INTRODUCTION The £4.5 billion Brent Cross Cricklewood development is Barnet Council’s most significant growth and regeneration programme. It will create a new sustainable mixed use town centre for Barnet and North London. This regeneration is underpinned by major transport improvements, including an additional new Thameslink railway station connecting to King’s Cross St Pancras in under 15 minutes. The Brent Cross Thameslink project includes: An additional Thameslink station between Cricklewood and Hendon stations; Relocated sidings and stabling (train storage) facilities; A new 24 hour access pedestrian bridge across the railway; A Waste Transfer Station; A Rail Freight Facility; A new vehicle and pedestrian bridge across the Midland Main Line; Junction improvement works on the A5 Edgware Road. Aerial view of the site today, looking south BRENT CROSS THAMESLINK PART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT Brent Terrace Midland Main Line (between King’s Cross St Pancras and Bedford/the Midlands) Edgware Road Brent South Shopping Park Staples Corner Retail Park North Circular Correct as of 19.04.2017

Upload: others

Post on 13-May-2022

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BRENT CROSS THAMESLINK - Amazon S3

INTRODUCTIONThe £4.5 billion Brent Cross Cricklewood development is Barnet Council’s most significant growth and regeneration programme. It will create a new sustainable mixed use town centre for Barnet and North London.

This regeneration is underpinned by major transport improvements, including an additional new Thameslink railway station connecting to King’s Cross St Pancras in under 15 minutes.

The Brent Cross Thameslink project includes:

• An additional Thameslink station between Cricklewood and Hendon stations;

• Relocated sidings and stabling (train storage) facilities;

• A new 24 hour access pedestrian bridge across the railway;

• A Waste Transfer Station;

• A Rail Freight Facility;

• A new vehicle and pedestrian bridge across the Midland Main Line;

• Junction improvement works on the A5 Edgware Road.

Aerial view of the site today, looking south

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

Brent Terrace

Midland Main Line (between King’s

Cross St Pancras and Bedford/the Midlands) Edgware Road

Brent South Shopping Park

Staples Corner Retail Park

North Circular

Correct as of 19.04.2017

Page 2: BRENT CROSS THAMESLINK - Amazon S3

BRENT CROSS CRICKLEWOODCovering around 151 hectares, this project includes the transformation of Brent Cross Shopping Centre, a thriving new town centre and high street, 7,500 new homes and attractive green spaces, new schools and health facilities, and the creation of 1000’s of new jobs.

Planning permission for the Brent Cross Cricklewood project was first granted in 2010 and subsequently amended in 2014.

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

M1CREST ROAD

DOLLIS HILL LANE

PENNINE DRIVE

A41 HEN

DON W

AY

FIN

CHLE

Y RO

AD

MM11

A5 CRICKLEWOOD

BROADWAY

O

CRICKLEWO D LANE

BRENT CROSS LONDONModernising Brent Cross shopping centre, improving road, cycling

and pedestrian access and building up to 800 new homes. Delivered

by Hammerson and Standard Life Investments.

Visit www.brentcrosslondon.co.uk

BRENT CROSS SOUTHCreating a new town centre, building 6,700 homes and improving

public spaces. Delivered by the BXS Limited Partnership between

Barnet Council and Argent Related. Visit www.brentcrosssouth.co.uk

BRENT CROSS THAMESLINK (this project)Barnet Council, with Network Rail, are building an additional

Thameslink station, new Midland Main Line Bridge and station

sidings, and replacing outdated waste and freight facilities.

Visit www.barnet.gov.uk/brentcross

THE BRENT CROSS CRICKLEWOOD PROJECTS

Overall Brent Cross Cricklewood Regeneration Area

BRENT CROSS SHOPPING

CENTRE

NORTH CIRCULAR RD

NORTH CIRCULAR ROAD

M1

NEW STATION

BRENT CROSS

CRICKLEWOOD

All three schemes are working together to review the emerging construction programmes and ensure that construction traffic in particular is managed communicated in a co-ordinated and effective manner.

