brief introduction to earned value management (evm)earned value management (evm) 12/25/06 evm...

43
12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Brief Introduction to Earned Value Management (EVM)

Upload: others

Post on 23-May-2020

28 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 1

12/25/06 EVM Introduction 1

Brief Introduction toEarned Value Management (EVM)

Page 2: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 2

12/25/06 EVM Introduction 2

Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

Page 3: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 3

12/25/06 EVM Introduction 3

The Problem

• A successful program manager says: “We completed the project we promised to deliver in the time we promised and with the budget we asked for.”

• The standard source of information about the status of the project is the status of the budget, which only tells you how quickly and how completely you are spending the money you have.

• What you really want to track is how quickly and how completely you are accomplishing the work you promised to do.

• The coupling of money spent to work done or schedule consumed is loose and nonlinear.

• Also, the expenditure track is a one-dimensional projection of a two-dimensional problem.

ScheduleVariance

BudgetVariance

(under)

(over)

(ahead)(behind)

Page 4: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 4

12/25/06 EVM Introduction 4

Why You Need to Know BothCost and Schedule Variances

• Project A is in good shape, under budget and ahead of schedule.• Project B is over budget, but if we realize

it is ahead of schedule, we canslow the effort to save money.

• Project D’s cost variance looks better than A’s, but if we realize it is behind schedule, we can spend more to catch up.

• Project C looks just like B if we only look at the cost variance, but we can’t slow down to save money.And it looks just like D if we only look at schedule, but we can’t spend more to catch up. It’s time to rescope!

ScheduleVariance

BudgetVariance(under)

(over)

(ahead)(behind)

A

BC

D

Page 5: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 5

12/25/06 EVM Introduction 5

1. DEFINE THE WORK AND ORGANIZE TEAMS

100

4060

1525

3030

2. SCHEDULE THE WORK

3. ALLOCATE BUDGETS

$

CONTRACT BUDGET BASE

TIMEBASELIN

E

So What Do We Have to Work With?

MANAGEMENT RESERVE (MR)

Each chunk of work corresponds to a chunk of budget and a chunk of schedule.

Page 6: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 6

12/25/06 EVM Introduction 6

• For each chunk of work, define its ‘value’ as the budget assigned to it.

• When you complete that chunk of work, you have ‘earned’ its value.

• The total earned value to date gives you a point on the ($,time)graph – the Budgeted Cost of Work Performed (BCWP).

• You could compare this to the actual amount of work that you were supposed to have completed by this point in the schedule, as measured by its budgeted cost – the Budgeted Cost of Work Scheduled (BCWS), another point on the ($,time) graph.

• You could also compare it to the actual amount spent to complete the chunks of work done to date – the Actual Cost of Work Performed (ACWP), a third point on the ($,time) graph.

• Look at what information these comparisons give about the status of the project.

The Basic Idea

Page 7: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 7

12/25/06 EVM Introduction 7

Budgeted Cost of Work Scheduled(BCWS)

Total Budget = $5,000to be spent over 5 monthsWe plan to deploy 1 standeach month at an estimated cost of $1,000.BCWS each month = $1,000Month 1

BCWS = $1,000

Month 4BCWS = $1,000

Month 3BCWS = $1,000

Month 5BCWS = $1,000

Month 2BCWS = $1,000

Each dollar of BCWS represents a specific dollar of work scope. BCWS is aggregated and summed as the performance measurement baseline.

Each dollar of BCWS represents a specific dollar of work scope. BCWS is aggregated and summed as the performance measurement baseline.

Page 8: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 8

12/25/06 EVM Introduction 8

Budgeted Cost of Work Performed(BCWP)

We’re at the end of thesecond month, but only1 stand is complete. Value of work performed = $1,000

You earn value the same wayas it was budgeted in the baseline.

You earn value the same wayas it was budgeted in the baseline.

Page 9: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 9

12/25/06 EVM Introduction 9

Schedule Variance(SV)

BC WSBC WP

Of the work we scheduled to have done,how much did we budget for it to cost?

Of the work we actually performed,how much did we budget for it to cost?

SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)

formula: SV $ = BCWP - BCWS

example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)

SCHEDULE VARIANCE is the difference between work scheduled and work performed (expressed in terms of budget dollars)

formula: SV $ = BCWP - BCWS

example: SV = BCWP - BCWS = $1,000 - $2,000 SV= -$1,000 (negative = behind schedule)

BU

DG

ET B

ASE

D

Page 10: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 10

12/25/06 EVM Introduction 10

Schedule Variance(SV)

$

5 months

BCWS“the baseline”

BCWP“earned value”

TIME

5,000

sv

Page 11: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 11

12/25/06 EVM Introduction 11

Actual Cost of Work Performed(ACWP)

Labor came to $1,300,and materials cost$1,100. That first standcost $2,400!

actual expenditures vs. budgetactual expenditures vs. budget

Page 12: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 12

12/25/06 EVM Introduction 12

Cost Variance(CV)

BC WPAC WP

Of the work we actually performed,how much did we budget for it to cost?

Of the work we actually performed,how much did it actually cost?

COST VARIANCE is the difference between budgeted costand actual cost

formula: CV $ = BCWP - ACWP

example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)

COST VARIANCE is the difference between budgeted costand actual cost

formula: CV $ = BCWP - ACWP

example: CV = BCWP - ACWP = $1,000 - $2,400 CV= -$1,400 (negative = cost overrun)

PER

FOR

MA

NC

E B

ASE

D

Page 13: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 13

12/25/06 EVM Introduction 13

Cost Variance(CV)

$

TIME 5 months

BCWP“earned value”

ACWP“actual cost”

5,000

cv

Page 14: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 14

12/25/06 EVM Introduction 14

Note That We Can IsolateSchedule and Cost Variances

schedule variance = BCWP - BCWS = negative numbercost variance = BCWP - ACWP = negative number

behind schedule,over cost

behind schedule,over cost

5 months

BCWS

BCWP

ACWP

TIME

5,000

svcv

$

Page 15: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 15

12/25/06 EVM Introduction 15

Where are the significant problems?

WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC

1 3600 PCC Zepka 28.99 34.09 0.850 ↑ -296.2 -17.62 ↔ -187.2

2 3200 COMMUNICATIONS Tideman 34.63 41.03 0.844 ↓ -130.8 -18.49 ↔ -87.0

3 G&A GEN & ADMIN 33.67 36.11 0.932 ↓ -45.2 -7.26 ↔ -36.8

4 2200 SYS ENGINEERING Price 85.04 94.35 0.901 ↓ -26.4 -10.95 ↔ 0.0

5 3800 I & A Troop 35.40 37.08 0.955 ↓ -24.2 -4.75 ↔ -24.8

6 2100 PROJ MANAGEMENT Brown 45.70 48.51 0.942 ↔ -17.4 -6.16 ↔ -3.2

7 2300 FUNC INTEGRA Price 71.62 75.23 0.952 ↓ -17.4 -5.03 ↔ -30.8

8 5200 MANAGEMENT DATA Simmons 84.18 98.10 0.858 ↓ -13.2 -16.54 ↑ -16.0

9 3100 SENSORS Smith 20.87 21.49 0.971 ↓ -10.6 -2.94 ↔ -21.6

10 4000 SPARES Blair 17.87 18.90 0.945 ↑ -7.8 -5.78 ↔ -6.2

11 6200 SYSTEM TEST Hall 60.82 61.66 0.986 ↑ -5.6 -1.38 ↔ -2.0

12 5100 ENG DATA Novak 38.51 52.80 0.729 ↓ -4.6 -37.10 ↔ 0.0

13 MR MGT RESERVE 0.00 0.00 0.0 ↔ 439.2

14 UB UNDIST BUDGET 0.0 0.0

15 COM COST OF MONEY 0.0 0.0

16 3700 DATA DISPLAY Troop 41.13 41.13 1.000 ↔ 0.0 0.00 ↔ 0.0

17 OV OVERHEAD 0.0 0.0

18 6100 TEST FACILITIES Smart 100.00 98.02 1.020 ↔ 2.0 1.98 ↔ 0.0

19 3500 COMP PROGRAMS Pino 46.46 44.66 1.040 ↓ 3.4 3.87 ↔ -1.4

20 6300 PCC TEST Bond 23.13 22.64 1.021 ↓ 4.2 2.10 ↔ 0.0

21 3400 ADPE Zepka 41.89 39.79 1.053 ↓ 12.6 5.02 ↔ 4.6

22 3300 AUX EQUIP Tideman 27.57 24.33 1.133 ↓ 78.2 11.73 ↓ 8.4

sorted by CV ($)By tracking and sorting on variances, we can isolate the troublesome WBS elements.

