book 1 terms and conditions for construction
TRANSCRIPT
CDWM 1 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Addendum No. 3
Central Park Pumping Station Electrification Project DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
For which bids will be opened in the office of the Department of Procurement Services, Room 103, City Hall Chicago, Illinois 60602, on Thursday, July 14, 2016 August 4, 2016 at 11:00 a.m. Chicago time. BIDDER WILL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON
THE PROPOSAL PAGE
NOTICE OF Addendum
Book 1 – Terms and Conditions for Construction 1. None.
Book 2 – Instructions and Execution Documents 1. None.
Book 3 – Technical Specifications 1. Section 01 12 16, 1.10.E.2.c - Replace text “Disconnect and remove existing steam turbine
for Pump 1 which must include, but is not limited to, the following” with “Disconnect and remove existing steam turbine for Pump No. 3 which must include, but is not limited to, the following”.
2. Section 01 29 50, 1.24.A - Delete “1.6” and replace with“1.7”.
3. Section 05 51 00, 2.6.F.5 - Delete “Type 1 welds” and replace with “Type 2 welds”.
4. Section 08 71 00 - See attached revised Section 08 71 00.
5. Section 09 96 00, 2.2.C - At Paint Schedule / Class of Work / Concrete Floors, delete “Light traffic / Low Impact (Urethane Finish)” system in its entirety.
6. Section 22 10 00, Schedule – For item Natural Gas 2 -1/2” – 6”/ Joints, delete “SW” and replace with “W.”
CDWM 2 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
7. Section 22 10 00, Schedule – For item Pump Discharge / Joints, delete “SW” and replace
with “W.”
8. Section 22 10 00, Schedule – For item Non Potable Water / Joints, delete “SB” and replace with “Sd.”
9. Section 26 05 73, 3.3.A. - Replace paragraph in its entirety with the following text:
“A. Evaluate the following operating scenarios for each study. For medium-voltage
switchgear configuration under each scenario refer to Section 26 13 11.
1. Scenario 1: Normal operation; all four ComEd Lines in service; minimum ComEd fault current; Pumps 1 and 2 in service; stand-by generators off-line; USS-1 and all motor control centers double-ended.
2. Scenario 2: Normal operation; all four ComEd Lines in service; maximum ComEd
fault current; Pumps 1, 2, and 4 in service; stand-by generators off-line; USS-1 and all motor control centers double-ended.
3. Scenario 3: Normal operation; all four ComEd Lines in service; minimum ComEd
fault current; Pumps 1 and 2 in service; stand-by generators off-line; USS-1 and all motor control centers single-ended.
4. Scenario 4: Normal operation; all four ComEd Lines in service; maximum ComEd
fault current; Pumps 1, 2, and 4 in service; stand-by generators off-line; USS-1 and all motor control centers single-ended.
5. Scenarios 5 - 8: Same as Scenarios 1 - 4 but with loss of one ComEd Line of each
Service.
6. Scenarios 9 - 12: Same as Scenarios 1 - 4 but with loss of one ComEd Service.
7. Scenarios 13 - 16: Same as Scenarios 1 - 4 but with loss of three ComEd Lines, and all four stand-by generators on-line.
8. Scenarios 17 - 20: Same as Scenarios 1 - 4 but with loss of all four ComEd Lines,
and all four stand-by generators on-line.”
10. Section 26 05 73, 3.6 - Add the following text after paragraph B.: “C. Report worst case results (highest incident energy) for each location in the distribution system. For any locations where the worst case is found to be under a single-ended Scenario, or under any Scenario with one or more ComEd Line(s) out of service, perform additional analysis of similar locations based on all permutations of source feeder(s) being out of service.”
11. Section 26 27 26, 1.6.A. - Replace paragraph in its entirety with the following text:
“A. General: Furnish the following spare parts.
CDWM 3 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
1. Five (5) 15-ampere, 125-volt, 2-pole, 3-wire grounding type plugs, NEMA 5-15P nylon housing, Hubbell Cat. No. HBL5266C.
2. Twenty (20) 20-ampere, 125-volt, 2-pole, 3-wire, grounding type plugs, NEMA 5-
20P, nylon housing, Hubbell Cat. No. HBL5366C.
3. Ten (10) 20-ampere, 125-volt, 2-pole, 3-wire, grounding type plugs, NEMA 5-20P, corrosion resistant, yellow nylon housing, Hubbell Cat No. HBL 53CM66C.
4. Ten (10) 30 ampere, 480-volt, 3 pole, 4-wire, grounding type twist-lock plugs,
NEMA L16-30P, nylon housing, Hubbell Cat. No. HBL2731.”
12. Section 26 27 26, 2.5.B. - Add the following item to the table:
DESCRIPTION RATING COLOR HUBBELL CAT. NO.
Single – twist- lock 3 phase
NEMA L16-30R 30A, 480V, 3P, 4W
Black HBL2730
13. Section 33 30 00, 2.1.A.3 - Delete the last sentence “Cable bands must be provided across
the joints to maintain positive electrical conductivity.”
14. Section 40 05 20, 2.12.M.3 – Add the following text after “Water Piping:”: “For 1 in and less than 1 in piping.”
15. Section 40 05 10, Interior and Exposed Exterior Piping Schedule - Item Soil, waste, drain /
vent and Storm / Remarks, delete “Sched. 50” and replace with “Sched 40.”
16. Section 40 05 10, Interior and Exposed Exterior Piping Schedule – For item Sump Pump Discharge / Protective Coatings/Ext, delete “BH” and replace with “P.”
17. Section 40 05 10, Interior and Exposed Exterior Piping Schedule – For item Dewatering
Pump Discharge / Protective Coatings/Ext, delete “BH” and replace with “P.”
18. Section 40 91 00, 2.10.A.2. - Replace paragraph in its entirety with the following text:
2. Condition monitoring system shall be Allen Bradley Dynamix 1444 Series for Vibration and Motor shaft speed. Provide Allen Bradley 1443 Sensors for vibration sensors and Allen Bradley 1442 sensors for motor shaft speed sensor.
19. Section 43 21 15, 2.5 - Replace paragraph in its entirety with the following text:
2.5 TRANSMITTERS AND SENSORS A. Equip each pump with pressure indicating transmitters and a motor shaft speed
sensor. Provide transmitters and sensors meeting the requirements of Section 40 91 00.
CDWM 4 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Drawings:
1. Drawing C-6 – See attached revised Drawing C-6.
2. Drawing C-10 –
1. At UNDERGROUND DEMOLITION PLAN, delete note “EXISTING FIRE HYDRANT AND VALVE BOX TO BE REMOVED AND STORED. TO BE REINSTALLED AFTER TEMPORARY PARKING LOT HAS BEEN DEMOLISHED.”
2. At UNDERGROUND DEMOLITION PLAN, delete note “TEMP PLUG PIPE”. See attached revised Drawing C-10.
3. Drawing C-13 - At UTILITY PLAN, delete note “RELOCATED HYDRANT (BY OTHERS).” See attached revised Drawing C-13.
4. Drawing S-71 – See attached revised Drawing S-71.
5. Drawing S-98 – See attached revised Drawing S-98.
6. Drawing S-116 – See attached revised Drawing S-116.
7. Drawing S-118 – See attached revised Drawing S-118.
8. Drawing A-1 – At ABBREVIATIONS, delete note “HDCT HEAVY DUTY CONCRETE
TOPPING” and replace with “HDCT HIGH DENSITY CONCRETE TOPPING”
9. Drawing A-6 - At Details 2 and 3, Existing Rails to Be Restored, Conditions 1 and 2, delete note “STL ANGLE PAINTED TO MATCH” and replace with “MECHANICALLY FASTENED 1/4” X 4” STEEL PLATE PAINTED TO MATCH RAIL” See attached revised Drawing A-6.
10. Drawing A-9 – At DOOR SCHEDULE make following revisions:
The following doors are revised: 1. Door No. 121-1, change from a door type 5 to a door type 1. 2. Door No. 207-1, change from a door type 5 to a door type 1. 3. Door No. B107-1, change from a door type 6 to a door type 2. 4. Door No. 110-1, change from a door type 5 to a door type 1. 5. Door No. 112B-1, change from a door type 6 to a door type 2. 6. Door No. 112B-3, change from a door type 5 to a door type 1. 7. Door No. 122-1, change from a door type 5 to a door type 1. 8. Door No. 124-1, change from a door type 5 to a door type 1. 9. Door No. 124-2, change from a door type 5 to a door type 1. 10. Door No. 124-4, change from a door type 5 to a door type 1. 11. Door No. 208-1, change from a door type 5 to a door type 1. 12. Door No. 208-2, change from a door type 5 to a door type 1. 13. Door No. 208-3, change from a door type 5 to a door type 1. 14. Door No. 208-4, change from a door type 5 to a door type 1. 15. Door No. 211-1, change from a door type 5 to a door type 1. 16. Door No. 211-2, change from a door type 5 to a door type 1.
CDWM 5 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
17. Door No. 301-2, change from a door type 5 to a door type 1. 18. Door No. 301-3, change from a door type 5 to a door type 1. 19. Door No. 128-3, change from a door type 7 to a door type 1. 20. Door No. 129-1, change from a door type 6 to a door type 2. 21. Door No. 130-4, change from a door type 5 to a door type 1.
For door types 5 and 6 the glass size is be changed from 4” (W) x 2’-1” (H) to 8” (W) x 12” (H), affecting the following doors:
1. Door No. 117-2, change from a door type 7 to a door type 5. 2. Door No. 117-3, change from a door type 7 to a door type 5. 3. Door No. 207-2, change from a door type 7 to a door type 5. 4. Door No. 112-1, change from a door type 7 to a door type 5. 5. Door No. 201-2, change from a door type 7 to a door type 5. 6. Door No. 210-1, change from a door type 7 to a door type 5. 7. Door No. B102-1, change from a door type 7 to a door type 5. 8. Door No. B102-2, change from a door type 7 to a door type 5. 9. Door No. 130-1, change from a door type 7 to a door type 5. 10. Door No. 130-3, change from a door type 7 to a door type 5. 11. Door No. 130-5, change from a door type 7 to a door type 5. 12. Door No. 133-2, change from a door type 7 to a door type 5.
See attached revised Drawing A-9.
11. Drawing A-12 – At ROOM FINISH SCHEDULE, delete following items: 118 ROOM, 120
VESTIBULE, and 134 VESTIBULE. See attached revised Drawing A-12.
12. Drawing A-24 - At Detail 1, Partial Demolition Plan at El. +11.00 to + 14.04, near column
Line 8, delete note, “DEMOLISH ELEVATOR” in its entirety. See attached revised Drawing A-24.
13. Drawing A-25 - At Detail 2, Partial Demolition Plan at El. +54.50, immediately to the west of
column line 10 and adjacent to area noted as “DEMOLISH ROOFING IN THIS AREA”, provide the following note:
“DEMOLISH EXISTING SCUPPER AND DOWNSPOUT - PATCH MASONRY” See attached revised Drawing A-25.
14. Drawing A-40 - See attached revised Drawing A-40.
See attached revised Drawing A-40.
15. Drawing A-45 - At Detail 1, Partial Plan at +EL. +80.00, at landing pad adjacent to door R3/3, add dimensions indicating slab extends east 5’-0” from exterior face of masonry and extends north 6’-0” from face of bottom stair riser. See attached revised Drawing A-45.
16. Drawing A-79 - At Detail 6, Section at Stair in Corridor 112B, provide 6” SGU aligned to east
edge of slab to close off space below landing. See attached revised Drawing A-79.
CDWM 6 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
17. Drawing A-87 - At Detail 2, Wall Section Detail – Area E, delete note “SS CONDUCTOR HEAD” and replace with the following: “24” X 10” SS CONDUCTOR HEAD TO 4” X 4” SS DOWNSPOUT AND CONCRETE SPLASH BLOCK (TYP AT ALL DOWNSPOUTS AND SCUPPERS).” See attached revised Drawing A-87.
18. Drawing M-51 – For Section 1 – Equipment Area Section 1, see revised Section 4/P-8 on Drawing P-21 in this Addendum No. 3 for the connection between two 3” CW. See attached revised Drawing M-51.
19. Drawing H-48 – Add following Note 3 after Note 2.
“PROVIDE FLOW SWITCH ON THE MAKE-UP WATER TO 55 GALLON GLYCOL WATER STORAGE TANK. ALARM MAKE-UP WATER INDIVIDUALLY ON BOTH FLOW SWITCHES AT THE MAKE-UP WATER SYSTEM TO TCP-1 AND THE DDC SYSTEM.” See attached revised Drawing H-48.
20. Drawing H-52 – Add following Note under HVAC – PACKAGED AC UNITS. “PACKAGED AIR CONDITIONING UNITS PACU-1 AND PACU-2 ARE TO BE EQUIPPED WITH VARIABLE SPEED INVERTER DRIVEN COMPRESSOR, SINGLE ZONE VAV SUPPLY, DIRECT DRIVEN SUPPLY FANS, SPRING ISOLATED FAN ASSEMBLY, UL LISTING, AND LOW AMBIENT CONTROL DOWN TO 0 DEGREES F.” See attached revised Drawing H-52.
21. Drawing P-7 – Remove existing roof drains with portions of associated drain piping between column lines 7 and 8, and D and E. See attached revised Drawing P-7.
22. Drawing P-13 - Add 6 inch roof drain and 6 inch overflow drain and associated piping and connect to existing storm drainage. See attached revised Drawing P-13.
23. Drawing P-17 - Add 6 inch roof drain RD-1 and 6 inch overflow drain ORD-1. See attached
revised Drawing P-17.
24. Drawing P-21 – Section 4, add 3”CW connection between two 3” CW. See attached revised Drawing P-21.
25. Drawing P-22 – On Domestic Water Piping Diagram, add 3”CW connection between two 3”
CW at Pump Room. See attached revised Drawing P-22.
26. Drawing E-47 - 1. Revised PUMP NO.1 BLOCK DIAGRAM. 2. Revised NOTE 2. 3. Added NOTE 4. See attached revised Drawing E-47.
27. Drawing E-51 -
1. Revise circuit breaker designation for circuits 11 and 12 on panel UDP-1 from “SPARE” to “WATER QUALITY MONITORING PANEL”.
CDWM 7 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
See attached revised Drawing E-51.
28. Drawing E-53 – 1. Revise the “CONDUCTOR QUANTITY AND SIZE” cell for 1MP4 to be “14 – 3/C#16”
in lieu of “11 – 2/C#16 TWSP”. 2. Revise the “REMARKS” cell for 1MP4 to be “TEMPERATURE SENSORS” in lieu of
“VIBRATION/SPEED/TEMPERATURE SENSOR”. 3. Revise the “REMARKS” cell for 1MP5 to be “VIBRATION AND SPEED SENSORS” in
lieu of “VIBRATION/SPEED/TEMPERATURE SENSOR”. 4. Revise the “CONDUCTOR QUANTITY AND SIZE” cell for 2MP4 to be “14 – 3/C#16”
in lieu of “11 – 2/C#16 TWSP”. 5. Revise the “REMARKS” cell for 2MP4 to be “TEMPERATURE SENSORS” in lieu of
“VIBRATION/SPEED/TEMPERATURE SENSOR”. 6. Revise the “REMARKS” cell for 2MP5 to be “VIBRATION AND SPEED SENSORS” in
lieu of “VIBRATION/SPEED/TEMPERATURE SENSOR”. 7. Revise the “CONDUCTOR QUANTITY AND SIZE” cell for 3MP5 to be “14 – 3/C#16”
in lieu of “11 – 2/C#16 TWSP”. 8. Revise the “REMARKS” cell for 3MP5 to be “TEMPERATURE SENSORS” in lieu of
“VIBRATION/SPEED/TEMPERATURE SENSOR”. 9. Revise the “REMARKS” cell for 3MP6 to be “VIBRATION AND SPEED SENSORS” in
lieu of “VIBRATION/SPEED/TEMPERATURE SENSOR”. 10. Revise the “CONDUCTOR QUANTITY AND SIZE” cell for 4MP5 to be “14 – 3/C#16”
in lieu of “11 – 2/C#16 TWSP”. 11. Revise the “REMARKS” cell for 4MP5 to be “TEMPERATURE SENSORS” in lieu of
“VIBRATION/SPEED/TEMPERATURE SENSOR”. 12. Revise the “REMARKS” cell for 4MP6 to be “VIBRATION AND SPEED SENSORS” in
lieu of “VIBRATION/SPEED/TEMPERATURE SENSOR”. 13. Revise the “CONDUCTOR QUANTITY AND SIZE” cell for 5MP5 to be “14 – 3/C#16”
in lieu of “11 – 2/C#16 TWSP”. 14. Revise the “REMARKS” cell for 5MP5 to be “TEMPERATURE SENSORS” in lieu of
“VIBRATION/SPEED/TEMPERATURE SENSOR”. 15. Revise the “REMARKS” cell for 5MP6 to be “VIBRATION AND SPEED SENSORS” in
lieu of “VIBRATION/SPEED/TEMPERATURE SENSOR”. See attached revised Drawing E-53.
29. Drawing E-56
1. Add the following conduits:
N20A ¾” 1 – CAT6e NAP-VFD NAP-MSG
N22A ¾” 1 – CAT6e NAP-MSG NAP-M2
2. Revise the “TO” cell for N28A to be “NAP-M3” in lieu of “GCP-M3”. 3. Revise the “TO” cell for N28B to be “NAP-M3” in lieu of “GCP-M3”. 4. Delete conduit number 5C17.
See attached revised Drawing E-56.
30. Drawing E-73 1. Add existing Water Quality Monitoring Panel in same location as shown on Drawing
H-28. Add circuits 11 and 12 from Panel UDP-1.
CDWM 8 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
See attached revised Drawing E-73.
31. Drawing E-81 1. Revise Note 5 to read as follows: “ALL THREE PHASE RECEPTACLES SHOWN ON
THIS DRAWING ARE NEMA L16-30 FED FROM THE NEAREST PANELBOARD ON EL +11.00. COORDINATE RECEPTACLE TYPE AND LOCATION WITH THE COMMISSIONER’S REPRESENTATIVE.”
See attached revised Drawing E-81.
32. Drawing N-3 1. Revise “NETWORK ACCESS PANEL NAP-P1” to read “NETWORK ACCESS
PANEL NAP-P4”. 2. Revise “PUMP NO.1 CONTROL PANEL P1CP” to read “PUMP NO.4 CONTROL
PANEL P4CP”. 3. Revise “NETWORK ACCESS PANEL NAP-P2” to read “NETWORK ACCESS
PANEL NAP-P3”. 4. Revise “PUMP NO.2 CONTROL PANEL P2CP” to read “PUMP NO.3 CONTROL
PANEL P3CP”. 5. Revise “NETWORK ACCESS PANEL NAP-P3” to read “NETWORK ACCESS
PANEL NAP-P1”. 6. Revise “PUMP NO.3 CONTROL PANEL P3CP” to read “PUMP NO.1 CONTROL
PANEL P1CP”. 7. Revise “NETWORK ACCESS PANEL NAP-P4” to read “NETWORK ACCESS
PANEL NAP-P2”. 8. Revise “PUMP NO.4 CONTROL PANEL P4CP” to read “PUMP NO.2 CONTROL
PANEL P2CP”. See attached revised Drawing N-3.
33. Drawing N-12
1. Delete PASSENGER ELEVATOR CONTROL PANEL and its connection. See attached revised Drawing N-12.
CDWM 9 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Questions:
Question No. 1 Book 1, paragraph VII.E.Warranties, states that we are to “warrant all Work for a period of one year after the date of final completion”. Will the warranty for all equipment start at the final completion of all work, or will there be multiple warranties, with each warranty starting at the final completion of each phase? Answer: See Addendum No. 1, Question No. 17.
Question No. 2 Spec 43 21 15-3.6.B indicates that any additional refurbishment will be paid for under Contract Item G-2A specified in Section 01 29 50. G-2A is the ComEd allowance. Answer: See Addendum No. 1.
Question No. 3 Please provide a detail at the slab elevation change (2’-6”) at Elevation +27.50 in Area “C”. Refer to 2 on S-48. Answer: Provide 6” SGU to close off area below landing. See revised Sheet A-79 in this Addendum No. 3.
Question No. 4 Refer to Area “C” Elevation +27.50 on S-48. Does the 6” concrete slab at elevation +25.00 shown in Section 3 on S-96 extend to the wall that is 2’+- east of Column Line 5?
Answer: Yes, the 6" slab continues to the wall just east of line 5. Typical detail is 3/S-96 which shows the slab supported off the existing wall. Question No. 5 Please provide a detail at the slab elevation change (3’-5”) at the northwest corner of the elevator in Area “C”. Refer to 2 on S-98. Answer: See revised Sheet S-98 in this Addendum No. 3. Question No. 6 Section 9 on S-103 indicates that this is an existing slab. Section 1 shows a new 6” slab in close proximity to Section 9. Which is correct?
Answer: This is a new slab. See Sheet S-21 for selective demolition of existing slab in this area and Detail 7 on Sheet S-102 for new slab in this area. Question No. 7 What is the width of New Concrete Pier shown in Section 8 on S-105? Also, the note says to match the depth of the existing footing for the new footing. What are the dimensions of the new footing?
CDWM 10 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: The width of the new pier is per note 8 on Sheet S-48. For bidding purposes assume depth as 16" and width as 12’. Exact depth to be matched with existing footing during construction. Question No. 8 Please provide detail of the elevation change (2’-5-1/2”) at Area c +11.00 SOG shown on S-47.
Answer: See revised Sheet S-98 in this Addendum No. 3. Question No. 9 Are we to assume that the area between Column Lines 9-10 & D-G shown on S-47 gets a SOG like the area west? Answer: No; this area has existing fill. See Section 1 on Sheet A-61.
Question No. 10 On S-48 on Column Line 5 between E & F there is a note of 4-1/2” conc. Slab. Is this new? Answer: No. See Sheet S-21 where no demolition is shown in this area. Question No. 11 Sections 2/S-105 & 3/S-105 on Partial plan at Elev. +71.00 on S-50 show metal deck with no lightweight topping slab. Section 10/S-146 shows a topping slab. Which is correct? Answer: There is no lightweight topping slab. Per note 2 on Sheet S-50, Sections 2 and 3 on Sheet S-105 is correctly showing a roof metal deck. Section 10 on Sheet S-146 is a typical detail to show the lateral support provided to the masonry wall at the bottom of the metal deck.
Question No. 12 In Section 43 21 15, Item 1.3.C Operating Conditions Please explain what the expectation is if the pumps do not meet the rating point capacity and total head operating conditions listed in this article during the Pre-refurbishment Baseline Test is conducted in Article 3.4.C.1. Item 3.4.D states that the post-test acceptance criteria is to meet the reading of the pre-test. That would indicate that if the operating conditions are not met during pre-test, you don’t have to meet them after refurbishment. Answer: Both requirements must be satisfied. Question No. 13 Steiner Electric is the authorized Kohler Power Systems distributor in the Greater Chicago area, representing Kohler Emergency Standby Generators, Transfer Switches, and Paralleling Switchgear. As such, we have been asked by some of the electrical contractors bidding the Central Park Pumping Station Temporary Power project, to quote a Kohler generator and paralleling switchgear solution to the drawings and specifications provided for the project. Kohler generators and switchgear are not listed in the specifications as an approved supplier, but are a globally recognized manufacturer of industrial standby emergency generator systems, and are well qualified to bid to the subject specifications.
CDWM 11 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
My question is whether the City of Chicago will accept Kohler equipment, bid on this project, as an equal to the listed approved suppliers? I would appreciate your guidance in this matter. Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Question No. 14 Please provide the manufacturer and model/figure number for Suction Valve SV-3. Note that SV-3 was submerged below water and we were not allowed access. Answer: This information is not available. Question No. 15 Please provide drawings for Suction Valves SV-3, SV-4 and SV-5. Note that SV-3 was submerged below water and we were not allowed access. Answer: This information is not available. Question No. 16 Please provide any details in regards to the required torque for Suction Valves SV-3, SV-4 and SV-5. Answer: This information is not available. Question No. 17 Please provide drawings for Check Valves CV-1, CV-2, CV-3, CV-4 and CV-5. Answer: This information is not available. Question No. 18 With regards to Book 3 volume 2 of 2, Page 40 05 20-15 Paragraph T, five of the ten valves (e.g., the discharge valves DV-1 through DV-5) that require limit switches are receiving new electric actuators that will have integral limit switches. Please acknowledge that the integral actuator limit switches are sufficient for discharge valves DV-1 through DV-5. Answer: Yes. Question No. 19 With regards to Book 3 volume 2 of 2, Page 40 05 20-15 Paragraph U.2, ten of the valves (e.g., the discharge valves DV-1 through DV-5 and the suction valves SV-1B, SV-2B, SV-3 through SV-5) that require position transmitters are receiving new electric actuators that will have position transmitters. Please acknowledge that the integral actuator position transmitters are sufficient for discharge valves DV-1 through DV-5 and the suction valves SV-1B, SV-2B, SV-3 through SV-5. Answer: Yes.
CDWM 12 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 20 With regards to Book 3 volume 2 of 2, Page 40 05 20-15 Paragraph U.2, please confirm suction valves SV-1A and SV-2A do not require position transmitters. Answer: Bid per Contract Documents. Question No. 21 Due to the complex nature of this project and concern from subcontractors on being able to provide pricing by the current bid date, we would like to request a 4 week bid postponement. Answer: See Addendum No. 2. Question No. 22 3.4.A.1 Factory witness inspection for each pump. For Witness test and inspection requirements refer to Section 26 05 01. This section states that at a minimum, provide standard factory and field test for each type of equipment. The type of test is not defined. Is this supposed to be a hydraulic performance test or just a hydro pressure test of the components, or a mechanical run test just to verify vibration within HI standards? If hydraulic performance test is required, is the purpose for comparison against the Operating conditions from the pretest or comparison against the operating conditions listed in section 43 21 15, item 1.3.C? We are also assuming that the factory test is meant to be a post refurbishment test and not a pretest. Answer: Section 26 05 01 referenced in question does not exist, we assume section referred is Section 26 05 10. Section 26 05 10 refers to motor testing. Section 43 21 15 refers to Main Pumps. See answer to Question No. 12. Question No. 23 IHC Construction respectfully requests a 2 week time extension to the bid date of July 14th. The request is necessary due to the complexity of the project and not being able to make contact with either of the acceptable main pump refurbishers named in Specification Section 43 21 15. Answer: See Addendum No. 2. Question No. 24 For existing materials to be demolished, the Contractor will assume the liability for compliance with all the disposal requirements. Will the Department assume the responsibility of the "Generator" for the Hazardous Waste manifest? Answer: Yes. Question No. 25 The indemnification set forth in Book 1, Gen. Conditions., Part VIII.A.1 will be difficult, if not impossible, to insure due to the fact that the obligation is not limited to defense and indemnification for losses caused by Contractor’s performance of the work. Will the City consider the following modifications to its indemnification provision: Contractor must protect, defend, indemnify, and hold the City, its officers, officials, representatives, and employees (collectively the “Indemnitees"), harmless from and against any and all claims, damages, demands, injury or death, in consequence of granting this Contract or arising out of or being in any way connected with arising
CDWM 13 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
out of your performance under this Contract except for matters shown by final judgment Answer: No. See Contract Terms and Conditions. Question No. 26 The specifications state we must coordinate with CDWM for use of the bridge crane. If contractor requests to use the crane will a dedicated CDWM staff be assigned for the entire working day requested? What if any cost will the Contractor be charged for the CDWM staff for each day? Answer: The intent is that the existing crane will be available to the Contractor for lifts and operations that cannot be performed by other means. These costs will be absorbed by the Commissioner. Crane usage will be coordinated by the Commissioner. See Addendum No. 1, Question No. 23. Question No. 27 Section 3.9 repetitive reviews says that subsequent reviews will be performed at Contractor's expense. Please provide the cost for a subsequent submittal review for consideration with our bid. Answer: We assume question is in reference to Section 01 33 00, 3.9. Costs incurred for repetitive reviews will be passed on by the City without markup per Section 01 33 00, 3.9. As such the costs will be dependent on the specific submittal and the effort necessary to adequately review it. Question No. 28 Book 1, page 80 refers to a field office with a pay phone. Please confirm if this is required? If so, can a common use cell phone paid for by Contractor be provided instead? Answer: Yes. The intent is that a phone will be available for use by persons other than your Superintendent. Question No. 29 Book 1, General Conditions Part VI.E.1 states that in event of default CDWM may either provide no cure period or provide a 10-day cure period. Can CDWM provide an automatic 10 day cure period for any default? Answer: No. See Contract Terms and Conditions. Question No. 30 Will the CDWM provide a 3 week bid extension? Answer: See Addendum No. 2. Question No. 31 Specification 40 94 43-7, 2.1B.4 – redundancy module. The Allen Bradley part indicated is not a redundancy module for PLC’s but an interface module for the redundant I/O. the redundancy module would be a 1756-RM. Is the intention of this project to have both redundant PLC’s and redundant I/O for all PLC systems? Please clarify. Answer: Yes. Refer to Section 40 94 13, 1.1.A.1.c.
CDWM 14 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 32 Drawing #N22 to N26. These drawings list a different Allen Bradley I/O card than is listed in the specifications. The card type on these drawings are for the Allen Bradley CompactLogix series of PLC and the type specified in 40 94 43 is redundant ControlLogix I/O. The points per card are also different. Please clarify what cards are required. Answer: Refer to Section 40 90 50, 1.4.B. I/O card requirements are specified in Section 40 94 43. Question No. 33 The drawings (N22-N26) shows hard wired I/O but drawings N32 and N33 shows additional hard wired signals that do not show up on N22-N26. Will the I/O schedules be updated to match? Answer: No. The list shown on Sheets N-22 through N-26 only contains the I/O related to Pumps 1 through 5. Refer to Section 40 90 50, 1.4.B. Question No. 34 Specification section 40 94 13 talks about the GE iFIX HMI software that is required for the project. Drawing N4 also mention using thin clients for the monitors which requires the use of another GE product, iFIX terminal Server, which is not mentioned in the specifications. Is the intention to have a separate server for these thin clients running GE terminal server? Answer: No. The intent is to run iClientTS (iFIX terminal Server) on the redundant iFIX servers. Question No. 35 Will we have access to the area to the north of the new Generator Building and closure of the railroad tracks so we can install the Permanent Generators through the new wall louvers in the north wall of the Generator Room (see drawing C-4)? Answer: This area is not City property. Permission and access must be pursued directly with the railroad. The current intent is to install the permanent generators and other equipment through the existing dock door at Col D-12A on elev. +27.5. Question No. 36 If required, would we have access to the area north of the “ 6’ tall chain link fence” shown on drawing C-4? Answer: This area is not City property. Permission and access must be pursued directly with the owner of the property. Question No. 37 Drawing E-6 shows a structure tagged as “Switchgear Building”. We cannot find any details or specifications on this building. Please clarify. Answer: This is a temporary building constructed by the Contractor to house the equipment associated with the temporary generators. As it is a temporary building designed, submitted, and subsequently removed, by the Contractor there are no details or construction specifications needed in the Contract Documents. It must be suitable for the intended use.
CDWM 15 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 38 Drawing E-81 shows (8) 3-phase receptacles in the Basement Shops. Please confirm the types of receptacles required and the panel and circuit numbers from where they are fed. Answer: For Bidding purposes assume NEMA L16-30 fed from the nearest panelboard on elev. +11. Exact NEMA configuration to be coordinated during Construction. See revised Sheet E-81 in this Addendum No. 3. Question No. 39 Drawings N-6 and N-7 show multiple redundant PLC in the network. Is it permissible to use one redundant PLC in the System Master Control with redundant I/O drops to generator and main switchgear and MCC’s 2 and 3 in the generator room? Answer: Bid per Contract Documents. Question No. 40 Enercon would like to propose Woodward Easygen generator controllers and Woodward LS-5 mains and tie breaker controllers in lieu of Woodward SPMA analog synchronizers. Woodward EasYgen is current technology and very robust. (Cut sheets attached). We have implemented these devices at the last two (2) pumping stations for the City of Chicago. Is this acceptable? Answer: Bid per Contract Documents. Question No. 41 Enercon would like to propose eliminating the light box annunciators and provide mimic screens in the HMI’s. A larger HMI would be selected with alarm initiating screen changes for improved visibility offsetting the loss of the light panels. This would also result in a significant cost and space reduction. Is this acceptable? Answer: Bid per Contract Documents. Question No. 42 Specification Section 131290 calls for an 8’-0” x 8’-0” Modular Office unit; however I do not see this unit on the drawings. Please confirm that this unit is to be used as the temporary pump engineer’s kiosk that is to be provided at Pump Room Elevation -18.00. If so, please indicate the location of this building for installation purposes. Answer: Refer to Sheet M-3 for usage of temporary kiosk. Coordinate and submit location during construction. Question No. 43 Please confirm that the contractor will be able to utilize the overhead crane in the existing pump room for the removal and reinstallation of the existing pumps, as well as the installation of the new medium voltage electric motors. Please confirm if the capacity of the crane will be adequate for the installation of the new motors.
CDWM 16 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: Usage of the existing overhead crane is addressed in Addendum No. 1, Question No. 23. Refer to Section 26 19 00, 3.1.B for installation of MV motors that exceed the capacity of the existing crane.
Question No. 44 Section 01-29-50 – Page 6 Art 1.24, contract item SP-3 – spare parts, in section 23-34-00 spare parts is paragraph 1.7 not 16. Please correct Art 1.24. Answer: This is a typographical error. Correct reference is Section 23 34 00, Paragraph 1.7 Spare Parts. Question No. 45 In Spec section 221000-13 it states that the Above Ground Sanitary Waste, Drain, Vent & Storm Piping is to be Cast Iron Service Weight with Lead & Oakum joints. This is a very antiquated and expensive way to install Cast Iron pipe. Would Cast Iron No-Hub or Sch. 40 PVC DWV be an acceptable alternative? Answer: Bid per Contract Documents. Question No. 46 In Spec section 221000-13 it states that the Under Ground Sanitary Waste, Drain & Vent Piping is to be Cast Iron Service Weight with Lead & Oakum joints. This is a very antiquated and expensive way to install Cast Iron pipe. Would Cast Iron Service Weight with Compression Gaskets or Sch. 40 PVC DWV be an acceptable alternative? Answer: Bid per Contract Documents. Question No. 47 In Spec section 221000-13 it states that the Natural Gas Piping 2-1/2” – 6” is to be Sch. 80 Steel with Solvent Welded joints. I believe this is supposed to be regular Welded joints. Answer: This is a typographical error. Correct joint type is W. Question No. 48 In Spec section 221000-13 it states that the Pump Discharge Piping is to be Sch. 80 Steel with Solvent Welded joints. I believe this is supposed to be regular Welded joints. Answer: This is a typographical error. Correct joint type is W. Question No. 49 In Spec section 221000-13 it states that Non Potable Water is to have “SB” joints. “SB” is not listed in the joints schedule. Is this supposed to be “Sd” for Soldered joints? Answer: This is a typographical error. Correct joint type is “Sd” Soldered joint. Question No. 50 Please extend the bid date 2 weeks to allow for time to determine the best way to place and install the (3) larger MV motors due to the lifting capacity limitations of the overhead crane. Answer:
CDWM 17 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
See Addendum No. 2. Question No. 51 Area D Plan shown on S-52 and S-110 shows slab elevation of +11’-7” down to +11-0” somewhere between columns 6 and 6B. Where is the location of the 7” difference? Please provide detail. Answer: No detail is required. Elevation varies as indicated in the Sections on Sheet S-118.
Question No. 52 On S-118 there is no Section number on the lower right section. We assume its number 4? There is a 5’ dimension labeled New FDN but it’s not shown as new like the other side. Is this new or existing? Answer: Assume the untitled Section is number 4. The word "NEW" beneath the 5'-0" dimension is a typographical error and should read "EXIST". See revised Sheet S-118 in this Addendum No. 3. Question No. 53 There is no N/S section through pier C1/6B/7A. Does the new foundation extend on the N/S side of the pier the same way as Section 1 on S-118? Answer: The N/S section is similar to Section 2/S-118. Refer to General Note 6 on Sheet S-1. Question No. 54 Is there any work at Pier C1/8A/8B on S-118? No section cuts or notes showing any. Answer: The work at this pier is similar to Pier C1/9A/10A. Question No. 55 There is no E/W section through pier C1/9A/10A. Does the new foundation extend on the E/W side of the pier the same way as Section 2 on S-118? Answer: No work is shown. Bid per Contract Document. Question No. 56 Section 3 on S-118 calls for #5 rebar @ 18” centers drilled and grouted into the existing slab. Note 5 refer us to 9/S-144 which has the dowels @ 12” on center. Is Note 5 for waterstop and vapor barrier only? Answer: Yes. Question No. 57 Does the beam shown in 2/S-114 run the all the way between Columns A & B2? Answer: Yes, as shown on 7/S-112.
CDWM 18 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 58 Does the beam shown in 3/S-114 run the length of the grating platform only? Answer: Yes. Refer to 1/S-120 between column lines 12A and 13. Question No. 59 What is the length of the pad shown on 2/S-114 & 11/S-115? Answer: See revised Sheet A-45 in this Addendum No. 3.
Question No. 60 Section 11/S-121 shows a beam and SOG. Is this SOG poured on top of existing slab? If so, the demo drawings do not show any concrete removal for the beam. If it’s open area than it’s not a SOG. Also, does this slab get any drilled dowels into any existing concrete? Answer: There is no existing slab in this area. Provide new SOG as shown. See Sheet S-143 for typical SOG details. Question No. 61 Section 3/S-57 shows existing sand fill in the hoppers. When the hopper is partially demolished and the new wall is built do we put the sand fill back into the hoppers? Answer: Yes; the intent is to not have a void below the slab between Column Lines A and B. Question No. 62 Section 1/S-130 shows lean concrete fill west of 16A. What are the dimensions of this area? The drawings are unclear. Answer: On Sheet S-58, the length of this area is provided and the width is 5’-2”. See Sections 1 and 4 on Sheet S-130 for vertical profiles. Question No. 63 Approximately how many minutes does it take the bridge crane, over the pump area, to raise and lower the hook from -18 elevation to the overhead door in the southeast corner and back to -18? From the Compass Rose for reference would be good. Answer: The round trip from Compass Rose at Elevation -18 to the overhead door at Elevation +25 and return takes approximately 10-11 minutes without a load. The overall travel speed when loaded is dependent on the weight and inertia of the load. Question No. 64 Questions 1a-1e: Per Page 40 05 20-15, Paragraph 2.11.S, “…Where the operators are located over 7 feet from the floor or in an inaccessible location, connect all internal control and indication wiring to a terminal block within the operator enclosure and provide a separate control station for remote mounting…” a. It would seem several of the required electric motor operators for valves are on the margin of
CDWM 19 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
whether they would require separate control stations. Please identify which actuator or actuators require a remote control station.
Answer: Refer to Section 40 05 20, 2.11.S. b. Please describe from what point on the operator the distance to the floor is to measured. For
simplicity, we would propose the top of the actuator. Answer: This is reasonable.
c. How do you define “floor” in regards to the 7 foot measurement for the remote control station?
We would define the “floor” as any structure that could support a person. Answer: Floor in this instance refer to the surface that operating personnel would normally stand. d. With regards to DV-5, does the “floor” indicate EL -8.42 feet or on the platform approximately 8
feet off the main floor? Answer: Floor in this instance would be EL -8.42. e. How do you define “inaccessible” in regards to the need for the remote control stations? Would
any operator other than DV-4 be considered “inaccessible”? Answer: Inaccessible in this instance refers to the inability to readily access the actuator for operation. Operators located more than 7 feet above the floor are inaccessible. Question No. 65 Please clarify that Paragraph 2.3.E of Page 40 05 20-8, which specifies “…bonnets for 4-inch and larger gate valves are to be provided with outside screw and yoke bonnets…”, does not apply to the 36-inch non-rising stem gate valve with electric motor operator to be installed in the suction pipe of each of Main Pumps No.1 (SV-1B) and No.2. (SV-2B) pursuant to Paragraph 1.1.A.1 of Page 40 05 20-1. Answer: Yes. See this Addendum No. 3. Question No. 66 Specification 01 789 00 1.7-B indicates 260 hours per session for training for Specification 40 98 00. Based on 4 sessions, this will be a total of 1,040 hours. This seems excessive. Please confirm the number of training hours is correct. Answer: Bid per Contract Documents. Question No. 67 Will partial warranties be granted as equipment is started up and put into operation? The project will be implemented over several years so some equipment will be put into service and in operation for years before the project Final Completion date. Answer: See Addendum No. 1, answer to Question No. 17.
