BROOKHAVEN SCIENCE ASSOCIATES
1
2014 SC PM WorkshopJuly 15-17, 2014
Brookhaven National Laboratory
Cathleen Lavelle
Diane Hatton, Joe Eng
![Page 2: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/2.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
2
One of five multi-program science labs managed by DOE-SC
Established in 1947; operated by BSA since 1998
Approximately 3,000 scientists, engineers, and support staff; 4200 facility users; 1,000 scientists visit each year
BNL operates world-class user facilities for research
Key missions in: Basic Energy Sciences Nuclear Physics Bio-medical Sciences High Energy Physics Energy Supply / Climate Change
Seven Nobel Prizes
BNL Overview
![Page 3: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/3.jpg)
BNL at a Glance: FY 2013DOE SC - Physical Assets
• 5322 acres• 310 buildings
Human Capital• 2882 FTEs (3012 heads)• Direct/indirect: 0.59/0.41• 480 undergrad/grad students • 4134 facility users• 1377 visiting scientists
3
FY 2013 Total Lab Operating Costs: $629.9 million ($652.8)*FY 2013 Total DOE/NNSA Costs: $22.6 millionFY 2013 WFO (Non-DOE/Non-DHS) Costs: $52.5 millionFY 2013 WFO as % Total Lab Operating Costs: 8.3%FY 2013 DHS Costs: $0.8 million *including OLABS ($8.5M) and A/R Other ($14.4M)
FY 2013 Funding by Source ($M)
![Page 4: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/4.jpg)
4
Historical Project Budget and 5 Year Project Outlook
Historical Annual Construction Budget (10 year average not including GPP/IGPP)•Line Item—$109M•MIE—$21M•Operating Expense*—$467M
Projected Annual Construction Budget (not including GPP/IGPP)•Line Item—$12M•MIE—$46M•Operating Expense*—$561M
*Operating includes all operating. Historically, operating funds associated with construction projects are not reported separately.
![Page 5: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/5.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
5
BNL Organization
![Page 6: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/6.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
6
Project Management Center Organization
Recent Change at BNL:
Provide centralized tools and standards to BNL project managers:Large Capital Asset Projects andSmall projects (tailored approach)
•Keep core staff small•Centralized Resource Pool•Process Improvement•Transfer knowledge•Support/Train Dept. resources
![Page 7: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/7.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
7
BNL’s Major Projects
Completed Projects CFN, ISB, RSLII
Ongoing Projects NSLS-II NEXT (NSLS-II Experimental Beamlines) ABBIX (Advanced Biological Beamlines)
US Atlas Upgrade Partner/Other Beamlines
Future Projects sPHENIX Electron Ion Collider
TPC greater than $20M
![Page 8: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/8.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
8
• Large Projects managed within Directorate
• Central Project Management Center (PMC) provides support, tools , systems, process, training, resources
• Institutional Risk Management Committee (IRMC)
– Comprised of Lab Director and senior management
– conducts periodic project reviews status/issues (quarterly)
– Scope, schedule, cost, ESH, procurement, staffing, risks, PM concerns
• Institutional Key Performance Parameters (IKPIs) – monitored quarterly reporting of major project performance
• Director’s Reviews in advance of DOE reviews (Internal/External) and EVMS Annual Laboratory Self Assessment
• Standardization of PM Systems and Reporting
Managing Major/MIE ProjectsLab Oversight
![Page 9: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/9.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
9
BNL Project ProjectionProjects Program Sponsor TPC ($M) &
BNL's WBS FY Start FY Finish CD-Status
