JSR Broadband For All Project
Title : OWNER’S Requirements
Contractor
Project : JSR Broadband
Issue Date : 20/07/
Rev. Status : 1st
Release
1. Project Brief
It is the intention of Realm Energy Sdn
the Broadband Network Facilities, Infrastructure and Services
Cables for backhaul connectivity, and Broadband Power Line (BPL)
technologies and solutions for last mile connectivity
broadband connectivity to a
provide internet services
internet is limited.
2. Objective
The objective of this document is to
submitting the proposal to undertake this project
content of Contractor’s proposal.
project requirement prior to
project will be awarded to the
or any of the combinations deemed
3. Requirement of the Proposal
The Contractor shall submit the
a) Commercial Proposal
b) Technical Proposal
I. Commercial Proposal
The Contractor shall include the following items in the commercial proposal for this project.
a) Executive Summary
project
b) Schedule of Information on Company’s Background
c) Certified Copies of Relevant Certificates from governing body
Board & Commission, etc.)
Owner’s Requirement
Confidential
OWNER’S Requirements for Operation and Management System
Contractor
Broadband for All Project
2011
Release
is the intention of Realm Energy Sdn. Bhd. and Jaluran Satu Rakyat Sdn. Bhd.
Broadband Network Facilities, Infrastructure and Services including Optical Fibre
Cables for backhaul connectivity, and Broadband Power Line (BPL), Wired
technologies and solutions for last mile connectivity through-out Malaysia
broadband connectivity to a targeted 2.5 million homes. The project is
at the speed of up to 2 Mbps to areas where
this document is to provide minimum guide for the
to undertake this project. This document shall not limit the
s proposal. The Contractor is required to unde
requirement prior to producing detail proposal to undertake this
project will be awarded to the Contractor on a development, operate and manage basis
or any of the combinations deemed suitable and agreed upon by both parties.
the Proposal
shall submit the proposal in two sections:
Commercial Proposal
shall include the following items in the commercial proposal for this project.
Executive Summary – a brief write up about the company and the
Schedule of Information on Company’s Background (i.e. paid up capital, etc.)
of Relevant Certificates from governing body (i.e. MOF, Industry
Board & Commission, etc.)
Owner’s Requirements for O & M System
1
Operation and Management System
and Jaluran Satu Rakyat Sdn. Bhd. to deploy
including Optical Fibre
Wired and Wireless
out Malaysia enabling
project is expected to
to areas where accessibility to
for the Contractor in
document shall not limit the
required to understand the total
to undertake this project. This
development, operate and manage basis
suitable and agreed upon by both parties.
shall include the following items in the commercial proposal for this project.
the intended
(i.e. paid up capital, etc.)
(i.e. MOF, Industry
![Page 2: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/2.jpg)
JSR Broadband For All Project
d) Project Organisation Chart including background of Key Officers.
e) Project overall cost
f) Schedule of Prices for material, manpower,
g) Bill of Material
h) Proposed Mode of Payment
i) Schedule of Payment
j) Performance Security
II. Technical Proposal
The Contractor shall include the following items in the technical proposal for this project.
a) Overall System Architecture
The Contractor shall describe
for the Operation and Management Application System.
modules in the proposed solution shall be described in detail including the
infrastructure, detailing all hardware and supporting applications in support of the
solution. The proposed solution shall be based on an Open System
b) Proposed O&M Application
The Contractor shall include
i. Customer Information Module
the subscriber details. This detail will be
Support purposes. This module shall basically support the following functions:
a. Basic Customer Profile
b. Extended Customer P
ii. Subscriber Management Module
management functionality in terms status of subscriber activation, subscriber
suspension and type of packages subscribes. This Module will also provide historical
information to support information sales
functions shall be included:
a. Basic Subscriber Profile
b. Extended Subscriber Profile
c. Subscriber Location
iii. Infrastructure Module –
stages from pending, in
limiting to, the following information on:
Owner’s Requirement
Confidential
Project Organisation Chart including background of Key Officers.