CDWM 20 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 68 Specification 40 94 43 2.1-B-2 Indicates 1756-PA72 power supply for PLC chassis. 40 94 13 1.1-A-1-c indicates redundant PLC power supplies are to be used. 1756-PA72 is not a redundant power supply. Please confirm the type of power supply to be used. Answer: Refer to Section 40 94 43, 2.3.B.1.
Question No. 69 Specification 40 94 43 2.1-B-4 lists P/N 1715-AENTR is listed as the redundancy module. This is the Ethernet adapter for the Redundant I/O chassis (not a redundancy module). The redundancy module for the ControlLogix Processor Chassis should be 1756-RM2. Please confirm. Answer: Confirmed, refer to Section 40 94 13, 1.1.A.1.c. Question No. 70 Various N Drawings (N-22 through N-26) indicate using 1769 series I/O. This conflicts with Specification 40 94 43 which specifies 1715 Series ControlLogix redundant I/O. Confirm which I/O is to be used. Answer: Refer to Section 40 90 50, 1.4.B. Sheets N-22 through N-26 are intended to provide a partial list of I/O points only. I/O card requirements are specified in Section 40 94 43. Question No. 71 Network Configuration Drawings and Panel Detail Drawings both show only two PLC racks. Redundant ControlLogix requires a minimum of three racks: Two identical racks for the PLC Processors and a third (or more) rack for I/O. Please confirm the PLC architecture. The intent of the plans/specs appears to be using Redundant ControlLogix PLCs with Series 1715 Duplex redundant I/O (meaning all I/O modules will be duplicated). Please confirm. Answer: Confirmed. Panel detail on Sheet N-27 shows two ControlLogix chassis, two redundant power supplies, and two Bulletin 1715 redundant I/O chassis. Note 1 indicates that the Detail is diagrammatic and is not intended to be a panel fabrication drawing. Question No. 72 Does the City have a preference for MFR/Model of DIN rail mount industrial Ethernet switches? I could not find any specifications for these items in either 40 94 13 or 40 95 13. I assume DIN rail mount Ethernet switches are to be installed inside the PLC panels, not rack mount switches. Please confirm. Answer: Confirmed. Sheets N-27 through N-30 show DIN-rail mounted switches. The manufacturers listed in Section 40 94 13, 2.3.A.4.b are acceptable.
CDWM 21 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 73 Specification 40 94 13 2.10-A indicates providing one development and two iClient licenses for iFix SCADA software. Specification 40 94 13 2.8-A indicates three iClient desktops are required (CPPS Control Room, Server Room and Station’s Chief Office). Drawing N-4 shows two servers, one desktop computer in the Chief’s office based on Note 8, two other clients (presumably as they are not referenced to Note 8) in the Server Rack and the Server Room, and four other “thin client” monitors as indicated by Note 7. Are the “thin client” monitors actual Thin Client machines with monitors? There is no specification for Thin Client machines or licensing to support a thin client architecture (which typically would require a Remote Desktop Services (RDS) sever). Please provide clarification of the SCADA Server/Client architecture and licensing required. Answer: “Thin client” is used to reference computer hardware meeting the generally accepted industry definition of the term, consisting of at minimum a display, keyboard, and mouse as shown on Sheet N-4. Any additional hardware and software required to achieve the thin client architecture are to be provided in accordance with Section 40 90 00, 1.1.C. Refer to Section 01 11 00, 1.2.D, Section 40 90 50, 1.4.B, and Question No. 34. Question No. 74 Do the generator circuit breakers (in GSG-1) have to conform to generator breaker standards C37.013/013a Answer: No. Bid per Contract Documents. Question No. 75 Refer drawing # E-13 (MSG-1 Elevation). Please confirm if we have to provide an empty vertical section for the Remote I/O shown on the left hand side of the switchgear elevation. Also per paragraph M.5 on page 26 13 00-17 of Medium Voltage Switchgear specification, it is mentioned that the Generating Paralleling Controller “GPC” remote I/O modules should be installed in an auxiliary compartment of the switchgear. If we have to install the remote I-O modules in the switchgear, we will need more details and make of the remote I/O modules. Answer: Confirmed, the leftmost section of MSG-1 is an “empty” section which does not include the main power bus. Provide remote I/O in accordance with Section 40 94 43 per Section 26 13 23, 2.2.D.3.a.(3). Question No. 76 Refer drawing # E-16. This drawing shows a separate elevation for the switchgear GSG-1 and a separate elevation for the GPC (Generator Paralleling Controller). We assume that the GPC is a separate 9 section control panel board with all paralleling controls installed. Please confirm. Answer: The GPC and GSG-1 are separate pieces of equipment. Their locations are shown on Sheet E-82.
CDWM 22 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 77 Refer drawing # E-45. We need complete catalog numbers of the SEL relays shown on the table on the RHS bottom. The table gives only the basic catalog numbers. The relay prices can vary significantly based on the catalog numbers selected. The catalog numbers of the following relays are needed:
SEL-351
SEL-587Z
SEL-311
SEL-751A
SEL-700G
SEL-734 Answer: Exact catalog numbers will not be provided. Relay models are specified to show design intent; determination of exact catalog number is the responsibility of the switchgear manufacturer based on meeting all specified functional requirements.
Question No. 78 Will equivalent Siemens numerical relays be acceptable in lieu of the specified SEL relays?
Answer: Bid per Contract Document. Acceptable manufacturers are listed in Section 26 13 00, 2.1. Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Questions No. 79 Refer paragraph 2.4.A.3 on page 26 13 00-17 of Medium Voltage Switchgear specifications. Please furnish details (make and model #) of the remote operator interface terminal to be installed in the LCP (Main Switchgear Local Control Panel) mentioned under this paragraph. Answer: Refer to Section 26 13 23, 2.2.B.2.j and Section 40 94 43 for operator interface terminal requirements. Question No. 80 Refer paragraph “h” on page 26 13 00-14 of Medium Voltage Switchgear specifications. We need to know the communication protocol required for the SEL relays and SEL meter installed in the switchgear. Answer: Contractor to select communication protocol for the microprocessor based relays. Relay must be able to communicate with PLC per Section 26 13 00, 2.3.J.2.h and Section 40 94 43, 3.1.C. Question No. 81 Specification 26 18 39 2.2d1 – Siemens drive does not have electrostatic shield on the transformer due to the custom phase shifting transformer we include. Will this be acceptable? Answer: Bid per Contract Documents.
CDWM 23 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 82 Specification 26 18 39 2.2d2 – Can we get more information on where the temperature control panel should be located? Answer: Temperature control panel is located in VFD transformer compartment since it is specified under “Input Transformer” in Section 26 18 39, 2.2.D. Question No. 83 Specification 26 18 39 2.2m7 – please clarify where SEL-4600 will be installed and why is it needed? Answer: There is nothing to clarify. Test blocks are designed to be mounted on the VFD enclosure to be accessible from the outside; exact location to be determined by manufacturer based on their specific design. Bid per Contract Documents. Question No. 84 Specification 26 18 39 2.7H – please confirm that VFD and motor string will be done at the pump manufacturer? And not at VFD and/or motor factories Answer: Bid per Contract Documents. VFD and motor testing location is specified in Section 26 18 39, 2.7.H.3.
Question No. 85 Specification section 26 05 12, paragraph 3.2 TEMPORARY ELECTRIC SERVICE, states that the Contractor is to pay all Com-Ed charges and fees associated with securing temporary electric service. There will be a Com Ed excess facility charge for the temporary power drop at the site. We have no way of determining how much this charge will be. We request that an allowance be established for the Com Ed excess facility charge, or that the Contractor be paid by change order for this charge. Answer: The Contractor is responsible for providing temporary power for his trailers and other construction activities. This is considered normal construction practice. It is intended that such pricing and scheduling will be coordinated directly between the Contractor and the Utility (ComEd). Question No. 86 Please confirm the CDWM will claim “Generator” status for any pre-existing hazardous waste/special waste materials encountered on this project. Answer: See Question No. 24. Question No. 87 There is a discrepancy between Detail 1 and Detail 2 on Contract Drawing C-35. Detail 1 requires 3000 psi concrete around Detention Structure Precast Element, while Detail 2 calls for 250 psi flowable fill. Please advise on which detail is correct. Answer: Detail 2 on Sheet C-35 ‘Detail (A) Joint Tape Installation’ is intended to show installation of joint tape. Per Detail 1, 3000 psi concrete is required.
CDWM 24 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 88 Is railroad protective liability insurance required for this project? If so, please provide the limits. Answer: Limits must be coordinated with the railroad to satisfy the requirements stated in Book 2 of the Contract Specifications. Per best information available from CSX, railway insurance requirements are indicated on pages 10 and 11 of CSX’s Public Project Information manual. See attachment A. Complete Public Project Manual available in the following link: https://www.csx.com/index.cfm/library/files/about-us/property/public-project-manual/ Question No. 89 How many and what kind of trains per day utilize the tracks? Answer: Per best information available from CSX, less than one train per day. Question No. 90 When will railroad flaggers be required? Answer: See attachment A. Question No. 91 Who is responsible for the cost of the railroad flaggers? Answer: Cost of flagger to be included as Bid Item No. G-1, Lump Sum Project Work. Per best information available from CSX, current cost of flagger per day has been revised to $1,500. Question No. 92 Can the elevator in Area A be utilized for construction purposes? What is the load capacity of the elevator? Answer: No. Existing facilities, including the washrooms and elevators, are for use by City personnel only.
Question No. 93 On Drawing S-38, at the matchline for S-37, it calls for both ‘1” GAP’ and ‘1” EXP’ between slabs @ EL -9.92. Please clarify if the intent is a gap or expansion joint between the slabs? Answer: Provide 1" gap. Question No. 94 Can you please consider pushing the bid date back a week or so? Answer: See Addendum No. 2. Question No. 95 Will the Contractor be required to purchase a City of Chicago building permit for this project? Answer: Yes. The Contractor must secure and pay for all Permits.
CDWM 25 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 96 Are there any existing drawings showing the typical cross section of the RR tracks that are to be removed. Answer: Refer to Section 1 on Sheet S-80. Additional detail information is not available. Question No. 97 On Sheet P-4 , Note #3 states All Existing Sump Pumps to be demolished, Existing Duplex Sump Pumps #1 to #4 are not label to be demolished, please clarify if the Duplex pumps #1 to #4 are to be demolished. Answer: No conflict exists. Refer to Note 3 on Sheet P-4. Question No. 98 Please show where the temporary bridges for vehicular and pedestrian traffic are intended to be utilized as described in specification section 01 50 00, Section 1.8. Answer: Locations, quantities and details of temporary bridge are dependent on Contractor’s means and methods. Question No. 99 Specification section 26 27 26 – Wiring Devices does not list any spare parts for bid item SP-13. Answer: Addressed in this Addendum No. 3. Question No. 100 On Drawing S-47, the proposed SOG west of the new elevator pit is +14’-1” and the proposed SOG south of the new elevator pit is +11’-6-1/2”. Please provide a detail showing how these to SOG with different elevations connect. Answer: See Question No. 8 answer. Question No. 101 Please provide the elevation for the proposed foundation on sheet S-47 between column lines 9 and 10. Answer: Per Sheet S-47, match width and depth of existing foundation. Also see response to Question No. 7. The bottom of the footing is at EL. +8’-9”. This shall be verified in the field. Question No. 102 Will security be required at all construction access points during construction hours? Answer: Refer to Section 01 11 01, 1.2 P.
CDWM 26 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 103 Who is responsible for payment of the city-provided crane operator if utilized by the Contractor? Answer: The existing crane will be available to the Contractor for lifts and operations that can not be performed by other means. These costs will be absorbed by the Commissioner. It is not intended to be used for recurring construction activities. Crane usage will be coordinated by the Commissioner. Question No. 104 On drawing S-92, section 1, please provide a connection detail between the existing foundation and new concrete footing. Answer: There is no connection. Question No. 105 Plan sheet C-10 indicates there is a fire hydrant on the south side of W. Fillmore Street to be removed, stored, and reinstalled after the temp parking lot is installed. Sheet C-13 says this work is to be done by others. Is the work involved in relocating this hydrant part of this contract of will this be by others? Answer: The relocation of the existing fire hydrant has been already completed by Others. See revised Sheets C-10 and C-13 in this Addendum No. 3.
Question No. 106 In regards to the new 8” Water Services, plan sheet C-36 note 2 states “DWM to furnish valve basins, tees/taps, and valves. Contractor to install.” Spec section 33 10 00 sub section 3.5 A and 3.9 A state DWM will execute the tap and provide a point of continuation for the contractor. Please Clarify who is responsible to perform the actual tap of the existing water main. Answer: The City will cut in the new tees and corresponding valves. The contractor is responsible for prepping the site (excavation, shoring, etc.) and for continuing the service installations from the control valves to the building. Question No. 107 If the contractor is responsible for tapping the existing water main will the main be shut down for a “cut in connection” for the services and new valve? Or will pressure connections and insert-a-valves be required? Answer: See answer to Question No. 106 above. Question No. 108 Spec section 33 30 00 part 2.1 Ductile Iron Pipe for Storm Sewer - #3 requires cable bands across joints for cathodic protection. The specs for Ductile Iron Water Main do not state the need for cathodic protection. Please confirm that this is correct. Answer: Per Section 33 10 00, Ductile Iron Water Main do not need cathodic protection.
CDWM 27 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 109 After successful completion of the 30 day continuous operational testing of a single pump conversion, and in accordance with the Department of Water Management Terms and Conditions for Construction Contracts- Article IV “Property” paragraph E “Right to Occupy Before Substantial Completion”, will the City take responsibility to operate, maintain and repair (to the extent not covered by warranty) the pump, motor and VFD? Will the warranty period start after successful completion of the 30 day continuous operational testing of a pump conversion? Answer: Following the acceptance of the converted pump the City will operate the equipment. The Contractor must maintain and repair the equipment through the end of the Warranty period, which begins as described in Book 1 of the Contract Specifications. Question No. 110 Specification section 43 21 15 paragraph 3.6B states additional refurbishments so authorized by the Commissioner will be paid for under contract item G-2A. Contract item G-2A is titled “ComEd Optional Facilities Charge not specifically included in contract item No. G-1”. Please clarify. Answer: See Addendum No. 1, Book 3 – Technical Specifications, Item No. 17. Question No. 111 Is it the intent that W. Fillmore St. will be closed to thru traffic for the duration of the project? Answer: The portion of Fillmore St. shown on Sheet C-6 will be closed for the duration of the Project. CDOT coordination must be completed by the Contractor prior to road closure. Question No. 112 Due to the complex nature of this project and concern from subcontractors on being able to provide pricing by the current bid date, we would like to request a 4 week bid postponement. Answer: See Addendum No. 2. Question No. 113 Can the existing building plans be made available in order to calculate how much reinforcement is in the existing concrete? Answer: This information is not available during bidding. Question No. 114 Please provide a reinforcement/dowel detail for 19” concrete slab @ EL. 21’-7” on Contract Drawing 2/S-57. Answer: For bidding purposes, reference Detail 6 on Sheet S-84. Exact configuration to be coordinated during construction. Question No. 115 Please provide existing as built plans for the Hopper and beam support system (Sheet S-75) in Area D to be removed. i.e. wall thickness. Answer:
CDWM 28 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
This information is not available during bidding. Question No. 116 SPECS 03 30 00, 3.3.J requires construction key joints at all construction joints. However, the drawings show construction key joints only at specific construction joints on walls and slabs below the grade. Please clarify which is correct. Answer: Referenced specification clearly states, "Unless noted otherwise." Follow construction documents. Question No. 117 Sheet C-10, note 3 states that concrete foundations and demolition debris from the previously demolished Natorium are present below grade and is to be removed if encountered during the excavation work…work to include removal of 1440 cubic yards of material and replacement with backfill. Please clarify if this note means the total removal is 1440 CY or is it 1440 CY and any additional concrete foundations and demolition debris encountered. In addition, please address the type of material that is expected to be encountered if it is not concrete material. Is it all concrete foundation, is it broken concrete or unbroken material? Is it contaminated material? Answer: The note refers to 1,440 CY of total material removal. The material is anticipated to include, but not limited to, concrete foundations, broken concrete, brick, reinforcement and other various building debris. Question No. 118 The environmental report and drawings provide general locations and the type of materials that would need to be abated for asbestos. Can the quantity of the material that needs to abated for asbestos be provided? Answer: The Contractor is responsible for abatement of all ACM in the defined work area(s) as shown on the drawings and reflected in the specifications. The Contractor is responsible for abatement of all similar ACM materials not specifically enumerated in the table in the specification. Question No. 119 The environmental report and drawings provides general locations and the type of materials painted that would need to be abated for lead. Can the quantity of the material that needs to abated for lead be provided? Answer: The Contractor is responsible for abatement of all lead-based paint (LBP) in the defined work area(s) as shown on the drawings and reflected in the specifications. The Contractor is responsible for abatement of all similar LBP materials not specifically enumerated in the table in the specification. Question No. 120 Some of the items to be removed from the table provided in the hazardous and non-hazardous survey report does not match when you add up the totals quantities for each room and for each type of materials compared to the total on the bottom of the table. Please clarify which is the correct value to use for the removal of these items. Answer: The total is the sum of all rooms.
CDWM 29 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 121 Please confirm there no dowel required between the existing foundation and new wall foundation per Detail 7/S-133? Answer: Follow Detail 7/S-133. Question No. 122 Please clarify the difference between the PTD and HDPC floor finished as shown in the drawings. The specification section 096700 High Density Concrete Topping identifies two types of material a “Regular Duty” and “Heavy Duty”. How does the specification align with the designations in the drawings? Answer: There is no HDPC. It is assumed contractor is referring to HDCT (High Density Concrete Topping). See this Addendum No. 3. Provide floor finishes per Room Finish Schedule on Sheet A-12. At floors labeled HDCT, provide finish in accordance with Section 09 67 00 (High Density Concrete Toppings). Section 09 67 00 indicates where regular duty and heavy duty HDCT is to be used. At floors labeled PTD (painted), provide finish in accordance with Section 09 96 00 (High-performance Coatings). Question No. 123 Please identify the system components that should be used to achieve the topping surface as shown on A-33. Detail 2 shows an HDCT material at the top, but does not identify the material that “varies” in size. Please clarify. The specification section 096700 only calls for system thickness of 3/16” for regular and heavy duty topping materials. Answer: See Detail 6 on Sheet S-84 for construction of concrete topping material marked as “varies”. Question No. 124 Please identify the difference between Floor Type 1 and Floor Type 2 as shown on Drawings A-32 and A-33 Answer: Floor Type 1 and Floor Type 2 differ only in the finish color to delineate the (3) motor assembly areas. Question No. 125 Specification section 125000 item 2.2.A states “Manufacturers: Subject to compliance with requirements, provide products by one of the following:” to which it goes on to list various manufacturers for different products such as Steelcase and Allsteel. Please confirm if alternate manufacturers will be allowed. Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION Question No. 126 The High Performance Coatings spec 099600 details two types of paint for Concrete Floors for Light Traffic/Low Impact, Urethane Finish and Epoxy Finish. Please clarify where these two paint types should be installed. Answer: Provide Epoxy Finish. See this Addendum No. 3.
CDWM 30 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 127 Specification Section 43 21 15 paragraph 3.4D states that the refurbished pump will not be accepted unless the post-refurbishment readings and functionality meet the pre-refurbishment readings and functionality as a minimum. Our concern is that the refurbished pumps may not meet existing baseline hydraulic performance or vibration signature data points when compared to a pump that has settled in over the past 6o +/- years. Given there are numerous modifications relative to the pump electrification, including structural, it is plausible that the pump may not meet some of the baseline data points. For example, will the pump be accepted if 3 of 4 pump flows have been achieved? We request that the specification be clarified to state if post refurbishment readings do not meet pre-refurbishment results, but they do meet HI standards for the pump characteristics listed in section 43 21 15 1.3C, the refurbished pumps will be accepted. Answer: The intent of this Specification item is to require that the post-refurbishment conditions are not lesser than the pre-refurbishment conditions. If the post-refurbished readings are not the same, or better, than the pre-refurbished readings, the pump will not be accepted. Question No. 128 Specification section 43 21 15 paragraphs 3.6 & 3.7 discuss additional work that may be performed if authorized by the Commissioner. The contract states these additional services are to be paid for under an allowance but there is no mention of additional time. If Additional Refurbishment is requested by the Commissioner, will there also be a time extension granted for the work? Answer: This will be coordinated during Construction if it affects the Critical Path. Question No. 129 Specification section 43 21 15 paragraph 1.4(B)(4) states to submit “Motor Shop Test Procedures” and paragraph 3.2(C)(5) states to provide “balancing and testing procedures”. We can find no requirement to perform any shop testing of the pump after refurbishment. Please confirm what shop tests will be required. Answer: Performance testing at factory is not required. All other performance testing at Central Park Pumping Station to be performed per Section 43 21 15, 3.4.C. Question No. 130 Specification section 43 21 15 paragraph 3.2 C require written report to be submitted to Commissioner. How long should we include in the Project Schedule for Commissioner response to the report, to include formal direction to proceed with any Authorized Additional Refurbishments per 43 21 15 paragraphs 3.6 & 3.7? Answer: Assume that Report will be considered as Submittal. Question No. 131 The pump manufacturer has stated the original gaskets for the pumps contain asbestos. Please confirm if the gaskets have ever been replaced. If not, should we include asbestos abatement of gaskets in our proposal? Answer: Information about gasket replacement is not available. Per Section 43 21 15, 3.2.A provide
CDWM 31 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
abatement of asbestos and lead-based paint of Main Pump. Question No. 132 After successful completion of the 30 day continuous operational testing of a single pump conversion, and in accordance with the Department of Water Management Terms and Conditions for Construction Contracts- Article IV “Property” paragraph E “Right to Occupy Before Substantial Completion”, will the City take responsibility to operate, maintain and repair (to the extent not covered by warranty) the pump, motor and VFD? What about the ancillary systems required to run the pumps (lube oil, compressed air, scada, etc.)? Answer: Following the acceptance of the converted pump the City will operate the equipment. The Contractor must maintain and repair the equipment through the end of the Warranty period, which begins as described in Book 1 of the Contract Specifications. Question No. 133 After successful completion of the 30 day continuous operational testing of a single pump conversion, and in accordance with the Department of Water Management Terms and Conditions for Construction Contracts- Article IV “Property” paragraph E “Right to Occupy Before Substantial Completion”, will the Warranty period start after successful completion of the 30 day continuous operational testing of a pump conversion? This question would pertain to the pumps, motors, vfds, lube oil system, etc., and all ancillary systems necessary to run the pumps. Answer: See Addendum No. 1. Question No. 134 Please provide a valve list for the process mechanical system. Answer: All valve quantities and sizes are shown in the Contract Documents. Question No. 135 Please provide an instrument list for the process mechanical system. Answer: All instruments are shown in the Contract Documents. Question No. 136 Please provide technical information for the existing valves to be inspected as described in section 40 05 20 paragraph 2.14. Answer: This information is not available. Question No. 137 Please reference Contract Drawing H-23 and H-24. Please provide as-built drawings for the existing boiler flue. Contract drawings provide no exact information as to dimensions, thickness, and support system. Information requested is essential in preparation of demolition package for the project. Answer: This information is not available.
CDWM 32 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 138 Please reference Contract Drawing P-4, P-5, and P-6. Please confirm all piping for plumbing demolition is exposed and not encased in concrete. Answer: As shown on Sheets P-4, P-5, and P-6, all piping for plumbing demolition are exposed. Question No. 139 Spec section 05 51 00 F.5, Page 7 states: “…. At exposed connections, finish exposed welds to comply with NOMMA's "Voluntary Joint Finish Standards" for Type 1 welds: no evidence of a welded joint.” At least one of the approved fabricators does not finish to a Type 1 specification. Can this spec be modified to a Type 2 finish? Answer: Yes. Provide Type 2 welds. See this Addendum No. 3. Question No. 140 Are existing handrails on drawing A6, details 2 and 3 steel or wrought iron? Answer: This information is not available. Question No. 141 Since the true condition of the railing(s) on drawing A6 will not be known until they are blast cleaned, can the Owner establish an allowance item in the contract? If not, can the scope of repairs such as done for the gallery brackets be identified? Answer: No. Only minor repairs are anticipated. Question No. 142 Please provide the thickness of the new 4” kick plate for the existing handrail restoration. Answer: Provide ¼” thick kick plate. See revised Sheet A-6 in this Addendum No. 3. Question No. 143 Since the new handrail must be designed and stamped by the contractor’s engineer (note 25, Sheet S-3) can we assume the design of repairs/new kick plates/connections of the existing railing will be by the owner’s engineer? Answer: New handrails shall be designed and sealed by contractor's structural engineer per Note 25, Sheet S-3. This is not required for existing rails. Question No. 144 Can we assume the existing handrail meets current structural performance as described in Specification Section 05 52 00 B.1 for new aluminum handrails and railings? Answer: No. Do not assume existing handrails meet structural performance specified in Section 05 52 00, B.1.
CDWM 33 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 145 Will scaffold be allowed on the perimeter walkway at elevation +25.17 in the observation gallery of the Pump room? If so, what is the allowed loading in pounds per square feet? Answer: Use of scaffold is described in Section 01 50 00, 1.2.B. Allowable loads can be found on Sheet S-1. This allowable load is after the retrofit of the brackets supporting the walkway. Access must be maintained as required by City Staff. Question No. 146 Specification 01 12 16 “Construction Work Sequence & Limitations” requires the Contractor to “Demonstrate successful 30-day continuous operational testing of Pump Conversion work” prior to the next pump being taken out of service. In the event a pump does not meet existing pre-refurbishment readings and functionality, but is operating in accordance with HI standards, will the Commissioner allow the Contractor to proceed with work on the next pump so as to not delay the project? Answer: No. Question No. 147 Please reference spec section 26 05 73 paragraph 3.3 “Operating Scenarios”. Please provide the missing information. This information is critical to compiling the Preliminary Report per paragraph 1.3B and subsequent approval of all electrical distribution equipment per paragraph 1.3C. Answer: Addressed in this Addendum No. 3. Question No. 148 On sheet S-21, please provide the elevation and cross section of the existing foundation to be removed at the machine shop. Answer See revised Sheet S-71 in this Addendum No. 3. Question No. 149 Overhead Door Specifications (08-33-23)-2.3(Fabrication)-A (General). Mentions 24ga mill (aluminum) front and a 18ga steel back curtain. This is not available. Specified products cannot have 2 different metals. Please indicate single metal (aluminum or steel)? Answer: “Mill” does not imply aluminum. Question No. 150 Overhead Door Specifications (08-33-23)-1.3(Design Reqs) – A (General). Mentions a 30psf. This Windload is only available on a Steel Curtain. Please Confirm a Steel Curtain will be accepted. Answer: Provide unit capable of resisting 30 psf. Question No. 151 Overhead Door Specifications (08-33-23)-2.3(Fabrication)-F (Screen Curtain), mentions an aluminum security grille. While the plans seem to indicate a screen curtain, a screen curtain is only available in a Perforated Steel Slat. Please select an Aluminum Grille or a Steel Screen.
CDWM 34 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: Perforated steel slats is not acceptable. Provide screen curtain as specified in Section 08 33 23, 2.3.F. Question No. 152 Please provide contact information for CSX, Amanda DeCesare. Answer: Contact information for CSX, Amanda DeCesare will be shared during construction. Required CSX related information is provided in this Addendum No. 3. CSX will not communicate to potential bidders during bidding period. Question No. 153 Please provide soil analysis for special waste soils to be removed and disposed (required to obtain pricing for disposal) Answer: Refer to Information to Potential Bidders - Subsurface Soil Investigating Report (Task 2-130) dated March 2015. Question No. 154 Asbestos survey included in Asbestos Abatement specification (Section 02 82 13) directs that the contractor is responsible for asbestos containing materials not summarized in the survey – EPA regulation does not allow “visual” identification of suspect asbestos containing material. Under OSHA regulation, the Owner is required to identify, locate and quantify asbestos containing materials – Answer: The Contractor is responsible for abatement of all ACM in the defined work area(s) as shown on the drawings and reflected in the specifications. The Contractor is responsible for abatement of all similar ACM materials not specifically enumerated in the table in the specification. The Commissioner has defined the scope of work and provided the Contractor with available sampling and results or sampling defining the hazards as required by OSHA. Question No. 155 Please provide a full asbestos survey, to include ALL identified asbestos containing materials, including type, location and quantity. Answer: Refer to Information to Potential Bidders - Environmental Hazard Assessment Report (Task 2-140), dated March 2015. Bid per Contract Documents. Question No. 156 The specification for Area A: Pump Room states that “All TSI on mechanical, steam, and plumbing piping systems including all runs, fittings, elbows, tanks, risers and headers, etc. must be removed and disposed of as ACM as depicted on the demolition and environmental drawings” Can fiberglass insulation be removed and disposed as asbestos containing material, or does fiberglass need to be removed under abatement conditions (under containment or glove bagged) and disposed of as ACM? Further, this statement could be construed as contradicting previous specification which designates the contractor as responsible for removal of “materials that are not summarized here” (Asbestos Abatement Specification, Section 02 82 13, page 1, Part 1.1, Scope of work, item 3)
CDWM 35 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: All thermal system insulation (TSI) is inclusive of fiberglass and other TSI. Question No. 157 The specification for Area B: Northwest Rooms states that “All TSI on mechanical, steam, and plumbing piping systems including all runs, fittings, elbows, tanks, risers and headers, etc. must be removed and disposed of as ACM as depicted on the demolition and environmental drawings” Can fiberglass insulation be removed and disposed as asbestos containing material, or does fiberglass need to be removed under abatement conditions (under containment or glove bagged) and disposed of as ACM? Further, this statement could be construed as contradicting previous specification which designates the contractor as responsible for removal of “materials that are not summarized here” (Asbestos Abatement Specification, Section 02 82 13, page 1, Part 1.1, Scope of work, item 3) Answer: All thermal system insulation (TSI) is inclusive of fiberglass and other TSI. Question No. 158 The specification for Area C: Southeast Rooms states that “All TSI on mechanical, steam, and plumbing piping systems including all runs, fittings, elbows, tanks, risers and headers, etc. must be removed and disposed of as ACM as depicted on the demolition and environmental drawings” Can fiberglass insulation be removed and disposed as asbestos containing material, or does fiberglass need to be removed under abatement conditions (under containment or glove bagged) and disposed of as ACM? Further, this statement could be construed as contradicting previous specification which designates the contractor as responsible for removal of “materials that are not summarized here” (Asbestos Abatement Specification, Section 02 82 13, page 1, Part 1.1, Scope of work, item 3) Answer: All thermal system insulation (TSI) is inclusive of fiberglass and other TSI. Question No. 159 The specification for Area D: Boiler Room, Paint Room, Ash Hopper, Stack and Fuel Tanks states that “All TSI on mechanical, steam, and plumbing piping systems including all runs, fittings, elbows, tanks, risers and headers, etc. must be removed and disposed of as ACM as depicted on the demolition and environmental drawings” Can fiberglass insulation be removed and disposed as asbestos containing material, or does fiberglass need to be removed under abatement conditions (under containment or glove bagged) and disposed of as ACM? Further, this statement could be construed as contradicting previous specification which designates the contractor as responsible for removal of “materials that are not summarized here” (Asbestos Abatement Specification, Section 02 82 13, page 1, Part 1.1, Scope of work, item 3) Answer: All thermal system insulation (TSI) is inclusive of fiberglass and other TSI.
CDWM 36 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 160 Asbestos Abatement Specification, Section 02 82 13, page 8, item 4 under Area D, scope direction states “Each boiler gas chamber flue (boiler breeching) is insulated ACM. Abate/remove and dispose as ACM as depicted on the demolition and environmental drawings” – Please clarify; Are you directing the contractor to abate the items describe, or to remove and dispose of all of the items (in their entirety) as ACM? The above quoted statement requires clarification due to the “Abate/remove and dispose as ACM” To abate, is to remove the hazard; once abated, the boiler, gas chamber, or flue would no longer require disposal as ACM. The slash mark used in the statement generally implies a choice – Please clarify Answer: The slash mark is not a choice to abate. ACM is required to be abated and disposed of by Specification. Question No. 161 Asbestos Abatement Specification, Section 02 82 13, page 8, item 6 under Area D, scope direction states “The interior gas chamber flue (boiler breeching and chimney stack could potentially be lined with ACM. The boiler gas chamber flue (boiler breeching) and chimney stack were inaccessible at the time of the assessment and sampling. Materials not specified in this specification section or survey reports shall be assumed positive until proper assessment and sampling is conducted.” This statement is in conflict with other statements as listed above – Please clarify – Who is performing additional sampling and testing, how are we to quantify any materials if no access was/is available? Answer: The Contractor should presume the materials as positive for bidding purposes. Upon award and prior to removal/abatement of the system, the contractor must make assessment and sampling through their defined EC and report findings to the Commissioner. If the materials are confirmed ACM (Hazardous), the Contractor already has pricing included in their bid. If the materials are reported as non-ACM (non-Hazardous), pricing will be per Schedule of Prices Bid Item G-4 and the City will be due a credit for the amount of the bid provided by the Contractor for the assumed system. Question No. 162 The specification for Areas E & F: Coal Bunkers states that “All TSI on mechanical, steam, and plumbing piping systems including all runs, fittings, elbows, tanks, risers and headers, etc. must be removed and disposed of as ACM as depicted on the demolition and environmental drawings” Can fiberglass insulation be removed and disposed as asbestos containing material, or does fiberglass need to be removed under abatement conditions (under containment or glove bagged) and disposed of as ACM? Further, this statement could be construed as contradicting previous specification which designates the contractor as responsible for removal of “materials that are not summarized here” (Asbestos Abatement Specification, Section 02 82 13, page 1, Part 1.1, Scope of work, item 3) Answer: All thermal system insulation (TSI) is inclusive of fiberglass and other TSI. Question No. 163 Please provide analysis for identified lead paint listed in Lead-Based Paint – Specification section 02 83 19. Answer:
CDWM 37 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Bid per Contract Documents. Question No. 164 The Pump Room network block diagram on dwg N-3 does not match the from/to on the conduit & cable schedules. Which is correct? Answer: Sheets N-3 and E-56 together describe the interconnections between network components. The intent of Sheet N-3 is to show the functional system. The intent of Sheet E-56 is to identify the preferred physical routing based on equipment layout. Question No. 165 Solenoid valves SV-170, SV-270, SV-370, SV-470 & SV-570 shown on N-8 thru N-12 respectively are not shown on the electrical plan drawings nor shown on the instrumentation schedule shown on N-21. Are these new or existing and where are/will they be physically located on the electrical drawings? Answer: Refer to Section 40 90 50, 1.4.B. These solenoid valves are new and are not on the instrumentation schedule shown on Sheet N-21 because they are not instruments. The general location of these solenoid valves is near its respective pump based on the “Typical Seal Water Diagram” on Sheet M-6 with the exact location to be field coordinated.
Question No. 166 Emergency Stop ES-101, ES-201, ES-301, ES-401 & ES-501 shown on N-8 thru N-12 respectively are not shown on the electrical plan drawings, instrument schedule on N-21 nor is there any conduit/cable assigned to these devices in the conduit & cable schedules. Are these required? Where are they located and what conduit & cable is required for these devices? Answer: Refer to Section 40 90 50, 1.4.B. Emergency stop buttons are not on the instrumentation schedule shown on Sheet N-21 because they are not instruments. Cable and conduit for the E-Stop buttons is shown on Sheet E-53. The E-Stop for each pump is at its respective pump control panel P1CP, P2CP, P3CP, P4CP and P5CP as shown on Sheet E-37. Question No. 167 AIT-901, AIT-902 & AIT-903 shown on N-9 are not shown on the electrical plans drawings or instrument schedule on N-21. What are these? Where are they located and are they new or existing? Answer: Addressed in this Addendum No. 3. Question No. 168 None of the pump and motor temperature and vibration I/O shown on N-8 thru N-12 have any conduit or cable assigned to them in the conduit and cable schedules. What are the conduit & cable requirements for these devices? Answer: Addressed in this Addendum No. 3.
CDWM 38 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 169 Please advise normal pump suction pressure at each pump. Are there any special limitations and/or time constraints that will be imposed for replacement of Pumps 1 & 2 suction valves? Answer: The information about pump suction pressure is not available. For limitations and constraints refer to Book 2 INSTRUCTIONS AND EXECUTION DOCUMENTS, Proposal Pages and Section 01 12 16, 1.10.
Question No. 170 Please make Worthington & DeLaval Pump I,O&M Manuals and any service documentation/history available for review prior to bid. Answer: This information is not available during bidding. Question No. 171 Please advise if any non-OEM modifications to the pump have been performed during the service life of the pump. Answer: This information is not available. Question No. 172 Please advise if pump component clearances shall match OEM requirements. If not, please advise standard to reference for refurbishment of pump. Answer: Match pump component clearances per Section 43 21 15. For pump component clearances not specified in Section 43 21 15, match with OEM requirements. Question No. 173 Please advise component weights of each Pump, Turbine, and Gear Reduction. Answer: This information about all existing pump system is not available. Refer to Information to Potential Bidders - Main Pump Info folder for additional information. Question No. 174 Please advise the type of existing coupling between the Gear Reduction and Pump. Answer: The existing coupling is to be demolished. Question No. 175 Please advise if any component disinfection is required to be performed by the contractor relative to pump removal and reinstall. Answer: Refer to Section 33 13 00 for disinfection requirements. Question No. 176 43 21 15-3, 2.1.A – Please advise if companies other than Flowserve and Xylem will be allowed to refurbish the 5 Main Pumps Answer:
CDWM 39 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Question No. 177 43 21 15-5, 3.1.E, H, & J include requirements to report stress and movements of piping when the pump is removed. 3.1.G requires restraint of piping to preclude movement eliminating the ability to measure and document movement and stress required by 3.1.E. We believe restraint should not be a requirement to allow for measurement of piping movement after pump removal. Please confirm restraint requirement detailed by 3.1.G can be omitted. Answer: Bid per Contract Documents. Question No. 178 43 21 15-14, 3.6.B indicates that additional pump refurbishments will be paid for under Contract Item G-2A. G2-A is described as ComEd optional facilities charge not specifically included in Contract Item G-1 in the Proposal Pages “Schedule of Prices”. Please confirm this the correct item number. Answer: See Addendum No. 1, Book 3 – Technical Specifications, Item No. 17. Question No. 179 43 21 15-14, 3.7.A – Please advise required type of bearing that shall be utilized as basis of pricing for Contract Item G-10. Answer: As indicated in Section 43 21 15, 3.7.A, bearing shall be thrust bearing. Question No. 180 43 21 15 – Testing requirements do not include any analysis of frequencies of the pump/gear reduction/turbine compared to the revised motor/pump assembly. Please confirm that this pre-modification testing and analysis has or will be performed by other to confirm proper operation of the system. Answer: Perform field services per Section 43 21 15, 3.4.B and testing per Section 43 21 15, 3.4.C. Question No. 181 43 21 60 – Please advise required flow rate of lube oil system and required motor voltage. Answer: Required flow rate will be based on equipment manufacturer to meet the requirements specified in Section 43 21 60, 2.2.A. As specified in Section 43 21 60 and indicated on Sheet E-51 and E-70, 208V, 3PH is available for Main Pump Oil Lubrication package system. Question No. 182 S-64 & S-65 – Demolition notes for Pumps 1 & 3 indicate that pump bearing curb/support shall be demolished. Please clarify extent of demo, i.e. does demolition include concrete supporting pump, or just the bearing support pads? Answer: For the extent of concrete demolition for Pump No. 1, refer to Sheets S-6 and S-7 and Section 2 on Sheet S-64. For the extent of concrete demolition for Pump No. 3, refer to Sheets S-6 and S-10 and Section 2 on Sheet S-65.