NSLS-II BES $912 2007 2015 CD-3NEXT BES $90 2013 2017 CD-3ABBIX BES $45 2013 2016 CD-3 EquivOperations (NxtGen) & Partner Beamlines BES $43 2014 2017 TBDNSLS Hazadous Removal BES $5-10 2015 2016 TBD APUL HEP $12 2011 2014 CD-4ATLAS PH-I HEP ($33) $12 2014 2018 CD-1ATLAS PH-II HEP ($200) $35-45 2016 2022 TBDLARP-LHC Accelerator Luminosity Upgrade HEP ($200) $35-45 2015 2024 TBDLSST HEP ($150) $40 2013 2019 CD-3LAR1-ND (Short Base Line Exp) HEP ($13) $3 2014 2018 TBDDark Side Dark Matter HEP ($10) $2 2014 2018 TBDAccelerator Test Facility (ATF) Relocation HEP $5 2014 2017 CD-2 EquivLBNE HEP ($1,500) $50 2013 2028 CD-1 HFT NP $16 2011 2015 CD-3sPHENIX NP $50 2015 2020 TBDBLIP Raster NP $5 2014 2016 CD-3 EquivLEReC NP $10 2014 2018 CD-2 EquivElectron Ion Collider (EIC) NP TBD 2018 2026 TBDEIC Detector NP TBD 2018 2026 TBD RSL II SLI $51 2010 2014 CD-4CFR-I SLI $25-31 2016 2018 TBDCFR-II SLI $30-36 2018 2020 TBDCFR-III SLI $40-45 2020 2022 TBDCentral Computer Bldg SLI $27-33 2022 2024 TBD UESC 3rd Party $15 2014 2017 CD-3 EquivAlternative Finance Office Bldg 3rd Party $38 2017 2021 TBDPortal to Discovery 3rd Party $50 2017 2021 TBDAEGIS 3rd Party $70 2016 2019 TBD
![Page 10: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/10.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
10
• Internal/External Director’s Reviews• Advisory Committees for Project guidance• IRMC –Institutional Risk Management Committee
(Project Management Reviews)• Home grown systems that provide tools/data for
PM/CAMs ( cost estimating, Risk ID, configuration management and cost/schedule reporting).
• Central Project Management support provides tools, templates, systems, process, training, resources
What works well at BNL
![Page 11: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/11.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
11
• Applying tailored Project Management for small R&D projects – Risk based graded approach
• Communicate Lessons Learned across projects – Directorates/projects act in isolation
• Develop Project Management “track” and formal training for Project Managers
• Streamline systems – Peoplesoft/Project SW tools interfaces need to be established. IT support required.
Improvements BNL is working on
![Page 12: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/12.jpg)
BROOKHAVEN SCIENCE ASSOCIATES
12
Backup Slides
![Page 13: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/13.jpg)
13 BROOKHAVEN SCIENCE ASSOCIATES
BNL Manages Projects with Proven Systems and Software
Deltek Cobra™
Cost and Earned Value Management Solution
Deltek Cobra™
Cost and Earned Value Management Solution
SchedulingSoftware Financial
Management System
StandardRates & Burdens
• Burdens• Rates• Escalation
• Milestones• Critical Path• Deliverables• Resource Loading
• Authorized Funding• Commitments• Actual Costs
• Performance Baseline• Analysis• Reporting
• Fiscal Year Budgets
![Page 14: BROOKHAVEN SCIENCE ASSOCIATES 1 2014 SC PM Workshop July 15-17, 2014 Brookhaven National Laboratory Cathleen Lavelle Diane Hatton, Joe Eng](https://reader034.vdocuments.mx/reader034/viewer/2022042821/56649cae5503460f949708fa/html5/thumbnails/14.jpg)
14 BROOKHAVEN SCIENCE ASSOCIATES
Web basedCost Estimating
(CED)
IntegratedProject Database
(IPD/IPDv2)
Web basedCost Estimating
(CED)
IntegratedProject Database
(IPD/IPDv2)
Primavera 6.2Schedule
Primavera 6.2Schedule
Cost/Schedule Baseline Development/Measurement
WBS &WBS DictionaryResources:-Labor hours-M&S $-Travel $Schedule:-Activities-Durations Risk ID & AssessmentBOE
Resources•Develop Logic/dates•Timephase resources•Milestones
ResourcesSchedule
•EV assessment•Rate Tables•Burdened Esc $
CobraCost Baseline
Reporting
Activities, Durations
Iterative Process to develop Proposed Baseline