Project overall cost
for material, manpower, applications
sed Mode of Payment
Schedule of Payment
Performance Security - 10% of the Contract Price
shall include the following items in the technical proposal for this project.
Overall System Architecture
shall describe the overall system architecture of the proposed
Operation and Management Application System. All relevant components and
modules in the proposed solution shall be described in detail including the
infrastructure, detailing all hardware and supporting applications in support of the
The proposed solution shall be based on an Open System Architecture Model.
O&M Application
include the following components in the proposed
Customer Information Module – This module shall provide the interface to input all
the subscriber details. This detail will be relationally linked to Help Desk Module for
This module shall basically support the following functions:
Basic Customer Profile
ed Customer Profile
Subscriber Management Module – This module shall be linked to CIS by providing
management functionality in terms status of subscriber activation, subscriber
suspension and type of packages subscribes. This Module will also provide historical
information to support information sales and marketing report. The following basic
functions shall be included:
Basic Subscriber Profile
Extended Subscriber Profile
– This module shall display the status of all sites at various
stages from pending, in progress to completion-in-services. It shall include and not
limiting to, the following information on:
Owner’s Requirements for O & M System
2
Project Organisation Chart including background of Key Officers.
shall include the following items in the technical proposal for this project.
the overall system architecture of the proposed solution
All relevant components and
modules in the proposed solution shall be described in detail including the
infrastructure, detailing all hardware and supporting applications in support of the
Architecture Model.
proposed solution:
This module shall provide the interface to input all
relationally linked to Help Desk Module for
This module shall basically support the following functions:
This module shall be linked to CIS by providing
management functionality in terms status of subscriber activation, subscriber
suspension and type of packages subscribes. This Module will also provide historical
. The following basic
the status of all sites at various
services. It shall include and not
![Page 3: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/3.jpg)
JSR Broadband For All Project
a. Devices
b. Inventory
c. Configuration
d. Area Map
e. Convergence Map
f. Site Status
iv. Work Order Module – This module shall comprise the following components:
a. Project Management
b. Pending order
c. Order History
d. Completed Orders
e. Tracking Work Order History
v. Partner Management Module
Contractors’ containing information of
This module shall also include the storage for retailer management and information.
This module shall comprise the following components:
a. Partner Information Portal
b. Retailer Management
vi. Workflow, Messaging & Collaboration Module
workflow engine supporting messaging, communication, escalation and change
management functionality along with audit capabilities. The components shall be the
following:
a. Workflow rule management
b. Email Management
c. Change Management
d. Escalation & Notification
vii. Helpdesk Module – This module shall be linked to the NMS, Workflow and the CIS
module to support incident ticketing, management and escalation to support the
tracking of incident reported by NMS and subscribers.
trail and historical data which is linked to the knowledgebase module. The following
components shall be included in this module:
a. Incident Management
b. NMS Integration
c. Incident History
d. FAQ and Solution
viii. Knowledgebase Module
following:
Owner’s Requirement
Confidential
This module shall comprise the following components:
Management
Tracking Work Order History
Partner Management Module – This module shall provide Repository for Partners and
Contractors’ containing information of the type of relationship and Scope of work
module shall also include the storage for retailer management and information.
This module shall comprise the following components:
Partner Information Portal
Retailer Management
Workflow, Messaging & Collaboration Module – This module shall provide a rule based
workflow engine supporting messaging, communication, escalation and change
management functionality along with audit capabilities. The components shall be the
Workflow rule management
ange Management
Escalation & Notification
This module shall be linked to the NMS, Workflow and the CIS
module to support incident ticketing, management and escalation to support the
tracking of incident reported by NMS and subscribers. It shall support a detailed audit
trail and historical data which is linked to the knowledgebase module. The following
components shall be included in this module:
Incident Management
Knowledgebase Module – This module shall, not limiting to, comprises and stores the
Owner’s Requirements for O & M System
3
This module shall comprise the following components:
This module shall provide Repository for Partners and
the type of relationship and Scope of work.
module shall also include the storage for retailer management and information.