CDWM 40 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 183 S-81 & S-82 – Note 5 on said drawings indicates that geometry of demolished concrete at the support bases shall be matched. Please advise rebar and anchor requirements for new concrete in these areas. Answer: For rebar and anchor requirements refer to Sheets S-37 and S-39 and respective details on Sheets S-136 through S-142. Question No. 184 IMI respectfully requests time extension to bid date to incorporate responses to these questions in the bid. Thank you Answer: See Addendum No. 2. Question No.185 The drawings call for installation of lean concrete prior to demolition of coal silos – Can coal silos be demolished to elevation +32.5 at south elevation of structure and 43’ 4 ½” at north elevation of structure, prior to installation of lean concrete material? Placing lean concrete material, prior to demolition of silos will require selective demolition of portion of existing concrete cones at all 10 silos – This work will need to be done by hand. Performing the work in the manner subscribed in the drawings is neither practical nor cost effective. Answer: No. The stability of the remaining structure is critical. Bid per Contract Documents. Question No. 186 What is the point of leaving portion of concrete cone @ silos? Can the cone be removed in its entirety? Answer: The portion of the concrete cone remaining provides additional stabilization to the remaining structure. The concrete cone is not to be removed in its entirety. Question No. 187 02 82 13-1, 1.1.A.3 – The paragraph concludes stating inclusive of materials that are not summarized here. Please advise if all asbestos in the area shall be abated. Answer: This is not a global abatement Project. Abatement is limited to the areas affected by the Work. Question No. 188 40 05 10-11 - VAC priming is specified to be Flanged Ductile Iron piping. Please confirm this is accurate. Answer: Bid per Contract Documents. Question No. 189 40 05 10 – Piping schedule states SCH 50 pipe to be used for 3” and under steel pipe for soil, waste, drain, vent, and storm piping. SCH50 piping does not exist. Please advise if SCH 40 pipe is acceptable for these services. Answer:
CDWM 41 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
See this Addendum No. 3. Question No. 190 40 05 10 – BH is listed for exterior coatings on the sump pump discharge and dewatering pump discharge. The definitions for acronyms in this section does not indicate what BH stands for. Please advise. Answer: See this Addendum 3 Question No. 191 40 05 20-16, 2.12.D – Please clarify if each accumulator system shall provide 200 gallons to each of the 5 valves in the event of a power failure, for a total reserve of 1,000 gallons. Answer: Per Section 40 05 20, 2.12.D, each hydraulic accumulator system shall provide a minimum of 200 gallons of water under pressure total. Question No. 192 40 42 00 – Please clarify the extent of which the pump discharge piping shall be abated and reinsulated. 02 82 13 indicates that a fitting only shall be abated. Answer: This is not a global abatement Project. Abatement is limited to the areas affected by the Work. Question No. 193 Please provide time extension to the current bid date to allow adequate time to get accurate cost proposal together. Answer: See Addendum No. 2. Question No. 194 In the “Construction Work Sequence and Limitations” section of book 3, (section 01 12 16) page 12 under C. 3. c. (first Pump Conversion) directs removal of steam turbine for pump no. 1. On page 16, under E. 2. C. (third pump conversion) direction is to disconnect and remove existing steam turbine for pump no. 1. – Steam turbine for pump 1 has already been disconnected and removed per previous direction – I would assume that the pump 3 conversion is supposed to direct disconnect and removal of pump 3 steam turbine – Please clarify. Answer: See this Addendum No. 3. Question No. 195 Please provide soil analysis for special waste soils to be removed and disposed of (Section 02 61 00) Answer: See answer to Question No. 153. Question No. 196 Asbestos survey included in Asbestos Abatement specification (Section 02 82 13) directs that the contractor is responsible for asbestos containing materials not summarized in the survey – EPA regulation does not allow “visual” identification of suspect asbestos containing material. Under OSHA regulation, the Owner is required to identify, locate and quantify asbestos containing
CDWM 42 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
materials – OSHA 1926.1101 Answer: The Contractor is responsible for abatement of all ACM in the defined work area(s) as shown on the drawings and reflected in the specifications. The Contractor is responsible for abatement of all similar ACM materials not specifically enumerated in the table in the specification. The Commissioner has defined the scope of work and provided the Contractor with available sampling and results or sampling defining the hazards as required by OSHA. Question No. 197 Due to the magnitude, complexity, multiple phases, stages, enormous volume of drawings and specification of this project we would like to request at least a 30 day extension of the bid date from July 14. Answer: See Addendum No. 2. Question No. 198 In Specification Section 400510-10 the piping material schedule for Soil, Waste, Drain, Vent & Storm Piping is listed as “HS” for the joints. “HS” is not in the key. Is this supposed to be “HSC” or “ HSL”? Answer: See piping schedule in Section 22 10 00 for the correct piping material and fitting for sanitary waste, Waste Drain, Vent and Strom piping. Question No. 199 In Specification Section 221000-13 there is a piping material schedule for Above Ground & Below Ground Sanitary Waste, Drain, Vent & Storm Piping. In Specification Section 400510-10 there is also a piping material schedule for the same piping systems. Which one is the correct one to use? Answer: See piping schedule in Section 22 10 00 for the correct piping material and fitting for above Ground and Below Ground Sanitary Waste, Drain, Vent and Storm Piping. Question No. 200 In Specification Section 221000-13 there is a piping material schedule for the Pump Discharge Piping. In Specification Section 400510-10 there is also a piping material schedule for the same piping system. Which one is the correct one to use? Answer: There is no conflict. Pump discharge piping in Section 22 10 00-13 is for pumps related to Division 22- Plumbing. Pump discharge in Section 40 05 10-10 is for piping related to Division 40- Process Integration. Question No. 201 In Specification Section 335616-18 there is a piping material schedule for the Lube Oil Piping. In Specification Section 400510-11 there is also a piping material schedule for the same piping system. Which one is the correct one to use? Answer: There are no discrepancies between two sections.
CDWM 43 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 202 The Engineer doesn’t specify Simplex or Duplex Mode on the Redundant PLC IO which could essentially double the IO Cards and associated equipment across 12 PLC Cabinets. Which is required? Answer: The redundant plc I/O is simplex mode. Question No. 203 In Specification Section 404200-4, Item 3.2.A states that we are to insulate the “Plant Water”. Which items are considered “Plant Water” – Seal Water Piping, Process Water Piping, Hydraulic Water Piping, Vacuum Priming Water Piping? Answer: Refer to Section 40 05 10, Interior and Exposed Exterior Piping Schedule for piping systems that require insulation. Question No. 204 In Specification Section 335616-16, 2.7A Fuel Oil Piping & Specialties, it states that we are to use a double wall containment system for the piping. But in 2.11 Fuel/Lube Oil Pipes & Valves, it states that piping above and below ground is to be single wall Sch. 80 piping. Which one is the correct one to use for this project? Answer: There is no conflict. Section 33 56 16, 2.11 specifies material for the fuel carrier pipe. Question No. 205 The way that the retention system at the silos (to be demolished) and the east end, along the tracks has been designed will be very costly – The drawings require a lot of hand demolition and construction work in tight quarters, not to mention the bracing required at the east end of the silos for track retention – There is a better (easier and more cost effective) way to do all of this and get the retention that you are looking for. The GC is supposed to hire a structural engineer to verify that the planned construction does not destabilize the structures – If GC’s engineer signs off on plan revision for demolition/construction/retention procedure for this work, can an alternative method be submitted as base bid – Or should it be listed as a voluntary alternate? Answer: Bid per Contract Documents. Question No. 206 We are formally requesting a two week time extension to the bid date for this project. There are many RFI’s that have not been answered and our subcontractors and suppliers can’t get us pricing without the answers. And once we receive the answers they will need time to work up the quotes. Answer: See Addendum No. 2. Question No. 207 Drawing M-6 New Process Water diagram shows a valve tying the two 3” cold water lines together before splitting to two 3” lines that run to backflow preventers. P-21 Section 4 detail does not show this tying valve. Please advise which detail is correct. Please confirm that two backflow preventers only are required in this area, not two for process piping, and two for plumbing. Answer:
CDWM 44 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
M-6 is correct. The 2 Backflow Preventers are shown on both Sheets. See revised Sheets P-21 and P-22 in this Addendum No. 3. Question No. 208 40 05 10-11 schedule indicates that Hydraulic Water piping over 1” shall be galvanized steel. Spec 40 05 20-20 2.12.M.3 indicates type K copper. Similarly, 40 05 20-20, 2.12.M.4 indicates that air piping shall be stainless steel, while schedule indicates galvanized stee. Please advise if 40 05 10 schedule supercedes any discrepancies that may be encountered in the specification. Answer: Hydraulic Water piping over 1" is shown on Sheet M-11 and shall be per Section 40 50 10, Piping Schedule. Hydraulic piping for 1" and less than 1" pipe shall be as indicated on Section 40 50 20, 2.12.M.3. See Addendum No. 3. Piping provided as part of package system provided under Section 40 05 20, 2.12 shall be as specified in Section 40 05 20, 2.12. Question No. 209 Drawing M-36 Note #4 (same note for balance of pumps) indicates to refurbish the valve and hydraulic in accordance with Spec 40 05 20. Said specification includes provisions for testing operation of the valve and reporting. Please confirm that any repairs to the CV’s and associated hydraulic cylinder will be directed at additional cost. Answer: As indicated in note 4 on Sheet M-36, only refurbish valve operator and hydraulic cylinder. Any repairs to the Check Valves (CV’s) excluding hydraulic cylinder shall be per Section 40 05 20, 3.3 and for payment see Addendum No. 1, Book 3 Technical Specifications Item No. 16. Question No. 210 In reference to existing pumps, please advise if pump the pump to turbine coupling has been spaced to transfer pump thrust loads to the gear reduction bull gear. Answer: No. Question No. 211 Please provide time extension to the current bid date to allow adequate time to get accurate cost proposal together. Answer: See Addendum No. 2. Question No. 212 The Louver Schedule on sheet A-12, louver types 1,2,4,5 call for security grills. There is no information in the specifications regarding what is required for these security grills. Please provide more information on the louver security grills. Answer: See Section 05 50 00, 2.10, Security Grilles. Question No. 213 There is an unmarked hatched area on 1 / A-25 between Column lines 10 and 12. The area actually goes past column line 12, but there is no other column line shown to the right of column line 12. Please confirm the scope of work in this area. Answer: This is the existing Machine Shop. See Plan 2 on Sheet A-24.
CDWM 45 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 214 On Sheets A-38 & A-72, “provide gypsum over plywood finished wall” is called out at various partitions. What is the required height of the gypsum board and plywood (to the ceiling, to a certain height a.f.f., to the deck/structure above, etc.)? Answer: Both gypsum and plywood are full height. Question No. 215 On Sheets A-38, “metal stud and drywall assembly” is called out at two partitions. No details or further information (for example stud size & gauge, gypsum board type & thickness, in-wall insulation) are found in the drawings regarding this assembly. Please advise. Answer: 4-inch 18 Ga. Studs with 5/8" gypsum, both sides. See this Addendum No. 3. Question No. 216 Detail 4 on Sheet A-4 calls for newly exposed terracotta to be restored. There is no newly exposed terracotta called out on the drawings. Please provide the locations of the terracotta to be restored. Answer: It is assumed this question is related to Detail 4 on Sheet A-6. See answer to Question No. 227. Question No. 217 On Sheet A-24 along column line 7, a single door and a double door are shown to be removed. On sheet A-38, the wall at these removed doors are shown to be filled in, however no detail is given as to the composition of the wall infill/what the existing adjacent walls are composed of. Please advise. Answer: The wall infill in Room 115 shall be PFCMU, see schedule on Sheet A-12. The wall infill in Room 114 is CMU. Question No. 218 On Sheet A-35, an abandoned door opening is called out to be infilled. Please advise on what the existing adjacent wall is composed of (block & brick, concrete, etc.). Answer: The existing adjacent wall is composed of brick. Question No. 219 On Sheet A-44 and at 7/A-79, abandoned openings are called out to be infilled to match adjacent masonry, however no details are givens as to what the existing adjacent wall is composed of. Please advise. Answer: The existing adjacent wall is composed of block Question No. 220 In Spec section 335616-18 it states that the Fuel/Lube Oil Piping Joints are to be - 2” & Smaller – Butt Welded & 2-1/2” & Larger is to be Socket Welded. I believe these are reversed. Please advise.
CDWM 46 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: Yes; joint 2” and smaller to be socket welded and joints 2” and larger to be butt welded. Question No. 221 On Sheets H-36 & H-37 there are several HHW lines that are either not shown connecting to anything, or don’t show where they continue on other sheets. Please see attached drawings for clarification. Please advise on the questions listed on the drawings. (Question on H-36: Pipe between Column line 9 and 10 and north of line D – still going up/down. Question on H-37: Pipe between Column line 9 and 10 and north of line D – down not shown on +11 plan, where does this go?) Answer: Refer to hydronic piping flow diagram shown on Sheet H-48. Question No. 222 We would really like to quote this job, we feel that our product would be very successful. The problem is that for the motor portion of the spec we are not on there, I believe it is TECO, Siemens, Louis Allis, and Hyundai. Is there any chance I can come in and meet with you tomorrow or next week to discuss the possibility of being added to the spec? Both the low voltage and medium voltage portions Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Question No. 223 Please clarify if the 21CB and 10CB beams in Area A are to be removed or to remain. Drawing S-18 calls out to remain, but note 9 reads “the bracing members shown on S-46 (including 21CB and 10CB beams and new members) can be removed after the design strength is attained for stage 2 concrete slab at el +33.00”. Drawing S-46 note 1 reads “the bracing members (including 21CB beams, 10CB beams, LL6x4 bracing angles, W8X48 and MC18x58 beams) can be removed after the design strength is attained for stage 2 concrete slab at EL +33.00”. Drawing S-88 calls out the 21CB beam to remain, but refers to note 10 for the 10CB beam which reads “the bracing members shown on S-46 are to be removed after the design strength is attained for stage 2 concrete slab at EL +33.00”. Answer: This question relates to Area "B" and not Area "A". Please follow Note 9 on Sheet S-18 and Note 1 on Sheet S-46. Question No. 224 Please specify if the two 10 CB 21 beams between reference lines 4A and 5 in Area A as shown on drawing S-18 are to be removed after the stage 2 slab is in place or to be reconnected to the wall. Answer: This question relates to Area "B" and not Area "A". The two 10CB21 beams in question are to be removed after stage 2 slab attains design strength. Question No. 225 Specification 260512-3.2-F states that the temporary electric service including monthly ComEd charges are to be included in the project lump sum cost. Please provide ComEd’s consumption charges, rates, etc. Answer:
CDWM 47 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
It is intended that such pricing and scheduling will be coordinated directly between the Contractor and the Utility (ComEd). Question No. 226 What is the height of the wire mesh partition doors in shops B104 and B109-111? Answer: See Sheet A-9. Question No. 227 Detail 4 on sheet A-6 shows newly exposed terracotta restoration. Are there specific location where this is expected? Answer: The intent is to restore Terra Cotta that was covered up by the Machine Shop but will now be exposed to view. The detail should match the adjacent. Question No. 228 Detail 4 on sheet A-6 shows newly exposed terracotta restoration, how will this item be paid (i.e. lump sum, unit price)? If lump sum please provide specific locations where this is to occur or a basis of bid quantity? Answer: This is to be included as Bid Item No. G-1, Lump Sum Project Work. See answer to Question No. 227. Question No. 229 Will the repairs shown on A-93, A-94, and A-95 be paid for in Contract Items G-5 and G-6? Answer: Yes, as described. Question No. 230 Will the repairs shown on A-96 be paid for in Contract Items G-8 and G-9? Answer: Yes, as described. Question No. 231 To provide more competitive pricing, can the AISC Quality Certification for Fabricator for Steel Building Structures (STD) requirement be waived. Answer: No. Question No. 232 To provide more competitive pricing, can the AISC Quality Certification for Certified Steel Erector (CSE) requirement be waived. Answer: No. Question No. 233 Refer to 31 20 00 - Does the 25% of surface area to be removed and replaced 12" deep include the areas of the proposed building footprint in areas C, E And F? If so, is the 25% in addition to the 1,440 cy described on Sht C-10 - Note 3?
CDWM 48 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: Yes, the Remediation of Subgrade Soils is in addition to the 1,440 CY described on Sheet C-10. Question No. 234 Refer to EDI Report - Task 2-130, Page 1 - 1st finding and recommendation: Is it the contractors responsidbility to determine the quantities of soils to be disposed of at SubTitle D landfill and CCDD disposal site? Answer: Yes. Question No. 235 Section 31 20 00 - 2.1B - Where can Select Borrow be used as fill or backfill? Are the on-site lean clays suitable for use as Select Borrow? Answer: Per Section 31 20 00, 2.1B, Clay or Lean Clay soils are not acceptable. Question No. 236 On drawing S-52 between columns 12 & 13 there are symbols for 8 micropiles under the new concrete wall. These piles do not show any callout for quantity or size. Are these micropiles existing? Answer: On Sheet S-52, there is reference to a blow-up partial plan, 1/S-112. On Plan 1 on Sheet S-112, there is a section cut labeled 1/S-113. The micropiles are called out on the Section 1 on Sheet S-113. Note that revised Sheet S-113 was issued under Addendum No. 1. Question No. 237 Contract Insurance Requirement, Section I.A.2, Commercial General Liability Insurance requires a $25,000,000 per occurrence limit but doesn't provide an aggregate limit. It's an insurance industry standard to place an aggregate limit on insurance policies, an unaggregated insurance policy may not be commercially available. Please confirm a $25,000,000 aggregate limit will apply. Answer: Bid per Contract Documents. Question No. 238 Contract Insurance Requirement, Section I.A.2, Subcontractors Commercial General Liability Insurance requires a $2,000,000 per occurrence limit but doesn't provide an aggregate limit. It's an insurance industry standard to place an aggregate limit on insurance policies, an unaggregated insurance policy may not be commercially available. Please confirm a $2,000,000 aggregate limit will apply to the Subcontractor requirements. Answer: Bid per Contract Documents. Question No. 239 Contract Insurance Requirement, Section I.A.3, Owner’s and Contractor’s Protective Liability Insurance requires a $2,000,000 per occurrence limit but doesn't provide an aggregate limit. It's an insurance industry standard to place an aggregate limit on insurance policies, an unaggregated insurance policy may not be commercially available. Please confirm a $2,000,000 aggregate limit will apply. Answer:
CDWM 49 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Bid per Contract Documents. Question No. 240 Contract Insurance Requirement, Section I.A.10, Contractors Pollution Liability Insurance requires a $1,000,000 per occurrence limit but doesn't provide an aggregate limit. It's an insurance industry standard to place an aggregate limit on insurance policies, an unaggregated insurance policy may not be commercially available. Please confirm a $1,000,000 aggregate limit will apply. Answer: Bid per Contract Documents. Question No. 241 Contractor requests that the 2nd to last paragraph in the Contract Insurance Requirement section is removed and replaced with the following: The Contractor must require all subcontractors to provide the insurance required herein, or Contractor may provide the coverages for subcontractors. All subcontractors are subject to the same insurance requirements of Contractor unless otherwise specified in this Contract. Contractor must that ensure the City is an additional insured on Endorsement CG 2010 of the insurance required from subcontractors. Contractor shall, at his own expense, procure and maintain insurance of the type and in the limits as set forth in the contract. Contractor shall require subcontractors to procure and maintain types and amounts of insurance based on the subcontractor’s scope of work and in accordance with Contractor’s usual business practices. Answer: Bid per Contract Documents. Question No. 242 Specification 31200.3.4.P states: "Excavation for utilities and structures may require the removal of boulders and rocks of all sizes, cemented slag, existing abandoned buried structures and utilities, or other obstructions for the construction of new structures and utilities, whether or not said abandoned buried structures and utilities are shown or specified, at no additional cost to the City." Please confirm that the differing site conditions clause stated in Book 1, General Conditions, Part III.C.4. takes precedence. Answer: See Book 1 Part 1 F. Question No. 243 Book 1 V.F (page 22) requires record shop drawings on Mylar or such other medium as directed by the Commissioner. Can transbond material be used instead of Mylars? Answer: Intent is for reproducible document. Question No. 244 The following door numbers shown on the door schedule are not designated in the hardware specification 08 71 00 "hardware schedule" as receiving a hardware set. Please clarify the required hardware sets for these door numbers: #100-2, #B106-1, #B1071, #109-2, #112B-2, #112B-3, #116-1, #201-2, #B110-2, #B115-1, #124-4, #125-1, #208-4 and #224-1. Answer: See this Addendum No. 3 for revised schedule.
CDWM 50 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 245 The hardware schedule beginning on page 17 of the specification lists the following door numbers and the corresponding door hardware set, however, the door numbers are not shown on the door schedule on sheet A-9 of the drawings. Please clarify if these door numbers should be added to the door schedule and if so, please provide applicable information on door sizes and types. #117-1, #B106-9, #134-1, #210-2, #B102-3, #B112-1, #109-1 and #125-2. Answer: See this Addendum No. 3 for revised schedule. Question No. 246 Drawing S-45 shows Stairwell D, but there are no structural details for this staircase. Please provide structural drawings. Answer: As indicated in Note 8 on Sheet S-45, framing of Stair Landing at floor level shall be part of stair design. Fabricator’s licensed structural designer to design stair framing and submit to the Commissioner for approval (typical). See architectural Details 1, 2, and 3 on Sheet A-79 for geometry details on Stair D. Question No. 247 Drawing H-36, note 12 makes reference to “ engine manufacturer’s ancillary containment skids”. Where are these skids specified? Who provides them? Answer: The engine manufacturer’s ancillary containment skids are to be provided by the engine manufacturer. They are called out on drawing Sheet E-82. Question No. 248 Who provides the final fuel fill for the permanent generators? Answer: See Section 01 12 16, 1.10.J.8.b. Question No. 249 We respectfully request your consideration on the enclosed proposal for product substitution. Attached is the required product information including product description, specifications, drawings, performance and test data needed for your review. We appreciate your attention to our proposal and hope that you deem us an equal for this and future projects. I am attaching detail 1/A-8 of the basis of design, as I don't see their serrated version online. We are offering a corrugated aluminum insert, in our standard aluminum hinge mat. Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Question No. 250 Sheet S-86; Current crane girder is shown as an S-20 size. We need to match the existing size for replacement. Can the owner provide more detail such as the weight per foot and/or web and flange dimensions? Answer: The crane girder is S20x75 as shown on Sheet S-86.
CDWM 51 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 251 Spec section 40 94 43 – 2.1-B-2 and 2.3-A list the Allen Bradley 1756-PA72 which is not a redundant power supply, but in 2.3.B, it states that all power supplies are to be redundant. Please clarify the correct part number and verify if all PLC supplies are to be redundant Answer: See answer to Question No. 68. Question No. 252 Spec Section 40 94 43 – 2.1-B-10 lists the Ethernet adapter for messaging between PLC’s and I/O chassis but does not mention communications to SCADA. Is it the intent to use one (1) 1756-EN2TR for both PLC to PLC, I/O, and SCADA, or is it the intent to use two (2) modules for this. Please clarify. Answer: Per Section 40 94 43, 2.1.B.10 the adapters are for redundant communication between PLC and I/Os only. Refer to Section 40 94 13 and drawing N5 for PLC and SCADA Communications. Question No. 253 We would appreciate at least a 3 week extension of the bid date. This is a very complex project with a lot of pieces to tie together. Answer: See Addendum No. 2. Question No. 254 Rooms 120 and 134 were not labeled on the Drawing (A-42). Please clarify. Answer: Rooms 120 and 134 do not exist. See this Addendum No. 3. Question No. 255 I was inquiring about getting these manufacturers as approved equals on this particular job for the following specification sections: Air Outlets and Inlets: Section 233700- Price Industries as approved equal for Grilles, Registers, and Diffusers Ductwork Accessories: Section 233300- Greenheck as approved equal for Fire Dampers Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION. Question No. 256 Specification section 12 35 00 references 3 stainless steel kitchen cabinet manufactures. Only one of the listed manufactures produces stainless steel cabinets. Are there any other manufactures that are acceptable? Answer: Substitutions are addressed in Book 1 – TERMS AND CONDITIONS FOR CONSTRUCTION.
CDWM 52 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 257 Amanda DeCesare with CSX, informed us today that all questions related to work around the CSX railroad tracks would be filtered through Eli Petrova with RME. We still have not received a response to any of the questions regarding work on CSX property. Please advise if RME will be responding to contractor's questions prior to bid day. Answer: Required CSX related information is provided in this Addendum No. 3. See answer to Question No. 152. Question No. 258 Can an allowance be added to the bid to cover costs that may be incurred by the contractor form CSX? Including permits, safety training inspections, track closures, flaggers, ect. Answer: No. This is to be included as Bid Item No. G-1, Lump Sum Project Work. Question No. 259 Specification section 40 05 20, paragraph 3.3.H, states additional valve refurbishment will be paid for under contract Item G-2B. Bid item G-2B relates to the CSX Railroad Earth retention. Please advise. Answer: See Addendum No. 1, Technical Specifications Item No. 16. Question No. 260 Door schedule that calls for 3 hour rated glass, door size is too big. 3 hour need be 100 sq inches. Should a smaller window be used in the door or use 90 minute? Answer: See revised Sheet A-9 in this Addendum No. 3. Question No. 261 Please provide mounting detail for all fence that goes on top of concrete wall and on top of building. Answer: For fence at the roof of Area B, please see note 7 and plan 2 on S-46 and details 3 & 4/S-91. The fence in Area E & F will be mounted on the 16" curb shown on 1 & 2/S-129 and 1/S-134 along the North property line. The fence post base detail will be similar to 4/S-91. See Arch drawings for fence elevations. The fence post size and spacing (max 10') will be as required by the fence manufacturer. Question No. 262 Sheet C-40 shows a detail for a chain link slide gate but on sheet C-6 (where the chain link fence is shown) no indication is given that any slide gates are to be installed? Are there any chain link slide gates on this project? Answer: See revised Sheet C-6 in this Addendum No. 3.
CDWM 53 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 263 See sheet A-52, there are several areas like this where two levels of fence meet, the way it is drawn seems to indicate a 24’ high continuous fence panel is that correct? Is it acceptable to stop and start the two levels of fence without connecting them vertically? Answer: Yes. No. Question No. 264 Section 31 23 15 – 1.2D – Please provide a definition of Select Fill. Are the on-site lean clays suitable for use as Select Fill? Answer: No. Question No. 265 Section 31 23 15 – 3.4 – Please provide a definition of Common Fill. Are the on-site lean clays suitable for use as Common Fill? Answer: No. Question No. 266 Specification section 01 12 16 1.10.B.5 states the bridge crane may be utilized and will be operated by CDWM staff. Will there be any costs associated with the use of the crane? Answer: See answer to Question No. 26. Question No. 267 Specification section 43 21 15 2.3.A references the new pump motors. Is it the intent that the Main Pump Refurbishers provide the motors as part of their scope of work? Answer: No. Question No. 268 Specification section 43 21 15 2.4.A references the new variable frequency moto controllers. Is it the intent that the Main Pump Refurbishers provide the variable frequency motor controllers as part of their scope of work? Answer: No. Question No. 269 S-129 shows 1,200psi lean concrete fill in the coal bins. This concrete cannot be pumped due to the lack of cement content. Question is: what is the weight per cubic foot of this lean concrete. The material weight schedule only has normal and light weight concrete. If we keep the weight within spec can we increase the strength so it can be pumped? Answer: There is no requirement that the lean concrete is installed by pumping. Bid per Contract Documents.
CDWM 54 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Question No. 270 Based on 26 18 39 section 2.7.H.6.d, the motor/VFD test is to be performed at a minimum of 60% full speed. Is 60% of full speed the minimum speed the motors will see? If not, please specify. Answer: Motor operation at speeds lower than 60% of full speed is not anticipated. Question No. 271 Spec section 26 33 60 2.2.C for the battery installation calls out for Nema 1 enclosure around the batteries. This is unusual for the City use compared to their other installations. The batteries are in a special ventilated room and having an enclosure around the batteries holds back the gases from properly venting. I recommend an open rack for visibility of liquid levels in cells and ease of maintenance. Answer: Bid per Contract Documents. Question No. 272 Specification paragraph 26 19 00.2.9.C specifies Bearing Vibration Detectors for the MV Motors. There are (4) Motor Vibration (VE) outputs from each MV Motor as shown on the Pump P&ID Drawings N-8 thru N-12, and described in the on the I/O list on drawings N-24 & N-25. Please verify that these (4) outputs are from the Bearing Vibration Detectors. Answer: Verified. Question No. 273 Specification paragraph 40 91 00.2.10 specifies Condition Monitoring System for Shaft Speed and Vibration. There is (1) Motor Shaft Speed (SE) output from each MV Motor shown on the Pump P&ID Drawings N-8 thru N-12, and described in the on the I/O list on drawings N-24 & N-25. Please verify that this (1) output is from the Shaft Speed Detector. Answer: Verified. Question No. 274 Specification paragraph 43 21 15.2.5 refers to “Optical Sensors” meeting the requirements of section 40 91 00. We do not see an “Optical Sensor” described in section 40 91 00. What output on the P&ID drawings is the Optical Sensor providing? Answer: Motor Shaft Speed. See answer to Question No.277. Question No. 275 For the barrier beams spec section 32 32 00 asks for a mechanically operated barrier beam at west entrance along Fillmore Ave, basis of design is TCRB12 by TyMetal. TyMetal informs me that they cannot provide this barrier beam controlled by card readers – “The operator for the crash barrier arms is not UL325 certified. The only exception that UL allows is if the security of the site comes before safety, as in class IV operation in which a guard operates the arm with constant pressure. They cannot use card readers or any other device that is not controlled by a guard with constant pressure to operate the system.” Please advise if this barrier beam should be changed to manual operation or if it can be controlled with constant pressure from a guard?
CDWM 55 ADDENDUM NO. 3 DWM PROJECT NO. 13-102 SPECIFICATION NO. 146286
Answer: The barrier beam has to be operated by card reader as specified in Section 32 32 00. Question No. 276 Can you please confirm that the balance of the barrier beams (1 @ west Fillmore entrance, 1 @ far east Fillmore entrance, and 2 @ Central Park) are all to be manually controlled. Answer: Yes. Question No. 277 Confirm the sensor type to be used for Motor Shaft Speed specified in 40 91 00 2.10 A 2. The 1443 sensors (specified) are used for monitoring vibration only. The 1442 Eddy Current sensor can be used to measure shaft speed. Answer: See Addendum No.3. Question No. 278 Are the allowance items to be included when calculated the MBE/WBE percentages? Allowance items G-2A and G-2B total $5,055,000 and do not offer MBE/WBE participation. Answer: No, not unless the firm being utilized for credit is certified in that area of specialty and can provide the service.
CDWM 1 Addendum No. 3 DWM PROJECT NO.: 13-102 Attachment A SPECIFICATION NO.: 146286
Addendum No. 3 Attachment A
Central Park Pumping Station Electrification Project
DWM PROJECT NO.: 13-102 SPECIFICATION NO.: 146286
Excerpt from CSX’s Public Project Information manual. Full manual is available at following link: https://www.csx.com/index.cfm/library/files/about-us/property/public-project-manual/
Public Project
InformationFor Construction and
Improvement Projects That May Involve the Railroad
Prepared by the Public Projects Group CSX Transportation Inc.
Jacksonville, Florida (last revised April 8, 2015
CSX Corporation PAGE 2 Revised 09-09-2014
CSXT Public Project Policy InformationTable of Contents
Topic Page Revised
Information Covered in this Manual 3 9-09-14CSXT Public Projects Staff and Territory Map 4 4-14-15Additional CSXT Resources and Contacts 5 4-14-15Definitions 6 9-09-14Requirements for Preliminary Engineering Review 8 9-09-14Payment of CSXT’s Cost and Expense 9 9-09-14Insurance Requirements for Public Projects 10 9-09-14Entry onto CSXT Property 12 9-09-14Construction Monitoring Requirements 13 9-09-14Railroad Flagging for Activities On or Near CSXT Property and Tracks 14 9-09-14Highway-Rail Grade Crossing Surface Maintenance and Replacement 16 9-09-14Alterations to Highway-Rail Grade Crossing Warning Devices 17 9-09-14Overhead and Undergrade Bridge Projects 18 9-09-14Parallel Road Construction 19 9-09-14Painting and Cleaning CSXT Bridges to Improve Appearance 20 9-09-14Cleaning and Painting of Bridges over CSXT 21 9-09-14Public Road Crossing Openings and Closures 22 9-09-14Bicycle/Pedestrian Pathways and Multi-Use Trails 24 9-09-14Quiet Zone Proposals 25 9-09-14
Appendix
Standard Preliminary Engineering Agreement 27 05-09-11Standard Construction Agreement 32 10-01-99Temporary Right of Entry Agreement 43 09-09-14ROE and Maintenance Agreement for Painting of CSXT Bridges (Aesthetic) 49 09-09-14Special Provisions for Construction near CSXT Property 62 09-14-07Overhead Bridge Criteria 66 10-01-99Criteria for Ballast Deck Railroad Bridges 72 05-09-11Construction Submission Criteria 78 04-14-15Drainage Criteria 87 09-09-14
Additional information can be obtained by contacting the following:
n American Railway Engineering and Maintenance of Way Association,(301) 459-3200, or www.arema.org
n U.S. Department of Transportation, Manual of Uniform Traffic Control Devices, http://mutcd.fhwa.dot.gov/
CSX Corporation PAGE 3 Revised 09-09-2014
Information Covered in This ManualThis information is intended to assist communities and other project sponsors to plan and implement construction and improvement projects that may involve the CSXT rail property. Examples of such projects include:
n Highway-Rail Grade Crossings: Closure, removal, installation and alterations of public highway-rail grade crossings. CSX’s Property Services department manages private crossings.
n Bridges Over CSXT: Construction, reconstruction, rehabilitation, repair, removal, and maintenance of bridges over the railroad by outside parties.
n Bridges Carrying CSXT: Construction, reconstruction, rehabilitation, repair, removal, and maintenance of bridges carrying CSXT over highways and other public properties initiated by outside parties.
n Parallel Roads/Facilities: Construction, reconstruction, modification, removal, and maintenance of parallel roads or other public facilities affecting CSXT property or operations.
n U.S. Army Corps of Engineers Projects: Any project undertaken by the Corps of Engineers that involves CSXT property or operations.
n Entry Onto CSXT Property: Temporary rights of entry onto CSXT property, easements, utility installation and bridge inspections.
n Other Projects Involving CSXT Rail Corridors: Publicly sponsored projects involving or altering CSXT facilities or its property. These projects may be on, above, adjacent to, or otherwise have the potential to impact CSXT property.
Important notes:
The information herein is intended to be a tool only and all statements in this manual are intended to be for broad use. This manual cannot be taken as authority to construct. Specific projects will be subject to analysis of all factors leading to formal agreements between all parties. The purpose of review by CSXT is solely to ensure compliance with the minimum standards of CSXT, and not for any other purpose.
The guidelines and requirements herein are provided for reference only and are subject to revision without notice. All new projects shall be designed in accordance with the most current policies, requirements, and standards of CSXT.
Any items affecting railroad property not covered in this manual shall be subject to CSXT’s prior review and approval.
The safety of CSXT employees and the general public is of paramount importance to CSXT.
CSX Corporation PAGE 8 Revised 09-09-2014
Requirements for Preliminary Engineering Review
Key Pointsn Starting CSXT Preliminary Engineering (PE) early by providing conceptual plans lowers project costs and shortens the time required for CSXT review and approvaln Using standard agreements lowers costs and saves timen If the proposal requires an easement on CSXT property, the project sponsor should contact CSXT Real Property when beginning PE.n If the proposal requires a utility encroachment, the project sponsor should contact CSXT Property Services when beginning PE.n PE typically costs $8,000 to $25,000n CSXT PE Review will not begin until the PE Agreement is fully executed and PE funds are received.
OverviewAny project proposals that may affect or be near the CSXT right-of-way must be evaluated by CSXT. To initiate a construction or improvement project, a PE agreement is required to identify the project sponsor, the scope, define the tasks to be accomplished, and specify the payment required. Once the plans for the project are approved by CSXT, a construction agreement will be developed.
PurposeThe purpose of the PE is to identify issues related to safety, engineering, customer service, operations, legal and regulatory matters, expense, risk and other considerations specific to any proposed project. CSXT review of plans is only to determine that the plans, and improvements constructed in accordance with the plans, satisfy CSXT’s requirements. Plans should be submitted early in project development to ensure that CSXT requirements can be incorporated.
Process Steps To Be Takenn Notify CSXT Public Projects Group of the project by providing location information and conceptual plans.n Provide CSXT authorization to incur preliminary engineering costs.n Review and complete a standard PE agreement and provide payment for expenses as specified in the agreement.n Provide project information; attend meetings (as needed), review site with CSXT or GEC personnel.n Submit initial plans to CSXT or designated GEC for review. n Respond to CSXT or designated GEC comments and adjust design if necessary.n Submit final design for CSXT or designated GEC review.n CSXT will perform final review to ensure compliance with railroad requirements.n CSXT will estimate the cost of the work to be done by CSXT, including flagging.n If CSXT takes no exceptions to the design plans (or once all CSXT concerns have been addressed), CSXT will prepare a standard construction agreement for execution.
Costs and Expenses These matters are covered in more detail in the section that follows (“Payment of CSXT’s Costs and Expenses”). For the reasons described in that section, CSXT requires advance payment for its costs and expenses of reviewing and handling the PE. All expenses of the party seeking the review will be borne by that party, including expenses for CSXT employees or GEC personnel attending meetings, reviewing plans, preparing correspondence and other activities to support the review of the project.
TimingIt is in the interest of all parties to complete the PE review before commitments are made or construction steps begin. CSXT will work to be responsive, with timing depending upon the complexity of the project. CSXT and its GEC will work with the project sponsor to schedule PE and construction to meet project schedule objectives whenever possible, considering available resources.
Standard DocumentsCSXT executes hundreds of agreements each year for preliminary engineering and construction of projects. CSXT has developed standard agreements which can be executed by CSXT without additional legal review. Non-standard agreements or modifications to the CSXT standard agreement terms will require additional legal review and may increase project duration and/or cost. Sample standard agreement documents are available in the Appendix.
CSX Corporation PAGE 9 Revised 09-09-2014
Payment of CSXT’s Costs and Expenses
Key Points and Proceduresn Preliminary Engineering (PE) costs are paid in advance.n CSXT construction expenses will be estimated during PE and the estimate will be incorporated into the construction agreement. Advance payment is required to cover these expenses prior to the start of project construction. n If CSXT anticipates that actual expenses will exceed the advance payment, additional payment will be required. Project work may be stopped until additional payment is received.n If CSXT’s actual expenses are less than the sum of any deposits the difference will be refunded after final cost accounting.n All funding sources must be identified up front, and any time funding sources change, CSXT must be immediately informed.
Overview The types of projects being addressed in this manual usually do not directly benefit and, in some cases, create risk to, and hurdles for, CSXT’s core business of providing transportation service vital to its customers and the American economy. For these reasons, CSXT seeks payment for its costs and expenses incurred in connection with project review or construction.
Examples of Costs and ExpensesAgency shall reimburse CSXT for all costs and expenses incurred by CSXT in connection with the Project, including, without limitation:
n All out of pocket expensesn Travel and lodging expensesn Telephone, facsimile, and mailing expensesn Costs for equipment, tools, materials and suppliesn Sums paid to CSXT’s consultants and subcontractorsn CSXT labor in connection with the Project (included but not limited to flagging), together with CSXT labor overhead percentages established by CSXT pursuant to applicable lawn For estimating purposes only, typical flagging costs are $1,300 per day.
CSX Corporation PAGE 10 Revised 09-09-2014
Insurance Requirements for Public Projects I. Insurance Policies: Agency and Contractor, if and to the extent that either is performing work on or about CSXT’s property, shall procure and maintain the following insurance policies:
1. Commercial General Liability (CGL) coverage at their sole cost and expense with limits of not less than $5,000,000 in combined single limits for bodily injury and/or property damage per occurrence, and such policies shall name CSXT as an additional insured.
2. Statutory Worker’s Compensation and Employers Liability Insurance with limits of not less than $1,000,000, which insurance must contain a waiver of subrogation against CSXT and its affiliates [if permitted by state law].
3. Commercial Automobile Liability insurance with limits of not less than $1,000,000 combined single limit for bodily injury and/or property damage per occurrence, and such policies shall name CSXT as an additional insured.