Correct as of 19.04.2017

Page 3: BRENT CROSS THAMESLINK - Amazon S3

A NEW STATION, SOONER

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

• Building the station earlier supports the comprehensive regeneration of the Brent Cross Cricklewood area and helps to unlock the economic and employment benefits associated with the development sooner

• Current and future residents will be able to use the new Thameslink station sooner and benefit from better public transport links and reduced journey times to central London

• Opening the new bridge earlier will improve links between the Brent Cross Cricklewood development, the Edgware Road and Brent

THE THAMESLINK AREA

Thameslink Sidings (Indicative Area) Thameslink Station Midland Main Line Bridge

Waste Transfer Station Rail Freight Facility

EDGWARE ROAD

N

We will shortly submit an application to allow the new Thameslink station and associated infrastructure works to be constructed at the same time.

Grouping all of the rail-related projects and infrastructure works together into Phase 2. This allows them to be delivered earlier in the programme than previously planned with the station due to open in 2022 rather than 2031.

NO

RT

H C

IRC

UL

AR

Correct as of 19.04.2017

Page 4: BRENT CROSS THAMESLINK - Amazon S3

We recently asked for your views on bringing all of the rail related projects together and delivering them in a single phase.

You told us:

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

We support the bringing forward of this project and is it is important that transport links are in place as soon as possible for the new development.

Please make sure traffic and timescales are properly managed

Can we please make sure the connection between Brent Cross Thameslink area and Childs Hill & Golders Green be enhanced so we can benefit from this project

Sooner the better

Really excited to see it executedIt is important that people can cycle to and from the station from the new development and from the other side of the station.

Reduce car, air, noise, waste pollution etc. around the area.

Just get on with it!

Correct as of 19.04.2017

Page 5: BRENT CROSS THAMESLINK - Amazon S3

Outline planning permission has been granted for a Waste Handling Facility to replace the existing Hendon Waste Transfer Station adjacent to Brent Terrace.

The proposed facility is significantly smaller than the one that was previously approved and will now be a transfer station where recycling, food and household waste will be collected and transferred to other processing centres. It will not include the incinerator that was originally proposed. The site of the existing Hendon Waste Transfer Station is needed to facilitate the comprehensive regeneration of Brent Cross Cricklewood.

The new facility will be operated by the North London Waste Authority.

Subject to approval of the Re-Phasing Application, construction is expected to start in 2019 and be completed in early 2020.

WASTE TRANSFER STATION

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

Size of the previously approved facility shown in yellow Size of the proposed new transfer station in blue

EDGW

AR

E ROAD

BR

ENT TER

RACE

OXGATE GARDENS

HUMBER R

OAD

EDGW

AR

E ROAD

BR

ENT TER

RACE

OXGATE GARDENS

HUMBER R

OAD

Correct as of 19.04.2017

Page 6: BRENT CROSS THAMESLINK - Amazon S3

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

DESIGN & APPEARANCE, MATERIALS, LAYOUT

WASTE TRANSFER STATION

The designs for the Waste Transfer Station are at a very early stage. We are considering a range of options for the external appearance of the building.

• The facility will be approximately five storeys high; within the heights permitted by the S73 application.

• Options for cladding the building include metal framing or Rodeca, a translucent light weight polycarbonate.

We will be doing more design work before we submit a planning application in the summer of 2017.

We would appreciate your views on these ideas to inform that design work.

Early building design for the Waste Transfer Station Early building design for the Waste Transfer Station

Example of Rodeca cladding Example of metal screeningExample of metal framing cladding

NEW MIDLAND

MAINLINE BRIDGE

CLADDING OPTIONS BEING CONSIDERED

Correct as of 19.04.2017

Page 7: BRENT CROSS THAMESLINK - Amazon S3

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

OPERATION PROPOSED SITE LAYOUT AND VEHICLE ACCESS ROUTES

WASTE TRANSFER STATION

The site has been designed to:

• Process and store all waste inside the building;

• Prevent odours leaving the building;

• Have a similar capacity to the existing facility;

• Provide space for vehicles to queue inside the site;

• Provide parking on site for Waste Transfer Station staff.

