boq dan harga perkiraaan sendiri dan desain pengaman tebing
DESCRIPTION
DESAIN PENAHAN TANAH GRAVITASI,TRANSCRIPT
HARGA PERKIRAAN SENDIRI
( HPS )
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM DAERAH
BIDANG BINA MARGA
2015
PAKET PEKERJAAAN :
PEMBANGUNAN TALUD PENGAMAN TEBING
DESA OO PARESE KEC. KULAWI SELATAN
Kegiatan : -
Pekerjaan : Talud Pengaman Tebing
Lokasi : Desa Oo Parese Kec. Kulawi Selatan
Tahun Anggaran : 2015
I.
1 Pembersihan Lapangan M2 906.500 11,250.00Rp 10,198,125.00Rp
2 Pengukuran Dan Pasang Bouwplank M' 181.380 55,765.00Rp 10,114,655.70Rp
20,312,780.70Rp
III.
1 Galian Tanah Biasa dalam 1 meter M3 243.676 58,125.00Rp 14,163,682.03Rp
2 Urugan Sirtu M3 43.801 270,625.00Rp 11,853,510.31Rp
26,017,192.34Rp
VI.
1 Pasangan Batu Kali 1 Pc : 3 Ps M3 243.601 946,875.00Rp 230,660,004.61Rp
2 Finishing Siar Pas. Batu Kali adukan 1 Pc : 2 Pp M2 424.505 51,428.00Rp 21,831,443.14Rp
252,491,447.75Rp
VII
1 Papan Proyek Ls 1.000 250,000.00Rp 250,000.00Rp
2 Dokumentasi dan Pelaporan Ls 1.000 1,000,000.00Rp 1,000,000.00Rp
1,250,000.00Rp
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 300,071,420.79Rp
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 30,007,142.08Rp
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 330,078,562.87Rp
(D) DIBULATKAN 330,078,000.00Rp
Terbilang :
PEKERJAAN TANAH
PEKERJAAN STRUKTUR
PEKERJAAN LAIN-LAIN
HARGA PERKIRAAN SENDIRI (HPS)
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
Tiga Ratus Tiga Puluh Juta Tujuh Puluh Delapan Ribu
JUMLAH HARGA
PEKERJAAN PERSIAPAN
1 Pasir Pasang (Sedang) M3 250,000.00
2 Pasir Urug (ada unsur lempung) M3 250,000.00
3 Batu Kali M3 280,000.00
4 Agregat Kasar M3 250,000.00
5 Agregat Halus M3 250,000.00
6 F i l l e r Kg 1,300.00
7 Batu Belah / Kerakal M3 200,000.00
8 Batu Pecah 2/3 M3 300,000.00
9 Batu Pecah 3/5 M3 300,000.00
10 Abu Batu M3 125,000.00
11 G r a v e l M3 200,000.00
12 Bahan Tanah Timbunan M3 90,000.00
13 Bahan Pilihan M3 100,000.00
14 Aspal KG 14,500.00
15 Kerosen / Minyak Tanah LITER 15,000.00
16 Semen / PC (50kg) Zak 85,000.00
17 Semen / PC (kg) Kg 1,700.00
18 Kayu Kelas I M3 2,500,000.00
19 Kayu Kelas II M3 2,000,000.00
20 Kayu Perancah M3 1,000,000.00
21 B e n s i n ( Industri ) LITER 11,000.00
22 S o l a r ( Industri ) LITER 11,000.00
23 Minyak Pelumas / Olie LITER 35,000.00
24 Besi Beton D-8 mm Btng 57,000.00
25 Besi Beton D-10 mm Btng 84,000.00
26 Besi Beton D-12 mm Btng 125,850.00
27 Besi Beton D-14 mm Btng 178,875.00
28 Besi Beton D-16 mm Btng 256,125.00
29 Besi Plat 5 mm M 27,500.00
30 Bendrat/Kawat Beton Kg 15,000.00
31 Paku Biasa 5 s/d 10" Kg 27,000.00
32 Paku Beton Kg 85,000.00
33 Besi Penggatung D-14 mm M 203,000.00