4. Railroad Protective Liability (RPL) insurance with limits of not less than $5,000,000 combined single limit for bodily injury and/or property damage per occurrence and an aggregate annual limit of $10,000,000, which insurance shall satisfy the following additional requirements:
a. The Railroad Protective Liability Insurance Policy must be on the ISO/RIMA Form of Railroad Protective Insurance - Insurance Services Office (ISO) Form CG 00 35.
b. CSX Transportation must be the named insured on the Railroad Protective Liability Insurance Policy. The named insured’s address should be listed as:
CSX Transportation, Inc. 500 Water Street, C-907 Jacksonville, FL 32202
c. The name and address of the Contractor and of the Project Sponsor/Involved Governmental Agency must be shown on the Declarations page.
d. A description of operations and location must appear on the Declarations page and must match the Project description.
e. Terrorism Risk Insurance Act (TRIA) coverage must be included.
f. Authorized endorsements must include:
(i). Pollution Exclusion Amendment - CG 28 31, unless using form CG 00 35 version 96 and later
g. Authorized endorsements may include:
(i). Broad Form Nuclear Exclusion - IL 00 21
(ii). Notice of Non-renewal or cancellation
(iii). Required State Cancellation Endorsement
(iv). Quick Reference or Index - CL/IL 240
CSX Corporation PAGE 11 Revised 09-09-2014
h. Authorized endorsements may not include:
(i). A Pollution Exclusion Endorsement except CG 28 31
(ii). An Endorsement that excludes TRIA coverage
(iii). An Endorsement that limits or excludes Professional Liability coverage
(iv). A Non-Cumulation of Liability or Pyramiding of Limits Endorsement
(v). A Known Injury Endorsement
(vi). A Sole Agent Endorsement
(vii). A Punitive or Exemplary Damages Exclusion
(viii). A “Common Policy Conditions” Endorsement
(ix). Policies that contain any type of deductible
(x). Any endorsement that is not named in Section 4 (f) or (g) above that CSXT deems unacceptable
5. All insurance companies must be A. M. Best rated A- and Class VII or better
6. Such additional or different insurance as CSXT may require
II. Additional Terms
1. Contractor must submit the complete Railroad Protective Liability policy, Certificates of Insurance and all notices and correspondence regarding the insurance policies in an electronic format to:
Neither Agency nor Contractor may begin work on or about CSXT property until written approval of the required insurance has been received from CSXT or CSXT’s Insurance Compliance vendor, Ebix.
CSX Corporation PAGE 12 Revised 09-09-2014
Entry onto CSXT Property
Key Points Written permission is required for all parties entering CSXT property.
n Construction Agreements authorize entry onto CSXT property.n Temporary right-of-entry agreements can also be used for limited purposes. n CSXT Property Services handles temporary rights of entry for non-construction activities. n CSXT Public Projects handles temporary rights of entry for construction activities.n All parties must adhere to CSXT Safety procedures. n Appropriate insurance is required.
OverviewTo maintain efficient customer service and to ensure the safety of CSX employees and of those parties requesting access to CSXT property, CSXT requires all parties accessing its right-of-way for investigative activities or for the performance of construction work to have a written agreement with CSXT fully detailing each party’s responsibilities. Activities by others with the potential to affect CSXT’s property, operations, and or personnel without actually entering CSXT property must also be reviewed with CSXT and appropriate arrangements and agreements completed.
The process by which an appropriate agreement covering entry and/or the other necessary conditions or requirements can be developed and implemented is typically dependent upon the scope of the activities proposed by an outside party or agency. Although the type of agreement may vary, most agreements include insurance and liability provisions, work procedures and conditions and reimbursement provisions relating to payment to CSXT for costs it may incur in relation to the entry or work. The following summarizes the various types of CSXT agreements and contracts most frequently utilized to accommodate the requested entry and the proposed work activities.
Entry for Construction Work via CSXT Public ProjectsEntry for construction work (not exclusively associated with utility work) will require a Construction Agreement or a Temporary Right-of-Entry Agreement, as determined by the magnitude of potential impacts to CSXT.
A Construction Agreement will be required for construction work that could impact CSXT facilities or operation, such as construction or rehabilitation of a bridge over CSXT, roadway construction or other highway improvements, or grading and/or drainage work.
Construction work that will not impact CSXT facilities or operation may be handled by a Temporary Right-of-Entry Agreement, as determined by CSXT Public Projects.
Entry for Non-Construction Work via CSXT Property ServicesA Temporary Right-of-Entry agreement is utilized by CSXT primarily in situations where outside parties or agencies desire to undertake investigative work such as performing survey work, taking borings, performing bridge inspections or undertaking other activities requiring only access to CSXT property and not construction work activities. Different agreements are used for temporary private crossings.
Applications for Temporary Right-of-Entry agreements for investigative and non-construction work activities (including movement of off-highway or oversized loads at grade crossings) within CSXT’s right-of-way can be obtained by contacting CSXT Property Services department online at www.csx.com. Click on “Community – Property and Projects,” and then click on “Learn more” under “Utility installations and Rights of Entry.”
Entry For Other Purposes via CSXT Property ServicesCSXT may use other forms of agreements covering entry by outside parties or agencies depending on work scope or other factors. The process to obtain right of entry for these purposes as listed below may also be initiated through CSXT’s Property Services department. Information also is available by visiting www.csx.com
n Environmental Right-of-Entryn Utility Permit/License Agreement for pipeline and wire line construction – both for specifications and applications n Land Lease applications n Movement of oversized loads across CSXT tracks at private or public highway-rail grade crossings n Movement of off highway construction equipment across CSXT tracks at private or public highway-rail grade crossings
CSX Corporation PAGE 14 Revised 09-09-2014
Railroad Flagging for Activities On or Near CSXT Property and Tracks
Key Points n Flagging services are required when projects are within close proximity to active rail lines, as required by federal law.n Flagging services can only be performed by qualified CSXT personnel.n Arrangements for flagging services may take up to 90 days to schedule a qualified employee.
OverviewIn the interest of public safety and the safety of employees and property, CSXT will work cooperatively with agencies, consultants, contractors and others who need to access railroad property when work brings them in close proximity to active railroad tracks to determine the appropriate flagging services needed and to make arrangements for those services.
Conditions When CSXT Flagging Services Are Required:n When any entity is working on, near or adjacent to active railroad tracks. n When an outside party is using railroad property or performing operations that may affect railroad property or facilities. This includes occasions when a party has been given express permission from CSXT to enter railroad property or perform such operations under the terms of a Construction agreement, Temporary Right-of-Entry agreement or other appropriate documentation.n When work off railroad property has the potential to impact CSXT property or operations.n When off-highway construction equipment is crossing the railroad at a private or public crossing.n When oversized equipment or highway vehicles are to cross the railroad at a private or public crossing.n In other instances as determined by CSXT.
Qualified Flagging Personnel CSXT flagging services may only be performed by qualified CSXT employees who are trained in the proper procedures related to rail operations and safety requirements, familiar with rail operations and procedures in a project area and able to communicate directly with CSXT dispatching personnel and train crews. Arrangements for CSXT Flagging Services
n CSXT will make arrangements for flagging services related to planned work by an outside party under the terms of a temporary right-of-entry agreement, construction agreement, environmental license agreement or other mutually acceptable arrangements. n Advance notice must be provided to secure CSXT flagging services. The level of advance notice may vary from site to site or project to project or if CSXT determines, under the provisions of its labor agreements with its union forces, that flagging services can only be provided as a result of the flagging position being bid and awarded to qualified CSXT personnel.
Responsibility for Costs and Expensesn All costs and expenses associated with CSXT flagging services are the sole responsibility of the agency, consultant or contractor. n CSXT will provide its estimated costs prior to the start of the project work or its assignment of flagging personnel. n Once flagging personnel are formally assigned by CSXT to a specific work location, the period of assignment can only be changed with appropriate advanced arrangements. n Charges for providing flagging services beyond a normal eight-hour weekday are calculated and billed at an overtime rate.n For initial planning purposes, typical flagging cost is $1,300 per day.
CSX Corporation PAGE 15 Revised 09-09-2014
Examples of Flagging Costs and Expenses
Charges billed by CSXT to the agency, consultant or contractor may include, but are not limited to: n Employee Salary
n Hourly employee charges are based on the time an employee departs and returns to his or her headquarters location. As such, the charges can be expected to exceed the level actually incurred during the assigned coverage period or while the flagman is present at the specific work location.
n This period also includes the time required for flagging personnel to perform the required preparations and termination procedures associated with flagging services at a location.
n Overhead Costsn These charges are assessed against the hourly employee charges and determined in accordance with
standard accounting procedures or as mandated by State and/or Federal regulations.n Employee Expenses or Per Diem Rate
n This amount is calculated based on an employee’s actual expenses or on a per diem rate according to the terms of applicable collective bargaining agreements between CSXT and its assigned union flagging employees.
n The amount includes travel and lodging expenses and the cost for a leased, rented, CSXT, or personal vehicle to be used for transportation.
n Administrative, Accounting, and Billing Services n This amount is related to the time associated with setting up the agreement, arranging for and
supervising the employee, billing and collection of costs, and other expenses associated with CSXT providing flagging services.
CDWMCPPS 08 71 00-1 Door Hardware
SECTION 08 71 00
DOOR HARDWARE
PART 1 GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Commercial door hardware for the following:
a. Swinging doors.
b. Other doors to the extent indicated.
2. Cylinders for doors specified in other Sections.
B. Related Work Specified in Other Sections Includes, But is Not Limited to, the
Following:
1. Section 01 79 00 - Training
2. Section 05 50 00 - Metal Fabrications
3. Section 08 11 13 - Steel Doors and Frames
1.2 REFERENCES
A. Codes and standards referred to in this Section are:
1. BHMA A156.1 - Butts and Hinges
2. BHMA A156.2 - Bored and Preassembled Locks and Latches
3. BHMA A156.4 - Door Controls and Closers
4. NFPA80 - Fire Doors and Windows
5. NFPA101 - Life Safety Code
6. UL10B - Fire Tests of Door Assemblies
7. UL305 - Panic Hardware
1.3 DEFINITIONS
A. Hardware Sets: "Hardware Sets" described in the Hardware Schedule in this Section
are as shown in the Door Schedule.
CDWMCPPS 08 71 00-2 Door Hardware
B. Fire-Rated Opening: Fire-rated doors, frames and hardware that conform to all
applicable requirements of a governing authority and bear the inspecting authority's
identification label.
1.4 SUBMITTALS
A. General: Provide all submittals, including the following, as specified in Division 1.
B. Product Data: Include construction and installation details, material descriptions,
dimensions of individual components and profiles, and finishes.
C. Product Test Reports: Based on evaluation of comprehensive tests performed by
manufacturer and witnessed by a qualified testing agency, for locks and closers.
D. Maintenance Data: For each type of door hardware to include in maintenance
manuals. Include final hardware and keying schedule.
E. Warranty: Special warranty specified in this Section.
F. Other Action Submittals:
1. Door Hardware Sets: Prepared by or under the supervision of Architectural
Hardware Consultant, detailing fabrication and assembly of door hardware,
as well as procedures and diagrams. Coordinate the final door hardware sets
with doors, frames, and related work to ensure proper size, thickness, hand,
function, and finish of door hardware.
a. Format: Use same scheduling sequence and format and use same door
numbers as in the Contract Documents.
b. Content: Include the following information:
(1) Identification number, location, hand, fire rating, and material of
each door and frame.
(2) Type, style, function, size, quantity, and finish of each door
hardware item.
(3) Complete designations of every item required for each door or
opening including name and manufacturer.
(4) Fastenings and other pertinent information.
(5) Location of each door hardware set, cross-referenced to
Drawings, both on floor plans and in door and frame schedule.
CDWMCPPS 08 71 00-3 Door Hardware
(6) Explanation of abbreviations, symbols, and codes contained in
schedule.
(7) Mounting locations for door hardware.
(8) Door and frame sizes and materials.
c. Submittal Sequence: Submit the final door hardware sets at earliest
possible date, particularly where approval of the door hardware sets
must precede fabrication of other work that is critical in Project
construction schedule. Include Product Data, Samples, Shop Drawings
of other work affected by door hardware, and other information
essential to the coordinated review of the door hardware sets.
2. Keying Schedule: Prepared by or under the supervision of Architectural
Hardware Consultant, detailing City's final keying instructions for locks.
Include schematic keying diagram and index each key set to unique door
designations.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: Substantial documented experience required for company
specializing in performing the Work of this Section.
B. Hardware Consultant Qualifications: A person who is currently certified by DHI as
an Architectural Hardware Consultant and who is experienced in providing
consulting services for door hardware installations that are comparable in material,
design, and extent to that indicated for this Project.
C. Source Limitations: Obtain each type and variety of door hardware from a single
manufacturer, unless otherwise indicated.
D. Fire-Rated Door Assemblies: Assemblies complying with NFPA 80 that are listed
and labeled by a testing and inspecting agency acceptable to authorities having
jurisdiction, for fire ratings indicated, based on testing according to NFPA 252.
E. Pre-installation Conference: Conduct conference at Project site to comply with
requirements in Section 01 31 00.
1.6 SPARE PARTS
A. Not Used
1.7 DELIVERY, STORAGE AND HANDLING
A. General: Deliver, store and handle hardware as specified in Division 1 and as
follows:
CDWMCPPS 08 71 00-4 Door Hardware
B. Identification: Have the hardware supplier package and label each item of hardware
separately. Tag each item in accordance with the approved final hardware schedule.
Have each package contain the appropriate fastenings, instructions and installation
templates.
C. Schedule: Furnish a complete hardware supplier's schedule when the hardware is
delivered. Direct supplier to deliver applicable items of hardware to door fabricators
for factory installation.
D. Storage: When received, properly store the hardware in a safe place.
E. Keys: Deliver the keys to the Commissioner, tagged and plainly marked on the face
of the envelope with the key change number, door designation and all other required
identifying information.
1.8 COORDINATION
A. Coordinate all Work involving manufacture or fabrication of internal reinforcement
for door hardware.
B. Templates: Distribute door hardware templates for doors, frames, and other work
specified to be factory prepared for installing door hardware. Check Shop Drawings
of other work to confirm that adequate provisions are made for locating and
installing door hardware to comply with indicated requirements.
1.9 WARRANTY
A. Provide one (1) year warranty or manufacturer’s standard warranty, whichever is
longer. Warranty period will begin as defined in Specifications Book 1 – Terms and
Conditions for Construction.
1.10 MAINTENANCE MATERIALS
A. Provide the following maintenance materials:
1. Provide special wrenches, tools and accessories applicable to each different
or special hardware component.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. Acceptable manufacturers are listed below. Other manufacturers of equivalent
products may be submitted.
CDWMCPPS 08 71 00-5 Door Hardware
2.2 MATERIALS
A. General: Provide hardware needed for the Work as shown, meeting or exceeding
the following standards of quality.
2.3 HINGES, GENERAL
A. Quantity: Provide the following, unless otherwise indicated:
1. Three Hinges: For doors with heights 61 to 90 inches
2. Four Hinges: For doors with heights 91 to 120 inches
B. Template Requirements: Provide only template-produced units.
C. Hinge Weight: Unless otherwise indicated, provide the following:
1. Entrance Doors: Heavy-weight hinges.
2. Doors with Closers: Antifriction-bearing hinges.
3. Interior Doors: Heavy-weight hinges.
D. Hinge Base Metal: Unless otherwise indicated, provide the following:
1. Exterior Hinges: Stainless steel, with stainless-steel pin.
2. Interior Hinges: Stainless steel, with stainless-steel pin.
3. Hinges for Fire-Rated Assemblies: Stainless steel, with stainless-steel pin.
E. Hinge Options: Where indicated in door hardware sets or on Drawings:
1. Nonremovable Pins: Provide set screw in hinge barrel that, when tightened
into a groove in hinge pin, prevents removal of pin while door is closed; for
outswinging exterior doors and outswinging corridor doors with locks.
F. Fasteners: Comply with the following:
1. Machine Screws: For metal doors and frames. Install into drilled and tapped
holes.
2.4 HINGES
A. Butts and Hinges: BHMA A156.1
B. Template Hinge Dimensions: BHMA A156.7.
C. Available Manufacturers:
1. Bommer Industries, Inc. (BI).
CDWMCPPS 08 71 00-6 Door Hardware
2. Hager Companies (HAG).
3. McKinney Products Company; an ASSA ABLOY Group company (MCK).
2.5 LOCKS AND LATCHES, GENERAL
A. Provide operating devices that do not require tight grasping, pinching, or twisting of
the wrist and that operate with a force of not more than 5 lbf
B. Latches and Locks for Means of Egress Doors: Comply with NFPA 101. Provide
Latches that require no more than 15 lbf to release the latch. Locks must not require
use of a key, tool, or special knowledge for operation.
C. Lock Trim:
1. Levers: Cast.
a. Best – 3H
b. Schlage – 03A
c. Dorma – LTA
d. Sargent – LNJ
D. Lock Throw: Comply with testing requirements for length of bolts required for
labeled fire doors, and as follows:
1. Mortise Locks: Minimum 3/4-inch latchbolt throw.
E. Backset: 2-3/4 inches, unless otherwise indicated.
F. Strikes: Manufacturer's standard strike with strike box for each latchbolt or lock
bolt, with curved lip extended to protect frame, finished to match door hardware set,
and as follows:
1. Strikes for Mortise Locks and Latches: BHMA A156.13.
2. Aluminum-Frame Strike Box: Manufacturer's special strike box fabricated
for aluminum framing
2.6 MECHANICAL LOCKS AND LATCHES
A. Lock Functions: Function numbers and descriptions indicated in door hardware sets
comply with the following:
1. Mortise Locks: BHMA A156.13.
B. Mortise Locks: Stamped steel case with steel or brass parts;
BHMA A156.13, Grade 1; Series 1000
CDWMCPPS 08 71 00-7 Door Hardware
C. Available Manufacturers:
1. SARGENT Manufacturing Company; an ASSA ABLOY Group company
(SGT).
2. Schlage Commercial Lock Division; an Ingersoll-Rand Company (SCH).
3. Dorma Americas (DA).
4. Best Access Systems (BES).
2.7 EXIT DEVICES
A. Exit Devices: BHMA A156.3, Grade 1
B. Exit Devices for Means of Egress Doors: Comply with NFPA 101. Provide exit
devices that require no more than 15 lbf to release the latch and locks that do not
require use of a key, tool, or special knowledge for operation.
C. Fire Exit Devices: Devices complying with NFPA 80 that are listed and labeled by
a testing and inspecting agency acceptable to authorities having jurisdiction, for fire
and panic protection, based on testing according to UL 305 and NFPA 252.
1. Outside Trim: Lever with cylinder; material and finish to match locksets,
unless otherwise indicated.
a. Match design for locksets and latchsets, unless otherwise indicated.
D. Available Manufacturers:
1. Precision Hardware Inc.
2. SARGENT Manufacturing Company; an ASSA ABLOY Group company
(SGT).
3. Schlage Commercial Lock Division; an Ingersoll-Rand Company (SCH).
4. Dorma Americas (DA).
2.8 LOCK CYLINDERS
A. Standard Lock Cylinders: BHMA A156.5, Grade 1
1. The Chicago Department of Water Management will prepare and provide
cores and keys to the Contractor.
CDWMCPPS 08 71 00-8 Door Hardware
a. Manufacturer: Best COREMAX 6 Pin SFIC Small Format
Interchangeable Cores.
2. Install cores, test and adjust the operation of the locks doors, and provide the
key back to the Commissioner identifying which doors each key will open.
Provide final updated drawings and schedule showing doors and door
numbers.
3. Furnish temporary cores for the construction period, and remove when
directed.
4. If arranged by the Commissioner, attend a workshop with DWM staff to
review the drawings and schedule to finalize the lock plan.
2.9 KEYING
A. Key System:
1. Comply with Commissioner's instructions for master keying and, except as
otherwise indicated, provide individual change key for each lock that is not
designated to be keyed alike. Permanently inscribe each key with the number
of the lock that identifies the cylinder manufacturer's key symbol, and notate
each key "DO NOT DUPLICATE."
B. Quantities: Furnish 3 change keys for each lock, 5 master keys for each master
system, and 5 grandmaster keys for each grandmaster system.
1. Furnish one extra blank for each lock.
2. Deliver keys to the Commissioner.
C. Key Numbering: Provide keys stamped with factory key numbers.
D. Provide keys of nickel silver only.
2.10 OPERATING TRIM
A. Standard: BHMA A156.6
B. Materials: Fabricate from stainless steel, unless otherwise indicated.
C. Available Manufacturers:
1. Burns Manufacturing Incorporated (BM).
2. Hager Companies (HAG).
3. Hiawatha, Inc. (HI).
CDWMCPPS 08 71 00-9 Door Hardware
4. IVES Hardware; an Ingersoll-Rand Company (IVS).
2.11 CLOSERS
A. Comply with the following maximum opening-force requirements:
1. Interior, Non-Fire-Rated Hinged Doors: 5 lbf applied perpendicular to door.
2. Fire Doors: Minimum opening force allowable by authorities having
jurisdiction.
B. Door Closers for Means of Egress Doors: Comply with NFPA 101. Provide door
closers that require no more than 30 lbf to set door in motion and not more than 15
lbf to open door to minimum required width.
C. Size of Units: Unless otherwise indicated, comply with manufacturer's written
recommendations for size of door closers depending on size of door, exposure to
weather, and anticipated frequency of use. Provide factory-sized closers, adjustable
to meet field conditions and requirements for opening force.
D. Surface Closers: BHMA A156.4, Grade 1 Provide type of arm required for closer
to be located on non-public side of door, unless otherwise indicated.
1. Available Manufacturers:
a. LCN Closers; an Ingersoll-Rand Company (LCN).
b. SARGENT Manufacturing Company; an ASSA ABLOY Group
company (SGT).
c. Dorma Americas (DA).
2.12 STOPS AND HOLDERS
A. Stops and Bumpers: BHMA A156.16, Grade 1
1. Provide wall stops for doors unless other type stops are scheduled or
indicated.
2. Where floor or wall stops are not appropriate, provide overhead stops or
holders.
B. Combination Overhead, Floor and Wall Stops and Holders:
BHMA A156.8, Grade 1
C. Silencers for Metal Door Frames: BHMA A156.16, Grade 1; neoprene or rubber,
minimum diameter 1/2 inch; fabricated for drilled-in application to frame.
CDWMCPPS 08 71 00-10 Door Hardware
1. Available Manufacturers:
a. Architectural Builders Hardware Mfg., Inc. (ABH).
b. Glynn-Johnson; an Ingersoll-Rand Company (GJ).
c. Hiawatha, Inc. (HI).
d. IVES Hardware; an Ingersoll-Rand Company (IVS).
e. Dorma Americas (DA).
f. Rixson; ASSA ABLOY Group Company (RIX).
2.13 ELECTROMAGNETIC HOLDERS
A. General: Provide UL listed electromagnetic holders at gates indicated on the
drawings, consisting of a wall mounted heavy-duty electromagnet, a self-adjusting
and pivoting armature, and all necessary mounting hardware.
1. Voltage: Field selectable to operate on 12 VDC, 24 VAC/VDC, or 120 VAC
input voltage.
2. Holding Force: 30-45 lbs. allow manual door closure when electromagnet is
energized.
3. Operation: Fail-Safe. Electromagnet releases instantly upon power loss.
4. Material: Heavy-duty die cast metal housings & faceplates. (2806 & 2810 -
Stainless steel faceplates)
5. Subject to compliance with the requirements, products that may be
incorporated into the work include, but are not limited to the following:
a. Dyna-lock Corporation Series 2800 Surface Mounted electromagnetic
holder Ref 2805.
2.14 DOOR GASKETING
A. Standard: BHMA A156.22
B. General: Provide continuous weather-strip gasketing on exterior doors and provide
smoke, light, or sound gasketing on interior doors where indicated or scheduled.
Provide noncorrosive fasteners for exterior applications and elsewhere as indicated.
CDWMCPPS 08 71 00-11 Door Hardware
1. Perimeter Gasketing: Apply to head and jamb, forming seal between door
and frame.
2. Meeting Stile Gasketing: Fasten to meeting stiles, forming seal when doors
are closed.
3. Door Bottoms: Apply to bottom of door, forming seal with threshold when
door is closed.
C. Air Leakage: Not to exceed 0.50 cfm per foot of crack length for gasketing other
than for smoke control, as tested according to ASTM E 283.
D. Smoke-Labeled Gasketing: Assemblies complying with NFPA 105 that are listed
and labeled by a testing and inspecting agency acceptable to authorities having
jurisdiction, for smoke-control ratings indicated, based on testing according to
UL 1784.
1. Provide smoke-labeled gasketing on 20-minute-rated doors and on smoke-
labeled doors.
E. Fire-Labeled Gasketing: Assemblies complying with NFPA 80 that are listed and
labeled by a testing and inspecting agency acceptable to authorities having
jurisdiction, for fire ratings indicated, based on testing according to NFPA 252
1. Test Pressure after 5 minutes into the test, neutral pressure level in furnace
will be established at 40 inches or less above the sill.
F. Sound-Rated Gasketing: Assemblies that are listed and labeled by a testing and
inspecting agency, for sound ratings indicated, based on testing according to
ASTM E 1408.
G. Replaceable Seal Strips: Provide only those units where resilient or flexible seal
strips are easily replaceable and readily available from stocks maintained by
manufacturer.
H. Gasketing Materials: ASTM D 2000 and AAMA 701/702.
1. Available Manufacturers:
a. Hager Companies (HAG).
b. Pemko Manufacturing Co. (PEM).
c. Zero International (ZRO).
d. K.N. Crowder (KNC).
CDWMCPPS 08 71 00-12 Door Hardware
2.15 THRESHOLDS
A. Standard: BHMA A156.21
B. Bevel raised thresholds with a slope of not more than 1:2.
C. Thresholds for Means of Egress Doors: Comply with NFPA 101. Maximum 1/2
inch high.
D. Available Manufacturers:
1. Hager Companies (HAG).
2. Pemko Manufacturing Co. (PEM).
3. Zero International (ZRO).
4. K.N. Crowder (KNC).
2.16 FABRICATION
A. Manufacturer's Nameplate: Do not provide products that have manufacturer's name
or trade name displayed in a visible location except in conjunction with required
fire-rated labels and as otherwise approved by Commissioner.
1. Manufacturer's identification is permitted on rim of lock cylinders only.
B. Base Metals: Produce door hardware units of base metal, fabricated by forming
method indicated, using manufacturer's standard metal alloy, composition, temper,
and hardness. Furnish metals of a quality equal to or greater than that of specified
door hardware units and BHMA A156.18. Do not furnish manufacturer's standard
materials or forming methods if different from specified standard.
C. Fasteners: Provide door hardware manufactured to comply with published templates
generally prepared for machine, wood, and sheet metal screws. Provide screws
according to commercially recognized industry standards for application intended,
except aluminum fasteners are not permitted. Provide Phillips flat-head screws with
finished heads to match surface of door hardware, unless otherwise indicated.
1. Concealed Fasteners: For door hardware units that are exposed when door is
closed, except for units already specified with concealed fasteners. Do not
use through bolts for installation where bolt head or nut on opposite face is
exposed unless it is the only means of securely attaching the door hardware.
Where through bolts are used on hollow door and frame construction, provide
sleeves for each through bolt.
2. Steel Machine: For the following fire-rated applications:
a. Mortise hinges to doors.
b. Strike plates to frames.
CDWMCPPS 08 71 00-13 Door Hardware
c. Closers to doors and frames.
3. Steel Through Bolts: For the following fire-rated applications unless door
blocking is provided:
a. Surface hinges to doors.
b. Closers to doors and frames.
c. Surface-mounted exit devices.
4. Spacers or Sex Bolts: For through bolting of hollow-metal doors.
2.17 FINISHES
A. Standard: BHMA A156.18, as indicated in door hardware sets.
B. Protect mechanical finishes on exposed surfaces from damage by applying a
strippable, temporary protective covering before shipping.
C. Appearance of Finished Work: Variations in appearance of abutting or adjacent
pieces are acceptable if they are within one-half of the range of approved Samples.
Noticeable variations in the same piece are not acceptable. Variations in appearance
of other components are acceptable if they are within the range of approved Samples
and are assembled or installed to minimize contrast.
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine doors and frames, with Installer present, for compliance with requirements
for installation tolerances, labeled fire door assembly construction, wall and floor
construction, and other conditions affecting performance.
B. Examine roughing-in for electrical power systems to verify actual locations of
wiring connections before electrified door hardware installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected
3.2 PREPARATION
A. Steel Doors and Frames: Comply with DHI A115 Series.
1. Surface-Applied Door Hardware: Drill and tap doors and frames according
to ANSI A250.6.
CDWMCPPS 08 71 00-14 Door Hardware
3.3 INSTALLATION
A. Mounting Heights: Mount door hardware units at heights indicated as follows unless
otherwise indicated or required to comply with governing regulations.
1. Standard Steel Doors and Frames: DHI's "Recommended Locations for
Architectural Hardware for Standard Steel Doors and Frames."
B. Install each door hardware item to comply with manufacturer's written instructions.
Where cutting and fitting are required to install door hardware onto or into surfaces
that are later to be painted or finished in another way, coordinate removal, storage,
and reinstallation of surface protective trim units with finishing work specified in
Division 9 Sections. Do not install surface-mounted items until finishes have been
completed on substrates involved.
C. Set units level, plumb, and true to line and location. Adjust and reinforce attachment
substrates as necessary for proper installation and operation.
1. Drill and countersink units that are not factory prepared for anchorage
fasteners. Space fasteners and anchors according to industry standards.
3.4 ADJUSTING
A. Initial Adjustment: Adjust and check each operating item of door hardware and each
door to ensure proper operation or function of every unit. Replace units that cannot
be adjusted to operate as intended. Adjust door control devices to compensate for
final operation of heating and ventilating equipment and to comply with referenced
accessibility requirements.
1. Door Closers: Unless otherwise required by authorities having jurisdiction,
adjust sweep period so that, from an open position of 70 degrees, the door will
take at least 3 seconds to move to a point 3 inches from the latch, measured
to the leading edge of the door.
B. Occupancy Adjustment: Approximately six months after date of Substantial
Completion, Installer's Architectural Hardware Consultant will examine and
readjust, including adjusting operating forces, each item of door hardware as
necessary to ensure function of doors, door hardware, and electrified door hardware.
3.5 CLEANING AND PROTECTION
A. Clean adjacent surfaces soiled by door hardware installation.
B. Clean operating items as necessary to restore proper function and finish.
C. Provide final protection and maintain conditions that ensure that door hardware is
without damage or deterioration at time of Substantial Completion.
CDWMCPPS 08 71 00-15 Door Hardware
3.6 DEMONSTRATION
A. Engage a factory-authorized service representative to train maintenance personnel
to adjust, operate, and maintain door hardware and door hardware finishes.
B. See additional requirements in Section 01 79 00 – Training.
3.7 DOOR HARDWARE SETS
A. Furnish products as listed in the following hardware sets:
B. Manufacturers, finish and their abbreviations used in the schedule:
BOM Bommer Industries, Inc.
DOR Dorma Americas.
DYN Dynalock Corporation.
HIA Hiawatha, Inc.
PEM Pemko Manufacturing Co.
LUN Lund Equipment Co., Inc.
600 Primed Coat
626 Brass/Satin Chrome
628 Anodized Aluminum
630 Satin Stainless Steel
652 Steel/Satin Chrome
689 Aluminum
Blu-Wht Blue & White
Gry Gray
Wht White
AMS All Machine Screws
AWS All Wood Screws
MS Machine Screws
MS/ES Machine Screws/Expansion Shields
WS Wood Screws
SMS Sheet Metal Screws
SNB Sex Nuts & Bolts
SSMS/ES25 ¼” – 20 Stainless Steel Machine Screws/Expansion Shields
STK Strike Plate
STMS Strike Template Machine Screws
T Temporary Construction Core
T.B. Toggle Bolt
.050 16 Gauge
CDWMCPPS 08 71 00-16 Door Hardware
3.8 SCHEDULE
A. General: Provide hardware for each door in accordance with the Hardware
Schedule. In the event of a discrepancy between the hardware items and the
Hardware Schedule, the Hardware Schedule governs.
1. Coordinate ComEd core requirements with ComEd.
B. Listing: The items of hardware listed in the following schedule are as required for
each door or each pair of doors as indicated. Where the symbol "NF" is used after
a lockset number, provide a case with nonferrous parts.
C. Completeness of Schedule: Do not construe the schedule of hardware included to
be complete. Provide hardware for all doors unless otherwise specified. Provide
hardware for doors not scheduled similar in type and quality to that provided for
scheduled doors that are to be used for similar purposes.
D. Intent of Schedule: Provide hardware of the type, materials, strength, design,
quality, weight, mechanical construction and operation of hardware as described by
the catalog numbers specified, or equal.
E. The numbers and descriptions shown in the following Hardware Schedule refer to
the following manufacturers:
1. Hinges: Lawrence Brothers, Inc. (LB), and Hager Hinge
Company (HH), or equal
2. Locksets and Latchsets: Corbin Russwin Architectural Hardware (CR), or
equal
3. Closers: Corbin Russwin Architectural Hardware (CR), or
equal
4. Overhead Holders and Glynn-Johnson (G-J)
and Stops:
5. Exit Devices: Corbin Russwin Architectural Hardware (CR), or
equal
6. Flush Bolts and H.B. Ives (I), and Glynn-Johnson (G-J),
Dustproof Strikes: or equal
7. Kickplates: H.B. Ives (I), and Brookline Industries, Inc. (BL),
or equal
8. Door Stops and Holders: H.B. Ives (I), Brookline Industries, Inc. (BL), and
Hager Hinge Company (HH), or equal
CDWMCPPS 08 71 00-17 Door Hardware
9. Door Coordinators: H.B. Ives (I), and Glynn-Johnson (G-J), or equal
F. Schedule: Provide products as listed in the following schedule:
HARDWARE SCHEDULE
SET
NO. QUANTITY, DESCRIPTION AND FINISH MFG.
OVERHEAD COILING DOORS (NO.S B112-2, 109-2, 109-3, 124-3, 130-2 CEE-2, CEW-
2 AND 207-3): HARDWARE TO BE PROVIDED BY DOOR MANUFACTURER.
AREA A
HW-1
PAIR OF DOOR NO. 112B-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. PASSAGE SET M9010 X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
660002 KNURLED OWNER STANDARD
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM (ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (INACTIVE LEAF) 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
AREA B
HW-2
PAIR OF UNEVEN DOOR NO. 117-1
8 EA. HINGES BB5002 4.5” X 4.5” NRP 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
CDWMCPPS 08 71 00-18 Door Hardware
STOP ARM (ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (INACTIVE LEAF) 689 DOR
2 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
2 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
HW-3
SINGLE DOOR NO. 117-2, 207-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-4
SINGLE EXISTING DOOR NO. 100-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-5
SINGLE DOOR NO. 121-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-6
SINGLE DOOR NO. 121-2
4 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
CDWMCPPS 08 71 00-19 Door Hardware
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
1 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
HW-7
SINGLE DOOR NO. 207-1, 117-3
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. RIM EXIT DEVICE F9300 X YT09 X 463 STK 630 DOR
1 EA. I.C. MORTISE CYLINDER 97D10BLK138 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
AREA C
HW-8
PAIR OF DOOR NO. B106-1, B107-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SIS SPRING ASSIST INTEGRAL STOP ARM 689 DOR
(ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
(INACTIVE LEAF)
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PULL SIDE.
HW-9
PAIR OF DOOR NO. 101-1
1 EA. ELECTRFIED HINGE BB5066 ETW 4 WIRES 4.5” X 4.5” NRP 630 BOM
CDWMCPPS 08 71 00-20 Door Hardware
7 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
2 EA. AUTOMATICFLUSH BOLTS 3142-METAL (INACTIVE LEAF) 630 HIA
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. ELECTRIFIED LOCKS M9080T-EU X LTA X 5007 STK 630 DOR
FAIL-SECURE X 12VDC (ACTIVE LEAF)
1 EA. PERMANENT CORES PROVIDED BY CDWM
2 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. COORDINATOR 3652-84 W/FILLER BAR 600 HIA
2 EA. COORDINATOR BRACKETS MB37 OR MB38 (AS REQUIRED) 600 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
2 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
1 EA. POWER SUPPLY PS610RF X 120V X 12.24VDC X 1 AMP (VERIFY) ----- DOR
1 EA. WIRING DIAGRAM ----- DOR
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
CARD READER, DOOR CONTACT, REQUEST TO EXIT PROVIDED BY SECURITY
CONTRACTOR.
DOOR SHALL BE SECURED AT ALL TIMES. AFTER SWIPING THE CARD READER
IT WILL ACTIVATE AND RETRACT THE LATCH BOLT AND ALLOW TO PULL
THE DOOR OPEN. ROTATING THE LEVER FROM THE INSIDE IT WILL ALLOWED
TO RETRACT THE LATCH BOLT AND ALLOWED TO EXIT.
IN CASE OF EMERGENCY OR POWER FAILURE THE DOOR REMAIN SECURED,
BY USING THE KEY IT WILL UNLOCKED AND RETRACT THE LATCH BOLT AND
ALLOWED TO PULL THE DOOR OPENED.
HW-10
SINGLE DOOR NO. 110-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89 REGULAR ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-10A
SINGLE DOOR NO. 102-1, 113B-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EACH OFFICE LOCK M9050T X LTA X LESS STK (DOOR NO. 102-1) 630 DOR
1 EA. STOREROOM LOCK M9080T X LTA X LESS STK 630 DOR
CDWMCPPS 08 71 00-21 Door Hardware
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. ELECTRIC STRIKE 6210 X 12VDC X FAIL-SECURE 630 VON
1 EA. DOOR CLOSERS 8916 AF89 REGULAR ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
CARD READER, DOOR CONTACT, REQUEST TO EXIT PROVIDED BY SECURITY
CONTRACTOR.
DOOR SHALL BE SECURED AT ALL TIMES. AFTER SWIPING THE CARD READER
WILL ACTIVATE, AND RETRACTING THE ELECTRIC STRIKE KEEPER AND
ALLOWING THE DOOR OPEN. ROTATING THE LEVER FROM THE INSIDE WILL
RETRACT THE LATCH BOLT AND ALLOWEXIT.
IN CASE OF EMERGENCY OR POWER FAILURE, THE DOOR WILL REMAIN
SECURED, IT WILL UNLOCK BY USING THE KEY WHICH WILL RETRACT THE
LATCH BOLT ALLOWING THE DOOR TO BE OPENED.
HW-11
SINGLE DOOR NO. B113-1, 104-1, 204-1, 220-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. WALL STOPS 9211T X T.B. 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
HW-12
SINGLE DOOR NO. 103-1, 106-1, 116-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PRIVACY LOCK W/INDICATOR M9046 X LTA X 5007 STK 630 DOR
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (AT DOOR NO. 103-1) 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
HW-13
PAIR OF DOOR NO. 105-1, 113-1
1 EA. ELECTRFIED HINGE BB5066 ETW 4 WIRES 4.5” X 4.5” 630 BOM
7 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
CDWMCPPS 08 71 00-22 Door Hardware
1 EA. ELECTRIFIED LOCKS M9080T-EU X LTA X 5007 STK 630 DOR
FAIL-SECURE X 12VDC (ACTIVE LEAF)
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM (ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (INACTIVE LEAF) 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
1 EA. POWER SUPPLY PS610RF X 120V X 12.24VDC X 1 AMP (VERIFY) ----- DOR
1 EA. WIRING DIAGRAM ----- DOR
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
CARD READER, DOOR CONTACT, REQUEST TO EXIT PROVIDED BY SECURITY
CONTRACTOR.
DOOR SHALL BE SECURED AT ALL TIMES. AFTER SWIPING THE CARD READER
IT WILL ACTIVATE AND RETRACT THE LATCH BOLT AND ALLOW TO PULL
THE DOOR OPEN. ROTATING THE LEVER FROM THE INSIDE IT WILL ALLOWED
TO RETRACT THE LATCH BOLT AND ALLOWED TO EXIT.
IN CASE OF EMERGENCY OR POWER FAILURE THE DOOR REMAIN SECURED,
BY USING THE KEY IT WILL UNLOCKED AND RETRACT THE LATCH BOLT AND
ALLOWED TO PULL THE DOOR OPENED.