Page 16: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 16

12/25/06 EVM Introduction 16

COST PERF INDEX (CPI) = BCWPACWP

SCHED PERF INDEX (SPI) = BCWPBCWS

COST PERF INDEX (CPI) = BCWPACWP

SCHED PERF INDEX (SPI) = BCWPBCWS

1.0

.9

1.1

“GO

OD

”“B

AD

1.2

.8

CPI

SPI

TIME

Performance Indices

We can also get a sense of the overall performance of the project by tracking performance indices.

Page 17: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 17

12/25/06 EVM Introduction 17

Budget at Completion(BAC)

$

time

BACsum of all BCWS =

$

$

$$

$

$

$

When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000

When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000

$5,000$5,000

The most important markers of the overall performance of the project look at predictions of the variances at the end. These require several quantities, the first being the Budget at Completion.

Page 18: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 18

12/25/06 EVM Introduction 18

• Estimate at Completion (EAC)

– defined as actual cost to date + estimated cost of work remaining– usually develop comprehensive EAC at least annually

• reported by WBS in cost performance report

– should examine on monthly basis– consider the following in EAC generation:

• performance to date• impact of approved corrective action plans• known/anticipated downstream problems• best estimate of the cost to complete remaining work

– also called latest revised estimate (LRE), indicated final cost, etc.

What will be the final cost?

ACWP + ETC = EAC

Page 19: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 19

12/25/06 EVM Introduction 19

Getting the Estimate at Completion

Just a few little glitches…. We should be able to do the complete job….ack…

let’s see, for about $7,500

Page 20: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 20

12/25/06 EVM Introduction 20

• Common EAC Formulae:

EAC = BAC/CPI

= ACWPcum + Budgeted Cost of Work RemainingCPI3

= ACWPcum + Budgeted Cost of Work Remaining.8(CPI) +.2(SPI)

= ACWPcum + Budgeted Cost of Work RemainingCPI * SPI

Determining EAC via Statistics

Page 21: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 21

12/25/06 EVM Introduction 21

Other methods of EAC calculation

• “Grass Roots” or formal EAC

– detailed build-up from the lowest level detail– hours, rates, bill of material, etc.

• Average of statistical formulae

• Show range of EACs (optimistic, most probable, pessimistic)

• Complete schedule risk analysis for remaining work, estimate work remaining

Page 22: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 22

12/25/06 EVM Introduction 22

Variance at Completion(VAC)

VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.

FORMULA: VAC = BAC - EAC

Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

VARIANCE AT COMPLETION is the difference between what the total job is supposed to cost and what the total job is now expected to cost.

FORMULA: VAC = BAC - EAC

Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

B AC

E AC

what the total job is supposedto cost

what the total job is expectedto cost

Page 23: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 23

12/25/06 EVM Introduction 23

Variance at Completion(VAC)

VAC = Budget at Completion - Estimate at Completion= BAC - EAC

$

BAC

EACVAC

TIME

Page 24: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 24

12/25/06 EVM Introduction 24

• Variance at Completion vs. Contractor Loss– Positive VAC:

• EAC < BAC underrun contractor gain

– Negative VAC:• EAC > BAC share area contractor partial loss• EAC > ceiling overrun contractor loss (100%)

• Government develops top level EAC for comparison– Government will limit progress payments if EAC is greater than

ceiling– Government needs forecast of fund requirements

• May still have time to change the final outcome

VAC is Particularly Importantfor Government Contracts

Page 25: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 25

12/25/06 EVM Introduction 25

• A survey of over 800 military programs showed that no program ever improved performance better than the following EAC calculation:

EAC = BAC/CPI,

at the 15%-complete point in the program.

• Thus, there is strong empirical evidence that EVM translates early information into essential guidance for program re-baselining.

Probably the BiggestSelling Point for EVM

Page 26: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 26

12/25/06 EVM Introduction 26

EVM Analyses

PCUM

Term Formula

Percent Complete

Cost Performance Indexor Performance Factor

Checklist ActionsRatio of work accomplished in terms of the total amount of work to do.

