Gateway to the Future
Project Collaboration for Optimal Results
Engineering & Construction
ONE TEAM
ONE VISION
ONE RESULT
Greg Short - KiewitBrent Beguin – Kiewit
Gateway to the Future
• Project Goals Aligned• Client Goals – Firm Price and Completion Date• Engineer’s Goals – Accurate Estimate and Schedule• Contractor Goals – Accurate Estimate and Execution of
project on schedule• Progressive Design-Build or ECI Execution Model
• Client and Engineer and Contractor work together to develop and finalize scope of work
• Gaps Eliminated • Risks documented and managed• Schedule developed pre-contract
Engineering & Construction
Collaboration ONE TEAM
ONE VISION
ONE RESULT
EARLY AND CONTINUOUS COLLABORATION IS KEY
Early Contractor Involvement
Gateway to the Future
• Set-up the project for success from day 1• Starts early in the FEL process• Clear goals and expectations• Share ideas on optimization• Select best contracting structure• Develop solid estimate and schedule• Outage Planning from Day 1
EARLY AND CONTINUOUS COLLABORATION IS KEY
Gateway to the Future
• Good Collaboration • Full Engagement• Co-Location• One Vision• Zipper Plan
• Conflict Management• Competing interests• Detached• Personalities that Clash
Client/Engineer/Contractor
Collaboration
One Team, One Vision, One Result
Gateway to the Future
• Engineering Execution• Schedule is King
• IFR is the new IFC• Collaboration eliminates rework• Pre-design meetings set expectations• “Over-the-shoulder” in lieu of paper reviews
Engineering Collaboration
SCOPE, COST and SCHEDULE CERTAINTY
Gateway to the Future
• Expedited Procurement• Holds are primarily driven by vendor info• Procurement schedule has to be driven by
engineering need dates.• Selection of Key Vendors and
Subcontractors• All-Holds-Barred
Engineering Collaboration
SCOPE, COST and SCHEDULE CERTAINTY
Gateway to the Future
• Lock-down scope as early as possible• Minimize and manage field changes• Field changes are highest cost and can effect schedule• Recognize the 1-10-100 rule:
• $1 to change in design• $10 to change in manufacturing• $100 to change in field
• Communicate & Plan - Plan - Plan
Construction Collaboration
Controlling Costs & Minimizing Changes
SCOPE, COST and SCHEDULE CERTAINTY
Gateway to the Future
• Lock-down schedule as early as possible• Single integrated Project Schedule, including:
• Owner requirements• Engineering deliverables• Procured Equipment/Material deliveries• Construction sequencing• Turnover & Startup
• Minimize and manage schedule changes• Communicate & Plan - Plan - Plan
Construction Collaboration
Controlling Costs & Minimizing Changes
SCOPE, COST and SCHEDULE CERTAINTY
Construction Collaboration
Detailed, Current & Transparent Project Controls
Gateway to the Future
REDUCE Risk. MAXIMIZE Efficiency. BUILD Project Confidence.
ACCURATE ESTIMATES QUANTITY-LOADED
SCHEDULES AND DETAILED
VISUAL TRACKING
REAL-TIME REPORTING
Gateway to the Future
• 3 Phases • ECI – Optimize layout with safety and access in mind• Engineering – Collaborate via “Design for Safety”• Construction - Most incidents on a project associated with a change in plan
Collaboration Effect on Safety
Gateway to the Future
Owner – Engineer – Procurement – Contractor collaboration results:• On-budget results with minimal/no change orders• On-schedule results• Minimal impacts to operating mill• Safety of all personnel• A high quality project
Construction Collaboration
Successful Project Results