HW-14
SINGLE DOOR NO. 107-1, 112B-3
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89 REGULAR ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-15
SINGLE DOOR NO. 108-1, 112-1. 210-1, 112B-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
(DOOR NO. 210-1)
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-16
CDWMCPPS 08 71 00-23 Door Hardware
SINGLE DOOR NO. 108-2,
4 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
1 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
HW-17
SINGLE DOOR NO. 111-1, 202-1. 205-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89 REGULAR ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
(DOOR NO. 201-1, 205-1 - LOCKER ROOM)
1 SET HEAD/JAMB SEALS S88W Wht PEM
3 EA. DOOR SILENCERS 601 (AS REQUIRED) Gry HIA
HW-18
SINGLE DOOR NO. 111-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. SURFACE OVERHEAD STOPS 900S SERIES 689 DOR
3 EA. DOOR SILENCERS 601 Gry HIA
HW-19
SINGLE DOOR NO. 114-1, 206-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (DOOR NO. 114-1) 689 DOR
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
(DOOR NO. 206-1 OVERHEAD STOP MOUNT ON THE PULL SIDE)
3 EA. DOOR SILENCERS 601 Gry HIA
CDWMCPPS 08 71 00-24 Door Hardware
HW-20
SINGLE DOOR NO. 115-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. OFFICE LOCK M9050T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
3 EA. DOOR SILENCERS 601 Gry HIA
MOUNT OVERHEAD STOPS ON THE PULL SIDE.
HW-20A
SINGLE DOOR NO. 124-4
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSER 8916 DS PARALLEL DEAD STOP ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-21
PAIR OF DOOR NO. 201-1, 221-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
KNURLED 660002 OWNER STANDARD
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SIS SPRING ASSIST INTEGRAL STOP ARM 689 DOR
(ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
(INACTIVE LEAF)
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PULL SIDE.
HW-22
SINGLE DOOR NO. 201-2
CDWMCPPS 08 71 00-25 Door Hardware
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-23
SINGLE DOOR NO. R1-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK KEYED BOTH SIDE M9082T X LTA X 5007 STK 630 DOR
2 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
AREA D
HW-24
SINGLE DOOR NO. B102-2, B102-1 122-2, 124-1, 301-2, 301-3, B110-2, 208-4
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-25
PAIR OF DOOR NO. B103-1, B104-1, B109-1, B110-1, B111-1, 209-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SIS SPRING ASSIST INTEGRAL STOP ARM 689 DOR
(ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
(INACIVE LEAF)
CDWMCPPS 08 71 00-26 Door Hardware
1 SET HEAD/JAMB SEALS S88W Wht PEM
2 EA. DOOR SILENCERS 601 (AS REQUIRED) Gry HIA
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PULL SIDE.
DOOR NO. B105-1, B109B-2, B110B-2, B111B-2, HARDWARE TO BE PROVIDED
BY CHAIN LINK FENCE MANUFACTURER.
HW-26
SINGLE DOOR NO. B103-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. WALL STOPS 9211T X T.B. 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
HW-27
NOT USED
HW-28
SINGLE DOOR NO. 109-2, 224-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORESPROVIDED BY CDWM
1 EA. DOOR CLOSER 8916 IS INTEGRAL STOP ARM 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
DOOR NO. 109-1 AND B102-3 MOTOR OPERATED OVERHEAD BY OTHERS
HW-29
SINGLE DOOR NO. 122-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. RIM EXIT DEVICE F9300 X YT09 X 463 STK 630 DOR
1 EA. I.C. MORTISE CYLINDER 97D10BLK138 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
CDWMCPPS 08 71 00-27 Door Hardware
1 EA. DOOR CLOSER 8916 SPA HEAVY DUTY PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-30
PAIR OF DOOR NO. 123-1, 123-2
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALEL DEAD 689 DOR
DEAD STOP ARM (ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (INACTIVE LEAF) 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
HW-31
SINGLE DOOR NO. 124-2, 322-1, B115-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSER 8916 IS INTEGRAL STOP ARM 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-32
PAIR OF DOOR NO. 125-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SIS SPRING ASSIST INTEGRAL STOP ARM 689 DOR
(ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES X 7090 BRACKETS 689 DOR
(INACTIVE LEAF)
CDWMCPPS 08 71 00-28 Door Hardware
1 SET HEAD/JAMB SEALS S88W Wht PEM
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
2 EA. DOOR BOTTOM 217AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5” W X ½”H X SSMS/ES 628 PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER & OVERHEAD STOP ON THE PULL SIDE.
HW-33
SINGLE DOOR NO. 208-1, 208-2, 208-3, 211-1, 211-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-34
SINGLE DOOR NO. 209-2, 302-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-35
PAIR OF DOOR NO. 301-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALEL DEAD 689 DOR
DEAD STOP ARM (ACTIVE LEAF)
1 EA. SURFACE OVERHEAD STOPS 900S SERIES (INACTIVE LEAF) 689 DOR
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
CDWMCPPS 08 71 00-29 Door Hardware
MOUNT CLOSER & OVERHEAD STOP ON THE PUSH SIDE.
HW-36
SINGLE DOOR NO. R3-1, R3-2, R3-3
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK KEYED BOTH SIDE M9082T X LTA X 5007 STK 630 DOR
2 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
AREA E
HW-37
SINGLE DOOR NO. 126-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORESPROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
HW-38
SINGLE DOOR NO. 126-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-39
SINGLE DOOR NO. 127-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
CDWMCPPS 08 71 00-30 Door Hardware
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-40
PAIR OF DOOR NO. 128-1, 129-2
8 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
2 EA. AUTOMATICFLUSH BOLTS 3142-METAL (INACTIVE LEAF) 630 HIA
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCKS M9080T X LTA X 5007 STK 630 DOR
(ACTIVE LEAF)
1 EA. PERMANENT CORES PROVIDED BY CDWM
2 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. COORDINATOR 3652-84 W/FILLER BAR 600 HIA
2 EA. COORDINATOR BRACKETS MB37 OR MB38 (AS REQUIRED) 600 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
2 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER ON THE PUSH SIDE.
HW-41
SINGLE DOOR NO. 128-2, 128-3, 130-5
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. PASSAGE SET M9010 X LTA X 5007 STK 630 DOR
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-42
PAIR OF DOOR NO. 129-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. AUTOMATICFLUSH BOLTS 3142-METAL (INACTIVE LEAF) 630 HIA
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. PASSAGE SET M9010T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
CDWMCPPS 08 71 00-31 Door Hardware
1 EA. DOOR CLOSERS 8916 SPA HEAVY DUTY PARALLEL ARM 689 DOR
1 EA. COORDINATOR 3652-84 W/FILLER BAR 600 HIA
2 EA. COORDINATOR BRACKETS MB37 OR MB38 (AS REQUIRED) 600 HIA
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER ON THE PUSH SIDE.
HW-43
SINGLE DOOR NO. 130-1, 130-3
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
3 EA. DOOR SILENCERS 601 Gry HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-44
SINGLE DOOR NO. 130-4
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. CLASSROOM LOCK M9070T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-45
PAIR OF DOOR NO. 131-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. MORTISE EXIT DEVICE CD9500 X YT08M X 465 STK 630 DOR
(ACTIVE LEAF)
2 EA. I.C. MORTISE CYLINDER 97D10BLK138 (Trim & Cylinder Dogging) 630 DOR
2 EA. PERMANENT CORES PROVIDED BY CDWM
CDWMCPPS 08 71 00-32 Door Hardware
1 EA. DOOR CLOSERS 8916 SPA HEAVY DUTY PARALLEL ARM 689 DOR
(ACTIVE LEAF)
2 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER ON THE PUSH SIDE.
HW-46
PAIR OF DOOR NO. 132-1
8 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
2 EA. MANUAL FLUSH BOLTS 3780F – 24” TOP & 12” BOTTOM ROD 630 HIA
(INACTIVE LEAF)
1 EA. DUST PROOF STRIKE 382 X MS/ES 630 HIA
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK (ACTIVE LEAF) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89 REGULAR ARM (ACTIVE LEAF) 689 DOR
2 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
ASTRAGAL PROVIDED BY DOOR MANUFACTURER.
MOUNT CLOSER ON THE PULL SIDE.
HW-47
SINGLE DOOR NO. 132-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSER 8916 IS INTEGRAL STOP ARM 689 DOR
3 EA. DOOR SILENCERS 601
Gry HIA1 SET HEAD/JAMB SEALS S88W Wht
PEM
HW-48
SINGLE DOOR NO. 133-1
4 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
1 EA. STOREROOM LOCKS M9080T X LTA X 5007 STK 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. LATCH PROTECTOR LP111 X 3” X 11” X 12 GA. (VERIFY) 630 DON-JO
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
CDWMCPPS 08 71 00-33 Door Hardware
STOP ARM
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
1 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
HW-49
SINGLE DOOR NO. 133-2
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. RIM EXIT DEVICE F9300 X YT08 X 463 STK 630 DOR
2 EA. I.C. MORTISE CYLINDER 97D10BLK138 (Trim) 630 DOR
2 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSER 8916 SPA HEAVY DUTY PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
HW-50
SINGLE DOOR NO. R2-1
4 EA. HINGES BB5006 4.5” X 4.5” 630 BOM
1 EA. STOREROOM LOCK KEYED BOTH SIDE M9082T X LTA X 5007 STK 630 DOR
2 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 EA. KICKPLATES J102 – 10” X 2” LDW X .050 X SMS X B4E 630 HIA
1 SET HEAD/JAMB SEALS S88W Wht PEM
AREA F
HW-51
SINGLE DOOR NO. CEE-1, CEW-1
4 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
1 EA. RIM EXIT DEVICE F9300 X YT09 X 463 STK 630 DOR
1 EA. I.C. MORTISE CYLINDER 97D10BLK138 (Trim & Cylinder Dogging) 630 DOR
1 EA. PERMANENT CORES PROVIDED BY CDWM
1 EA. DOOR CLOSERS 8916 SDS SPRING ASSIST PARALLEL DEAD 689 DOR
STOP ARM
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
1 EA. DOOR BOTTOM W/DRIP 2221AV X SMS 628 PEM
1 EA. THRESHOLD 171A X 5”W X ½”H X SSMS/ES 628 PEM
HW-52
CDWMCPPS 08 71 00-34 Door Hardware
SINGLE DOOR NO. CEE-3
4 EA. HINGES BB5006 4.5” X 4.5” NRP 630 BOM
1 EA. RIM EXIT DEVICE F9300 X YT09 X 463 STK 630 DOR
1 EA. I.C. MORTISE CYLINDER 97D10BLK138 (Trim & Cylinder Dogging) 630 DOR
1 EA. PERMANENT BEST CORES PROVIDED BY COMED.
1 EA. DOOR CLOSERS 8916 AF89P PARALLEL ARM 689 DOR
1 EA. WALL STOPS 9211T X T.B. 630 HIA
1 SET HEAD/JAMB SEALS 315CR X SMS 628 PEM
1 EA. DOOR SWEEPS 315CN X SMS 628 PEM
COMED TO PROVIDE BEST PERMANENT CORE.
HW-53
MISCELLANEOUS
1 EA. KEY CONTROL WALL CABINETS 1202 – 130 CAPACITY EXPAND Gry LUN
UP TO 300 CAPACITY TWO TAG KEY SYSTEM
END OF SECTION
S. S
T. L
OU
IS
A
V
CONTRACTOR STAGING & WORK AREA
EXISTING BUILDING
EXISTING CSX RR TRACKS
CPPS EMPLOYEE PARKING AREA
(22 SPACES, 1 OFFICE TRAILER,
& 2 STORAGE CONTAINERS)
ROAD CLOSURE BARRICADES
CONTRACTORS
STAGING
AREA
TEMPORARY CHAIN LINK
SECURITY FENCE (TYPICAL)
TEMPORARY
CHAIN LINK
SECURITY FENCE
(TYPICAL)
102.60'
152.50'
SIDEWALK TO REMAIN OPEN
SIDEWALK CLOSED DURING CONSTRUCTION
24' SLIDE GATE
GATES
GATE
OF
FIC
E T
RA
IL
ER
**CAUTION** INDICATES LOCATION OF
EXISTING LARGE DIAMETER CAST IRON &
CONCRETE WATER MAINS (DEPTH VARIES).
CONTRACTOR TO FIELD VERIFY AND
PROTECT DURING ALL CONSTRUCTION
OPERATIONS IN THE VICINITY OF THE MAINS
143.25'
TEMP PARKING LOT AND
DRIVEWAY TO BE ASPHALT PER
DETAIL 9/C-28. CONTRACTOR TO
GRADE THE LOT TO PROVIDE
POSITIVE DRAINAGE.
125.00'
76.00'
456.75'
184.00'
692
CENTRAL PARK PUMPING STATION
ELECTRIFICATION
DRAWN
DWG
SHEET OF
FILE
: P
:\R
M083713\D
ES
IG
N\D
WG
\C
IV
IL\21.05 W
OR
KIN
G D
RA
WIN
GS
\12354C
006
DEPARTMENT OF WATER MANAGEMENT
BUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO.
13 - 102
REVISIONS
PROJECT NO.
NO. DATE APPD DESCRIPTION
MA
TT
HE
W W
HIS
LE
R 2016-07-14
3:54 P
M
100 S. WACKER DRIVE, SUITE 1400
CHICAGO, ILLINOIS 60606
200 South Michigan Avenue, Suite 1500
Chicago, Illinois 60604
C-6
CONSTRUCTION STAGING PLAN
ASW
MDW
MF
MAY 2016
1"=30'
12
CIVIL
30 0 FT30 60
1"=30'
NOTE:
1) TEMPORARY CPPS EMPLOYMEE PARKING AREA
CONSTRUCTED OF TEMPORARY HMA PAVEMENT
PER DETAIL 9/C-28 PROVIDE EAST- WEST RIDGE
AND SLOPE TO NORTH , SOUTH TO PROVIDE
POSITIVE DRAINAGE.
2) SEE C-4 AND C-5 FOR PROPERTY SURVEY
INFORMATION.
3) TEMPORARY CHAIN LINK SECURITY FENCE SHALL
BE FE6-TBR-96 SEE SHEETS C-39 AND C-40 FOR
CHAIN LINK FENCING DETAILS.
4) TEMPORARY FENCING GATES SHOWN ARE
MINIMUMS. GATES MAY BE ADDED TO ALLOW FOR
CONSTRUCTION ACTIVITIES AS REQUIRED BY
CONTRACTOR AND APPROVED BY THE
COMMISSIONER.
5) ALL TEMPORARY FENCING AND GATES,
INCLUDING CONCRETE FOOTING AND GROUND
RODS TO BE REMOVED COMPLETELY AT
COMPLETION OF PROJECT.
** PROTECTION OF EXISTING UTILITIES DURING CONSTRUCTION:
1) SEE SPECIFICATIONS, INCLUDING 01 50 00 CONSTRUCTION FACILITIES AND
TEMPORARY CONTROLS, CONTRACTOR IS RESPONSIBLE TO PROTECT ALL EXISTING
UTILITIES DURING CONSTRUCTION. CONTRACTOR IS RESPONSIBLE FOR REPAIRING
ANY DAMAGE.
2) THESE ARE EXISTING WATER FEEDER MAINS, STEEL SHELL CONCRETE PIPE & CAST
IRON DIAMETER VARY BETWEEN 36" TO 54" , TOP OF PIPES ARE 2 TO 3 FEET BELOW
EXISTING GRADE, CONTRACTOR MUST PROTECT THESE PIPES AND ALL OTHER
UNDERGROUND UTILITIES DURING CONSTRUCTION AGAINST DAMAGE. CONTRACTOR IS
RESPONSIBLE FOR REPAIRING ANY DAMAGE.
3) ALL EXISTING UTILITIES MUST REMAIN FULLY FUNCTIONAL DURING CONSTRUCTION.
CONSTRUCTION STAGING PLAN
SCALE: 1" = 30'
1
1
1 07/15/16 MF ADDENDUM NO. 3
DEMOLISH
EXISTING CB 1759
DEMOLISH
EXISTING CB 1769
DEMOLISH
EXISTING MH 1753
DEMOLISH
EXISTING CB 1754
DEMOLISH
EXISTING MH 1718
W. FILLMORE ST.
S. S
T. LO
UIS
A
V
EXISTING CSX RR TRACKS
EXISTING BUILDING
REMOVE EXISTING 6" SEWER PIPES
DEMOLISH EXISTING
8" SEWER PIPES
DEMOLISH
MANHOLE 1553
DEMOLISH EXISTING
±4" WATER SERVICE
(VIF)
DEMOLISH
EXISTING CATCH BASIN
DEMOLISH
EXISTING CATCH BASINS
CAP SERVICE AT VALVE
TEMP PLUG
PIPE
TEMP PLUG
PIPE
APPROXIMATE LOCATION OF REMAINING
UNDERGROUND NATATORIUM BUILDING.
CONTRACTOR TO REMOVE (SEE NOTE 3)
EXISTING WALL AND FENCE
EXISTING DOCK AND DRIVE
S. C
EN
TR
AL
P
AR
K A
V
EXISTING BUILDING
EXISTING CSX RR TRACKS
692
CENTRAL PARK PUMPING STATION
ELECTRIFICATION
DRAWN
DWG
SHEET OF
FILE
: P
:\R
M083713\D
ES
IG
N\D
WG
\C
IV
IL\21.05 W
OR
KIN
G D
RA
WIN
GS
\12354C
010
DEPARTMENT OF WATER MANAGEMENT
BUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO.
13 - 102
REVISIONS
PROJECT NO.
NO. DATE APPD DESCRIPTION
AN
DR
EW
W
YN
N 2016-07-21
2:26 P
M
100 S. WACKER DRIVE, SUITE 1400
CHICAGO, ILLINOIS 60606
200 South Michigan Avenue, Suite 1500
Chicago, Illinois 60604
C-10
UNDERGROUND DEMOLITION PLAN
RME
MDW
MF
MAY 2016
1"=20'
16
CIVIL
20 0 FT20 40
1"=20'
NOTES:
1. SEE SHEET C-4 AND C-5 FOR UNDERGROUND
STRUCTURE INFORMATION
2. SEE SHEET C-9 FOR SITE DEMOLITION PLAN
3. IT IS ANTICIPATED THAT CONCRETE FOUNDATIONS
AND DEMOLITION DEBRIS FROM THE PREVIOUSLY
DEMOLISHED NATATORIUM ARE PRESENT BELOW
GRADE. IF ANY ITEMS ARE ENCOUNTERED
DURING EXCAVATION WORK, REMOVE THESE
ITEMS THAT CONFLICT WITH OR WILL BE
UNDERNEATH ANY NEW WORK IN THEIR ENTIRETY,
CONTRACT WORK TO INCLUDE REMOVAL OF 1,440
CUBIC YARDS OF MATERIAL AND REPLACEMENT
WITH BACKFILL PER SPECIFICATION 31 20 00 -
EARTH MOVING.
SE
E B
ELO
W F
OR
C
ON
TIN
UA
TIO
N
SE
E A
BO
VE
F
OR
C
ON
TIN
UA
TIO
N
UNDERGROUND DEMOLITION PLAN
SCALE: 1" = 20'
1
1 07/15/16 MF ADDENDUM NO. 3
CONNECT 4" SANITARY
TO 6" ESVCP RISER
RISER INV ±17.92
WYE - 6"X6"
INV 12.20
CO-2
INV 12.22
80'-12" ESVCP
@ 0.57%
4" SANITARY
FROM BUILDING
INV ±17.97
64'-6" ESVCP SANITARY
SEWER @ 1.00%
CO-3
INV 16.53
WYE - 8"X8"
INV 16.51
TRENCH DRAIN
OUTLET BOTTOM OF
TRENCH DRAIN
INV 16.20
33'-8" ESVCP
@ 1.50%
CO-4
INV 16.03
20'-8" ESVCP
@ 1.50%
MH-08 CLOSED LID
RIM 20.18
INV 11.56 (W)
INV 10.81 (N)
INV 10.15 (E) W/ BACKFLOW PREVENTER
INV 10.05 (S)
W. FILLMORE ST.
S. S
T. L
OU
IS
A
V
CB-04 W/ HALF-TRAP AND
RESTRICTOR
OPEN LID
RIM 19.30
INV 12.08 (N)
INV 10.98 (W)
INV 11.98 (HALF TRAP)
UNDERGROUND
DETENTION BASIN
SEE C-35
BOTTOM=12.10 CCD
MH-01
OPEN LID
RIM 19.45
INV 16.58 (N)
INV 13.80 (W)
INV 13.70 (E)
RISER MH
RIM 19.26
ELECTRICAL
DUCTBANK
8" WATER SERVICES
CAP EXISTING
WATER SERVICE
4" GAS SERVICE. PROVIDE 4" TEE OFF
OF EXISTING 8" SERVICE. CAP NORTH
LEG AND REMOVE EXISTING 8"
SERVICE TO THE BUILDING.
EXIST COMED 9-DUCT
EX SEWER MH 1288
RIM 18.82
INV 9.67 15" (E)
INV 9.62 15" (W)
EX SEWER MH 1531
RIM 18.19
INV 9.84 15" (E)
INV 9.79 15" (W)
EX SEWER MH 1559
RIM 18.21
INV 10.06 15" (E)
INV 10.01 15" (W)
EX 12" GAS
EX 6" WATER
EX 15" SEWER
EX 12" SEWER
CB-05
OPEN LID
RIM 18.60
INV 14.85
MH-06
OPEN LID
RIM 29.40
INV 13.60
135'-15" ESVCP STORM
SEWER @ 0.76%
65'-18" ESVCP STORM
SEWER @ 0.46%
INV. 12.60
51'-8" DIP STORM SEWER
@ 1.96%. TO BE
JACKED/BORED UNDER
THE EXISTING
RETAINING WALL
8'-12" ESVCP STORM
SEWER @ 0.25%
ELECTRICAL
DUCTBANK
EHH-1
RIM 21.60
EHH-2
RIM 21.60
EHH-3
RIM 20.30
ELECTRICAL
DUCTBANK
TELEPHONE AND
COMMUNICATION
DUCTBANK
(3) NEW VALVES IN
VAULT
SEE DETAIL 4/C-36
EXISTING BUILDING
NEW
BUILDING
F.F.=21.58
NEW BUILDING
F.F.=21.58
INV 12.10
54'-6" ESVCP
SANITARY SEWER
@ 2.02%
SEE ENLARGED UTILITY
PLAN #2 THIS SHEET
258'-8" EXVCP STORM
SEWER @ 0.73%
INV 14.80
5'-8" ESVCP STORM
SEWER @ 1.00%
SEE ENLARGED UTILITY
PLAN #1 THIS SHEET
INV 12.30
SEE ENLARGED UTILITY
PLAN #3 THIS SHEET
VV-01
RIM ±19.05
VV-03
RIM ±18.56
RISER MH
RIM 20.13
45' - 8" DIP EMERGENCY
PUMP DISCHARGE @ 0.96%
1000GPM MAX FLOW
INV ±15.24
8" ESVCP DIRECT
CONNECTION TO
EXISTING 15" SEWER
INV ±9.57
CONNECT DOWNSPOUT
TO 8" PIPE PER DETAIL
6/C-33. INV ±17.82
CONNECT DOWNSPOUT
TO 8" PIPE PER DETAIL
6/C-33. INV ±16.50
50' - 8" ESVCP DOWNSPOUT
CONNECTION @ 2.50%
75' - 8" DIP
@ 1.00%
EX WVV 1506
ADJ RIM 18.56
EX STM MH 1544
ADJ RIM 18.50
EX WVV 1387
ADJ RIM 18.83
SEE ENLARGED UTILITY
PLAN #1 THIS SHEET
INV. 16.00
NEW GAS METER
DS-1
DS-2
DS-3
DS-4
DS-6
DS-5
12' - 8" DIP @
1.00%
14'-8' DIP @ 1.00%
57'-8' DIP
@ 1.00%
TRENCH DRAIN
RIM 18.85-18.63
SLOPE INVERT TO
DRAIN
13'-6" ESVCP @ 1.00%
MH-07 CLOSED LID
RIM 21.04
INV 13.81 (E)
INV 12.90 (NW)
INV 11.95 (S)
REPLACE 30' ESVCP
SANITARY SEWER @
1.00% MINIMUM
CONNECT 4" SANITARY
TO 4" ESVCP
INV ±15.17
CO-1
INV 15.16
WYE - 6"X4"
INV 15.12
30'-6" ESVCP SANITARY
SEWER @ 4.37%
CONNECT TO EXISTING
6" SANITARY AT
FOUNDATION WALL.
INV ±13.0
INV ±15.22
692
CENTRAL PARK PUMPING STATION
ELECTRIFICATION
DRAWN
DWG
SHEET OF
FILE
: P
:\R
M083713\D
ES
IG
N\D
WG
\C
IV
IL\21.05 W
OR
KIN
G D
RA
WIN
GS
\12354C
013
DEPARTMENT OF WATER MANAGEMENT
BUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO.
13 - 102
REVISIONS
PROJECT NO.
NO. DATE APPD DESCRIPTION
AN
DR
EW
W
YN
N 2016-07-21
2:24 P
M
100 S. WACKER DRIVE, SUITE 1400
CHICAGO, ILLINOIS 60606
200 South Michigan Avenue, Suite 1500
Chicago, Illinois 60604
C-13
UTILITY PLAN
RME
MDW
MF
MAY 2016
1"=20'
19
CIVIL
20 0 FT20 40
1"=20'
NOTES:
1. SEE SHEET C-33 THRU C-38 FOR UTILITY DETAILS
2. SEE SHEET C-14 TO C-16 FOR STORM SEWER,
SANITARY SEWER, WATER MAIN,ELECTRICAL DUCT
BANK AND COMMUNICATION PROFILES & UTILITY
CONFLICT RESOLUTION.
3. SEE E-80 FOR ELECTRICAL HANDHOLE & CONDUIT
DETAIL.
4. SEE E-3 FOR DUCTBANK TYPICAL SECTIONS.
5. UTILITY TRENCH BEDDING AND BACKFILL PER
DETAILS ON C-33 TO C-36. IF NOT SPECIFIED,
BEDDING SHALL BE CA-11 OR CA-6, BACKFILL SHALL
BE FA-6, CA-6, CA-11 OR CA-16.
6. 2-COMED DUCTBANKS (FROM BUILDING TO R/W) TO
BE EXTENDED FROM ROW TO THE SOUTH BY
COMED. COORDINATE WITH COMED.
7. PROVIDE TELEPHONE AND COMMUNICATIONS
DUCTBANK FROM BUILDING TO UTILITY POLE ON
SOUTH SIDE OF FILLMORE, AS SHOWN.
COORDINATE WITH AT&T.
8. SEE C-36 FOR 8" WATER SERVICE DETAIL.
9. GAS SERVICE MODIFICATION AND ACTUAL GAS
SERVICE CONNECTION SIZE SHALL BE
COORDINATED WITH PEOPLE'S GAS.
10. CONTRACTOR SHALL PROVIDE PAVEMENT
SAW-CUTTING, EXCAVATION, BEDDING, BACKFILL,
RESTORATION AND PAVEMENT PATCHING FOR ALL
UTILITY TRENCH WORK.
11. TRAFFIC CONTROL PER CDOT STANDARDS SHALL
BE PROVIDED FOR ALL WORK IN CDOT R/W.
UTILITY PLAN
SCALE: 1" = 20'
ENLARGED UTILITY PLAN #2
SCALE: 1" = 10'
ENLARGED UTILITY PLAN #3
SCALE: 1" = 10'
ENLARGED UTILITY PLAN #1
SCALE: 1" = 10'
10 0 FT10 20
1"=10'
MH-09 CLOSED LID
RIM 20.34
INV 16.08 (S)
INV 15.71 (SW)
INV 14.80 (N)
INV 14.25 (E)
TRENCH DRAIN
RIM 19.80
SLOPE INVERT TO DRAIN
CONNECT DOWNSPOUT
TO 8" PIPE PER DETAIL
6/C-33. INV ±16.64
TRENCH DRAIN
OUTLET BOTTOM OF
TRENCH DRAIN
INV 15.00
10'-8" [email protected]%
EA
ST
R
.O
.W
. O
F S
. C
EN
TR
AL P
AR
K A
VE
UNDERGROUND DETENTION BASIN
VOLUME REQUIREMENTS
RATE CONTROL STORAGE REQUIRED = 10,834 CUBIC FEET
RATE CONTROL STORAGE PROVIDED = 11,083 CUBIC FEET
1
1 07/15/16 MF ADDENDUM NO. 3
LEGEND
EXISTING STRUCTURE TO BE DEMOLISHED
10
(E)T3 1/2x3 1/2x3/8
EXIST CONCFOOTING TO BEDEMOLISHED
EXIST MACHINE SHOPBUILDING
EXIST STORAGEROOM
T/WALLEL +22'-1"
T/ EXIST ROOFEL +38'-1"
3S-71
B/FTGEL +15'-0"
1
T/EXIST CONC SLABEL +21'-7"
11
D
T/BASEMENT SLABEL +11'-1"
EXIST CONCPIER (BEYOND)
EXIST CONCFDN (BEYOND)
T/CONC SLABEL +27'-6"
EXIST CONCSLAB
EXIST CONCCOL
F1
S-71
E9
T/EXIST CONC SLABEL +21'-7"
B/FTGEL +15'-0"
T/WALLEL +22'-1"
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
RA
KN
MF
100 SOUTH WACKER DRIVE, SUITE 1400CHICAGO, ILLINOIS 60606-4003
STRUCTURAL
D:\T
EM
P\R
EV
IT\1
2354-C
PP
S-S
_A
Abdelrahm
an.r
vt
7/1
2/2
016 4
: 10:0
8 P
M
As indicated
S-71
DEMOLITION - AREA C - SECTIONS ANDDETAILS
121
JUNE 2016
3/8" = 1'-0"1
SECTION 3/8" = 1'-0"
2SECTION
(S-21, S-22)(S-21, S-22)
3/8"=1'-0"
1 0 1 2 43 5 6 7 FT
NOTES:
1. FIELD VERIFY ALL EXISTING CONDITIONS AND DIMENSIONS. REPORT TO REPRESENTATIVE OF THE COMMISSIONER, ALL DISCREPANCIES PRIOR TO CONSTRUCTION.
2. REFER TO ARCHITECTURAL DRAWINGS FOR DEMOLITION OF EXISTING BUILDING FAÇADE.
3. REFER TO HZ DRAWINGS AND RELATED SPECIFICATIONS FOR REMEDIATION, ABATEMENT, REMOVAL AND DISPOSAL PROCEDURES REQUIRED FOR DEMOLITION AND EXCAVATION WORK.
4. REFER TO SPECIFICATION SECTION 01 12 16 - CONSTRUCTION WORK SEQUENCE AND LIMITATIONS.
5. SAFETY AND INTEGRITY OF THE STRUCTURE AND SURROUNDING AREAS ARE RESPONSIBILITY OF THE CONTRACTOR DURING DEMOLITION.
6. MEANS AND METHODS OF THE DEMOLITION ARE FULL RESPONSIBILITY OF THE CONTRACTOR.
7. CONTRACTOR MUST PROTECT THE EXISTING AREAS TO REMAIN DURING DEMOLITION WORK.
8. ALL SPECIFICATION REQUIREMENTS MUST BE ADHERED TO DURING THE DEMOLITION.
9. FOR ADDITIONAL DEMOLITION AND SHORING NOTES SEE S-1.
NO. DATE APPD DESCRIPTION
1 7/15/16 MF ADDENDUM NO.3
3/8" = 1'-0"3
SECTION
(S-21, S-22)
1
X XX X
X XX X
87
E
D
17' -
6"
W14x74
T/S
TL 2
' - 1
1"
(E)W14x68(E)W14x68
(E)W14x43
(E)W14x43
(E)W16x40
T/STL -2"
(E)W
24x74
T/S
TL -
2"
T/SLABEL +21'-7"
T/SLABEL +25'-0"
6S-98
6" CONCSLAB
6" CONC SLAB
W8x15
T/S
TL -
6"
7S-102
3S-103
2S-103
(E)S12x31.8
T/STL 9 1/2"
6S-102 1
S-103
2#7
6' - 0 1/4"
9S-103
5"
10' - 9 1/4"
8' -
2"
UP
T/SLAB EL 21'-7"
MC8x22.8
87
E
D
17' -
6" 1
1' -
6"
2 EQ SPA = 9' - 11 1/4"EXIST MASONRYWALL
8" CMUWALL (TYP)
SEE NOTE 11
(E)W14x68
W12x40
T/S
TL 4
' - 5
3/4
"
BEAM POCKETSEE DETAIL 8/S-147
L8x6x1/2
T/S
TL 4
' - 5
3/4
"
L8x6x1/2 T/STL 4' - 5 3/4"
L8x6x1/2
L8x6x1/2
L8x6x1/2 T/STL 4' - 5 3/4"
L8x6x1/2
T/S
TL 4
' - 5
3/4
"
SEE NOTE 11
W8x15
T/S
TL -
6"
W8x15
T/S
TL -
6"
5S-101
SIM
4S-101
SIM
2S-101
SIM
5S-101
SIM3S-101
5S-101
SIM
SEE NOTE 12
2' - 4 1/2"
2' - 10 1/4"1' - 7 1/2"
1S-107
2' - 0" 10' - 9 1/4"
4' -
11"
8' -
2"
987
E
D
(E)W14x68 (E)W14x68 (E)W14x68
(E)W14x43 (E)W14x43 (E)W14x43
(E)W
18x47
T/S
TL -
1 1
/2"
(E)W
18x47
T/S
TL -
1 1
/2"
(E)W12x28
T/STL -1 1/2"
(E)W12x28
T/STL -1 1/2"
(E)W
16x40
T/S
TL -
1 1
/2"
(E)W12x28
T/STL -1 1/2"
(E)W
14x34
T/S
TL -
1 1
/2"
T/SLABEL +37.50'
(E)W12x28
T/STL -1 1/2"
(E)W18x55
T/STL -1 1/2"
16' - 0" 16' - 0"
17' -
6"
SEE NOTE 11
W12x40
T/STL -6"6
S-100
6"
CO
NC
SLA
B
W8x31
T/S
TL -
6"
+WT4x33.5
EXIST. SLAB
11S-101
+W
T 6
x76
BEARING POCKETCONNECTION (TYP)
W8x15
T/S
TL -
6"
W8x15
T/S
TL -
6"
W8x15
T/S
TL -
6"
W8x31
T/STL -6"
W16x50
T/STL -5 1/2"
W8x31
T/S
TL -
5 1
/2"
W8x31
T/S
TL -
5 1
/2"
W8x31
T/STL -5 1/2"
L8x6x1/2 LLV
L8x6x1/2 LLV
4S-101
SIM
5S-101
SIM
5S-101
SIM
5S-101
SIM
11S-101
4S-105
4' - 9"
4' -
11"
1' - 7 1/2"
1' - 7 1/2" 2' - 10 1/4"
7' - 8"
4' -
7 1
/4"
SEE NOTE 11
12S-101
4S-103
5S-103
4' -
4"
5' - 0 1/4" 4 1/4"
SEE NOTE 12
+W
T 6
x76
8' -
2"10' - 9 1/4"
8S-105
9S-148
W8x15
T/S
TL -
6"
+WT6x76
W14x90
T/S
TL -
6"
1
1
1
1
1
876A
E
D
2S-97
1S-97
4' - 9 1/2" 2' - 0" 4' - 9 1/2" 2' - 9 3/4"5' -
1"
4' -
4"
1' -
10"
1' -
0"
1' -
8"
8' -
2"
10' - 9 1/4"
17' -
6"
16' - 0"
1' -
2"
4' -
4"
1' -
10"
6' -
3"
18"x18"x12" DEEP SUMP PITCOORDINATE SIZEW/ ARCH & MEP DWG'S
T/CONCEL 8'-4"
T/CONCEL +14'-1 1/2"
MICROPILES 5 1/2" OD DIA.0.415" WALL THK.39.5 TONS SERVICELOAD CAPACITY(10 THUS)
2' -
0"
3' -
2"
2S-102
6" SOGOVER COMPACTEDGRANULAR FILLSEE S-143
3S-102
4S-102
5S-102
5S-98
COORDINATE MICROPILESLOC W/ ELEVATOR BUFFERLOC - TYP @ 2 LOC
10"
2' -
8"
RAMPT/CONCEL +14'-1 1/2"
6" CONC SLAB
8' - 7 1/4"
7"
2' - 6"
1' -
0"
WALL8" CONC
T/SOGEL +14'-1 1/2"
T/SOGEL +11'-6 1/2"
8" CMUWALL
6" SOG
6" SOG
2#4
#4 @12" OC
COMPACTEDGRANULARFILL (TYP)
1
1
1
1
1/2" PJF
1/2" PJF
7
6" CONC SLABSEE 2/S-103FOR REINF
EXISTCONCSLAB
6" CONC SLABSEE 3/S-103FOR REINF
GYPSUM STUD WALLASSEMBLY, SEE ARCH
T/SLABEL 21.58'
T/SLABEL 25.00'
2#7
8" CMUWALL
DOWELSTO MATCHREINF
MC8
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
RA
KN
MF
100 SOUTH WACKER DRIVE, SUITE 1400CHICAGO, ILLINOIS 60606-4003
STRUCTURAL
D:\T
EM
P\R
EV
IT\1
2354-C
PP
S-S
_A
Abdelrahm
an.r
vt
7/1
2/2
016 4
: 41:0
5 P
M
As indicated
S-98
AREA C - PARTIAL PLANS
148
JUNE 2016
1/4" = 1'-0"2
AREA C - PARTIAL PLAN AT EL +21.58'
1/4" = 1'-0"4
AREA C - PARTIAL PLAN AT EL +42.50'
1/4" = 1'-0"3
AREA C - PARTIAL PLAN AT EL +37.50'
1/4" = 1'-0"1
AREA C - ELEVATOR PIT PARTIAL PLAN
1/4"=1'-0"
4 0 4 8 FT
(S-47) (S-48)
(S-49)
(S-49)
1. ELEVATOR TOWER 8" CMU WALLS SHALL BE REINFORCED WITH #6 @24" OC. REBARS SHALL RUN FULL HEIGHT OF WALL AND THE ENTIRE WALL SHALL BE GROUTED SOLID. PROVIDE DOWELS AT FOUNDATION TO MATCH SIZE AND SPACING OF WALL REINFORCING. PROVIDE BOND BEAMS W/2-#5 SPACED AS SHOWN ON SECTIONS AND MAX @ 48" OC ALONG THE HEIGHT OF THE WALL.
2. FOR PIER REINFORCING SEE DETAIL 9/S-101 . ALL PIER REINFORCING SHALL BE CONTINUOUS THROUGH LINTELS AND BOND BEAMS. PROVIDE DOWELS AT FOUNDATION TO MATCH SIZE AND LOCATION OF PIER REINFORCING.
3. PROVIDE HORIZONTAL JOINT REINFORCEMENT @ 16" OC MAX SEE ARCHITECTURAL DRAWINGS.
4. CONTRACTOR TO SUBMIT TO REPRESENTATIVE OF COMMISSIONER COMPLETE SHOP DRAWINGS SHOWING ALL OPENING W/ LINTEL TYPE INCLUDING REINFORCED CMU LINTELS AND WALL REINFORCING.
5. FOR ELEVATOR DOOR OPENING PROVIDE 24" DEEP BOND BEAM LINTEL WITH 2-#6 IN EACH COURSE, SEE DETAIL 3/S-146 EXTEND LINTEL FROM NORTH TO SOUTH END WALL PIERS.
NOTES:
6. LAY ALL MASONRY WITH FULL BED AND HEAD JOINTS OF MORTAR.
7. SHORE CMU WALLS UNTIL LATERAL SUPPORT IS PROVIDED AT FLOORS AND ROOF LEVELS.
8. FOR TYPICAL DETAILS OF INTERSECTING MASONRY WALLS SEE S-147.
9. FOR CONTROL JOINT LOCATIONS IN CMU WALLS SEE ARCH DRAWINGS.
10. GENERAL CONTRACTOR TO COORDINATE/VERIFY WITH ELEVATOR MANUFACTURER AND PROVIDE INSERTS IN CMU WALLS. PROVIDE 3 COURSES BOND BEAM AT BEARING PLATES OR INSERTS LOCATIONS IN 8" CMU WALL. BOND BEAMS IN 8" CMU WALL TO BE REINFORCED WITH 2-#5 AT EACH COURSE OF BOND BEAM. EXTEND REINFORCEMENT INTO THE END WALLS.
11. ( ) DENOTES 2" COMPOSITE 2VLI16 DECK W/4" LW CONCRETE ON TOP (TOTAL T=6") REINFORCED W/6X6 W2.1XW2.1 WWF (TYP).