34 Besi Strip / Klem Bh 8,500.00
35 Besi Kabel /Sling Utama D- 1 1/2" M 178,000.00
36 Besi Kabel /Sling D- 1" M 78,000.00
37 Besi Strip / Klem Penggatung Bawah 3 mm Set 153,000.00
38 Besi Strip / Klem Penggatung Atas 3 mm Set 153,000.00
39 Baut Mur 12 Bh 6,000.00
40 Kawat Harmonika M2 25,000.00
41 Cat Kayu Kg 57,000.00
42 Cat Tembok Kg 22,750.00
43 Cat Besi Kg 59,800.00
44 Cat Meny Kg 19,500.00
45 Minyak Cat Kg 21,000.00
46 Minyak Bekisting Ltr 19,500.00
47 Residu / Ter Ltr 188,500.00
48 Kertas Pasir Lbr 13,000.00
49 Kawat Bronjong Kg 20,000.00
50 Seng Gelombang Lbr 73,000.00
51 Seng Plat Lbr 53,500.00
52 Paku Seng Kg 30,000.00
1 Pekerja HOK 75,000Rp
2 Tukang HOK 80,000Rp
2 Kepala Tukang HOK 85,000Rp
3 M a n d o r HOK 75,000Rp
UPAH Satuan
Bahan Satuan
DAFTAR UPAH, MATERIAL DAN BAHAN
HARGA SATUAN
No HARGA SATUAN
No
SNI 03-2835-2002 1 M²
Tenaga
0.100 Oh Pekerja @ Rp. 75,000.00 Rp. 7,500.00
0.050 Oh Mandor @ Rp. 75,000.00 Rp. 3,750.00
Jumlah Rp. 11,250.00
SNI 03-2835-2002 1 M'
A. Bahan
0.012 M³ Kayu 5/7 ( Klas III ) @ Rp. 2,000,000.00 Rp. 24,000.00
0.020 Kg Paku Biasa 5 s/d 10" @ Rp. 27,000.00 Rp. 540.00
0.007 M³ Papan 3/20 ( Kls III ) @ Rp. 2,000,000.00 Rp. 14,000.00
Jumlah A Rp. 38,540.00
B. Tenaga
0.100 Oh Tukang Kayu @ Rp. 85,000.00 Rp. 8,500.00
0.100 Oh Pekerja @ Rp. 75,000.00 Rp. 7,500.00
0.010 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 850.00
0.005 Oh Mandor @ Rp. 75,000.00 Rp. 375.00
Jumlah B Rp. 17,225.00
Jumlah A + B Rp. 55,765.00
SNI : 2835:2008 1 M³
Tenaga
0.750 Oh Pekerja @ Rp. 75,000.00 Rp. 56,250.00
0.025 Oh Mandor @ Rp. 75,000.00 Rp. 1,875.00
Jumlah Rp. 58,125.00
Anl. SNI 1 M³
A. Bahan
1.100 M³ Batu Kali @ Rp. 280,000.00 Rp. 308,000.00
202.000 Kg Semen Portland @ Rp. 1,700.00 Rp. 343,400.00
0.485 M³ Pasir Pasang @ Rp. 250,000.00 Rp. 121,250.00
Jumlah A Rp. 772,650.00
B. Tenaga
1.500 Oh Pekerja @ Rp. 75,000.00 Rp. 112,500.00
0.600 Oh Tukang Batu @ Rp. 85,000.00 Rp. 51,000.00
0.060 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 5,100.00
0.075 Oh Mandor @ Rp. 75,000.00 Rp. 5,625.00
Jumlah B Rp. 174,225.00
Jumlah A + B Rp. 946,875.00
Anl. SNI 1 M³
A. Bahan
1.000 M³ Pasir urug @ Rp. 250,000.00 Rp. 250,000.00
Jumlah A Rp. 250,000.00
B. Tenaga
0.250 Oh Pekerja @ Rp. 75,000.00 Rp. 18,750.00
0.025 Oh Mandor @ Rp. 75,000.00 Rp. 1,875.00
Jumlah B Rp. 20,625.00
Jumlah A + B Rp. 270,625.00
Anl. SNI 1 M²
A. Bahan
6.340 Kg Semen Portland @ Rp. 1,700.00 Rp. 10,778.00
0.012 M³ Pasir Pasang @ Rp. 250,000.00 Rp. 3,000.00
Jumlah A Rp. 13,778.00
B. Tenaga
0.300 Oh Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.150 Oh Tukang Batu @ Rp. 85,000.00 Rp. 12,750.00
0.015 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 1,275.00