This module shall provide a rule based
workflow engine supporting messaging, communication, escalation and change
management functionality along with audit capabilities. The components shall be the
This module shall be linked to the NMS, Workflow and the CIS
module to support incident ticketing, management and escalation to support the
It shall support a detailed audit
trail and historical data which is linked to the knowledgebase module. The following
This module shall, not limiting to, comprises and stores the
![Page 4: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/4.jpg)
JSR Broadband For All Project
a. SOP
b. Forum
c. Document Repository
d. Advanced Search Capabilities
e. Manufacturer’s Trou
ix. Reporting & Dashboard Module
myriad of reports to support all areas of the operational aspects from all modules
within this framework. The report can be saved and generated on a schedule basis. It
also flexible enough to generate an ad
rules. The components shall be as follows:
a. Preset Reports
b. Custom Reports
c. Standard Dashboard
x. Billing Module – This module
billing from the subscribers
with the work order module. It will have a set of secured reporting access to ensure
that adequate security is maintained with regards to Financial Information
Management.
a. Billing management
i. Charging
ii. Invoicing
iii. Settlement
iv. Secured Customer Access for Bill Viewing
v. Outstanding Bill
xi. User Profile Module – This module shall include the following capabilities:
a. Creating User Profile
b. Managing Access Control
c. Managing Group Policy
d. Security
xii. Interface Module – This module shall provide interface to other system related to this
project.
c) Implementation Strategy
The Implementation Strategy is the vital element to ensure the successful execution of
this project. The Contractor
development of the O&M application to ensure the basic vital functions shall be
available at the shortest possible duration for the immediate launch of this project
Owner’s Requirement
Confidential
Document Repository
Advanced Search Capabilities
ubleshooting
Reporting & Dashboard Module – This module shall provide the interface for building
myriad of reports to support all areas of the operational aspects from all modules
within this framework. The report can be saved and generated on a schedule basis. It
also flexible enough to generate an ad-hoc reporting based on a pre
rules. The components shall be as follows:
Standard Dashboard
This module shall provide the functionality of managing all aspects of
billing from the subscribers’ perspective to contractors and partners tightly integrated
with the work order module. It will have a set of secured reporting access to ensure
that adequate security is maintained with regards to Financial Information
shall include
Secured Customer Access for Bill Viewing
This module shall include the following capabilities:
Creating User Profile
Managing Access Control
Managing Group Policy
This module shall provide interface to other system related to this
The Implementation Strategy is the vital element to ensure the successful execution of
Contractor shall explicitly describe the implementation strategy for the
the O&M application to ensure the basic vital functions shall be
available at the shortest possible duration for the immediate launch of this project
Owner’s Requirements for O & M System
4
the interface for building
myriad of reports to support all areas of the operational aspects from all modules
within this framework. The report can be saved and generated on a schedule basis. It
on a pre-defined set of
provide the functionality of managing all aspects of
ctors and partners tightly integrated
with the work order module. It will have a set of secured reporting access to ensure
that adequate security is maintained with regards to Financial Information
This module shall include the following capabilities:
This module shall provide interface to other system related to this
The Implementation Strategy is the vital element to ensure the successful execution of
ementation strategy for the
the O&M application to ensure the basic vital functions shall be
available at the shortest possible duration for the immediate launch of this project. The
![Page 5: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/5.jpg)
JSR Broadband For All Project
proposal shall cover every aspect of the
and promoting plan to ensure smooth execution of
Project management
The Contractor shall establish
implementation of the project.
all activities and resources scheduled during the project implementation.
Risk management
The Contractor shall identify
during project implementation. The
plans to manage, control
schedule.
Change management
The Contractor shall establish the procedure to manage any deviation,
non-conformity and ad
implementation.