12. PROVIDE 3/4" DIA THREADED ROD X30" LONG. INSTALL INTO THE EXISTING BRICK WALL WITH HILTI HIT HY70 W/SCREEN @ 8" OC, MIN EMBED 8".
13. FOR TYPICAL CONCRETE DETAILS SEE DWGS S-143 TO S-145. FOR TYPICAL MASONRY DETAILS SEE DWGS S-146 AND S-147. FOR TYPICAL STEEL DETAILS SEE DWG S-148.
14. SEE MASONRY NOTE #14 ON S-3 FOR CMU WALL REINFORCEMENT (TYP UNO).
NO. DATE APPD DESCRIPTION
1 6/20/16 MF ADDENDUM NO.1
2 7/15/16 MF ADDENDUM NO.3
3/4" = 1'-0"5
SECTION
3/4" = 1'-0"6
SECTION
2
2
X XX X X X X X X
B2 AC1
2S-116
S-116
3
20' - 0" 23' - 10"
1' - 1 7/8"4' - 5" 4' - 5" 4' - 5" 4' - 5"
1' - 2 1/8"5' - 3" 5' - 3" 5' - 3" 5' - 3"
EQUIPMENT CONCRETE PADSEE TYPICAL DETAILS 2/S-144
T/ STLEL 54'-0"
T/ STLEL 54'-4 1/4"
T/ STLEL 53'-3"
NEW W14 BEAM SHIM PLATE(TYP)
NEW W14 BEAM
NEW W16 BEAM
EXISTINGW14 COL
EXISTINGW14 COL
EXISTINGW14 COL
L3x3x1/4 L3x3x1/4
STEEL DECK
DECK WELDTO BEAM DECK WELD
TO ANGLESHIM PLATE(TYP)
T/ SLABEL 54'-6"
STIFF. PLATE
NEW W16BEAM
BENT PL
EXISTING W12 BEAM
TOP FLANGE OFEXIST W12 BEAM
1' - 5"
6B6
1S-116
EXIST W12 BM (TYP)
NEW W14 BEAM
EXISTW12 BEAM
NEW W14BEAM
EXISTING W12 BEAM
NEW W14 BEAM
NEW W16 BEAM
NEW W16 BEAM
NEW W16 BEAM
NEW W10BEAM BEYOND
S-116
4
EXISTINGW14 COL
8' - 0"17' - 0"
T/STLEL 54'-4 1/4"T/ STL
EL 54'-0"SHIMPLATE
L3x3x1/4
T/ SLABEL 54'-6"
T/ STLEL 53'-3"
T/STLEL 53'-3"
DECK WELDTO BEAM
STIFF. PLATE STIFF PLATE
L3x3x1/4
BENT PL
7A
2" DECK W/4" LW CONC (TYP)SEE PLAN
8" CMUWALL
SEE 1/S-121FOR CONN
A
L3x3x1/4
STEEL DECK
SHIMPLATEEXISTING W12 BEAM
DECK WELDTO ANGLE
NEW W14 BEAM
EXISTINGW14 COL.
EXISTING W12BEAM TOP FLANGE
1/2" THKSTIFF. PLATE
REMOVE THE CONCRETEENCASEMENT FOR NEWBEAM CONNECTION
SEATPLATE
1/4"
1/4"
1/4"TYP
T/ STLEL 54'-0"
T/ SLABEL 54'-6"
T/ STLEL 53'-3"
T/ STLEL 54'-4 1/4"
6B
1S-116
EXISTING W14 COL
5 5
/8"
NEW W16 BEAM
EXISTING W12BEAM TOP FLANGE
SHIM PLATE
L3x3x1/4
1/2" THK STIFF. PLATE
DECK WELD TO BEAM
DECK WELD TO ANGLE
NEW W14BEAM
10"
1/2" THKSEAT PLATE
T/ STLEL 54'-0"
T/ SLABEL 54'-6"
T/ STLEL 53'-3"
T/ STLEL 54'-4 1/4"
1/4"
1/4"TYP
1/4"
1/4"
12A
T/CONC SLABEL +27'-6"
4"CONC+2" METAL DECK
#5 @48" DOWELS6" EMBED HILTI HIT-HY200
EXIST W24ENCASED IN CONC
W24
CONT L4x4x3/8
#5 @12"
#5 @12" EW
1/4"
1/4" 2@8"
CONT 3/8" THK BENT PL
FILL WITH COMPRESSIBLEFILLER (TYP)
2'-6"
1"
10 1/2"
5/8" DIA x0'-4"WELDED STUDS@18" OC (TYP) 6
"
SOG
T/SOGEL +11'-0"
1
1
1' - 6"
#4@12" OC
3-#4 BOT
8" CMU WALLSEE ARCH DWG'S
WALL DOWELS TO MATCHSIZE & SPACING W/WALL VERT REINF
TYP
1'-6"
6"
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
RA
KN
MF
100 SOUTH WACKER DRIVE, SUITE 1400CHICAGO, ILLINOIS 60606-4003
STRUCTURAL
D:\T
EM
P\R
EV
IT\1
2354-C
PP
S-S
_A
Abdelrahm
an.r
vt
7/1
2/2
016 4
: 10:0
9 P
M
As indicated
S-116
GENERATOR ROOM – SECTIONS ANDDETAILS
166
JUNE 2016
1/2" = 1'-0"1
SECTION
1/2" = 1'-0"2
SECTION
1" = 1'-0"3
DETAIL
1" = 1'-0"4
DETAIL 1" = 1'-0"
5SECTION
(S-55,S-116)
(S-55,S-116)
(S-116)
(S-116) (S-53)
1"=1'-0"
1 0 1 2 FT
1/2"=1'-0"
01 1 42 3 5 FT
1" = 1'-0"6
TYPICAL INTERIOR MASONRY WALL FOUNDATION SECTION
NO. DATE APPD DESCRIPTION
1 7/15/16 MF ADDENDUM NO.3
1
6B
2' - 6"
2' - 5"
2' - 6" 8' - 0"2' - 0" 1' - 9"
2' - 0"
EXISTINGFOOTING
(E) W14HSS10x10
2" THKBASE PL
1' -
10" 1
1
COMPACTEDBACKFILL (TYP)3/4" DIA EXP ANCHOR
TYP
1' - 0"
TY
P
1' -
0"
2"
TYP1' - 0"
CONT CUT-OFFSHEAR KEY
CONT CUT-OFFSHEAR KEY
T/CONC SLABEL 11'-7'±
4' - 5"
#5@12" DRILL THROUGH &EPOXY GROUTED INTOEXIST CONC
#5@12"DRILL THROUGH & EPOXYGROUTED INTO EXIST CONC
8#5(TYP)
(E) W14
CONCENCASEMENT CONCRETE
ENCASEMENT
NEWFOUNDATION
NEW SOG
1
1
NEW FDN
2' - 0"
EXIST FDN
17' - 2"
NEW FDN
2' - 0"
2"
5S-118
6"
VA
RIE
S
3' -
6"
7A
1' - 6"
11"
6"
6"
3'-
10
"
EL 7'-9"
B2
1
1
1
1
3S-118
EXIST FDN
5' - 0"
EXIST FDN
10' - 3"
NEW FDN
2' - 9"
1' -
4"
6"
2"
6"
1' - 0"
1' -
0"
1' -
0"
5' - 6"
3' - 0"
3' - 0" 6"5' - 6"3' - 0"6"
7' - 6"7' - 6"
1' -
0"
1' -
0"
CONT SHEAR KEY
EXIST W14 COL
EXIST I24 BEAMS
EXIST CONCUNDER COLUMNSHALL REMAIN
EXIST BEAMW18 @ 2'-6" OC
6 NEW BEAMSW6x25 @ 2'-6" OC
6 NEW BEAMSW6x25 @ 2'-6" OC
#5@12" DWLS
NEW 4000 PSI CONCRETE
#5@12" OCDRILL THROUGH &EPOXY GROUTEDINTO EXIST CONC(TYP EW)
#5@12"
TYP DOWELEMBED
EXIST CONCENCASEMENT
EXIST LEANCONCRETE
EXISTINGFOUNDATION
NEW 4000 PSICONCRETE POUR
REMOVE EXIST CONC TOOUTSIDE FACES OF EXISTBEAM TO ALLOW ATTACHMENTOF NEW BEAMS AS SHOWN
B/CONC SLAB11' - 1"
T/CONC SLABEL 11'-7"±
T/FOUND.9' - 11"
1/4" 2@8"
6" EA ENDTYP
1/4"TYP 6
"
EXISTCONC WALL
4' -
0"
6"
1' -
6"
2'-
8"
EL 7'-7"
4' -
0"
NEW SOG
4"
1
6B
4S-118
6S-118
4' - 3"
(E) W14 (E) W14
HSS10X10X1/2
1' -
0"
EXIST I24 BM'S
EXISTW18
W6x25(6 THUS)
NEW 4000 PSICONCRETE POUR
#5@12" OC - DRILLTHROUGH & EPOXYGROUTED INTOEXISTING CONC (TYP)
EXIST LEANCONC
EXISTFDN
TYP
2' - 6"
#5@12"EW
1' -
0"
11
11
NEWSOG
3/4" DIA EXP.ANCHOR 6 1/2"EMBED
2" THKBASE PL
EXISTPEDESTAL
7A
6"
4' - 3"
T/CONC SLABEL 11'-7"±
9"
#5x1'-6" @18" OCDRILL THROUGH &EPOXY GROUT INTOEXIST CONC SLAB(TYP)
2'-
8"
CJ, SEENOTES 1 & 2
EXIST 4" SOG
C1
6B 7A
1' -
5"
1' - 6"
2' - 6" 8' - 0" 2' - 6"
1' - 4"
1' -
4"
5' -
0"
1 1
/2"
1 1/2"
EXISTINGPEDESTAL
EXISTINGCOLUMN
4x 3/4" DIA. KWIK BOLT 3EXP. ANCHORSW/ 6 1/2" EMBED(TYP)
BASE PLSEE DETAIL 7
NEW COL.HSS 10x10x1/2
1' - 6"
1' -
8"
1' - 6"
1' -
8"
EXISTCOLBASE PL
EXISTINGCOLUMN
REMOVED AND REPLACEDSURFACE CONCRETESEE 1/ S-118
B2
6B 7A
1' - 6"
4' - 3" 8' - 0" 4' - 3"
1' - 4"
1' -
4"
3' -
0"
1 1
/2"
EXISTINGPEDESTAL
EXISTINGCOLUMN
(E) W14x150
4x 3/4" DIA. KWIK BOLT 3EXP. ANCHORSW/ 6 1/2" EMBED
BASE PLSEE DETAIL 8
NEW COLHSS 10x10x1/2
1 1/2"1' - 1"
1 1/2"
DO NOT REMOVE EXISTINGCONCRETE WITHIN THIS AREA
2' -
4"
1' -
10"
2' -
4"
1' -
10"
1' - 10"
EXISTING COL.BASE PLATE
DO NOT REMOVE EXISTINGCONCRETE WITHIN THIS AREA
1' - 4"
1' -
4"
1 1
/2"
1 1/2"
4x 3/4" DIA. KWIK BOLT 3EXP. ANCHORSW/ 6 1/2" EMBED (TYP)
BASE PL.16"x16"x2"
NEW COL.HSS 10x10x1/2
1/4TYP
C1
(E) W14
HSS10x10
2" THKBASE PL
1
1
COMPACTEDBACKFILL (TYP)
3/4" DIA EXP ANCHOR
T/CONC SLABEL 11'-7"±
NEWFOUNDATION
1
1
CONCRETEENCASEMENT
EXISTINGFOOTING
3' -
3"
VA
RIE
S
NEW SLABON GRADE
2"
1' - 0"
CONT CUT-OFFSHEAR KEY
6"
EXIST FDN
11' - 3"
NEW FDN
2' - 0"
NEW FDN
2' - 0"
3' - 0"2' - 7 1/2"2' - 0" 3' - 0" 2' - 7 1/2" 2' - 0"#5@12"DRILL THROUGH & EPOXYGROUTED INTO EXIST CONC
#5@12"DRILL THROUGH & EPOXYGROUTED INTO EXIST CONC
8#5(TYP)
10 1
/2"
1' -
9"
EL 7'-9"
3'-
10
"
6"
SEE NOTE5 (TYP)
6"
SEE DET 9 FORWOOD BLOCKINGAT EXCAVATION (TYP)
FOR DOWELSEE SECTION 3 (TYP)
EXCAVATIONLINE (TYP)
2"
1' - 4"
1' -
4"
1 1
/2"
1 1/2"
4x 3/4" DIA. KWIK BOLT 3EXP. ANCHORSW/ 6 1/2" EMBED (TYP)
BASE PL.16"x16"x2"
NEW COL.HSS 10x10x1/2
7" 9"
1
1
4" EXISTSOG
6" NEW SOGTO COMELATER
2x12 WOOD BLOCKINGSEE NOTES 3 & 4
ANCHOR AS REQUIRED
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
RA
KN
MF
100 SOUTH WACKER DRIVE, SUITE 1400CHICAGO, ILLINOIS 60606-4003
STRUCTURAL
D:\T
EM
P\R
EV
IT\1
2354-C
PP
S-S
_A
Abdelrahm
an.r
vt
7/1
2/2
016 4
: 10:1
6 P
M
As indicated
S-118
GENERATOR ROOM – SECTIONS ANDDETAILS
168
JUNE 2016
(S-52,S-118)
1/2" = 1'-0"1
SECTION(S-52)
1/2" = 1'-0"4
SECTION 1/2" = 1'-0"
3SECTION
(S-52,S-118)
1/2" = 1'-0"5
FOOTING TOP VIEW 1/2" = 1'-0"
6FOOTING TOP VIEW
(S-52)
1" = 1'-0"7
BASE PLATE 1 - DETAIL
1/2" = 1'-0"2
SECTION
1" = 1'-0"8
BASE PLATE 2 - DETAIL
1"=1'-0"
1 0 1 2 FT
1/2"=1'-0"
01 1 42 3 5 FT
(S-118)
(S-118)
NOTES:
1. RETROFIT FOR FOOTING SHALL BE DONE IN TWO STAGES. THE EXCAVATION AT THE TOE OF THE RETAINING WALL SHOWN IN SECTION 4 SHALL MATCH THE EXTENT OF THE WORK ON THE FOOTING AND SHALL BE BACKFILLED BEFORE THE SECOND STAGE IS STARTED.
2. THE NEW REBARS ALONG THE EAST-WEST DIRECTION SHALL BE PROVIDED WITH COUPLERS TO MAINTAIN THEIR CONTINUITY.
3. TO PREVENT EROSION OF SOIL FROM UNDERNEATH THE EXISTING SLAB ON GRADE, CONTRACTOR SHALL INSTALL WOOD BLOCKING AS SHOWN. THIS SHALL BE REMOVED BEFORE BACKFILLING OPERATIONS ARE DONE AND NEW SLAB ON GRADE POURED.
4. WHEN FOOTINGS ARE RETROFFITED IN THE GENERATOR BASEMENT, THERE SHALL BE NO LIVE LOAD (MATERIAL STOCKPILES OR HEAVY EQUIPMENT) PLACED ON THE SLAB-ON-GRADE ADJACENT TO THE CUT LOCATIONS.
5. FOR WATERSTOP AND VAPOR RETARDER, SEE 9/S-144. 1" = 1'-0"
9DETAIL
(S-118) (S-118)
NO. DATE APPD DESCRIPTION
1 7/15/16 MF ADDENDUM NO.3
1
AFF ABOVE FINISH FLOORAL ALUMINUMB/ BOTTOM OFCCCW CAPILLARY CRYSTALLINE CEMENTITIOUS WATERPROOFINGCOL COLUMNCONC CONCRETECMU CONCRETE MASONRY UNITCONT CONTINUOUSCRCT CHEMICAL RESISTANT CONCRETE TOPPINGCTR CENTERCL CENTER LINECTSK COUNTERSUNKCJ CONTROL JOINTCSU CAST STONE UNITFB FACE BRICKDIA DIAMETERDIM DIMENSIONDN DOWNDPC DUST PROOF COATINGDWG DRAWINGEA EACHEL ELEVATIONEQ EQUALEPDM ETHYLENE PROPYLENE DIENE
MONOMEREJ EXPANSION JOINTEXP EXPOSEDEXT EXTERIORFE FIRE EXTINGUISHERFD FLOOR DRAINFDR FABRIC DOORFLR FLOORFLTR FILTERFP FIREPROOFINGFRJS FIRE RATED JOINT SYSTEMFR FRAMEFRP FIBER REINFORCED PLASTIC
(FIBERGLASS)GA GAUGEGLV GALVANIZEDGR GRADEGT GLAZING TYPEHDCT HIGH DENSITY CONCRETE TOPPINGHVAC HEATING VENTILATION AND
AIR CONDITIONINGHT HEIGHTHPT HIGH POINTHM HOLLOW METALHORIZ HORIZONTALHR HOURINSUL INSULATIONINT INTERIORIPS IRON PIPE SIZEJT JOINTLPT LOW POINTMAT MATERIALMAX MAXIMUMMECH MECHANICALMIN MINIMUMMO MASONRY OPENINGML MATCH LINENC NON-COMBUSTIBLENIC NOT IN CONTRACTNOM NOMINALNO NUMBEROC ON CENTEROCV ON CENTER VERTICALLYOCH ON CENTER HORIZONTALLYOHCD OVERHEAD COILING DOOROPP OPPOSITEOPNG OPENINGPC PRECASTPFCMU PRE-FACED CONCRETE
MASONRY UNITPTD PAINTEDPVC POLYVINYL CHLORIDEREINF REINFORCEMENTRD ROOF DRAINRM ROOMSATC SUSPENDED ACOUSTICAL
TILE CEILINGSBS STYRENE BUTADIENE STYRENESGU STRUCTURAL GLAZED UNIT
(STRUCTURAL GLAZED BRICK, (STRUCTURAL GLAZED TILE)SIM SIMILARSPECS SPECIFICATIONSSS STAINLESS STEELSTD STANDARDSTL STEELT/ TOP OFTWP TRANSLUCENT WALL PANELTYP TYPICALU.O.N UNLESS OTHERWISE NOTEDVCT VINYL COMPOSITION TILEVERT VERTICALVEST VESTIBULEVRC VERTICAL RECIPROCATING
CONVEYORVYNL VINYLW/ WITHW/O WITHOUT
ABBREVIATIONS
ELEVATION CALLOUT
SECTION CALLOUT
DETAIL CALLOUT
DETAIL BOUNDARYCALLOUT
COLUMN CENTER LINE
WALL TYPE
WINDOW TYPE
DOOR TYPE
ROOM NAMEAND NUMBER
FLOOR ELEVATION
FIRE EXTINGUISHERLOCATIONS ON PLANS
EGRESS PATH ANDTRAVEL DISTANCE(300') MAXIMUM ALLOWED
VAPOR BARRIER
SYMBOLS
EXTENT OFDEMOLITION WORK
SIGNAGE TYPE
FURNITURE TYPE
E.01A3.00
Room name
101
VIEW NAMESCALE: 1/8" = 1'-0"
1R101
NameElevation
1
A101
SIM
1i
1t
101C
VIEW TITLE
1A101
1A101
04
SIM
MATCHLINEML
00
000
INTERIOR ELEVATIONCALLOUT
FE
FACE BRICK STYLE TYPE01
EXISTING WALL
SPRAY-ON FIREPROOFING
1. CONDITIONS AFFECTING THE WORK: BEFORE PROCEEDING WITH THE WORK THOROUGHLY EXAMINECONDITIONS AT THE PROJECT SITE TO ENSURE THAT THE WORK CAN PROCEED IN ACCORDANCE WITH THECONTRACT DOCUMENTS. REPORT CONDITIONS FOUND WHICH WILL ADVERSELY AFFECT THE WORK TO THEOWNER AND THE COMMISSIONER PRIOR TO PROCEEDING WITH THE WORK.
2. DIMENSIONS: UNLESS OTHERWISE SHOWN OR INDICATED, DIMENSIONS SHOWN ON ARCHITECTURALDRAWINGS ARE INDICATED TO FACE OF MASONRY.
3. DIMENSIONAL VERIFICATION: BEFORE PROCEEDING WITH ANY WORK VERIFY ALL ASSOCIATEDDIMENSIONS. REPORT ANY DIMENSIONAL VARIATIONS BETWEEN FIELD CONDITIONS AND PROPOSED WORKWHICH WILL ADVERSELY AFFECT THE WORK TO THE COMMISSIONER PRIOR TO PROCEEDING. DO NOT SCALEDRAWINGS. WRITTEN DIMENSIONS TAKE PRECEDENCE
4. NOTES: NOTES APPEAR ON VARIOUS DRAWINGS FOR DIFFERENT SYSTEMS AND MATERIALS. REVIEWALL SHEETS AND APPLY NOTES TO RELATED BUILDING COMPONENTS. REFER TO COMPLETE SET OF ISSUEDCONTRACT DOCUMENTS FOR OTHER APPLICABLE NOTES, ABBREVIATIONS, AND SYMBOLS.
5. GRAPHIC REPRESENTATION: ITEMS NOT NOTED ON DRAWINGS ARE TO BE CONSIDERED THE SAME ASNOTED ITEMS WHICH ARE GRAPHICALLY REPRESENTED IN THE SAME MANNER, UNLESS OTHERWISE NOTED.
6. DISSIMILAR METALS: ISOLATE DISSIMILAR METALS TO PREVENT GALVANIC ACTION.
7. ANCHORAGE OF SYSTEMS: ANCHOR DOORS, WINDOWS, LOUVERS, CURTAIN WALLS, CLADDING, ETC.TO STRUCTURAL ELEMENTS OR MASONRY WALLS. DO NOT ANCHOR TO BLOCKING, VENEERS OR FINISHES.
8. ADJACENT WORK: WHERE MATERIALS ARE APPLIED TO, OR ARE IN DIRECT CONTACT WITH WORKINSTALLED BY ANOTHER SUBCONTRACTOR, COMMENCEMENT OF WORK IMPLIES ACCEPTANCE OF THESUBSTRATES AS SUITABLE FOR THE APPLICATION INTENDED.
9. DOORS: PROVIDE ALL DOOR OPENINGS 8" FROM INTERSECTING WALLS IN MASONRY WALLS AND 12"FROM INTERSECTING WALLS IN CONCRETE WALLS UNLESS OTHERWISE NOTED.
10. MASONRY BACK-UPS: SEE STRUCTURAL DRAWINGS FOR DESIGN OF CMU AND CONCRETE BACK-UPS.
11. RATED CONSTRUCTION: PROVIDE PARTITION TYPES AND FIRE RESISTIVE RATINGS INDICATED ON AWALL TO BE CONTINUOUS FOR THE LENGTH AND HEIGHT OF THE PARTITION. MAINTAIN FIRE RATING OFCONSTRUCTION AROUND CABINETS, PANELS, AND BOXES RECESSED IN FIRE RATED WALLS, FLOORS ANDCEILING ASSEMBLIES.
12. RATED FINISHES: ALL INTERIOR FINISHES MATERIALS ARE CLASS A.
13. RATED PENETRATIONS: SEAL OPENINGS IN RATED WALLS, FLOORS, CEILINGS AND ROOF ASSEMBLIESWITH PENETRATION SEALANT SYSTEMS MEETING OR EXCEEDING THE REQUIRED FIRE RESISTIVE RATINGS.
14. FIRESTOPPING AT CONCEALED SPACES: PROVIDE FIRESTOPPING AT CONCEALED SPACES WITHINPARTITIONS, WALLS, FLOORS, ROOFS, STAIRS, FURRING, PIPE SPACES, COLUMN ENCLOSURES, ETC.
15. FIRE SAFING: PROVIDE CONTINUOUS PERIMETER FIRE SAFING BETWEEN FLOORS AND COORDINATETHE INSTALLATION WITH THE EXTERIOR WALLS. MATCH FIRE RATING OF SAFING WITH FIRE RATING OFFLOOR CONSTRUCTION
16. FALL PROTECTION: PROVIDE GUARDS AT ELEVATION CHANGES OF MORE THAN 30” UNLESSOTHERWISE NOTED.
17. GAPS ADJACENT TO EQUIPMENT: PROVIDE CLOSURE PLATES, ANGLES AND OTHER MATERIALS ASREQUIRED TO ENSURE THAT NO GAP BETWEEN ANY EQUIPMENT AND THE FLOOR OR ADJACENT WALKINGSURFACE IS GREATER THAN 1-INCH.
18. OTHER DISCIPLINES: SEE STRUCTURAL DRAWINGS FOR NOTES REFERRING TO LIVE AND DEAD LOADS,STRUCTURAL WORK, AND FOUNDATIONS. SEE MECHANICAL DRAWINGS FOR HVAC AND PLUMBING WORK. SEEELECTRICAL DRAWINGS FOR ELECTRICAL WORK.
19. BELOW GRADE WALL INSULATION: PROVIDE 1 1/2-INCH (R 7.5 MIN) BELOW GRADE WALL INSULATIONWHERE INDICATED IN PLAN.
20. ADA COMPLIANCE: TO THE GREATEST EXTENT FEASIBLE, EXISTING FACILITIES HAVE BEEN ALTERED INSUCH MANNER THAT THE ALTERED PORTION OF THE FACILITY IS USABLE BY INDIVIDUALS WITH DISABILITIES.ALERT COMMISSIONER OF STRUCTURAL IMPEDIMENTS PREVENTING COMPLIANCE WITH ADA PROVISIONSIDENTIFIED IN DRAWINGS.
GENERAL NOTES
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
12: 4
9:18
PM
A-1
JJS
GENERAL NOTES, SYMBOLS ANDABBREVIATIONS & PERSPECTIVES
206
ARCHITECTURE
JL
TCB
MAY 2016
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
EXISTING RAILTO BE RESTORED
MECHANICALLY FASTENED 1/4" X 4" STL PLATEPAINTED TO MATCH RAIL
VE
RIF
Y I N
FIE
L D
3' -
6"
EXISTINGELECTRICAL FIXTURE
EXISTING POST TO BERESTORED
AFTER REMOVAL OF RAIL, PREPARESURFACE FOR REINSTALLATION -VERIFY ALL ANCHOR POINTS ARESOUND AND TRUE. REPAIR ASNEEDED
10' -
6"
EXISTING RAILTO BE RESTORED
MECHANICALLY FASTENED 1/4" X 4" STL PLATEPAINTED TO MATCH RAIL
EXISTINGELECTRICAL FIXTURE
EXISTING POST TO BERESTORED
AFTER REMOVAL OF RAIL, PREPARESURFACE FOR REINSTALLATION -VERIFY ALL ANCHOR POINTS ARESOUND AND TRUE. REPAIR ASNEEDED
1' -
6"
1' -
6"
3' -
0"
NEWLY EXPOSEDEXISTING TERRACOTTASEE RESTORATIONNOTES 7 AND 8
EXISTING BUILDINGBRICK
EXISTING FACE BRICK
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 0
7:58
AM
A-6
JJS
MASONRY AND TERRACOTTARESTORATION DETAILS
211
ARCHITECTURE
JL
TCB
MAY 2016
RESTORATION NOTES:1. REMOVE EXISTING HISTORIC RAILS FROM PUMP ROOM AND
STORE SAFELY AWAY FROM ANY ELEMENT THAT MIGHT CAUSEDAMAGE.
2. REMOVE AND STORE ELECTRICAL FIXTURE AND ALL OF ITSCOMPONENTS. SEE ELECTRICAL DRAWINGS FOR HANDLING ANDSTORING.
3. RAILS SHOULD BE BLAST CLEANED AND REPAINTED - SEE HZDRAWINGS.
4. REPLACE ANY DAMAGED COMPONENTS - USE SALVAGED RAILSNOT USED FOR REINSTALLATION FOR COMPONENTREPLACEMENT.
5. REPAINT RAILS ACCORDING TO SPECIFICATIONS - COLOR TO BESELECTED BY THE COMMISSIONER.
6. REINSTALL RAILS WITH STAINLESS STEEL ANCHOR BOLTSPROVIDING PERFORMANCE REQUIREMENTS PER CODE.
7. REMOVE PAINT PER SPECIFICATION AND SEE HZ DWG8. PATCH AND RESTORE TERRACOTTA PER SPECIFICATION9. PROVIDE NEW COMPASS ROSE BASED ON LASER CUT PLASTIC
OF CUSTOM PIECES.10. COMPASS ROSE ORIENTATION IS TO MATCH PLANTS TRUE
NORTH.11. PROVIDE SAMPLE LETTERS FOR COMPASS ROSE ORIENTATION
(N,S,E,W). COMPASS ROSE ORIENTATION LETTERS ARE TO BESELECTED BY THE COMMISSIONER.
SCALE: 1" = 1'-0"2
EXISTING RAILING TO BE RESTORED - CONDITION 1
1/2"=1'-0"01 1 42 3 5 FT
1"=1'-0"1 0 1 2 FT
SCALE: 1/2" = 1'-0"1
COMPASS ROSE RESTORATION
SCALE: 1" = 1'-0"3
EXISTING RAILING TO BE RESTORED - CONDITION 2
SCALE: 3/4" = 1'-0"4
TERRACOTTA RESTORATION
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
1
DOOR TYPE 1 DOOR TYPE 2
M.O.
M.O
.
DOOR TYPE 4
NOTE:1. GLAZING IN NON RATED DOOR TO BE GT-22. GLAZING IN RATED DOORS TO BE GT-53. SEE SCHEDULE FOR WIDTH AND HEIGHT OF M.O.4. SEE SCHEDULE FOR DIMENSION OF FR.5. ALL RATED DOORS TO BE PROVIDED CLOSERS.ADDITIONALLY, SEE HGARDWARE SPECIFICATION FORREQUIREMENT FOR CLOSERS AT NON-RATEDDOORS.6. ALL DOORS ARE KEYLESS IN THE DIRECTION OFEGRESS.7. GLAZING IN DOORS TO BE SAFETY TYPE, SEESPECIFICATIONS.
DOOR TYPE 3
EQ EQ VARIES 3' - 0"FR
VARIESFR
M.O
.
M.O.
8" 1' - 8"
3' -
6"3'
- 4"
10"
6"
8" 1' - 8"
3' -
6"3'
- 4"
DOOR TYPE 7 DOOR TYPE 8 DOOR TYPE 9
8"
DOOR TYPE 5
FRVARIES
FR FRVARIES
FR
1' - 2"
M.O
.
M.O.
M.O
.
M.O.
EQ EQ
EQEQ
M.O
.
M.O.
M.O
.
M.O.
M.O
.
M.O
.
M.O.M.O.
FRVARIES
FR FRVARIES
FREQ EQ
FRVARIES
FR
FRVARIES
FR
FRVA
RIE
S
FRVA
RIE
S
VAR
IES
FR FRVA
RIE
S
6" 6"
VAR
IES
FR
VAR
IES
FR
VAR
IES
FR
DOOR TYPE 6
EQ EQ
FRVARIES
FR
M.O
.
M.O.
VAR
IES
FR
5' -
7"
1' -
0"
EQ EQ
EQ EQ1' - 2" 8"
1' -
0"
1' - 2"8"
FINISHEDFLOOR
CARDREADER
DOORLEAF
ELECTRIFIEDLOCK
ELECTRIFIEDHINGE (TYP)
CONDUIT (TYP)
JUNCTIONBOX (TYP)
FINISHED CEILING(WHERE APPLICABLE)
SECURED SIDE UNSECURED SIDE
FINISHED CEILING(WHERE APPLICABLE)
SECURED SIDE UNSECURED SIDE
FINISHEDFLOOR
CARDREADER
DOORLEAF
ELECTRIFIEDLOCK
ELECTRIFIEDHINGE (TYP)
CONDUIT (TYP)
JUNCTIONBOX (TYP)
3' -
8" 8 1/8"
SEE FIRE PROTECTION, HVAC, ELECTRICAL DRAWINGS FOR COMPONENTS REQUIRED ATEACH DOOR. ELEVATIONS SHOWS ALL POSSIBLE COMPONENTS AT EACH DOOR. PLACEALL COMPONENTS IN ORDER SHOWN FROM DOOR JAMB AT LEVER SIDE AND FROMFINISHED FLOOR. IF NOT ALL COMPONENTS ARE REQUIRED AT DOOR, DELETE THOSECOMPONENTS AND SHIFT ALL OTHERS TOWARD DOOR JAMB TO FILL THOSE SPACES. ATDOORS WITHOUT WALL SPACE DIRECTLY ADJACENT TO DOOR LEVER, PLACECOMPONENTS ON WALL PERPENDICULAR TO DOOR.
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt
A-9
JJS
SCHEDULES AND DETAILS - SHEET 1 -DOORS
214
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 3/8" = 1'-0"3
DOOR AND FRAME TYPES
DOOR SCHEDULE
ROOM NO.DOOR
NO. TYPE
ROUGH OPENING DOOR FRAMEUL
LABEL
FIRERATING
(HR) HARDWARE COMMENTSWIDTH HEIGHT THICKNESS MTL JAMB HEAD MTLAREA A
100 2 7 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I100 1 4 12' - 0" 10' - 0" A-11 -- -- MOTOR OPERATED OHCD WITH SCREEN
AREA B117 1 3 5' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- -- UNEVEN DOOR PANELS117 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I117 3 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I121 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3 SIGNAGE - TYPE I121 2 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- --207 1 1 3' - 4" 7' - 4" 1 3/4" STL STL A 3 SIGNAGE - TYPE I207 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I207 3 4 9' - 8" 10' - 0" A-11 -- -- -- MANUAL/ CHAIN OPERATED OHCD - WALL
MOUNTED
R1 2 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- -- SIGNAGE - TYPE IAREA C
B106 1 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3B107 1 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3101 1 2 6' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --102 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4103 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --104 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --105 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- SIGNAGE - TYPE I106 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --107 1 7 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4108 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL B 1 1/2108 2 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --109 1 4 10' - 0" 14' - 0" -- A-11 -- -- -- MOTOR OPERATED OHCD - WALL MOUNTED109 2 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3109 3 4 10' - 0" 10' - 0" -- A-11 -- A 3 MOTOR OPERATED OHCD - WALL MOUNTED110 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3111 1 7 3' - 4" 8' - 0" 1 3/4" STL -- 4/A-10 STL C 3/4111 2 9 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- SIGNAGE - TYPE I112 1 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - NOT AN EXIT - BOTH SIDES
112B 1 2 6' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3 KNURLEDHARDWARE
112B 2 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 A 3112B 3 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3113 1 7 6' - 4" 8' - 0" 1 3/4" STL STL C 3/4
113B 1 9 3' - 4" 8' - 0" 1 3/4" STL -- 4/A-10 STL -- --114 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- --115 1 9 3' - 4" 8' - 0" 1 3/4" STL -- 4/A-10 STL -- --116 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- --201 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- KNURLED
HARDWARE
201 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I202 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --204 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --205 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --206 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --210 1 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I220 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --221 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- KNURLED
HARDWARE
R1 2 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL -- -- SIGNAGE - TYPE IAREA D
B102 1 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE IB102 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE IB102 3 4 14' - 0" 10' - 0" -- A-11 -- A 3 MOTOR OPERATED - 3HR RATEDB103 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4B103 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - DANGER -CONFINED SPACE- ENTER
BY PERMIT ONLY
B104 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4B109 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4B110 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4B110 2 1 3' - 4" 8' - 0" 1 3/4" STL 7/A-10 SIM TO JAMB STL A 3B111 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4B113 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --B115 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I122 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3122 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - NOT AN EXIT123 1 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3123 2 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3124 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 CLASS A FIRE DOOR - 1 DR AUTOMATIC-OTHER
DR AUTOMATIC OR SELF-CLOSING
124 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - NOT AN EXIT124 3 4 12' - 0" 14' - 0" -- A-11 -- -- -- MOTOR OPERATED OHCD WITH SCREEN124 4 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3 SIGNAGE - NOT AN EXIT125 1 2 6' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --208 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I208 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3208 3 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL A 3 SIGNAGE - TYPE I208 4 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3209 1 6 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- --209 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I211 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I211 2 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL A 3 SIGNAGE - TYPE I224 1 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL B 1 1/2 SIGNAGE - NOT AN EXIT301 1 8 6' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- -- SIGNAGE - TYPE I301 2 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL A 3 SIGNAGE - TYPE I301 3 1 3' - 4" 8' - 0" 1 3/4" STL 1/A-10 2/A-10 STL A 3 SIGNAGE - TYPE I302 1 5 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL B 1 1/2 SIGNAGE - TYPE I322 1 1 3' - 4" 8' - 0" 1 3/4" STL 7/A-10 SIM TO JAMB STL A 3 SIGNAGE - TYPE IR3 1 1 3' - 4" 7' - 4" 1 3/4" STL 5/A-10 6/A-10 STL -- -- SIGNAGE - TYPE IR3 2 1 3' - 4" 7' - 4" 1 3/4" STL 5/A-10 6/A-10 STL -- -- SIGNAGE - TYPE IR3 3 1 3' - 4" 7' - 4" 1 3/4" STL 5/A-10 6/A-10 STL -- -- SIGNAGE - TYPE I
AREA E126 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- SIGNAGE - TYPE I126 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I127 1 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2128 1 2 6' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --128 2 7 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL -- -- SIGNAGE - TYPE I128 3 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I129 1 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I129 2 2 6' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --130 1 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2130 2 6 10' - 0" 10' - 0" -- A-11 -- B 1 1/2 MOTOR OPERATED OHCD - WALL MOUNTED130 3 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2130 4 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3 SIGNAGE - TYPE I130 5 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE I131 1 8 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL C 3/4132 1 2 6' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2132 2 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2133 1 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --133 2 5 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL B 1 1/2 SIGNAGE - TYPE IR2 1 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL -- --
AREA FCEE 1 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL A 3CEE 2 4 16' - 0" 12' - 0" -- A-11 -- A 3 MANUAL/ CHAIN OPERATED OHCDCEE 3 1 3' - 4" 8' - 0" 1 3/4" STL 10/A-10 11/A-10 STL A 3CEW 1 1 3' - 4" 8' - 0" 1 3/4" STL 5/A-10 6/A-10 STL A 3CEW 2 4 16' - 0" 12' - 0" -- A-11 -- A 3 MANUAL/ CHAIN OPERATED OHCD
1/4"=1'-0"4 0 4 8 FT
1 1/2"=1'-0"1 0 1 FT
DOOR SCHEDULE NOTES:1. SIGNAGE TYPE I TO BE MOUNTED ON OPPOSITE FACE
OF DOORS IN RELATION TO THE DIRECTION OFEGRESS. REFER TO LIFE SAFETY SHEETS.
SCALE: 1/8" = 1'-0"1
ELECTRIFIED DOOR HARDWARE
SCALE: 3/8" = 1'-0"2
DOOR SECURITY COMPONENTS
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 4
6:37
AM
A-12
JJS
SCHEDULES AND DETAILS - SHEET 4 -ROOMS AND OPENINGS
217
ARCHITECTURE
JL
TCB
MAY 2016
OPENING SCHEDULE
TYPER.O.