Symbol% Done

CPI or PF

TCPI or VF

BCWPBAC

Average PerformanceBCWPcum

Duration (wks or mos) Since ACWP Began

BCWPcumDuration (wks or mos)

From Time Now to Manager's Stated Completion Date

SC or S/CSchedule Correlation

BCWPACWP

Ratio of work accomplished against money spent (an efficiency rating: Work Done for Resources Expended)

To CompletePerformance Index

or Verification Factor

BAC - BCWPEAC - ACWP

Ratio of work remaining against money remaining (Efficiency which must be achieved to complete the remaining work with the expected remaining money)

Schedule Performance Index SPI Ratio of work accomplished against what should have been done (Efficiency Rating: Work done as compared to what should have been done)

BCWPBCWS

SV

Ratio of Schedule Variance (SV) in terms of average amount of work accomplished (in weeks or months). It indicates a correlation to program true schedule condition

IEACIndependent EstimateAt Completion

BACPF

Calculation of a projected Estimate At Completion to compare with the CAM's Estimate At Completion:1) Ration of total work to be done against experienced cost efficiency2) Sunk costs added to a ratio of remaining work against weighted cost and schedule efficiencies

1)

2)BAC - BCWP.8CPI + .2SPI

ACWP +

Average Expected Performance To Finish

Average rate at which work has been accomplished since work began

Average rate at which work must be accomplished in the future to finish on the date the CAM has forecasted for completion of the work.PTO GO

PCUM

There are a wide variety of indicators to play with in EVM.

Page 27: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 27

12/25/06 EVM Introduction 27

EVM Analyses

• Sort on significant variances– eliminate almost complete, just starting, etc.

• Graph and analyze trends• Look at comparative data

– e.g. cumulative performance vs. projected performance• Examine written analysis by contractor

– does it answer why?– adequacy of corrective action plans

• Analysis of schedule trends, critical path• Analysis of EAC realism

what are the drivers?what can we do about them?what are the drivers?what can we do about them?

There are a wide variety of analytic techniques to play with in EVM.

Page 28: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 28

12/25/06 EVM Introduction 28

Graphical EVM Analyses

Dollars In M

illions

Estimates at Completion MEGA HERZ ELEC & VEN F04695-86-C-0050 RDPR FPI

Element: 3600 Name: PCC

BACLRECUM CPI

1992APR MAY JUN JUL AUG SEP OCT NOV DEC

1993JAN

5.0

6.0

7.0

8.0

5.1 5.4 5.1

5.1 5.4 5.7

5.1 5.4 5.9

5.1 5.4 6.0

5.1 5.5 6.3

5.1 5.5 5.8

5.1 5.5 6.5

5.5 5.7 7.6

5.5 5.7 6.8

5.8 6.0 6.8

MEGA HERZ ELEC & VEN Cost/Schedule VarianceF04695-86-C-0050 MOH-2 RDPR FPI POP: 01 MAR 1992 - 15 SEP 1993

Percent of D

ollars

COST VARIANCESCHEDULE VARIANCE

1992MAY JUN JUL AUG SEP OCT NOV DEC

1993JAN

-30.0

-20.0

-10.0

0.0

10.0

20.0

30.0

Cost Drivers, Cause

Dollars In MillionsBCWSBCWPACWP

CVSV

0.3 0.2 0.2 0.0 -0.1

0.6 0.5 0.5 -0.0 -0.1

1.0 0.9 0.9 -0.0 -0.1

1.4 1.4 1.5 -0.1 -0.0

2.2 2.2 2.2 0.0 -0.0

2.5 2.7 3.0 -0.3 0.2

4.2 3.8 4.2 -0.5 -0.4

5.6 5.3 5.6 -0.3 -0.3

7.3 6.9 7.3 -0.5 -0.4

At CompletionKTR PO

20.8 20.8

20.8 20.8 20.8 23.0 0.0 -2.2

PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0CURRENT FUNDING: 10.0

PO EPC: 24.0PROJ FUNDING: 23.0

AS OF: JAN 93OPR: MR B. TECH

PROGRAM: Mohawk Vehicle

0%

-11%-7%-6%

Overall cost and schedule trend

EAC realism

graphs show overall trend...are you getting better,

or worse?

graphs show overall trend...are you getting better,

or worse?

Page 29: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 29

12/25/06 EVM Introduction 29

Will the contractor come in on budget?

COST PERFORMANCE INDEX:

CPI = cost efficiency for work performed to date(The value of work accomplished for each dollar spent)

$1000= = = $2400 = .42

Compare the CPI to the TCPI-BAC:

TCPI(BAC) = Efficiency necessary to complete on budget

= = = $5000 - $1000$5000 - $2400

Example: Using Performance Efficiencies (1)

BCWPACWP

WORKACCOMPLISHED

ACTUALS

BAC-BCWPBAC-ACWP

WORKREMAINING

BUDGETREMAINING

= $4000$2600 = 1.54

HISTORY

FUTURE

Page 30: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 30

12/25/06 EVM Introduction 30

Example: Using Performance Efficiencies (2)

