comments from this presentation

• DGS to make recommendation to DPR and DCPS

• DGS, DPR and DCPS make final decision

• Next community meeting (Notification of Decision)

• Site Investigations and Traffic Study will continue

• Additional SIT team and community meetings schedule will be

announced (announcement of “Play DC” construction schedule,

site enhancements and parking will be discussed)

Page 14: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Questions & Answers

Timeline and next steps are next….

Page 15: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

COMMUNITY MEETING GOALS

• Where is the school situated on the site

• What is the status of the playground construction project

• What is the timeline for the school and playground initiatives

• What is the budget for the school and playground initiatives

• How is the school and recreation center parking going to be

addressed

• Who makes the final decisions

• How will information regarding the projects be communicated

more effectively

Page 16: Brookland & Turkey Thicket Community Meeting (03 23-13)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013