QTY MAT FINISHDETAILS
COMMENTSWIDTH HEIGHT HEAD JAMB SILL1 9' - 10" 9' - 9" 5 AL CLEAR ANODIZED 12/ A-88 3/ A-91 11/A-88 LOUVER WITH SECURITY GRILL2 9' - 10" 8' - 3" 5 AL CLEAR ANODIZED 12/ A-88 SIM 3/ A-91 13/A-88 LOUVER WITH SECURITY GRILL3 9' - 10" 9' - 1" 1 AL CLEAR ANODIZED 14/ A-88 3/ A-88 13/A-88 SIM LOUVER4 4' - 3" 9' - 9" 3 AL CLEAR ANODIZED 12/ A-88 3/ A-91 11/A-88 LOUVER WITH SECURITY GRILL5 4' - 3" 8' - 3" 3 AL CLEAR ANODIZED 12/ A-88 SIM 3/ A-91 13/A-88 LOUVER WITH SECURITY GRILL6 11' - 8" 11' - 8" 2 AL CLEAR ANODIZED 10/A-88 11/ A-90 9/ A-88 LOUVER8 3' - 11" 1' - 0" 1 AL CLEAR ANODIZED 12/ A-88 SIM 3/ A-88 15/A-88 SIM LOUVER9 10' - 0" 3' - 7" 3 AL CLEAR ANODIZED 16/A-88 2/ A-88 15/A-88 LOUVER10 3' - 0" 3' - 0" 1 AL CLEAR ANODIZED 12/ A-88 SIM 3/ A-88 15/A-88 SIM LOUVER
ROOM FINISH SCHEDULEROOM
NUMBER ROOM NAME FLOOR ELEVFINISH CEILING
HEIGHT COMMENTSFLOOR BASE WALL CEILINGAREA A
B101 PUMP ROOM -18.00 HDCT HDCT PTD PTD INCLUDING PUMP PLATFORMS 1-5100 MAINTENANCE OBSERVATION 25.00 EXISTING EXISTING EXISTING EXISTING
AREA BSTAIR D STAIR D 33.00 PTD -- PTD PTD
117 STORAGE 20.00 PTD VYNL PTD PTD119 STORAGE 25.00 PTD VYNL PTD PTD121 EXIT CORRIDOR 20.00 PTD VYNL PTD PTD
STAIR D STAIR D 20.00 PTD -- PTD PTD207 LOW VOLTAGE SWITCHGEAR 33.00 PTD VYNL PTD PTD
AREA CSTAIR A STAIR A 42.50 PTD -- PTD PTD
B106 POINT OF ENTRY ROOM 14.04 PTD HDCT PTD/GYPSUM
PTD PROVIDE GYPSUM OVER PLYWOODFINISHED WALL
B107 BOILER ROOM 11.00 PTD VYNL PTD PTDB113 ELEVATOR CONTROL ROOM 11.00 PTD VYNL PTD PTDB114 FREIGHT ELEVATOR PTD VYNL PTD PTD
STAIR A STAIR A 21.58 PTD -- PTD PTD101 ENTRY LOBBY 21.58 HDCT HDCT PFCMU SATC 10' - 0"102 SECURITY OFFICE 21.58 HDCT HDCT PFCMU SATC 9' - 0"103 TOILET 21.58 HDCT HDCT PFCMU SATC 9' - 0"104 STORAGE 21.58 HDCT HDCT PFCMU SATC 9' - 0"105 CORRIDOR 21.58 HDCT HDCT PFCMU SATC 10' - 0"106 TOILET 21.58 HDCT HDCT PFCMU SATC 9' - 0"107 LUNCH ROOM 21.58 HDCT HDCT PFCMU SATC 9' - 0"108 EXIT CORRIDOR 21.58 PTD VYNL PTD PTD109 LOADING DOCK 21.58 PTD VYNL PTD PTD110 LUBE OIL STORAGE 21.58 PTD VYNL PTD PTD111 BREAK/ MEETING ROOM 21.58 HDCT HDCT PFCMU SATC 10' - 0"112 CORRIDOR 21.58 HDCT HDCT PFCMU SATC 10' - 0"
112B UPPER CORRIDOR 25.00 HDCT HDCT PFCMU SATC 9' - 0"113 CONTROL ROOM 25.00 HDCT HDCT PFCMU SATC 9' - 0"
113 B SECURITY SERVER ROOM 25.00 HDCT HDCT PTD/GYPSUM
SATC 9' - 6" PROVIDE GYPSUM OVER PLYWOODFINISHED WALL
114 SCADA SERVER ROOM 25.00 HDCT HDCT PTD/GYPSUM
SATC 9' - 6" PROVIDE GYPSUM OVER PLYWOODFINISHED WALL
115 CHIEF'S AND ASST CHIEF'S OFFICE 25.00 HDCT HDCT PFCMU SATC 9' - 0"116 TOILET 25.00 HDCT HDCT PFCMU SATCOTB BOILER ROOM 11.00 PTD VYNL PTD PTD
STAIR A STAIR A 27.50 PTD -- PTD PTD201 FIRE PREVENTION ROOM 37.50 PTD VYNL PTD PTD202 LOCKER ROOM NO2 37.50 HDCT HDCT PFCMU SATC 9' - 0"204 JANITOR 37.50 PTD VYNL PTD PTD205 LOCKER ROOM NO1 37.50 HDCT HDCT PFCMU SATC 9' - 0"206 ARCHIVES 37.50 PTD VYNL PFCMU SATC 9' - 0"220 STORAGE 37.50 PTD VYNL PFCMU SATC 9' - 0"223 VESTIBULE 42.50 PTD VYNL PTD PTD/GYPSUM 9' - 0"
STAIR A STAIR A 37.50 PTD -- PTD PTD303 VESTIBULE HDCT HDCT PFCMU SATC 9' - 0"
STAIR A STAIR A 54.50 PTD -- PTD PTDAREA D
212 VESTIBULE HDCT PFCMU SATC 9' - 0"STAIR E STAIR E 21.58 PTD -- PTD PTD
HVAC PLENUM 11.00 PTD VYNL PTD PTDMECHANICAL SHAFT 11.00 PTD VYNL PTD PTDSTORAGE (STACK) 33.00 PTD VYNL PTD PTD
B102 CORRIDOR 11.00 PTD VYNL PTD PTDB103 PARTS ROOM 11.00 PTD VYNL PTD PTDB104 WELDING SHOP 11.00 PTD VYNL PTD PTDB105 WELDING STORAGE 11.00 PTD VYNL PTD PTDB109 ELECTRICAL SHOP 11.00 PTD VYNL PTD PTD
B109-B ELECTRICAL STORAGE 11.00 PTD VYNL PTD PTDB110 EXIT CORRIDOR 18.08 PTD VYNL PTD PTDB110 MECHANICAL SHOP 11.00 PTD VYNL PTD PTD
B110-B MECHANICAL STORAGE 11.00 PTD VYNL PTD PTDB111 PIPE FITTER SHOP 11.00 PTD VYNL PTD PTD
B111-B PIPE FITTER STORAGE 11.00 PTD VYNL PTD PTDB112 VRC 11.00 PTD VYNL PTD PTDB115 FUEL RETURN TANK ROOM 11.00 PTD VYNL PTD PTD
STAIR B STAIR B 11.00 PTD -- PTD PTDSTAIR C STAIR C 11.00 PTD -- PTD PTD
122 CORRIDOR 27.50 PTD VYNL PTD SATC 9' - 0"123 PARALLELING SWITCHGEAR ROOM 27.50 PTD VYNL PTD PTD124 GENERATOR ROOM 27.50 PTD VYNL PTD PTD125 STORAGE 20.00 PTD VYNL PTD PTD208 CORRIDOR 42.50 PTD VYNL PTD SATC 10' - 0"
STAIR B STAIR B 27.50 PTD -- PTD PTDSTAIR C STAIR C 27.50 PTD -- PTD PTDSTAIR F STAIR F PTD -- PTD PTD
209 MECHANICAL ROOM NO1 42.50 PTD VYNL PTD PTD210 CORRIDOR 37.50 PTD VYNL PTD SATC 10' - 0"211 EXIT CORRIDOR 42.50 PTD VYNL PTD PTD221 MECHANICAL ROOM NO 3 37.50 PTD VYNL PTD PTD222 FUEL OIL STORAGE AREA 35.00 PTD VYNL PTD PTD224 STORAGE 32.00 PTD VYNL PTD PTDOTB GENERATOR ROOM 42.50 PTD VYNL PTD PTD
STAIR B STAIR B 42.50 PTD -- PTD PTD301 CORRIDOR 54.50 PTD VYNL PTD SATC 10' - 0"302 MECHANICAL ROOM NO. 2 54.50 PTD VYNL PTD PTDOTB GENERATOR ROOM 54.50 DPC VYNL GLAZED
BRICKPTD
401 ROOF ACCESS AREA 81.33 PTD VYNL PTD PTDAREA E
126 BATTERY ROOM 21.58 PTD VYNL PTD PTD127 BATTERY CHARGER ROOM 21.58 PTD VYNL PTD PTD128 VESTIBULE 21.58 PTD VYNL PTD PTD129 CORRIDOR 21.58 PTD VYNL PTD PTD130 VFD ROOM 21.58 PTD VYNL PTD PTD131 MEDIUM VOLTAGE SWITCHGEAR ROOM 21.58 PTD VYNL PTD PTD132 ELECTRICAL STORAGE 21.58 PTD VYNL PTD PTD133 CORRIDOR 21.58 PTD VYNL PTD PTD
AREA F01 WEST ROOM 21.58 PTD VYNL PTD PTD02 EAST ROOM 21.58 PTD VYNL PTD PTD
NOTES:1. CLEAN AND RESTORE ALL EXISTING MASONRY
SURFACES TO REMAIN.2. WHERE PAINTED, STRIP MASONRY WALLS - SEE HZ
DRAWINGS - AND REPAINT PER SPECIFICATIONS.3. PROVIDE MOISTURE RESISTANT CERAMIC SATC AT
LOCKER ROOMS AND SHOWERS
NO. DATE APPD DESCRIPTION1 6/20/16 TCB ADDENDUM NO. 12 07/15/16 TCB ADDENDUM NO. 3
1
2
2
DNDN
DN
D
6A 7 8 9
E
F
G
5
MA
TC
HLI
NE
- S
EE
DR
AW
ING
1 /
A-2
1 F
OR
CO
NT
INU
AT
I ON
MATCHLINE - SEE DRAWING1 / A-26 FOR CONTINUATION
DEMOLISHCONCRETE STAIRS
ELECTIRCAL SHOP
STORAGE
18' - 11" 16' - 0" 16' - 0" 16' - 0"
17' -
6"
17' -
8"
17' -
6"
14.10'
E9
G2
D
6A 7 8 9 10
E
F
G
ML
ML
LOADINGDOCK
TOILET
LOADING DOCK
GENERATOR ROOM
ELECTRICAL SHOP
ASSIT. CHIEFOPERATING
ENGINEER'S OFFICE
TOILET
GAS
FITTER'S SHOP
5
DEMOLISHRAMP
17' -
6"
17' -
8"
17' -
6"
18' - 11" 16' - 0" 16' - 0" 16' - 0" 19' - 2 1/2"
KITCHEN
57' - 8"
42' -
8"
DEMOLISH DOORS
E2
E9
G2
10.2
11.9
11.9
DEMOLISH MACHINESHOP STRUCTURE
DEMOLISH PLUMBINGFIXTURES
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 1
1:58
AM
A-24
JJS
AREA C - DEMOLITION FLOOR PLAN AT EL+11.00, +14.04, +21.58 AND +25.00
229
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 1/8" = 1'-0"1
PARTIAL DEMOLITION PLAN AT EL +11.00 TO +14.04
SCALE: 1/8" = 1'-0"2
PARTIAL DEMOLITION PLAN AT EL +20.00 TO +25.00
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
8 0 8 16 FT1/8"=1'-0"
DEMOLITION NOTES
1 CONTRACTOR TO REMOVE AND THOROUGHLYCLEAN ALL SPACES OF ANY CHEMICALS, ASHESOR OTHER CONTAMINATION BEFORE NEWCONSTRUCTION ACTIVITIES ARE TO BEGIN.
2 REFER TO HZ DRAWINGS AND RELATEDSPECIFICATIONS FOR REMEDIATION, ABATEMENT,REMOVAL AND DISPOSAL PROCEDURESREQUIRED FOR DEMOLITION WORK.
3 REFER TO S DRAWINGS AND RELATEDSPECIFICATIONS FOR ADDITIONAL DEMOLITIONNOTES REGARDING STRUTURAL STEEL ANDCONCRETE.
4 ALL MATERIALS CONTAINING ASBESTOS,LEAD-BASED PAINT, MERCURY AND PCDB’S TO BEABATED/REMOVED PER THE ENVIRONMENTALREPORT, DRAWINGS AND SPECIFICATIONS.
5 EXISTING EGRESS PATHS MUST NOT BE ALTEREDOR OBSTRUCTED IN ANY WAY DURING WORK ATANY TIME.
6 EXECUTE THE DEMOLITION WORK IN A CAREFULAND ORDERLY MANNER WITH MINIMALDISTURBANCE TO BUILDING OCCUPANTS.
7 VERIFY EXTENT OF DEMOLITION SHOWN ON THEDEMOLITION DRAWINGS IS APPROPIATE TOPERMIT THE NEW WORK TO BE ACCOMPLISHED.ANY DAMAGE WHICH MAY BE CAUSED TO ANYPART OF EXISTING CONSTRUCTION TO REMAIN ASA RESULT OF DEMOLITION WORK MUST BE THERESPONSIBILITY OF AND BE CORRECTED BY THECONTRACTOR.
8 ALL EXISTING TO REMAIN WALLS AND COLUMNSDAMAGED BY DEMOLITION WORK MUST BEPATCHED BY CONTRACTOR.
9 PROTECT ALL FLOORS AND WALLS IN EXSITINGAREA DURING TRASH REMOVAL. NO TRASH ORMATERIAL MAY BE STORED IN EXISTINGCONSTRUCTION TO REMAIN.
10 UPON COMPLETION OF DEMOLITION WORK,REMOVE ALL MATERIALS AND RUBBISH OF ANYSORT AND LEAVE CONSTRUCTION PREMISESCLEAN.
11 TEMPORARY WEATHER TIGHT CONSTRUCTION TOBE INSTALLED UNTIL PROPOSED CONSTRUCTIONIS IN PLACE FOR OPENINGS RESULTING FROMDEMOLITION WORK REQUIRED FOR PROPOSEDWORK.
12 EXISTING HANDRAILS AT ABANDONEDCONDENSATE PITS TO BE REMOVED,REFURBISHED AND STORED FOR USE AT OTHERLOCATIONS.
13 REFER TO PROCESS, PLUMBING ANDSTRUCTURAL DRAWINGS FOR LOCATIONS OFEQUIPMENT PITS TO REMAIN.
14 PROVIDE 4" KICK PLATE AT ALL EXISTING ANDNEW HANDRAILS. EXISTING HANDRAILS TO BEABATED PER HZ DRAWINGS AND SPECIFICATION.
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
11
D
6A 7 8 9 10 12
E
F
G
ML
MECHANICALSHAFT
PLUMBINGSHAFT
LOCKER AREA
HVAC AREA
LOCKER ROOM LOCKER ROOM TRAINING ROOM MECHANICS SHOP
KITCHEN AREA
5
MATCHLINE - SEE DRAWING1 / A-28 FOR CONTINUATION
17' -
6"
17' -
8"
17' -
6"
E2
E9
G2
10.2 11.9
DEMOLISHSTAIR
DEMOLISHWINDOW DEMOLISH
WINDOW
DEMOLISH HATCHAND MONORAILABOVE
DEMOLISH RAILINGS, HOISTAND FLOOR HATCH.FILL OPENING PER S DWG
D
6A 7 8 9 10
E
F
G
ML
ML
5
DEMOLISH ROOFINGIN THIS AREA
17' -
6"
17' -
8"
17' -
6"
18' - 11" 16' - 0" 16' - 0" 16' - 0" 19' - 2 1/2"
E2
E9
G2
DEMOLISH EXISTINGSCUPPER AND DOWNSPOUT-PATCH MASONRY
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 1
1:07
AM
A-25
JJS
AREA C - DEMOLITION FLOOR PLAN AT EL+37.50, +42.50 AND +54.50
230
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 1/8" = 1'-0"1
PARTIAL DEMOLITION PLAN AT EL +37.50 TO +42.00
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
SCALE: 1/8" = 1'-0"2
PARTIAL DEMOLITION PLAN AT EL +54.50
8 0 8 16 FT1/8"=1'-0"
DEMOLITION NOTES
1 CONTRACTOR TO REMOVE AND THOROUGHLYCLEAN ALL SPACES OF ANY CHEMICALS, ASHESOR OTHER CONTAMINATION BEFORE NEWCONSTRUCTION ACTIVITIES ARE TO BEGIN.
2 REFER TO HZ DRAWINGS AND RELATEDSPECIFICATIONS FOR REMEDIATION, ABATEMENT,REMOVAL AND DISPOSAL PROCEDURESREQUIRED FOR DEMOLITION WORK.
3 REFER TO S DRAWINGS AND RELATEDSPECIFICATIONS FOR ADDITIONAL DEMOLITIONNOTES REGARDING STRUTURAL STEEL ANDCONCRETE.
4 ALL MATERIALS CONTAINING ASBESTOS,LEAD-BASED PAINT, MERCURY AND PCDB’S TO BEABATED/REMOVED PER THE ENVIRONMENTALREPORT, DRAWINGS AND SPECIFICATIONS.
5 EXISTING EGRESS PATHS MUST NOT BE ALTEREDOR OBSTRUCTED IN ANY WAY DURING WORK ATANY TIME.
6 EXECUTE THE DEMOLITION WORK IN A CAREFULAND ORDERLY MANNER WITH MINIMALDISTURBANCE TO BUILDING OCCUPANTS.
7 VERIFY EXTENT OF DEMOLITION SHOWN ON THEDEMOLITION DRAWINGS IS APPROPIATE TOPERMIT THE NEW WORK TO BE ACCOMPLISHED.ANY DAMAGE WHICH MAY BE CAUSED TO ANYPART OF EXISTING CONSTRUCTION TO REMAIN ASA RESULT OF DEMOLITION WORK MUST BE THERESPONSIBILITY OF AND BE CORRECTED BY THECONTRACTOR.
8 ALL EXISTING TO REMAIN WALLS AND COLUMNSDAMAGED BY DEMOLITION WORK MUST BEPATCHED BY CONTRACTOR.
9 PROTECT ALL FLOORS AND WALLS IN EXSITINGAREA DURING TRASH REMOVAL. NO TRASH ORMATERIAL MAY BE STORED IN EXISTINGCONSTRUCTION TO REMAIN.
10 UPON COMPLETION OF DEMOLITION WORK,REMOVE ALL MATERIALS AND RUBBISH OF ANYSORT AND LEAVE CONSTRUCTION PREMISESCLEAN.
11 TEMPORARY WEATHER TIGHT CONSTRUCTION TOBE INSTALLED UNTIL PROPOSED CONSTRUCTIONIS IN PLACE FOR OPENINGS RESULTING FROMDEMOLITION WORK REQUIRED FOR PROPOSEDWORK.
12 EXISTING HANDRAILS AT ABANDONEDCONDENSATE PITS TO BE REMOVED,REFURBISHED AND STORED FOR USE AT OTHERLOCATIONS.
13 REFER TO PROCESS, PLUMBING ANDSTRUCTURAL DRAWINGS FOR LOCATIONS OFEQUIPMENT PITS TO REMAIN.
14 PROVIDE 4" KICK PLATE AT ALL EXISTING ANDNEW HANDRAILS. EXISTING HANDRAILS TO BEABATED PER HZ DRAWINGS AND SPECIFICATION.
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
D
6A
6A
7
7
8
8
9
9
10
10
E
F
G
/ A-44 FOR CONTINUATIONMATCHLINE - SEE DRAWING 1
/A
-36
FO
R C
ON
TIN
UA
TIO
NM
AT
CH
LIN
E -
SE
E D
RA
WIN
G
1
1
A-61
EXISTING ROOF
2
A-73
1A-58
5
CLOSE OFF ABANDONEDPENETRATIONS PER POST-WARRANTY ALTERATION DETAILS 1,2, AND 3, SHEET A-15
3012
3
A-84
2
A-61
1
A-62
2
A-62
2
A-63
G2
3013
17' -
6"
17' -
8"
17' -
6"
6"
18' - 11" 16' - 0" 16' - 0" 16' - 0" 19' - 2 1/2"
FE 2' -
2"
CLOSE OFF ABANDONEDPENETRATIONS PER POST-WARRANTY ALTERATION DETAILS 1,2, AND 3, SHEET A-15
FLASHING PER POSTWARRANTY ALTERATIONREQUIREMENTS
FREIGHT ELEVATOR
B114
VESTIBULE
303
STAIR A
OPEN TO BELOW
NEW ROOFDRAIN (SEEPLUMBING)
ROTATE ELBOWAND SPLASH BLOCKTOWARDS DRAIN
NEW DOWNSPOUTSAND SPLASH BLOCKS
D
7
8 9 10
SCUPPER ANDDOWNSPOUT
3
A-84
2
A-62
2
A-63
CUT EXISTING DOWNSPOUTSFROM ROOF ABOVE, PROVIDE ELBOWSAND DIRECT DRAINAGE TO NEW ROOF- PROVIDE NEW SPLASH BLOCKS -SEE H-9 FOR ADDITIONAL WORK
EXISTINGDOWNSPOUT
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7/
12/2
016
4:09
:22
PM
A-40
JJS
AREA C - FLOOR PLAN AT EL +54.50
245
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 1/8" = 1'-0"A-181 PARTIAL PLAN AT EL +52.00
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
8 0 8 16 FT1/8"=1'-0"
SCALE: 1/8" = 1'-0"A-622 PARTIAL PLAN AT EL +75.33
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
1
1
DNUP
6
A
6B 7A 8A 8B 9A 10A
11
11 11A 12A
B2
C1
D
6A 7 8 9 10 12 13
14A
CL
1
A-65
3
A-65A-776
4
A-80
ROOFROOF
R33
R32
R31
17' - 0" 8' - 0" 17' - 0" 8' - 0" 17' - 0" 8' - 0" 17' - 0" 8' - 0" 17' - 0" 38' - 4"
ROOF
ROOF ACCESS AREA1
A-62
2
A-62
2
A-63
5
A-85
8
A-84
6
A-85
7
A-85
17' - 1" 16' - 0" 16' - 0" 16' - 0" 19' - 2 1/2" 19' - 4 1/2" 19' - 0 1/2" 19' - 6"
2A-82
4A-82
6A-82
7A-82
8A-82
9A-82
A-905
55.52'
ROOFHATCH
A-906
1/4"
/ 1'
-0"
SLO
PE
1/4"
/ 1'
-0"
SLO
PE
1/4"
/ 1'
-0"
SLO
PE
SCUPPER AND DOWNSPOUT
EXISTING AND NEWCONCRETE TO BE ALIGNED
ALSCREENRADIATOR (TYP)
SEE MECHANICAL DWGS
GRATING
HEAVY DUTYTYPE 304STEEL HOSERACK
11
A-15
B1
2
A-3
5' - 0"
6' -
0"
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 3
9:57
AM
A-45
JJS
AREA D - FLOOR PLAN AT EL +80.00
250
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 1/8" = 1'-0"
1 PARTIAL PLAN AT EL +80.00
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
8 0 8 16 FT1/8"=1'-0"
A-18
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
UP
DN
2A
3
A-79
B3
2
STAIR D
14' - 8" 2' - 7 5/8"
3' - 4" 8"
5' - 2 3/8"
8 TREADS @ 11"
7' - 4"
7' -
2"
3' -
4"
2A
3
A-79
B3
2
DN
5 TREADS @ 11"
4' - 7"
7' -
2"
7 TREADS @ 7"
6' - 5"
7' -
2"
3' -
4"
3' -
4"
5' - 0 3/4" 7' - 0 3/4"
PUMP ROOM L125.00'
CHLORINEBUILDING R150.58'
CHLORINEBUILDING L2
33.00'
CHLORINEBUILDING L1
20.00'
2A2
9 R
ISE
RS
5' -
0"
STAIR D
STAIR D 4' -
6 7
/8"
0" 11' -
4"
8"
1"
D
6A5
UPPER CORRIDOR
112B
FL EL 25.00
CORRIDOR
122
FL EL 27.50
6
A-79
4 TREADS @ 11"
3' - 8"
8' -
5"
3' -
10"
4' -
6"
5' - 8"
15A
C2
VESTIBULE
128
FL EL 21.58
22.08'
19.25'
4 E
Q T
RE
AD
S
3' -
8"
4' - 0"
6A
BOILER/GENERATOR L127.50'
PUMP ROOM L125.00'
PERSONNEL AREAL1 - UPPER
25.00'
5
5 R
ISE
RS
@ 7
"
2' -
6" 6" SGU
13
C9
C2
8
A-79
5' -
11"
7 T
RE
AD
S @
11"
6' -
5"
5' -
0"
27.50'1244
STORAGE
224
FL EL 32.00
2241
STAIR F
INFILL ABANDONNEDOPENING - TOOTH INMASONRY TO MATCHADJACENT SURFACES,BOTH SIDES
ALIGN DOORJAMB WITH CURB
CMU
DN
4' - 3 1/4"
GYPSUMWALLBOARD
7' -
11
7/8"
UL DES. NOG514
HANDRAIL
STAIR F
4' -
6"
8R @
6.7
5"
D
BOILER/GENERATOR L242.50'
EXIT CORRIDOR
211
FL EL 42.50 CORRIDOR
210
FL EL 37.50
9 E
Q R
ISE
RS
5' -
0"
8 EQ TREADS
7' - 4"5' - 3"
2"
A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 4
0:47
AM
A-79
JJS
ENLARGED VIEWS - MISC. STAIRS
284
ARCHITECTURE
JL
TCB
MAY 2016
SCALE: 1/4" = 1'-0"A-371 ENLARGED PLAN OF STAIR D AT EL 20.00
SCALE: 1/4" = 1'-0"A-372 ENLARGED PLAN OF STAIR D AT EL 33.00
SCALE: 1/4" = 1'-0"A-793 SECTION AT STAIR D
SCALE: 1/4" = 1'-0"A-34 ENLARGED PLAN OF STAIR IN CORRIDOR 112B
SCALE: 1/4" = 1'-0"A-65
ENLARGED PLAN OFSTAIR IN EXITCORRIDOR B1105
SCALE: 1/4" = 1'-0"A-796 SECTION AT STAIR IN CORRIDOR 112B
1/4"=1'-0"4 0 4 8 FT
SCALE: 1/4" = 1'-0"A-42
ENLARGED PLAN OFSTAIR F7 SCALE: 1/4" = 1'-0"A-42
SECTION AT STAIR F8
SCALE: 1/4" = 1'-0"A-399 SECTION AT STAIR IN CORRIDOR 210
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
SS COUNTERFLASHINGVEGETATEDROOFMODULE
RIGID POLYISOCYANURATEFOAM BOARD INSUL
HPT 43.52'
FB
CMU
RIGID POLYISOCYANURATEFOAM BOARD INSUL
WEEP/VENT
FLASHING
PVC ROOFMEMBRANE
T/ CONCRETE 55.17'
PFCMUT/ MASONRY 54.50'
T/ MASONRY 57.17'
BONDBEAM
CONCRETE SLAB -SEE STRUCTURAL
FB
METALCOPING
STEEL ANGLE -SEE STRUCTURAL
NAILER
FB
METALFLASHING
CAVITY DRAINAGE MAT
RIGID POLYISOCYANURATEFOAM BOARD INSUL
24" X 10" SS CONDUCTOR HEAD TO 4"X4"SS DOWNSPOUT AND CONCRETE SPLASHBLOCK ( TYP AT ALL DOWNSPOUTS AND SCUPPERS
EXISTING CONCRETESTRUCTURE
B/ MASONRY 58.50'
CMU
RIGID POLYISOCYANURATEFOAM BOARD INSUL
STL ANGLE- SEESTRUCTURAL
STL ANGLE - SEE STRUCTURAL
NAILER
CONCRETE SLAB- SEE STRUCT
METAL FLASHING
PFCMU
BELLOWS TYPEEXPANSION COVER
D
SS COUNTERFLASHING
RIGID POLYISOCYANURATEFOAM BOARD INSUL
STL ANGLE- SEESTRUCTURAL
CONCRETE DECK - SEESTRUCTURAL
CONCRETE SLAB -SEE STRUCTURAL
HORIZONTAL JOINTREINFORCEMENT
RIGID POLYISOCYANURATEFOAM BOARD INSUL
EXISTINGGLAZEDBRICK
PFCMU
CAVITY DRAINAGE MAT
FB
METAL FLASHINGSTL ANGLE - SEE STRUCTURAL
FB
CAVITY DRAINAGE MAT
RIGID POLYISOCYANURATEFOAM BOARD INSUL
CMU
EXISTING STEELBEAM - SEE STRUCTURAL
WEEP/VENT
METAL FLASHING
TAPERED RIGIDPOLYISOCYANURATEFOAM BOARD INSUL
SS COUNTERFLASHING
NOTE: AT EXISTING ROOFING TO REMAIN, COORDINATEDETAILS WITH SPECIFICATION SECTION 07 55 20, POSTWARRANTY ALTERATION TO EXISTING ROOFING
ELECTRICAL WINGR1
42.50'
B
VEGETATED ROOF MODULE
RIGID POLYISOCYANURATEFOAM BOARD INSUL
ALIGN INSULATION WITHTOP OF CONCRETE CURB
PVC ROOF MEMBRANE
10"
NORTH PROPERTY LINE
1' - 1"
8" M
IN
PALE
POST
RAIL
T/ CONCRETE 45.00'
EXISTING FACEBRICK
EXISTING COMMONBRICK
EXISTINGSTONE
1' - 9 7/8"
50.58'
1' - 0"
NOTE: AT EXISTING ROOFING TOREMAIN, COORDINATE DETAILS WITHSPECIFICATION SECTION 07 55 20,POST WARRANTY ALTERATION TOEXISTING ROOFING
CONCRETE BEAMSEE S DWG
PALE
POST
RAIL
STEEL BEAMSEE S DWG
PROPERTY LINE
EXISTING BEAM A R C H I T E C T S
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
AS SHOWN
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-A_o
chav
ez.r
vt7 /
21/2
0 16
10: 4
3:54
AM
A-87
JJS
WALL SECTION DETAILS - SHEET 2
292
ARCHITECTURE
JL
TCB
MAY 2016SCALE: 1 1/2" = 1'-0"A-801 WALL SECTION DETAIL - AREA E
SCALE: 1 1/2" = 1'-0"A-802 WALL SECTION DETAIL - AREA E
SCALE: 1 1/2" = 1'-0"A-804 WALL SECTION DETAIL - AREA E
1 1/2"=1'-0"1 0 1 FT
SCALE: 1 1/2" = 1'-0"A-626 WALL SECTION DETAIL - AREA C
SCALE: 1 1/2" = 1'-0"A-627 WALL SECTION DETAIL - AREA C
SCALE: 1 1/2" = 1'-0"A-663 WALL SECTION DETAIL - AREA E
SCALE: 1 1/2" = 1'-0"A-665 WALL SECTION DETAIL - AREA E
SCALE: 1 1/2" = 1'-0"A-608 WALL SECTION DETAIL - AREA B
NO. DATE APPD DESCRIPTION1 07/15/16 TCB ADDENDUM NO. 3
1
HYDRAULIC ACCUMULATORSYSTEM NO. 2SEE NOTE 2
RAILING (TYP)
PACKAGE VACUUMPRIMING SYSTEMSEE NOTE 3
STRUCTURALSUPPORT (TYP)
HYDRAULIC ACCUMULATORSYSTEM NO. 1SEE NOTE 2
FL EL 9.71'
FL EL -1.75'
42" VENTURI METER 42" PUMP DISCHARGE
NEW 2" VACUUM PRIMINGSEE NOTE 1
NEW 2" HYDRAULIC WATERSEE NOTE 1
FL EL -8.79'
NEW 2" SEAL WATERSEE NOTE 1
NEW 2" PROCESS WATERSEE NOTE 1
3" COLD WATERSEE NOTE 4
3" DOUBLE CHECKDETECTOR ASSEMBLY(TYP)
HYDRAULIC ACCUMULATORSYSTEM NO. 2SEE NOTE 2
RAILING(TYP)
42" PUMP DISCHARGE
FL EL -18.00'
FL EL -8.79'
NEW 2" HYDRAULIC WATERSEE NOTE 1
NEW 2" SEAL WATERSEE NOTE 1
NEW 2" PROCESSWATERSEE NOTE 1
3" COLD WATERSEE NOTE 4
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
12: 2
2:15
PM
3/8" = 1'-0"
M-51
OR
EQUIPMENT AREA SECTIONS
352
PROCESS / MECHANICAL
AM
AJM
MAY 2016
SCALE: 3/8" = 1'-0"M-501 EQUIPMENT AREA SECTION 1
SCALE: 3/8" = 1'-0"M-502 EQUIPMENT AREA SECTION 2
1. FOR CONTINUATION SEE DRAWING M-32.2. PROVIDE HYDRAULIC ACCUMULATOR SYSTEM.
REFER TO SPECIFICATION SECTION 40 05 20 VALVESAND DRAWING M-11 NEW HYDRAULIC WATERDIAGRAM.
3. PROVIDE VACUUM PRIMING SYSTEM. REFER TOSPECIFICATION SECTION 43 21 70 VACUUM PRIMINGEQUIPMENT AND DRAWING M-7 NEW VACUUMPRIMING SYSTEM DIAGRAM.
4. FOR CONTINUATION SEE DRAWING P-8 AND P-9.
NOTES:
3/8"=1'-0"1 0 1 2 43 5 6 7 FT
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
NO. DATE APPD DESCRIPTION1 07/15/16 AJM ADDENDUM NO. 3
1
HWB-1 HWB-2
ACU-1 ACU-2 HVU-1
HVU-2
HVU-3
P
HSP-5 HSP-6 HSP-7
HSP-8
HSP-9
HSP-2HSP-1
EXT-1
BLOWDOWNSEPERATOR
CHEMICALPOT-FEEDER
AS-1
AIRSEPARATOR
QUICKFILL
HPP-1 HPP-2
MECHANICALROOM 1
BOILER ROOM
CW
4" HWR
4" HWS
2 1/2" HWR
2 1/2" HWS
HSP-3
HVU-4 ACU-3
ACU-4
ACU-5
HSP-10 HSP-11
HSP-12
HSP-13MECHANICAL
ROOM 2
CW MAKE-UP1"
FILL
OVERFLOW
CIRCUTSETTER
FLOWCONTROL
55 GALGLYCOLWATER
STORAGETANK
M
F
EXTERNALFLOAT
LOW LEVELALARM TO TCP
FLOORDRAIN
GLYCOL PRESSURETANK AND PUMP
AIR PRESSURE CONTROLMAKE-UP WATER
PRESSURESWITCH
FS
1"
1"
4" HWR
4" HWS
4" HWR
4"4"4"4"
1"
3/4"3/4"
4"
4"
4"
4"
1"
4"4"
4"4"4"4"
1"
4"4"
4" H
WS 4"
HW
R
4" H
WS
4" H
WR
4" HWS
4" HWR
1 1/4" HWS
3/4" 1" 1 1/2"
3/4"
1 1/4"1 1/4"
3/4"
1 1/2"1"3/4" 1 1/2"1 1/2"
2"2"3 1/2"3 1/2" 1"1"
HSP-4
2" HWS
2" HWR
1 1/4" HWR
BOILER ROOM
PUMPROOM
FUEL OIL STORAGE AREA
GENERATOR ROOM
WUH-23 WUH-24
WUH-13 WUH-14 WUH-15 WUH-16 WUH-17 WUH-18 WUH-19 WUH-20
WUH-1 WUH-2 WUH-3 WUH-4 WUH-5 WUH-6 WUH-7 WUH-8WUH-9 WUH-10
3/4" TYP
3/4" TYP
3/4" 1 1/4"
1 1/4"
2" HWS
2" HWS
4" H
WS 4"
HW
R
EXPANSIONTANK
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
11: 0
6:52
AM
NONE
H-48
GS
HOT WATER PIPING DIAGRAM
401
HVAC
JM
GJ
MAY 2016SCALE: NONE
HOT WATER PIPING DIAGRAM
1. REFER TO GENERAL NOTES ON DRAWING H-2.2. FOR OTHER VALVE, EQUIPMENT AND PIPING
SYMBOLS SEE DRAWING M-1, MECHANICALSYMBOLS LIST.
3. PROVIDE FLOW SWITCH ON THE MAKE-UPWATER TO 55 GALLON GLYCOL WATERSTORAGE TANK. ALARM MAKE-UP WATERINDIVIDUALLY ON BOTH FLOW SWITCHES ATTHE MAKE-UP WATER SYSTEM TO TCP-1 ANDTHE DDC SYSTEM.
NOTES:
NO. DATE APPD DESCRIPTION1 07/15/16 JED ADDENDUM NO. 3
1
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
11: 1
2:33
AM
H-52
TK
EQUIPMENT SCHEDULES - SHEET 1
405
HVAC
JM
GJ
MAY 2016
HVAC - HEATING & VENTILATING UNITSUNITI.D. UNIT LOCATION UNIT AREA SERVED UNIT TYPE
FAN MOTOR ELECTRICAL HEATING COILS AIR CONFIGURATION FILTER
MANUFACTURER MODEL NO. REMARKS/NOTECFM
RPMEXT SP
"H2O BHP HP RPM DRIVEV PH HZ
HEAT'GEWT
HEAT'GLWT
HEAT'GGPM
HEAT'GTOT MBH %GLY
HEAT'GWPD 'H2O EAT LAT
SP"H2O
FACEFPM
FACESQFT ROWS FPI ARRGMT SIZE
HVU-1 MECH. ROOM 1 BASEMENT STORAGE MODULE 1550 1879 2 1.36 1.5 1800 BELT 460 3 60 190 175 19.00 142 30 0.34 10 97 0.139 332 4.51 2 (14) ANGLE 2" MERV 13 TRANE CSAA004UAHVU-2 MECH. ROOM 2 1ST FL STORAGE MODULE 575 2729 2 0.61 1 1800 BELT 460 3 60 190 170 7.00 67 30 0.08 0 103 0.056 206 2.92 4 (6) ANGLE 2" MERV 13 TRANE CSAA003UAHVU-3 MECH. ROOM 1 MECH, ROOMS MODULE 1750 1874 2 1.64 1.5 1800 BELT 460 3 60 190 170 15.00 148 30 0.42 25 103 0.175 388 4.51 4 (6) ANGLE 2" MERV 13 TRANE CSAA004UAHVU-4 MECH. ROOM 2 PUMP RM MODULE 15000 951 2 17.32 20 1800 BELT 460 3 60 195 175 100.00 1000 30 2.48 40 101 0.148 429 34.94 2 (10) ANGLE 2" MERV 13 TRANE CSAA035UA
HVAC - AIR CONDITIONING UNITSUNITI.D. UNIT LOCATION UNIT AREA SERVED
UNITTYPE
FAN MOTOR ELECTRICAL HEATING COILS AIR CONFIGURATION EVAPORATOR COIL FILTER
MANUFACTURER MODEL NO.REMARKS/
NOTECFMRPM
EXT SP"H2O BHP HP RPM DRIVE
V PH HZHEAT'G
EWTHEAT'G
LWTHEAT'G
GPMHEAT'G
TOT MBH %GLYHEAT'G
WPD 'H2O EAT LAT SP "H2OFACEFPM
FACESQFT
ROWS(FPI)
EVAP.EAT:DB
EVAP.EAT:WB
EVAP.LAT:DB
EVAP.LAT:WB
COOL.TOT. MBH
TONS(COOL)
COOL.VEL FPM REFR ARRGMT SIZE
ACU-1 MECH. ROOM 1 BASEMENT SHOPS MODULE 1550 1916 2 1.2 1.5 1800 BELT 460 3 60 195 175 4.00 41 30 0.17 60 88 0.096 343 3 2 (9) 80 67 51 51 48 4 343 R410a ANGLE 2" MERV 13 TRANE CSAA003UAACU-2 MECH. ROOM 1 2ND FL PERSONNEL AREAS MODULE 2250 2048 2 2.6 3 1800 BELT 460 3 60 195 175 9.00 92 30 0.93 45 84 0.204 487 4 2 (12) 80 67 54 54 90 7.5 487 R410a ANGLE 2" MERV 13 TRANE CSAA004UAACU-3 MECH. ROOM 2 LOW VOLTAGE SWITCHGEAR MODULE 9250 1041 2 8.6 10 1800 BELT 460 3 60 195 175 45.00 434 30 4.39 60 103 0.093 466 21 1 (12) 80 67 59 56 313 26 466 R410a ANGLE 2" MERV 13 TRANE CSAA021UA VFDACU-4 MECH. ROOM 1 1ST FL PERSONNEL AREAS MODULE 3495 1718 2 4 5 1800 BELT 460 3 60 190 175 22.00 161 30 2.6 60 102 0.193 438 8 1 (14) 80 67 60 58 77 8.5 438 R410a ANGLE 2" MERV 13 TRANE CCAA08UAACU-5 MECH. ROOM 2 PARALLEL SWITCHGEAR MODULE 2250 2048 2 2.6 3 1800 BELT 460 3 60 190 170 9.00 92 30 0.93 45 84 0.204 487 4 2 (12) 80 67 54 54 90 7.5 487 R410a ANGLE 2" MERV 13 TRANE CSAA004UA
HVAC - PACKAGED AC UNITSUNIT I.D. UNIT LOCATION UNIT AREA
SERVED UNIT TYPE DISCH CFMEXT SP
"H2O MBHTONS
(COOL)
EVAP. MOTOR ELECTRICAL EVAP. AIR CONDENSER COMPRESSOR
REFRFILTER
ARRGMT MANUFACTURERMANUFACTURER MO.
