Update/Accomplishments
• November 27-28 (Washington D.C.)– Reviewed Joint Operator Manual– Reviewed new language for Phase III work– Provided update on Phase II work (Field
Test)• January 29 (Houston, Texas)
– Agreed to post Joint Operator Manual for 45 day comment period
– General agreement on Phase III language for IRO-006
– Worked on requirements for IRO-017 (Eastern Interconnection)
– Provided update on Phase II work (Field Test)
3 Free Template from www.brainybetty.com 3
Next Steps• February 8
– Post Joint Operator Manual for 45 day comment period
• April 1-2 (Carmel, Indiana)– Develop response to comments for the Joint
Operating Manual– Approve IRO-006.5 and IRO-017.1 to post for
comments• End of April
– Post IRO-006.5 and IRO-017.1 for 45 day comment period
• June 26-27 (Toronto, Ontario)– Review comments and finalize standards for balloting
• TBD– Begin work on Annual Plan Item 1.d - Prepare
recommendations for future path for TLR in concert with NERC
4 Free Template from www.brainybetty.com 4
Volunteers Needed
• To work on Annual Plan Item 1.d
• From Western Interconnect to participate in joint BPS/NERC meeting to discuss impact TLR process has on interconnections