0.015 Oh Mandor @ Rp. 75,000.00 Rp. 1,125.00
Jumlah B Rp. 37,650.00
Jumlah A + B Rp. 51,428.00
Daftar Analisa Satuan Harga
Pembersihan Lapangan
Pengukuran Dan Pasang Bouwplank
Galian Tanah Biasa dalam 1 meter
Pasangan Batu Kali 1 Pc : 3 Ps
Urugan Sirtu
Finishing Siar Pas. Batu Kali adukan 1 Pc : 2 Pp
KEGIATAN : -
NAMA PAKET : Talud Pengaman Tebing
LOKASI : Desa Oo Parese Kec. Kulawi Selatan
TAHUN ANGGARAN : 2015
1 Pekerjaan Galian Tanah
A. Pek. Talud 1 A. TALUD 1
i. Koporan Talud
Panjang = 35.00 m
Lebar = 1.90 m
Tinggi = 0.75 m
Volume = P x L x T
= 35 x 1.9 x 0.75
= 49.875 m3
ii. Talud
Luasan I
Panjang = 35.00 m
Lebar = 0.73 m
Tinggi = 1.61 m
Volume = P x ( 1/2 x L x T )
= 35 x ( 1/2 x 0.73 x 1.61 )
= 20.57 m3
Luasan II
Panjang = 35.00 m
Lebar Atas = 0.73 m
Lebar Bawah = 0.45 m
Tinggi = 1.39 m
Volume = P x ( (La+Lb)/2 x T )
= 35 x ( (0.73+0.45)/2 x 1.39 )
= 28.70 m3 B. TALUD 2
B. Pek. Talud 2
i. Koporan Talud 1
Panjang = 43.00 m
Lebar = 0.30 m
Tinggi = 0.50 m
Volume = P x L x T
= 43 x 0.3 x 0.5
= 6.45 m3
ii. Koporan Talud 2
Panjang = 46.00 m
Lebar = 1.40 m
Tinggi = 0.50 m
Volume = P x ( 1/2 x L x T )
= 46 x ( 1/2 x 1.4 x 0.5 )
= 16.10 m3
iii. Koporan Talud 3
Panjang = 49.00 m
Lebar = 0.50 m
Tinggi = 0.50 m
Volume = P x L x T
= 49 x 0.5 x 0.5
= 12.25 m3
iv. Talud
Luasan I Panjang = 43.00 m
Lebar = 0.46 m
Tinggi = 3.50 m
Volume = P x ( L x T )
= 43 x ( 0.46 x 3.5 )
= 69.23 m3
C. Pek. Bronjong
Panjang = 36.00 m
Lebar = 1.50 m
Tinggi = 1.50 m
Volume = P x ( 1/2 x L x T )
= 36 x ( 1/2 x 1.5 x 1.5 )
= 40.50 m3
Total Volume = 243.68 m3
2 Pekerjaan Pasangan Batu
A. Pek. Talud 1
i. Koporan Talud
Panjang = 35.00 m
Lebar = 1.90 m
Tinggi = 0.45 m
Volume = P x L x T
= 35 x 1.9 x 0.45
= 29.925 m3
BACKUP PEKERJAAN PENGAMAN TEBING
NO URAIAN SKETSA
1.61
1.00
0.30
0.45
0.30
0.45 0.45
1.00
1.90
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TALUD PASANGAN
BATU KALI
1.39
0.73
KEGIATAN : -
NAMA PAKET : Talud Pengaman Tebing
LOKASI : Desa Oo Parese Kec. Kulawi Selatan
TAHUN ANGGARAN : 2015
BACKUP PEKERJAAN PENGAMAN TEBING
NO URAIAN SKETSA
ii. Talud
Luasan I
Panjang = 35.00 m A. TALUD 1
Lebar Atas = 0.30 m
Lebar Bawah = 1.00 m
Tinggi = 3.00 m
Volume = P x ( (La+Lb)/2 x T )
= 35 x ( (0.3+1)/2 x 3 )
= 68.25 m3
B. Pek. Talud 2
i. Koporan Talud Atas
Panjang = 43.00 m
Lebar = 0.30 m
Tinggi = 0.50 m
Volume = P x L x T
= 43 x 0.3 x 0.5
= 6.45 m3
ii. Koporan Talud Tengah
Panjang = 46.00 m
Lebar Atas = 0.95 m
Lebar Bawah = 1.40 m
Tinggi = 0.50 m
Volume = P x ( (La+Lb)/2 x T )
= 46 x ( (0.95+1.4)/2 x 0.5 ) B. TALUD 2
= 27.03 m3 B. TALUD 2
iii. Koporan Talud Bawah
Panjang = 49.00 m
Lebar = 0.50 m
Tinggi = 1.00 m