SCHEDULE PERFORMANCE INDEX:

SPI = schedule efficiency with which work has been accomplished(The rate at which work is being accomplished)

WORK= BCWP = ACCOMPLISHED = $1000 = .50

BCWS WORK $2000 SCHEDULED

Page 31: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 31

12/25/06 EVM Introduction 31

IS THE CONTRACTOR'S EAC (LRE) REASONABLE?Compare the CPI to the TCPI-LRE

TCPI(LRE) = Efficiency necessary to complete at the contractor’s estimate

WORKBAC-BCWP REMAINING $5000 - $1000 $4000 1.00LRE-ACWP ESTIMATE $6400 - $2400 $4000

REMAINING

Cumulative performance to date (CPI) = .42

Contractor has been performing at 42% efficiency, but expects tocomplete remaining work at 100% efficiency!

Example: Using Performance Efficiencies (3)

reasonable?

= == = =

Page 32: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 32

12/25/06 EVM Introduction 32

Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

Page 33: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 33

12/25/06 EVM Introduction 33

Control Account

Software Engineering

Getting at the Value

WorkPackages

PlanningPackages

OBS DATA SUMMARIZATION

SOFTWAREINTEGRATION

PROGRAM

Product Development

Master Planning

AdaProducts

Software Tools Standards

CPCI #1MOS

CPCI #2MOLE

CPCI #3MAC

AdaStudy

AdaConversion

AdaApproach

AdaApplications

Secure Systems

LAN Applications

Marketing

BCWSBCWPACWPBACEAC

FUNCTIONALORGANIZATION

CWBSEXTENSION

SELECTEDREPORTINGELEMENTS

SELECTEDPSWBS

ELEMENTS

Hardware Engineering

Engineering

Operations

WBS

DATA

SUMMARIZATION

VP/GM

Control Account

Control Account

Control Account

Control Account

Control Account

Control Account

Responsibility Matrix

Page 34: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 34

12/25/06 EVM Introduction 34

Control Account Elements

Work PackagesDetailed, short-span tasks, or

material items, required to

accomplish the CA objectives,

typically in the near term

Task 1Task 2

Task 4Task 5

Task 3Work Packages

Planning Packages

Planning PackagesFuture work that has not been

detail planned as work packages.

They are always scheduled to

occur in the future.

Work Packages have budgets

and schedules.

Page 35: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 35

12/25/06 EVM Introduction 35

• Development of Control Account Plans– MAY break down the control account budget into smaller work

packages

• Work Package• subset of control account• reasonably short in duration• single element of cost (e.g., labor)• single technique for earning value• consistent with detail schedules• has same characteristics as control account

– scope of work– milestone completion criteria– single performing organization– start and end dates

CONTROL ACCOUNT PLAN

Work Pkg #1

Work Pkg #2

Work Pkg #3

$$

$ $

$

$

$

$$

Work Packages

Page 36: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 36

12/25/06 EVM Introduction 36

• Work packages are discrete and measurable.

• Work packages yield products or accomplishments, such as

– design drawing package– conduct design review– install stand

• Often done in rolling wave

– detailed plans made for near term work packages– planning packages are for future work and are not detailed– CAMs periodically plan another increment of work packages

Work Package Characteristics

Page 37: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 37

12/25/06 EVM Introduction 37

• Should be a quantitative and discrete way to measure the work– Discrete

• physical, tangible end product

– Apportioned• discrete, dependent on another discrete work package• example: quality assurance• planned as historical estimating factor (e.g., 7%)

– Level of Effort• no tangible end product• basis of measurement: time• when clock starts ticking, you automatically accumulate earned value• no schedule variance• example: management personnel

• May tie in with success criteria or technical measure• e.g., successful completion of a specific test, reliability growth curve

Ways of Earning Value

Page 38: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 38

12/25/06 EVM Introduction 38

Method How Value is Earned

0/100 no EV at opening, 100% EV at close of WP

50/50 50% EV at opening, 50% EV at close of WP

Units Completed same budget value for identical units

Equivalent Units planned unit standards, allows partial credit

Weighted Milestone each milestone weighted based on planned resources

ideal to have a milestone each month

Percent Complete subjective (least desirable)

Methods for Assigning Earned Value

Page 39: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 39

12/25/06 EVM Introduction 39

Suggested for LWA

• 0/50/100 measurement• Typical work package length is 80 hours.• Work package status is reported at status meetings, held every

two weeks.– May just be that 50% of work packages are reported at weekly

status meetings.• EV is 0% (of budget for work package) if it has not yet been

started, or is only now starting.• EV is 50% if work is underway.• EV is 100% if work is complete.• If work package is at 50% two status meetings in a row, it is

flagged as a potential issue.• Avoids subjectivity of “% done”; compromises on granularity of

tracking, frequency of reporting• Puts the onus on doing the WPs right, up front.