The site will be accessed from Geron Way via a new signal-controlled junction on the A5.

Vehicles transferring waste from the Waste Transfer Station to Edmonton are expected to travel along the A5 and A406 North Circular and not travel along residential streets.

The Waste Transfer Station is expected to be used by Refuse Collection Vehicles to deliver waste and HGV’s to collect waste

Proposed site layout and vehicle access routes

Correct as of 19.04.2017

Page 8: BRENT CROSS THAMESLINK - Amazon S3

RAIL FREIGHT FACILITY A Rail Freight Facility is part of the approved Masterplan for Brent Cross Cricklewood to replace an existing strategic freight facility which has to be relocated to make way for the wider Brent Cross Cricklewood regeneration.

The Rail Freight Facility that is now being proposed has some significant differences to the original proposal:

• There is now more demand for a facility that can handle building aggregates and construction spoil. These materials have different handling requirements and so a building is not required as originally planned.

• Substantially fewer cars will park on site and HGV parking will now be within the working areas.

Barnet Council is in discussions with DB Cargo (the current tenant of the existing rail freight site) to develop the plans.

If planning permission is granted, construction of the facility will begin in 2019 and operation will commence in Spring 2020.

DB Cargo has submitted a temporary planning application to operate the northern part of the site which is currently being considered by the Local Planning Authority.

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

The plans presented today are for the facility in its simplest form. We will

continue to assess the impacts and work on the design to mitigate these

before we submit a planning application in the summer. Your comments

today will help us with this work.

The site at present

EDGWARE ROAD

N

Correct as of 19.04.2017

Page 9: BRENT CROSS THAMESLINK - Amazon S3

DESIGN AND LAYOUT

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

The rail freight facility will consist of two parallel rail sidings, with connections to the adjacent mainline at either end. The current proposal is for 5 bays where materials will be unloaded, stored and loaded.

Indicative DB Cargo proposed site layout

Proposed site plan

Each bay will have small single storey buildings to provide office and staff accommodation.

Dust Supression System, Pump House and Tank

Fuel Tank

Redundant Signal Box

Wheel Wash

Traverse Road 10m x 442m

On Hendon Line Network Rail

Weighbridge

Welfare Facilities

PLOT 1 - 6,636m2

Existing Electricity Shaft

Visitor Parking

Edgware Road

Weighbridge

Security Hut and Barrier

Accoustic Barrier 6.9m

Security Hut and Barrier

Proposed Access

Mobile Wheel

Brent Curve

PLOT 2 - 5,623m2

PLOT 3 - 4,924m2

PLOT 4 - 5,030m2

PLOT 5 - 5,212m2

Cricklewood Curve

Bund with 6m Accoustic Barrier

HGV Turning Head

N

Correct as of 19.04.2017

Page 10: BRENT CROSS THAMESLINK - Amazon S3

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

OPERATION The Rail Freight Facility will operate up to six days per week. It is currently anticipated that up to three trains will arrive and be unloaded per day. The arrival times will be determined by the available train slots on the network, but unloading and loading will only occur between 6am and 6pm.

Aggregate will be unloaded using excavators and placed in a stockpile, before being distributed to construction sites across London by road vehicle.

An internal access roadway will provide access to the material stockpiles.

Access will be via the existing junction with the A5, which will be upgraded. Most of the lorries leaving the site are expected to travel northwards.

There will be 24/7 night vision CCTV surveillance of the site.

DB Cargo will operate the facility but other rail freight operating companies will also be able to lease land and use the facility.

Example of wheel wash facility

Front loader used to load construction spoil onto trainsExcavator used to unload aggregate materials

Correct as of 19.04.2017

Page 11: BRENT CROSS THAMESLINK - Amazon S3

CONTROLLING DUST, NOISE AND LIGHT

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

We know that people will have concerns about the dust, noise and light generated by an open-air Rail Freight Facility. Incorporating screening and landscape measures has been a fundamental principle in developing the design of the Rail Freight Facility.