Volume = P x L x T
= 49 x 0.5 x 1
= 24.50 m3
iii. Talud 1
Panjang 1 = 43.00 m
Panjang 2 = 46.00 m
Lebar Atas = 0.17 m
Lebar Bawah = 0.36 m
Tinggi = 3.84 m
Volume = ((P1+P2)/2) x ( (La+Lb)/2 x T )
= ((43+46)/2) x ( (0.17+0.36)/2 x 3.84 )
= 45.28 m3
iv. Talud 2
Panjang 1 = 46.00 m
Panjang 2 = 49.00 m
Lebar Atas = 0.17 m
Lebar Bawah = 0.36 m
Tinggi 1 = 4.20 m
Tinggi 2 = 2.50 m
Volume = ((P1+P2)/2) x ((La+Lb)/2) x ((T1+T2)/2)
= ((46+49)/2) x ((0.17+0.36)/2) x ((4.2+F130)/2)
= 42.17 m3
Total Volume = 243.60 m3
3 Pekerjaan Bronjong
i. Bronjong 1
Panjang = 36.00 m
Lebar = 1.50 m
Tinggi = 1.00 m
Volume = P x L x T
= 36 x 1.5 x 1
= 54.00 m3
ii. Bronjong 2
Panjang = 36.00 m
Lebar = 1.25 m
Tinggi = 0.50 m
Volume = P x L x T
= 36 x 1.25 x 0.5
= 22.50 m3
iii. Bronjong 3
Panjang = 36.00 m
Lebar = 1.00 m
Tinggi = 0.50 m
Volume = P x L x T
= 36 x 1 x 0.5
= 18.00 m3
Total Volume = 91.81 m3
1.61
1.00
0.30
0.45
0.30
0.45 0.45
1.00
1.90
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TALUD PASANGAN
BATU KALI
1.39
0.73
KEGIATAN : -
NAMA PAKET : Talud Pengaman Tebing
LOKASI : Desa Oo Parese Kec. Kulawi Selatan
TAHUN ANGGARAN : 2015
BACKUP PEKERJAAN PENGAMAN TEBING
NO URAIAN SKETSA
4 Pekerjaan Timbunan Porus
i. Talud 1
Panjang = 36.00 m A. TALUD 1
Lebar = 0.10 m
Tinggi = 3.00 m
Volume = P x L x T
= 36 x 0.1 x 3
= 10.80 m3
ii. Talud 2 Atas
Panjang = 44.50 m
Lebar = 0.10 m
Tinggi = 3.84 m
Volume = P x L x T
= 44.5 x 0.1 x 3.84
= 17.09 m3
iii. Talud 2 Bawah
Panjang = 47.50 m
Lebar = 0.10 m
Tinggi = 3.35 m
Volume = P x L x T
= 47.5 x 0.1 x 3.35
= 15.91 m3
Total Volume = 43.80 m3
5 Pekerjaan Pemasangan Bouplank
i. Talud 1 B. TALUD 2
Panjang = 36.00 m
Lebar = 1.50 m
Volume = ( 2 x P ) + ( 2 x L )
= ( 2 x 36 ) + ( 2 x 1.5 )
= 75.00 m'
ii. Talud 2
Panjang Atas = 43.00 m
Panjang Bawah = 49.00 m
Lebar Kiri = 8.04 m
Lebar Kanan = 6.34 m
Volume = ( 2 x ((Pa+Pb)/2) + ( 2 x ((Lki+Lka)/2)
= ( 2 x ((43+49)/2) ) + ( 2 x ((8.04+6.34)/2) )
= 106.38 m'
Total Volume = 181.38 m'
6 Pekerjaan Pembersihan Lokasi
i. Talud 1
Panjang = 49.00 m
Lebar = 18.50 m
Volume = P x L
= 49 x 18.5
= 906.50 m2
1.61
1.00
0.30
0.45
0.30
0.45 0.45
1.00
1.90
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TALUD PASANGAN
BATU KALI
1.39
0.73
SHOP DRAWING( GAMBAR KERJA)
PAKET PEKERJAAAN :
PEMBANGUNAN TALUD PENGAMAN TEBING
DESA OO PARESE KEC. KULAWI SELATAN
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM DAERAHBIDANG BINA MARGA
2015
36.00
35.00
43.00
49.25
A
A
B
C
B
C
JA
LA
N T
RA
NS
K
UL
AW
I - G
IM
PU
46.83
KEGIATAN
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU
TELP. (0451) 4791666
JML. LBRKODE NO. LBR
U
PEKERJAAN
LOKASI
.........................................