Projected timeline
To ensure proper control, monitoring and updating
Contractor is required to establish the detail project time line. The
continuously keep the time line updated from time to time for comparison of planned
activities against actual physical implementation
d) Quality Management Plan
The Contractor shall provide a project quality plan for this project. The project quality
plan shall cover all aspect of quality assurance and quality
testing, design development, reworks and any other significant activities related to the
project. The project quality
corrective and preventive action.
project owner for approval
e) Product Standard & Certification
Owner’s Requirement
Confidential
proposal shall cover every aspect of the development cycle including
ensure smooth execution of the whole development cycle.
shall establish the project management methodology for the
of the project. This shall cover the planning, monitoring and control of
all activities and resources scheduled during the project implementation.
shall identify and anticipate all potential risks potential that will
during project implementation. The Contractor shall provide risk assessment
, control and reduce the impact of each risk towards project master
shall establish the procedure to manage any deviation,
conformity and ad-hoc decision and/or instruction occurs during project
To ensure proper control, monitoring and updating of the project progress, the
is required to establish the detail project time line. The
keep the time line updated from time to time for comparison of planned
physical implementation.
Quality Management Plan
all provide a project quality plan for this project. The project quality
aspect of quality assurance and quality control for work in progress,
esting, design development, reworks and any other significant activities related to the
project quality plan shall also include handling of non
corrective and preventive action. The project quality plan must be submitted to the
project owner for approval prior to commencement of the development
d & Certification
Owner’s Requirements for O & M System
5
including contingency plan
whole development cycle.
ethodology for the
nning, monitoring and control of
all activities and resources scheduled during the project implementation.
s potential that will occur
provide risk assessment/analysis
and reduce the impact of each risk towards project master
shall establish the procedure to manage any deviation, rescheduling,
instruction occurs during project
the project progress, the
is required to establish the detail project time line. The Contractor shall
keep the time line updated from time to time for comparison of planned
all provide a project quality plan for this project. The project quality
control for work in progress,
esting, design development, reworks and any other significant activities related to the
plan shall also include handling of non-conformance,
The project quality plan must be submitted to the
the development work.
![Page 6: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/6.jpg)
JSR Broadband For All Project
The Contractor shall submit all
application. The Contractor shall list all COTS Software to be included in the final
application and shall be initially approved by the owner.
be Web based adhering to the Open System Architecture Standards. All stages of the
development shall be documented and updated regularly based on approved proposed
standards. The application develop
f) Manpower
The Contractor shall provide qualified and sufficient
technical personnel to design
assigned to work in this project
must be well versed with Telecommunications
g) Training
The Contractor shall provide technical training
knowledge, successful trials, installation, configuration and testing of the
application systems and equipment which
The training syllabus, training
proposal.
The Contractor must submit training plan together with this proposal. The training plan
shall include commitment
installation of the works take place, which
h) Testing and Commissioning plan
The Contractor shall submit all testing schedule and procedures for approval prior to
commencement of development based on SDLC
shall include detail description of all testing required to be conducted
of the development. All testing reports must be presented to the project owner after
completion of each test.
i) Warranty Management
The Contractor shall provide warranty for
Contractor shall outline extensiveness of the warranty including
period of warranty, inclusion items
warranty, duration of claim,
Owner’s Requirement
Confidential
shall submit all methodologies used in the development of the
application. The Contractor shall list all COTS Software to be included in the final
application and shall be initially approved by the owner. All HCI for the
be Web based adhering to the Open System Architecture Standards. All stages of the
development shall be documented and updated regularly based on approved proposed
standards. The application developed shall comply with ISO-12207 Standa
shall provide qualified and sufficient administrative,
technical personnel to design, manage and develop the application
assigned to work in this project must be fluent to communicate and write in English and
Telecommunications related applications.
shall provide technical training related to this project
knowledge, successful trials, installation, configuration and testing of the
and equipment which will installed for the purpose of this project
training schedule and training location shall be included in the
must submit training plan together with this proposal. The training plan
shall include commitment to provide training to RESB and JSR team before the physical
installation of the works take place, which is immediately after signing of the agreement.
ommissioning plan
shall submit all testing schedule and procedures for approval prior to
development based on SDLC. The testing and commissioning plan
shall include detail description of all testing required to be conducted
All testing reports must be presented to the project owner after
provide warranty for the total system after the final handover.
extensiveness of the warranty including (but not limited to) the
inclusion items of the warranty, method to
duration of claim, workmanship and product return.