Page 40: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 40

12/25/06 EVM Introduction 40

Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

Page 41: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 41

12/25/06 EVM Introduction 41

A Spectrum of Implementation

Where

When

Core EV PrinciplesANSI/EIA-748-1998

(32 criteria)Tailored Applications

Small Companies Larger Companies

Major Defense

Contractors

as desired

Government Organic

Reports

Foreign Countries

streamlined, no paper?

corporate policy,

“enterprise wide”

DoD Non-Major Contracts (>12 months)

<$6M* >$6M

DoD Major Contracts

>$70M RDT&E

>$300M Prod

tailored to needs C/SSR CPR

*with judgment

FFP contracts?

Commercial or Defense

Page 42: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 42

12/25/06 EVM Introduction 42

Earned Value Management:History

• 1959 PERT and PERT/Cost— Milestone Charts And Rate-of-Expenditure

Curves— Dollars Spent Vs Estimates Of Percent

Complete (DD 1097)• 1963 Earned Value Concept (MINUTEMAN)• 1964 Cost Accomplishment Concept (TITAN III)• 1966 AF—Cost/schedule Planning And Control

Specification (C/SPCS)• 1967 DOD—Cost/Schedule Control Systems

Criteria (C/SCSC) (DODI 7000.2)• 1972 DOD—-Revised DODI 7000.2 and Issued the

Joint Implementation Guide (JIG)• 1972 NASA Marshall Space Flight Center—C/SPC• 1975 DOE—Performance Measurement System

(PMS)• 1976 DOD—Revised the C/SCSC JIG• 1980 DOD—Revised the C/SCSC JIG• 1982 National Security Agency—Earned Value• 1983 NASA—Goddard Space Flight Center—PMS• 1984 FAA & NASA Lewis Research Center—PMS

• 1985 NASA Johnson Space Flight Center—PMS• 1987 DOD—Revised DOD C/SCSC JIG• 1988 NASA Marshall SFC—Revised PMS

(MMI 8020.7C, 44 Criteria)• 1989 Australian DOD—DODI 7000.2• 1990 Canadian DOD—PMS• 1991 DODI 5000.2 replaces DODI 7000.2• 1992 National Oceanic And Atmospheric

Administration (NOAA)—PMS• 1993 Swedish FMV—C/SCSC• 1994 Internal Revenue Service (IRS)—C/SCSC• 1994 Federal Bureau Of Investigation (FBI)

—C/SCSC• 1996 DODR 5000.2-R replaces DODI 5000.2

C/SCSC revised from 35 to 32 criteria• 1996 Revised JIG—Renamed Earned Value

Management Implementation Guide (EVMIG)• 1997 EVMIG Revised• 1998 MIL-STD 881B replaced by MIL HDBK 881

Page 43: Brief Introduction to Earned Value Management (EVM)Earned Value Management (EVM) 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2 ... 12/25/06 EVM Introduction 5 12/25/06 EVM

12/25/06 EVM Introduction 43

12/25/06 EVM Introduction 43

EVM Resources

• BooksEarned ValueQuentin W. Fleming & Joel M. KopplemanCost/Schedule Control Systems CriteriaQuentin W. FlemingProject Performance MeasurementRobert R. KempsVisualizing Project ManagementKevin Forsberg, Ph.D., Hal Mooz and Howard Cotterman

• SoftwareArtemis ViewsArtemis Management SystemsContact: Patrick Perugini (303) 581-3102Web: http://www.artemispm.comCobraWelcom SoftwareContact: Diana Melton (281) 558-0514Web: http://www.wst.com

• Software [continued]Dekker TRAKKERDekker Ltd.Contact: Ron Barry (909) 384-9000Web: http://www.dtrakker.comMicroFrame Project Manager (MPM)MicroFrame Technologies, Inc.Contact: Carl Amacker (415) 616-4000Web: http://www.microframe.com

• InternetProject Management Institutehttp://www.pmi.org

US DoD Earned Valuehttp://www.acq.osd.mil/pm

Earned Value Bibliographyhttp://www.uwf.edu/~dchriste/ev-bib.html