.........................................
DI GAMBAR
.........................................
DI PERIKSA
ASISTEN TEKNIS
........................................
NIP.
MENGETAHUI/MENYETUJUI
PPTK
........................................
NIP.
KEPALA DINAS
H. ISKANDAR NONGTJI
PEMBINA
NIP. 19560606 199603 1 004
LEGENDA
PASANGAN BATU
TIMBUNAN PILIHAN
GALIAN BIASA
LPA KELAS B
BANGUNAN UTAMA
TEPI SUNGAI
GAMBAR SKALA
LAYOUT
1 : 350
1.00
1.25
1.50
0.50
0.50
0.50
0.50
1.00
0.50
0.15
2.50
H variasi
0.30
0.50
0.30
0.50
0.17
0.17
0.50
1.40
1.00
0.30
0.45
0.30
0.45
0.45
1.00
1.90
1.00
1
1.7
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
POTONGAN A - A
0.40
0.50
1.00
BAK KONTROL SALURAN
PIPA PEMBUANGAN
PIPA PVC AW Ø 6"
KEGIATAN
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU
TELP. (0451) 4791666
PEKERJAAN
LOKASI
.........................................
.........................................
DI GAMBAR
.........................................
DI PERIKSA
ASISTEN TEKNIS
........................................
NIP.
MENGETAHUI/MENYETUJUI
PPTK
........................................
NIP.
JML. LBRKODE NO. LBR
KEPALA DINAS
H. ISKANDAR NONGTJI
PEMBINA
NIP. 19560606 199603 1 004
GAMBAR SKALA
POTONGAN A-A
1 : 100
LEGENDA
PASANGAN BATU
TIMBUNAN BIASA
GALIAN TANAH
BRONJONG
1.00
1.25
1.50
0.50
0.50
0.50
0.501.00
0.50
0.15
2.50
H variasi
0.30
0.50
0.30
0.50
0.17
0.17
0.50
1.61
1.40
1.00
0.30
0.45
0.30
0.45
0.45
1.00
1.90
1.00
1
1.7
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
1.39
0.73
0.46
0.46
3.63
0.95
0.36
KEGIATAN
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU
TELP. (0451) 4791666
PEKERJAAN
LOKASI
.........................................
.........................................
DI GAMBAR
.........................................
DI PERIKSA
ASISTEN TEKNIS
........................................
NIP.
MENGETAHUI/MENYETUJUI
PPTK
........................................
NIP.
JML. LBRKODE NO. LBR
KEPALA DINAS
H. ISKANDAR NONGTJI
PEMBINA
NIP. 19560606 199603 1 004
GAMBAR SKALA
POTONGAN B-B
1 : 100
LEGENDA
PASANGAN BATU
TIMBUNAN BIASA
GALIAN TANAH
BRONJONG
1.00
0.50
0.15
0.30
0.50
0.30
0.50
0.17
0.17
1.00
0.30
0.45
0.30
0.45
0.45
1.00
1.90
1.40
2.50
H variasi
1.7
1
1.00
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
LUBANG PERESAPAN
DIPASANG PER 3 M SECARA HORISONTAL
PER 1 M SECARA VERTIKAL
PIPA PVC Ø 3"
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
TIMBUNAN PILIHAN PORUS
(PASIR KERIKIL), t = 10 cm
DITUTUP DENGAN
IJUK
3.00
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
TALUD PASANGAN
BATU KALI
POTONGAN C - C
LUBANG PERESAPAN
DIPASANG PER 3 M
PIPA PVC Ø 3"
DITUTUP DENGAN
IJUK
KEGIATAN
PEMERINTAH KABUPATEN SIGI
DINAS PEKERJAAN UMUM
BIDANG BINA MARGA
JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU
TELP. (0451) 4791666
PEKERJAAN
LOKASI
.........................................
.........................................
DI GAMBAR
.........................................
DI PERIKSA
ASISTEN TEKNIS
........................................
NIP.
MENGETAHUI/MENYETUJUI
PPTK
........................................
NIP.
JML. LBRKODE NO. LBR
KEPALA DINAS
H. ISKANDAR NONGTJI
PEMBINA
NIP. 19560606 199603 1 004
GAMBAR SKALA
POTONGAN C-C
1 : 100
LEGENDA
PASANGAN BATU
TIMBUNAN BIASA
GALIAN TANAH
BRONJONG