Owner’s Requirements for O & M System
6
methodologies used in the development of the
application. The Contractor shall list all COTS Software to be included in the final
All HCI for the application shall
be Web based adhering to the Open System Architecture Standards. All stages of the
development shall be documented and updated regularly based on approved proposed
tandards.
administrative, management and
application. The personnel
to communicate and write in English and
related to this project such as product
knowledge, successful trials, installation, configuration and testing of the all related
will installed for the purpose of this project.
shall be included in the
must submit training plan together with this proposal. The training plan
to RESB and JSR team before the physical
is immediately after signing of the agreement.
shall submit all testing schedule and procedures for approval prior to
. The testing and commissioning plan
shall include detail description of all testing required to be conducted after every phase
All testing reports must be presented to the project owner after
the total system after the final handover. The
(but not limited to) the
to claim against the
![Page 7: BPL - OWNER's Requirements for ONM](https://reader030.vdocuments.mx/reader030/viewer/2022020207/5530dc474a7959ad358b484b/html5/thumbnails/7.jpg)
JSR Broadband For All Project
The Contractor shall also provide defect liability period of at least 24 months for the
workmanship and performance of the
j) Support services
The Contractor shall propose the support services and maintenance plan that will be
implemented during the warranty period.
equipment during the warranty period, the
rectification work without incurring any additional cost to the Project Owner.
The Contractor shall elaborate support services offered during a
which includes (but not limited to)
upgrading of hardware and
Any upgrading of the software
be done at no additional cost to Project Owner.
k) Hand-over
Upon completion of testing
have a walk through with Project Owner
Consultants to officially hand over the
installation, testing and commissioning for each
hand over. On completion of the total application system, a final testing and
commissioning of the total system shall be done with final walk through before the final
handover. Warranty of the total system shall commence after the final handover.
Prepared by :
Project Management Office
Updated: 20/07/11
Owner’s Requirement
Confidential
shall also provide defect liability period of at least 24 months for the
and performance of the total related system.
shall propose the support services and maintenance plan that will be
implemented during the warranty period. Should there be failure of the system or
equipment during the warranty period, the Contractor shall undertake to perform the
thout incurring any additional cost to the Project Owner.
The Contractor shall elaborate support services offered during and after warranty period
which includes (but not limited to) after sales support, equipment replacement
pgrading of hardware and software, etc.
software and hardware required within the warranty period shall
be done at no additional cost to Project Owner.
Upon completion of testing and commissioning of each module, the
have a walk through with Project Owner and/or its appointed Project Management
to officially hand over the module. All relevant documents pertaining to the
installation, testing and commissioning for each module must be signed off during
On completion of the total application system, a final testing and
commissioning of the total system shall be done with final walk through before the final
handover. Warranty of the total system shall commence after the final handover.
Office of Realm Energy Sdn. Bhd.
Owner’s Requirements for O & M System
7
shall also provide defect liability period of at least 24 months for the
shall propose the support services and maintenance plan that will be
Should there be failure of the system or
shall undertake to perform the
thout incurring any additional cost to the Project Owner.
nd after warranty period
after sales support, equipment replacement,
and hardware required within the warranty period shall
, the Contractor shall
and/or its appointed Project Management
All relevant documents pertaining to the
must be signed off during the
On completion of the total application system, a final testing and
commissioning of the total system shall be done with final walk through before the final
handover. Warranty of the total system shall commence after the final handover.