This talk is a slightly modified and condensed version of one I gave at DCD Converged in London on the morning of November 19, 2014. I gave it at VIP dinner sponsored by Siemens on the evening of that same day. I moved "One boss, one team, and one budget" to be the 2nd thing management can do, because tying IT to business performance with metrics is a prerequisite to doing the hard work of busting the silos. I realized this during the talk ("One boss, one team, and one budget" was original item #1).TRANSCRIPT
![Page 1: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/1.jpg)
Bringing data center management and technology
into the 21st century Jonathan Koomey, Ph.D.
Research Fellow, Steyer-Taylor Center for Energy Policy and Finance, Stanford University
http://www.koomey.com Presented at DCD Converged
London, UK November 19, 2014
1 Copyright Jonathan G. Koomey 2014
![Page 2: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/2.jpg)
Can you answer these key management questions?
• How many servers do you have? • How many of the servers are comatose? • What is the average utilization for those that
aren’t comatose? • Do you track costs and benefits from data
center operations each year? – Total? – At the business unit level? – At the project level?
Copyright Jonathan G. Koomey 2014 2
![Page 3: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/3.jpg)
Most companies can’t!
3 Copyright Jonathan G. Koomey 2014
![Page 4: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/4.jpg)
What do executives need to know about information
technology (IT)?
4 Copyright Jonathan G. Koomey 2014
![Page 5: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/5.jpg)
Modern businesses can’t succeed without IT
5
Brynjolfsson, Erik, and Andrew McAffee. 2014. The Second Machine Age: Work, Progress, and Prosperity in a Time of Brilliant Technologies. New York, NY: W. W. Norton & Company. [http://amzn.to/1gYHEGk]
Copyright Jonathan G. Koomey 2014
![Page 6: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/6.jpg)
However…
6 Copyright Jonathan G. Koomey 2014
![Page 7: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/7.jpg)
IT is almost invariably fragmented and divorced from
business performance Only management can fix that
7 Copyright Jonathan G. Koomey 2014
![Page 8: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/8.jpg)
Almost all enterprise data centers are paragons of inefficiency, but management doesn’t know it, so
they don’t fix it.
8 Copyright Jonathan G. Koomey 2014
![Page 9: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/9.jpg)
Inefficient IT increases costs, decreases revenues, AND
reduces the rate of innovation
9 Copyright Jonathan G. Koomey 2014
![Page 10: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/10.jpg)
What can management do?
10 Copyright Jonathan G. Koomey 2014
![Page 11: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/11.jpg)
I. Tie IT performance to business performance
11 Copyright Jonathan G. Koomey 2014
![Page 12: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/12.jpg)
How?
12 Copyright Jonathan G. Koomey 2014
![Page 13: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/13.jpg)
Metrics!
13 Copyright Jonathan G. Koomey 2014
![Page 14: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/14.jpg)
Creating the right metrics is not as easy as it sounds
14 Copyright Jonathan G. Koomey 2014
![Page 15: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/15.jpg)
How far are you from this?
Copyright Jonathan G. Koomey 2014 15
ProfitsComputation
= (Revenues - Costs)/Computations
![Page 16: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/16.jpg)
Complexities • Some parts of IT are really cost centers, but
some generate revenues • Hard work needed to build up to revenues
and costs/computation – Activity based costing (Romonet) – Detailed cost and inventory modeling (Apptio) – Server based inventory and operations (DCIM)
• Computations – first order estimate = utilization * GHz * secs/year
(good enough to start)
Copyright Jonathan G. Koomey 2014 16
![Page 17: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/17.jpg)
Metrics drive organizational change
• Focus on the whole system – reducing total costs per computation – increasing total value from computation
• “Show back” the consequences of choices to every employee, then “charge back” if needed
• Key Performance Indicators (KPIs) for management include both costs AND benefits
17 Copyright Jonathan G. Koomey 2014
![Page 18: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/18.jpg)
You need a model of costs and revenues that tracks all
components in the data center over time!
18 Copyright Jonathan G. Koomey 2014
![Page 19: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/19.jpg)
II. One boss, one team, one budget!
19 Copyright Jonathan G. Koomey 2014
![Page 20: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/20.jpg)
III. Use IT to transform IT
• Standardized IT deployments • Move from “sit down restaurant” to “buffet
style” IT • Move many users to internal or external cloud • Software should matter more, hardware less • Measure, experiment, learn, and replicate • Use computer modeling to anticipate effects
on cooling/power of ∆s in existing facilities
20 Copyright Jonathan G. Koomey 2014
![Page 21: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/21.jpg)
Conclusions
• What management can do – I. Drive institutional change using metrics that
tie IT performance to business performance – II. One boss, one team, one budget – III. Use IT to transform IT
• Summary: Make IT serve the business!
21 Copyright Jonathan G. Koomey 2014
![Page 22: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/22.jpg)
IT should NOT be treated as a cost center, it should be a cost reducing
profit center that also improves corporate and customer
environmental performance
22 Copyright Jonathan G. Koomey 2014
![Page 23: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/23.jpg)
For more details on the ongoing (Nov 10 to Dec 12, 2014) online class titled Data Center
Essentials for Executives, see http://goo.gl/K4kJG2
Also see my 2014 article titled Bringing
Enterprise Computing into the 21st Century: A Management and Sustainability Challenge
http://goo.gl/WYFBjb
23 Copyright Jonathan G. Koomey 2014
![Page 24: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/24.jpg)
Watch Dean Nelson (eBay) talk about how companies can turn IT
into a profit center (35 mins): https://www.youtube.com/watch?
v=h6NJpHgReE8&feature=youtu.be
24 Copyright Jonathan G. Koomey 2014
![Page 25: Bringing data center management and technology into the 21st Century](https://reader033.vdocuments.mx/reader033/viewer/2022052907/559444f61a28ab0c308b4808/html5/thumbnails/25.jpg)
A case study of a company that has been successful at tying its IT performance to business performance
Schuetz, Nicole, Anna Kovaleva, and Jonathan Koomey. 2013.
eBay: A Case Study of Organizational Change Underlying Technical Infrastructure Optimization. Stanford, CA: Steyer-Taylor
Center for Energy Policy and Finance, Stanford University. September 26. [http://www.mediafire.com/view/8ema554a2ho9ifj/
Stanford_eBay_Case_Study-_FINAL-130926.pdf]
25 Copyright Jonathan G. Koomey 2014