A particular area of focus has been the relationship between the site and the Railway Terraces Conservation Area to the south east. A key principle of the site’s development has been to protect the amenity of the existing southern residential area and the emerging residential development to the north of the site.

We will develop the plans further based on your feedback today.

PLANTING

The redeveloped site will be far greener than it is at present. This will be achieved by:

• Introduction of new planting at the entrance to the site;

• The existing boundaries to the site will be improved with new trees or planting.

• Ornamental evergreen shrubs and wildflower-rich grasses will be planted where possible across the site.

LIGHTING

• Shields will be fitted to the new lighting columns to minimise light spill as much as possible.

• The existing Halogen lamps will be replaced with LED downlighters that will direct light onto the site and reduce the impact on local residents.

NOISE

• A 5m high 400m long acoustic barrier will be positioned along the sidings to prevent noise travelling across the mainline to the Brent Terrace area.

• Subject to detailed noise assessment:

• a bank and acoustic fence up to 12m high in total is proposed to reduce noise traveling to the Railway Terrace area to the South West of the site.

• an acoustic fence up to 5m high will be provided to protect buildings to the north west of the site.

6m High Landscape Bund+ 6m Fence

Cricklewood CurveJohnston Terrace Footway EmbankmentPrivate Property Plot 5 Working AreaNetwork RailAccess Road

Proposed option for site screening and noise mitigation in the south-west

Current view from Railway Terraces

View of proposed acoustic fence showing maximum height Final height will be subject to detailed noise assessment

Current view from rear of Brent Terrace

View of the proposed acoustic fence from the rear of Brent Terrace

DUST

• The design includes a water-based dust suppression system. This ensures material is dampened before any dust generating activities such as loading and unloading and prevents dust particles in the air travelling off site.

Top of Acoustic Screen

Correct as of 19.04.2017

Page 12: BRENT CROSS THAMESLINK - Amazon S3

NEXT STEPSThank you for taking the time to visit our exhibition today. If you have any questions, please ask a member of the project team.

All of the information presented here will also be available on www.barnet.gov.uk/BrentCrossThameslink after these events. Anyone who can’t make it along today can view the information and comment on the proposals online or by contacting a member of the project team via one of the options below.

HAVE YOUR SAY

We’re keen to hear your thoughts on the Brent Cross Thameslink project and in particular the early proposals for the Waste Transfer Station and Rail Freight Facility which are on display here today.

You can provide your feedback and ask any questions you might have via the council’s consultation portal at https://engage.barnet.gov.uk by 8th May 2017. If you would prefer not to use the council’s website to provide your feedback, please contact the project team via one of the options shown on this board, or complete a form today.

BRENT CROSS THAMESLINKPART OF THE BRENT CROSS CRICKLEWOOD DEVELOPMENT

CONTACT US

Call us: 0344 225 0003

Email us: [email protected]

Write to us: Freepost RTHZ-AKZT-SABG, GL Hearn, 280 High Holborn, London, WC1V 7EE

If you would like to register your interest in the Thameslink project in order to receive project updates in the future, please contact the team via one of these options.

INDICATIVE PROJECT TIMESCALES

• April 2017 – Public information events about the early design for the Waste Transfer Station and Rail Freight Facility TODAY

• June / July 2017 - Further public information events on the designs for the Brent Cross Thameslink project

• Summer 2017 - Submission of Brent Cross Thameslink planning applications , including new station, sidings, Midland Mainline Bridge, Rail Freight Facility and Waste Transfer Station.

• December 2017 – All planning applications to have been considered and determined by the end of the year

• 2018 onwards – Start of construction work on site, with the new station planned to open in 2022

NEXT STEPS

We will continue to work up more detailed designs for the Waste Transfer Station and Rail Freight Facility.

• In the summer we will hold more public exhibitions to present detailed designs for the Waste Transfer Station and the Rail Freight Facility and the designs for the Station and sidings and Midland Mainline Bridge.

• If you would like to register for updates on the project and be told about these events please speak to a member of the project team.

Correct as of 19.04.2017