# REMARKS/NOTEMOTOR
BHPMOTOR HP
(QTY)MOTOR
RPM V PH HZEVAP.
EAT:DBEVAP.
EAT:WBEVAP.LAT:DB
EVAP.LAT:WB
COND.CFM
COND.RPM
COND. HP(QTY)
COMPRESS.#'S
COMPRESS.RLA
COMPRESS.CONTROLS
PACU-1 VFD RM ROOF VFD ROOM PACKAGED DOWN 23,000 1.5 867 70 16.6 20 (2) 1400 460 3 60 80 67 57 56 -- -- 1 (6) 3 39 INTEGRAL R-410A ANGLE TRANE SAHLF704 VFDPACU-2 VFD RM ROOF VFD ROOM PACKAGED DOWN 23,000 1.5 867 70 16.6 20 (2) 1400 460 3 60 80 67 57 56 -- -- 1 (6) 3 39 INTEGRAL R-410A ANGLE TRANE SAHLF704 VFD
HVAC - AIR COOLED CONDENSER UNITS
UNIT I.D. UNIT LOCATION UNIT SYSTEM SERVED TONS
CONDENSER COMPRESSOR
REFR
ELECTRICALELECT.
RLA MANUFACTURER MANUFACTURER MO. # REMARKS/NOTECOND. #OF FANS
COND.CFM
COND.RPM COND. HP
COMPRESS. #'S
COMPRESS.KW
COMPRESS.CONTROLS ELEC. V ELEC. PH ELEC. HZ
ACCU-1 ENTRY ANNEX ROOF ACU-1 4 1 -- 835 0.2 1 0.2 -- R-410A 208 3 60 TRANE 4TTR7048AACCU-2 ENTRY ANNEX ROOF ACU-2 5 1 -- 835 0.3 1 0.2 -- R-410A 208 3 60 TRANE 4TTR7060AACCU-3 ENTRY ANNEX ROOF ACU-3 25 2 -- -- 3 2 23 -- R-410A 460 3 60 TRANE TTA300ACCU-4 ENTRY ANNEX ROOF ACU-4 10 1 -- -- 3 1 8 -- R410A 460 3 60 TRANE TTA120ACCU-5 ENTRY ANNEX ROOF ACU-5 5 1 -- 835 0.3 1 0.2 -- R-410A 208 3 60 TRANE 4TTR7060AACCU-6 ENTRY ANNEX ROOF ACU-7 2 1 2,350 -- -- -- -- -- R-410A 208 1 60 40 TRANE 4TXK2724A10N0A COMP. IN ACU-6ACCU-7 ENTRY ANNEX ROOF ACU-7 1.5 1 1,880 -- -- -- -- -- R-410A 208 1 60 40 TRANE 4TXK2718A10N0A COMP. IN ACU-7
HVAC - TANKSUNIT I.D. UNIT LOCATION
UNIT SYSTEMSERVED DIAMETER/LxWxH CAP. GAL'S
PSIGMAX/MIN MANUFACTURER MANUFACTURER MO. # REMARKS/NOTE
FODT-1 GENERATOR ROOM FUEL OIL 36x24x44 120 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL 200% CONTAINMENTFODT-2 GENERATOR ROOM FUEL OIL 36x24x44 120 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL 200% CONTAINMENTFODT-3 GENERATOR ROOM FUEL OIL 36x24x44 120 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL 200% CONTAINMENTFODT-4 GENERATOR ROOM FUEL OIL 36x24x44 120 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL 200% CONTAINMENTNLOT-1 LUBE OIL STORAGE LUBE OIL 60x32x60 500 HIGHLAND TANK 500LDW NEW OIL TANKWLOT-1 LUBE OIL STORAGE LUBE OIL 60x32x60 500 HIGHLAND TANK 500LDW WASTE OIL TANKFORT-1 BASEMENT CORRIDOR FUEL OIL 60x60x60 300 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL 200% CONTAINMENTFOST-1 FUEL OIL STORAGE FUEL OIL 12' DIA X 30' H 25000 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALLFOST-2 FUEL OIL STORAGE FUEL OIL 12' DIA X 30' H 25000 PHILLIPS FUEL SYSTEMS PDWT DOUBLE WALL
UNITI.D.
LOCATION(ROOM)
REFRIG.TYPE
LBS OFREFRIG.
NO OFCOMP.
TONS(TOTAL)
SUCTION LINE
HORIZONTAL VERTICAL
LIQUID LINE
HORIZONTAL VERTICALREMARKS/NOTE
HVAC - REFRIGERATION SCHEDULE
PACU-1PACU-2ACCU-1ACCU-2ACCU-3ACCU-4ACCU-5ACCU-6ACCU-7
ROOFROOFROOFROOFROOFROOFROOFROOFROOF
R410A 86 3 70 -- -- -- --R410A 86 3 70 -- -- -- --
R410A 12 1 4 1 1/8 1 1/8 1/2 1/2R410A 12 1 5 1 1/8 1 1/8 1/2 1/2R410A 40 2 25 2 1/8 2 1/8 7/8 7/8
1 10 1 5/8 1 5/8 5/8 5/820R410AR410AR410AR410A
12 1 5 1 1/8 1 1/8 1/2 1/212 1 3 1 1/8 1 1/8 1/2 1/212 1 3 1 1/8 1 1/8 1/2 1/2
HVAC - DUCTLESS SPLIT AIR CONDITIONING UNITSUNIT I.D. UNIT LOCATION UNIT AREA SERVED UNIT TYPE
FAN ELECT.RLA
ELECTRICAL EVAPORATOR COIL FILTERMANUFACTURER MODEL NO. REMARKS/NOTECFM V PH HZ COOL. TOT. MBH REFR TYPE
ACU-6 SCADA SERVER ROOM SCADA SERVER ROOM DUCTLESS 650 - 290 0.38 208 1 60 24.0 R-410A WASHABLE TRANE R SERIES 4MXW2724A10N COOLING ONLYACU-7 SECURITY SERVER ROOM SECURITY SERVER ROOM DUCTLESS 560 - 280 0.10 208 1 60 18.0 R-410A WASHABLE TRANE R SERIES 4MXW2718A10N COOLING ONLY
EXT-1 BOILER ROOM HTG SYSTEM 85L X 20D 132 TACO CA-500 ASME STAMP VERTICAL MODEL
NO. DATE APPD DESCRIPTION1 07/15/16 JED ADDENDUM NO. 3
NOTE: PACKAGED AIR CONDITIONING UNITS PCAU-1 AND PACU-2 ARE TO BE EQUIPPED WITH VARIABLE SPEED INVERTER DRIVEN COMPRESSOR, SINGLE ZONE VAV SUPPLY, DIRECT DRIVEN SUPPLY FANS, SPRING ISOLATED FAN ASSEMBLY, UL LISTING, AND LOW AMBIENT CONTROL DOWN TO 0 DEGREES F.
1
109876A
G
F
E
D
C1
B2
A
6 6B 7A 8A 8B 9A 10A 11 11A
12
12A
13 14 15 15A
C9
C2
14A 16A
B1
3" CW PIPE UP
FITTERS SHOPGAS
TOILET
ELECTRICALSHOP
LOADINGDOCK
ASST. CHIEF
OPERATING
ENGINEER'S
OFFICE
TOILET.
4" SAN
REMOVE EXISTING TOILETPLUMBING FIXTURES ANDASSOCIATED PIPING,VALVES, ETC. CAPSANITARY PIPE AT MAIN.
KS
DF
BOILER ROOMAT EL 27.50
BOILERNO. 4
CITYWATERPUMP
BOILERNO. 5
BOILERNO. 3
BOILERNO. 2
BOILERNO. 1
GENERATOR
ROOM
REMOVE EXISTINGCITY WATER BOOSTER PUMPAND ASSOCIATED PIPING,VALVES, ETC.CAP WATER PIPE AT MAIN
SINK
FDUR
WC
SH
WCL
EMERGENCY SHOWER/EYEWASHTO BE DEMOLISHED
4" BACK FLOW PREVENTERTO BE DEMOLISHED
4" CW TO BE DEMOLISHED
DRAIN PIPE TO BE DEMOLISHED
4" CW PIPE TO BE DEMOLISHED
4" BACK FLOWPREVENTER TOBE DEMOLISHED
4" CW PIPIES TO BEDEMOLISHED
4" CW PIPE TO BEDEMOLISHED
CHEMICAL TREATMENT TANKSSEE NOTE 4
SEE NOTE4
CONTROL PANELTO BE DEMOLISHED
SERVICE COLD WATERTO EXISTING HVU TOBE DEMOLISHED
SERVICE COLD WATER (DRAIN)FROM EXISTING HVUTO BE DEMOLISHED
CW PIPING TO BOILERSTO BE DEMOLISHED
OPEN HUB DRAINTO BE DEMOLISHED
SEE NOTE 4
CW PIPE TO BEDEMOLISHED
UR SH
FD
109876A
G
F
E
TOILETROOM
(2) L
WC
SH 6" RISER
REMOVE EXISTING TOILETPLUMBING FIXTURES ANDASSOCIATED PIPING, VALVES, ETC.CAP SANITARY PIPE AT MAIN.
EXISTING ROOF DRAIN TO REMAIN. REMOVEEXISTING COPPER PIPING AND REPLACE WITH CASTIRON HUB AND SPIGOT PIPE. SUPPORT AND INSULATENEW PIPING AS REQUIRED.
D
C1
B2
12A
13 14 15 15A
C9
C2
14A
REMOVE EXISTING PAINTERSOFFICE PLUMBING FIXTUREAND ASSOCIATED PIPING,VALVES, ETC.CAP SANITARY PIPE AT MAIN.
6" RISERPAINTERSOFFICE
SS
87
E
D
EXISTING 6" ROOF DRAINSTO BE DEMOLISHED WITHASSOCIATED PIPING INCLUDINGVERTICAL PIPING DOWN TOEL=27.50. REMOVE EXISTINGCOPPER PIPING AND REPLACEWITH CAST IRON HUB AND SPIGOTPIPE. SUPPORT AND INSULATE NEWPIPING AS REQUIRED.FOR REROUTING OF THE EXISTINGROOF DRAINAGE SEE DWG P-13.
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\ysa
vchenko
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
ysavc
henko
.rvt
7/1
4/2
016 9
:12: 2
9 A
M
As indicated
P-7
YS
AREA C AND D - DEMOLITION PLANS
415
PLUMBING
MLF
GJ
MAY 2016
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
SCALE: 3/32" = 1'-0"
AREA C AND D PLAN @ EL +20.00 TO +35.00
1. SEE GENERAL PLUMBING NOTES DEMOLITIONNOTES ON DRAWING P-1.
2. THIS DRAWING REFLECTS THE CONDITIONSVISUALLY FOUND AND A COMPILATION OF PASTPROJECT DRAWINGS.
3. REMOVE ALL EXISTING PLUMBING FIXTURES,EQUIPMENT, HOUSEKEEPING PADS, EQUIPMENTSUPPORT, AND PIPING SHOWN ON THIS DRAWING.
4. EQUIPMENT AND PIPING SHOWN NOT HATCHED,REFER TO HVAC DRAWINGS.
5. REMOVE EXISTING COPPER PIPING FROM EXISTINGROOF DRAINS AND REPLACE WITH CAST IRON HUB &SPIGOT PIPING. SUPPORT AND INSULATE NEWPIPING AS REQUIRED. TYPICAL FOR ALL EXISTINGROOF DRAIN PIPING MADE OUT OF COPPER.
NOTES:SCALE: 3/32" = 1'-0"
AREA C PARTIAL PLAN AT EL +37.50
8 0 8 16 24 FT3/32"=1'-0"
SCALE: 3/32" = 1'-0"
AREA D PARTIAL PLAN AT EL +37.50
NO. DATE APPD DESCRIPTION
1 07/15/16 JED ADDENDUM NO. 3
SCALE: 1/8" = 1'-0"
AREA C ROOF PLAN
1
1
1
109876A
G
F
E
D
11 12
TOILET
116
FL EL: 25.00
CONTROL ROOM
113
FL EL: 25.00
SECURITY SERVERROOM
113 B
FL EL: 25.00
CHIEF'S AND ASSTCHIEF'S OFFICE
115
FL EL: 25.00
EXIT CORRIDOR
108
FL EL: 21.58
STAIR A
TOILET
106
FL EL: 21.58
SECURITY OFFICE
102
FL EL: 21.58
CORRIDOR
105
FL EL: 21.58
ENTRY LOBBY
101
FL EL: 21.58
LUBE OIL STORAGE
110
FL EL: 21.58
LOADING DOCK
109
FL EL: 21.58
UPPER CORRIDOR
112B
FL EL: 25.00 CORRIDOR
112
FL EL: 21.58
SCADA SERVER ROOM
114
FL EL: 25.00
WC-2
L-1
KS
L-1
WC-2
4" FD-1
4"FD-1
L-1WC-2
EWC-1(SEE NOTE 6)
EWH-2
EWH-3
EWH-1
EWH-4
4" FD-1
5
BREAK/ MEETINGROOM
111
FL EL: 21.58
LUNCH ROOM
107
FL EL: 21.58
OPEN TO BELOW
4" FD-1SEE NOTE 5
WH
WH
4" SAN DN
4" SAN UPTO 4" FD-3(TYP 2)
2" V UP
2" V UP
4" CO
4" CO(TYP)
4" SAN UPTO 4" FD-2(TYP 2)
4" SAN UPTO 4" FD-3
2" V UP
4" SAN UPTO 4" FD-1(TYP 2)
4" SAN UP
4" SANUP&DN
4" CO
4" SAN UPTO 4" FD-1
3" SAN UPTO SH (TYP 4)
3" SAN UPTO JMB
4" SAN UPTO 4" FD-1
4"ø
4"ø
4"ø
4"ø
4"ø
4"ø
4" FCO
4" FCO
4" SAN DN
2" V UP
4" V DN
2" V UP
6" CW UP FOR FIREPROTECTIONSEE DWG FP-3FOR CONTINUATION
3" CW UP
6"ø
3"ø
CW
4" CW DNSEE DWG P-12FOR CONTINUATION
SAN
CW
4" CO
4" GATE VALVE
3" NATURAL GASPIPE DN. SEE DWG P-12FOR CONTINUATIONSEE NOTE 2.(6,000 CFH)
STORAGE
104
FL EL: 21.58
TOILET
103
FL EL: 21.58
3" NATURAL GASSEE DWG H-30FOR CONTINUATION
1 1
/4"ø
1 1/4"ø
1 1
/4"ø
1 1/2"ø
1 1/2"ø
3/4
"ø
CO
4" W UP & DN
3" V UP & DN
4"ø4" V UPSAN
4" V UP
4" V DN
V
4"ø
1 1
/2"ø
1 1/2" CWSEE DWG P-14 FORCONTINUATION
GREASEINTERCEPTOR(UNDER SINK)
FIRE-RATEDSLEEVE(TYP)
FIRE-RATEDSLEEV
SH
3/4" CW &3/4" TW UP
2" V DN
6" EXISTING STTO REMAIN
NEW 6" STUP
NEW6" CO
POINT OF NEW 6"ST CONNECTIONTO EXISTING PIPE
109876A
G
F
E
D
11 12
4" FD-34" FD-3
4" FD-3
FD-1
FD-1 FD-1
4" FD-1 (TYP)
EWC-1
WC-1
(2)SH (2)SH
JMB
EXPANSIONTANK, ET
L-1 L-2
LOCKER ROOM NO1
205
FL EL: 37.50
CORRIDOR
210
FL EL: 37.50
LOCKER ROOM NO2
202
FL EL: 37.50
ARCHIVES
206
FL EL: 37.50
HB
UR-2
FIRE PREVENTIONROOM
201
FL EL: 37.50
STAIR A
MECHANICAL ROOMNO 3
221
FL EL: 37.50
ELECTRIC FLOORMOUNTEDTANKLESSWATER HEATER(TYP 2)
EE
JANITOR
204
FL EL: 37.50
EYEWASHEMERGENCYALARM SYSTEM
5
ELECTRIC WALLMOUNTED TANKLESSWATER HEATER
EWH-5
EWH-6
EWH-7
4" FD-2
4" FD-2
4" SAN DN,4" V DN
2" V DN
2" V DN
3/4"ø
3"ø
2"ø
1"ø
1 1/2"ø
1 1/4"ø
3" CW DN
CW
HW
TMV-2
3/4"ø
1"ø
1"ø
3/4" HW DN
4" W DN
3" V UP & DN
2" V DN
4"ø
3"ø
3" V DN
4"ø4" V DN
4" V UP TO 4" VTR4" V DN
1 1/4"ø
V
1 1/2"HW DN
V
HW
CW
3"ø
1 1/4"ø
CORRIDOR
210
FL EL: 37.50
CORRIDOR
210
FL EL: 37.50
STORAGE
220
FL EL: 37.50
ROOF(SEE DWG A-39)
ROOF(SEE DWG A-39)
WC-2 WC-2
WC-1
WC-1
L-2 L-1L-2L-2
3/4" CW
3/4" TW 3/4" CW & TW DN
1 1/4"ø
TW
6" ST
6" OST
6" ST UPT0 6" RD-1
6" OST UPTO 6" ORD-1
CO
6" ST DNTO EL=27.50
SLOPE 1/4" PER FT
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\ysa
vchenko
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
ysavc
henko
.rvt
7/1
3/2
016 1
0:0
5:4
7 A
M
1/8" = 1'-0"
P-13
YS
AREA C - PERSONNEL AREAS PLUMBINGPLANS
421
PLUMBING
MLF
GJ
MAY 2016
SCALE: 1/8" = 1'-0"
AREA C PLAN AT EL +21.58, +25.00
SCALE: 1/8" = 1'-0"
AREA C PLAN AT EL +37.50
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
8 0 8 16 FT1/8"=1'-0"
1. ELECTRIC WATER HEATER #1, #3, AND #4 ARELOCATED ABOVE SUSPENDED REFLECTEDCEILING. FOR EACH WATER HEATER PROVIDESAFETY PAN AND RUN DISCHARGE PIPING FROMRELIEF VALVE TO THE NEAREST FLOOR DRAIN.
2. PROVIDE 3" GAS METER AND 3" GAS REGULATOR(INCOMING GAS PRESSURE 20 LBS. NEW GASSERVICE 2 LBS AFTER THE REGULATOR).
3. THE PLUMBING PIPES INSIDE PLUMBING CHASEARE NOT SHOWN. SEE PLUMBING DIAGRAMS P-22,P-23 AND P-24 FOR REFERENCES.
4. REFERENCE DRAWINGS P-22 TO P-24 FORDIAGRAMS.
5. FLOOR DRAIN UNDER SINK CABINET. PROVIDE 20"ØCIRCULAR OPENING ON BOTTOM SHELF ABOVEFLOOR DRAIN GRATING.
6. PROVIDE EWC PER ADA REQUIREMENTS.7. FOR UNDERGROUND PIPING SEE DRAWING P-19.
NOTES:
NO. DATE APPD DESCRIPTION
1 07/15/16 JED ADDENDUM NO. 3
1
1
109876A
D
C1
B2
A
6 6B 7A 8A 8B 9A 10A
11
11 11A
12
12A
13 14 15 15A
C9
C2
14A 16A
ROOF ACCESS AREA
401
FL EL: 81.33
ROOF OVERGENERATOR ROOM
(BARREL ROOF)
ROOF OVERFUEL OIL STORAGE AREA
3" ORD-1
3" RD-1 (800 SQ FT AREA)
3" ORD-1
3" RD-1 (650 SQ FT AREA)
3" ORD-1
3" RD-1 (650 SQ FT AREA)
3" ORD-1
3" RD-1 (550 SQ FT AREA)
3" ORD-1
3" RD-1 (800 SQ FT AREA)
4" VTR
4" VTR
ROOF HYDRANTRH
ROOF HYDRANTRH
4" VTR
109876A
E
D
5
6" RD-1(5200 SQ FT AREA) 6" ORD-1
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\ysa
vchenko
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
ysavc
henko
.rvt
7/1
3/2
016 1
0:0
4:2
9 A
M
1/8" = 1'-0"
P-17
YS
AREA D - ROOF PLUMBING PLAN
425
PLUMBING
MLF
GJ
MAY 2016
SCALE: 1/8" = 1'-0"
AREA D ROOF PLAN
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
8 0 8 16 FT1/8"=1'-0"
1. PROVIDE 3/4" CW SUPPLY FOR 2(TWO) ROOFHYDRANTS FROM THE COLD WATER PIPELOCATED IN MECHANICAL ROOM NO. 2 ATELEVATION +54.50.
2. RUN 3/4" DRAIN FROM 2(TWO) ROOF HYDRANTSTO THE NEAREST FLOOR DRAINS IN MECHANICALROOM NO. 2 AT ELEVATION +54.50.
NOTES:
NO. DATE APPD DESCRIPTION
1 07/15/16 JED ADDENDUM NO. 3
SCALE: 1/8" = 1'-0"
AREA C ROOF PLAN
1
PERSONNEL AREAB1
11.00'
PERSONNEL AREAL1
21.58'
9 8 76A
BOILER ROOM
B107
BOILER ROOM
OTB
BOILER ROOM
OTB
4" FD-3(TYP)
4" W
8" INCOMINGWATER SERVICE #1
8"ø
8"ø
6"ø
4" DOUBLE CHECKDETECTOR ASSEMBLY (DCDA)
4" GATE VALVE(MICV)
4" WATER METER
4" GATE VALVE (MOCV)
BYPASS
8" CHECKVALVE
8" OS&Y VALVE
TS
1' - 3"
2' -
4"
3" NATURALGAS PIPE
4"ø 4"ø
4" FCO
SAN
4" GATE VALVE (MICV)
4"ø
11 1/4"1' - 8"
4"ø
4"ø
4"ø
TS
4" GATE VALVE
4" DOUBLE CHECKDETECTOR ASSEMBLY (DCDA)
8" INCOMINGWATER SERVICE #2
8" CHECK VALVE
8" OS&Y VALVE
FOR FIRE PROTECTION6" DOUBLE CHECKDETECTOR ASSEMBLY
1' - 8"
4"ø
1"ø
4"ø
4"ø
8"ø8"ø
CW4"ø
FCO
BOILER/GENERATOR B111.00'
BOILER/GENERATOR L127.50'
PERSONNEL AREAL2
37.50'
GFED
8" INCOMINGWATER SERVICE #1CL EL=14.33SEE CIVIL DWG C-15FOR CONTINUATION
8" OS&Y VALVE
6" OS&Y VALVE6" DOUBLE CHECKDETECTOR ASSEMBLYWITH BY-PASS METER
6" OS&Y VALVE
TS TS
TS
4" FCO 4" FD-3
6"ø6"ø
6"ø
8"ø
WASTE LINE
BOILER ROOM
OTB
WATER TIGHT SLEEVE
CORRIDOR
112
FL EL: 21.584" GATE VALVE
3" CWPROCESS WATERSUPPLY
4" CWPROCESS WATERSUPPLY
6" CW FORFIRE PROTECTION
6"ø
4"ø
3"ø
4"ø
SAN
4"ø
4" SAN
3/4"ø
HW
SAN
3/4
"ø SS CW
3/4
"ø
GRADE EL=+/- 19.00
4" CW
4" CW
TS TS
FIRE PROTECTION PIPE
6" CW
2"ø
4"ø 4"ø
1 1/4"ø1 1/4" CW TO TOILET 116
1 1/2"øCW
CWCW
HW
HVAC PIPING
PUMP ROOM B1-18.00'
PUMP ROOM M1-9.92'
ED
1 1/2"ø
3"ø
3"ø
4"ø
3"ø3"ø
3"ø
3"ø
CW CW
3" DOUBLE CHECKDETECTOR ASSEMBLY
3" SHUT-OFF VALVE
3" DOUBLE CHECKDETECTOR ASSEMBLY
3" CWSEE DWG M-51FOR CONTINUATION
3" CWSEE DWG M-51FOR CONTINUATION
PROCESS PIPING
HVAC PIPING
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\ysa
vchenko
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
ysavc
henko
.rvt
7/1
5/2
016 2
:38: 1
2 P
M
1/4" = 1'-0"
P-21
YS
SECTIONS - SHEET 2
429
PLUMBING
MLF
GJ
MAY 2016
SCALE: 1/4" = 1'-0"P-11
1 SECTION 1/P-12
SCALE: 1/4" = 1'-0"P-12
2 SECTION 2/P-12
1/4"=1'-0"4 0 4 8 FT
SCALE: 1/4" = 1'-0"P-8
4 SECTION 4/P-8
1. ALL PIPING, ACCESSORIES AND DEVICES SHOWN ONTHIS DRAWING ARE NEW.
NOTE:
NO. DATE APPD DESCRIPTION
1 07/15/16 JED ADDENDUM NO. 3
1
EE
FLOOR AT EL +37.50
FLOOR AT EL +25.00
SH SH SH SH
CW
JMB
CORRIDOR210
JANITOR204
WC-1 UR-2 WC-1 WC-1 WC-2 WC-2
LOCKER ROOMS NO.1 & NO. 2205, 202
2-1/2"
CWHWLOCKER ROOMS NO.1 & NO. 2
205, 202
L-1 L-2
LOCKER ROOMS NO.1 & NO. 2205, 202
AIR GAP(TYP)
CWHW
CW
EWH-5 EWH-6 EWH-7
MECHANICALROOM NO.3
221
ELECTRIC TANKLESSWATER HEATER(TYP 3)
SHUT-OFF VALVE(TYP)
3"
1-1/4"
FIRE PREVENTIONROOM
201
HB
TOILET116
ENTRYLOBBY 101
TOILET106
LUNCHROOM 107
TOILET103
EWC-1 KS
4"
CW
EWH-4
(4) TMV-1
1-1/2"
ELECTRIC TANKLESSWATER HEATER(TYP4)
CWHW
FDEXPANSION TANK
CONDENSATEDRAIN, (TYP 3)
ROOF
FLOW SWITCH
EMERGENCYALARM SYSTEM
FLOOR AT EL +11.00
SERVICE VALVE(PROVIDED BY CIVIL)
MOCVGATE VALVE(TYP 2)
MICVGATE VALVE(TYP 2)
1-1/2" TO 6 HOSE BIBBSIN PUMP ROOM
1" TO HOSE BIBBIN BOILER ROOM
8" #1 CW FROMCITY MAIN
4"
4" WATER METER(TYP 2)(SEE NOTE 4)
DOUBLE CHECKDETECTOR ASSEMBLY(TYP 2)
POINT "A" - SEE DWG FP-6FOR CONTINUATION
TS
TS
DOUBLE CHECKDETECTOR ASSEMBLY(TYP 2)
FOR CONTINUATIONSEE DWGS M-6 AND M-51
3"
CHECK VALVE(TYP)
8"
8"
8" #2 CW FROMCITY MAIN
8"
8"
4"
4"
8"
PROCESSWATER
6"
3"
3/4" TO HOSE BIBBAND SERVICE SINKIN BOILER ROOM
EXTERIORWALL
GROUND
RH RH RH
3/4" DRAIN(TYP 3)
EEHBFLOW SWITCH
EMERGENCYALARM SYSTEM
HB
GENERATORROOM
124
BATTERYROOM
126
FLOOR AT EL +21.58
1 1/2"
1"
1 1/2"
EWH-1 EWH-3
EWH-2
(6) TMV-1
CW
3"
4"
4"
INSTALL PER ADAREQUIREMENTS
PROCESSWATER
1/2"1"
WH
3/4"
1/2"
WH
3/4"
3/4" 3/4" 1/2"
1" TO HOSE BIBBSIN MECHANICAL ROOM NO. 1,MECHANICAL ROOM NO. 2,AND TO ROOF HYDRANTS ATGENERATOR ROOF
CW
SH
3/4"3/4"
CW
HW
HW
1-1/4"
INSTALL PER ADAREQUIREMENTS
L-2 L-2 L-2 L-1
L-1 L-1 WC-2WC-2
EWC-1
WC-2 L-1
1/2" TYP
1/4" 1/2" 3/4"
1/2" 1"1"
3/4
"
HW
1 1/4"
1 1/2"
1 1/2"
2" 1/2" 3/4" 1"
1/2" TYP
1-1/4"
1 1/2"
1"
1/2"
3/4
"
3"
1"
1/2"
1"
1/4"
3/4"
1/2"
1/2"
1"
1-1/4"
1"
3/4
"
1/2"
1"
CW
HW
PUMP ROOMB101
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\ysa
vchenko
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
ysavc
henko
.rvt
7/1
5/2
016 2
:38: 5
4 P
M
NO SCALE
P-22
YS
DOMESTIC WATER PIPING DIAGRAMS
430
PLUMBING
MLF
GJ
MAY 2016
SCALE: NO SCALE
DOMESTIC WATER PIPING DIAGRAM
1. GAS SUPPLY PIPING SEE HVAC DRAWINGS.2. ELECTRICAL CONNECTIONS SEE ELECTRICAL
DRAWINGS.3. FOR WATER HEATERS # 1, 2, 3, AND 4 ONLY PROVIDE A
GALVANIZED STEEL PAN WITH A MINIMUM THICKNESS OF24 GAGE, 0.0276 INCH SIZE 36"x36"x2" DEEP. PROVIDE 1"DRAIN PIPE FROM PAN TO THE NEAREST FLOOR DRAIN.PROVIDE 1" RELIEF VALVE DISCHARGE PIPE FROM THERELIEF VALVE AND TERMINATE ATMOSPHERICALLY 6"ABOVE THE FLOOR.
4. ONE WATER METER SUPPLIED BY CITY OF CHICAGO.SECOND WATER METER SUPPLIED BY THE CONTRACTOR.
5. APPROVED T&P RELIEF REQUIRED FOR ALL WATERHEATERS.
6. PROVIDE AIR CHAMBERS AT ALL FIXTURES.
NOTES:
NO. DATE APPD DESCRIPTION
1 07/15/16 JED ADDENDUM NO. 3
1
GPCGENERATOR PARALLELING
CONTROLLER
LEGCP-1LOCAL ENGINE
GENERATOR CONTROLPANEL
MSG-14.16KV MAIN
SWITCHGEAR
MOTOR CONTROLCENTERMCC-2
*DISCRETE SIGNALS(ANCILLARY SYSTEMSTART, STATUS)
*DISCRETE SIGNALS (ENGINESTART, DRY CONTACTS)
*COMMUNICATION
*COMMUNICATIONC21
C23C22
GSMCPGENERATOR
MASTER CONTROLPANEL
RIO
C9
N24AN24B
NETWORKACCESS PANEL
NAP-M3
C30
SHOWN FOR GENERATOR G-1.SIMILAR FOR G-2, G-3, G-4.
N35
TO GPC
C32
PUMP NO.1 VFD
TYPICALFOR 4
VIBRATIONSENSORS
VE SE
101
PUMP NO.1CONTROL
PANELP1CP
469 RELAY
TE
SPEEDSENSOR
TYPICAL FOR 12TEMPERATURE
SENSORS
E-STOPTRANSMITTER
PUMP NO.1MOTOR
HEATER
1MP4 1MP3 1MP1
1MP2
1MP5
LUBE OIL PUMP NO.1CONTROL PANEL
LUBE OIL SKID
FS
123A
FLOWSWITCH
FS
123B
FLOWSWITCH
LS
110
LEVELSWITCH
PSL
170APRESSURE
SWITCH
FS
170AFLOW
SWITCH
PSL
170BPRESSURE
SWITCH
FS
170BFLOW
SWITCH
ZSH
180LIMIT
SWITCH
ZSL
180ALIMIT
SWITCH
PIT
104PRESSURE
TRANSMITTER
HYDRAULIC ACTUATORCABINET HAV-1
DV-1 ACTUATOR
PIT
150PRESSURE
TRANSMITTER
PIT
600
LS
201LEVEL
SWITCH
FT
160FLOW
TRANSMITTER
PRESSURETRANSMITTER
SV
170SOLENOID
VALVE
1C2
1C1
1C3
1C3B1C3A
1C4A1C4B
1C5
1C8
1C6
1C9
1C7
1C10
1C11
1C12
1C13A1C13B
1C14A1C14B
1C17
1C15
1C16
SEE NOTE 4
3/4"C - 3/C#16
3/4"C - 2/C#16 TWSP
3/4"C - 2/C#16 TWSP
DWP-1DEWATERING PUMP
CONTROL PANEL(SPECIFIED UNDERSECTION 22 14 29)
DWCC-1DEWATERING
SYSTEMCONTROL PANEL
(SPECIFIED UNDERSECTION 40 96 55)
*DISCRETE SIGNALS(START, STATUS)
MCC-1
USS-1
MLDP-1
*SHUNT TRIPSIGNALS
*HAS-1 CB*HAS-2 CB*VPS-1 CB*SL-2 CB
40
DEWATERING PUMP
40
DEWATERING PUMP
FROMMCC-1
LIST OF EQUIPMENT TOBE SHUNT TRIPPED
*FEEDER CB TO PP-1
*FEEDER CB TO LDP-1
MSG-1
*52P1*52P2*52P3*52P4*52P5
UDP-A *FEEDER BREAKER TO UDP-1*FEEDER BREAKER TO UDP-6
FS
920G
DEWATERING SYSTEMCONTROL PANEL
(SPECIFIED UNDERSECTION 40 96 55)
FS
920F
FS
920D
EL +25.00
EL +10.00
EL -9.92
EL -18.00
HAS-1HAS-2VPS-1SL-2
PUMP NO.1PUMP NO.2PUMP NO.3PUMP NO.4PUMP NO.5
PUMP CONTROL PANELSNETWORK ACCESS PANELSVALVE OPERATORSLUBE OIL PUMP CONTROLPANELS
SP-1SP-2SP-3SP-4
LIGHTINGRECEPTACLES
LIGHTINGRECEPTACLES
DISCHARGE VALVEOPERATORS
SUCTIONS VALVEOPERATORSPORTABLE ACTUATORRECEPTACLE
1M13
SEE NOTE 3
SEE NOTE 3
LDP-1 *AREA A LIGHTING*AREA A RECEPTACLES
FS
920B
FLOATSWITCH(TYP)
FS
920A
EL -20.00
PUMPSTOP
SEE NOTE 3
SEENOTE 3
DWP-1A DWP-1B
FROMUDP-A
1UP3
ALARM ROTARYBEACON LIGHTS
EVACUATION SIREN
MLDP-2
*CB TO PORTABLEACTUATORRECEPTACLEFS
920C
FS
920E
MONITORINGSYSTEM
*DISCRETE SIGNALS(STATUS, ALARMS)
SEENOTE 3
DWAA-1(ANNUNCIATOR)
SEENOTE 3
ENGINESKID
AUXILIARYSKID
(SEE NOTE 1)
REMOTERADIATOR
FUELSYSTEM
1
2
1 2
1
LEGEND
PROVIDED AND TESTED AS ACOMPLETE ASSEMBLY BY THEMANUFACTURER PER SPECIFICATION26 32 00.
PROVIDED BY THE CONTRACTOR ANDFIELD INSTALLED. (MULTIPLECONNECTIONS AS REQUIRED)
1
2
2
2
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\mm
onte
\Docu
ments
\12354-C
PP
S-G
CM
HP
EI_
mm
onte
.rvt
7/1
3/2
016 4
:39: 3
2 P
M
NONE
E-47
MTM
BLOCK DIAGRAMS - SHEET 1
486
ELECTRICAL
BRG
JFM
MAY 2016
SCALE: NONE
GENERATOR CONTROL BLOCK DIAGRAM
SCALE: NONE
PUMP NO.1 BLOCK DIAGRAM
SCALE: NONE
DEWATERING SYSTEM BLOCK DIAGRAM
SCALE: NONE
GENERATOR BLOCK DIAGRAM
(SIMILAR FOR PUMPS NO. 2, 3, 4, 5, SEE NOTE 2)
1. SKID INCLUDES CHARGED AIR COOLER, FUEL OILCOOLER, HEAT EXCHANGER, CIRCULATION PUMP ANDDAY TANK.
2. CONDUIT TAGS AND QUANTITIES DIFFER FOR PUMPSNO.2,3,4 AND 5. REFER TO CABLE AND CONDUITSCHEDULE FOR TAGS AND QUANTITIES.
3. PROVIDE CABLE, CONDUIT AND ANCILLARYEQUIPMENT AS NECESSARY FOR A COMPLETESYSTEM PER SPECIFICATION 40 96 55.
4. REQUIRED CONDUIT AND CABLE PROVIDED BYEQUIPMENT MANUFACTURER.
NOTES:
NO. DATE APPD DESCRIPTION
1 07/15/16 NV ADDENDUM NO. 3
1
1
1
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
A B C
200AT
225AF
SOLIDNEUTRAL
LOAD-VA
AN BN CNSUB TOT 20,498 20,498 21,098
TOTAL 62,094
UPS PANEL 1 UDP-1(PUMP ROOM)208Y/120V, 3PH, 4W, 12KA SCCR, 225A BUSALL CIRCUIT BREAKERS ARE 20A, 1PUNLESS NOTED OTHERWISE
P1CP SOURCE 1 (300)
P2CP SOURCE 1 (300)
P3CP SOURCE 1 (300)
P4CP SOURCE 1 (300)
P5CP SOURCE 1 (300)
WATER QUALITY MONITORING PANEL (600)
PUMP 1 LUBE OIL CP (4,200)
PUMP 3 LUBE OIL CP (4,200)
PUMP 5 LUBE OIL CP (4,200)
DV-2 DISCONNECT SWITCH (5,044)
DV-4 DISCONNECT SWITCH (10,880)
(300) P1CP SOURCE 2
(300) P2CP SOURCE 2
(300) P3CP SOURCE 2
(300) P4CP SOURCE 2
(300) P5CP SOURCE 2
(600) WATER QUALITY MONITORING PANEL
(4,200) PUMP 2 LUBE OIL CP
(4,200) PUMP 4 LUBE OIL CP
(5,044) DV-1 DISCONNECT SWITCH
(5,044) DV-3 DISCONNECT SWITCH
(10,880) DV-5 DISCONNECT SWITCH
35A 35A
20A20A
20A 20A
20A20A
20A 20A
20A
20A
20A
20A
20A
20A 20A
20A
20A
20A
20A
20A
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
A B C
200AT
225AF
SOLIDNEUTRAL
UDP-A(MAIN UPS DISTRIBUTION PANEL)208Y/120V,3PH,4W,12KA SCCR,225A BUS(SEE NOTE 1)
UDP-1DWCC-1(SEE NOTE 2)
30A
100AUDP-6
SPARE
100ASPARE
200A
100A
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
A B C
200AT
225AF
SOLIDNEUTRAL
UDP-B(MAIN UPS DISTRIBUTION PANEL)208Y/120V,3PH,4W,12KA SCCR,225A BUS
UDP-3UDP-2100A
100AUDP-4
SPARE
100AUDP-5
100A
100ASPARE
100A
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
A B C
50AT
100AF
SOLIDNEUTRAL
LOAD-VA
AN BN CNSUB TOT 5,220 5,040 4,040
TOTAL 14,300
UPS PANEL 2 UDP-2(SCADA SERVER ROOM)208Y/120V, 3PH, 4W, 12KA SCCR, 100A BUSALL CIRCUIT BREAKERS ARE 20A, 1PUNLESS NOTED OTHERWISE
SCADA SERVER RACK A (3,500) (180) RECEPTACLES40A 20A
EXISTING SCADA SERVER (3,500)40A
(180) RECEPTACLES
(180) RECEPTACLESSCADA SERVER RACK B (3,500)
RECEPTACLES (180)
RECEPTACLES (180)
RECEPTACLES (180)
RECEPTACLES (180)
(180) RECEPTACLES
(180) RECEPTACLES
(180) RECEPTACLES
(1000) TELECOM/DATA RACK
(1000) TELECOM/DATA RACK
20A
20A
40A
20A
20A
20A
20A
20A
20A
20A
20A
20A
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
A B C
50AT
100AF
SOLIDNEUTRAL
LOAD-VA
AN BN CNSUB TOT 3,920 2,520 4,200
TOTAL 10,640
UPS PANEL 3 UDP-3(SECURITY SERVER ROOM)208Y/120V, 3PH, 4W, 12KA SCCR, 100A BUSALL CIRCUIT BREAKERS ARE 20A, 1PUNLESS NOTED OTHERWISE
RECEPTACLES (180) (180) RECEPTACLES
RECEPTACLES (180) (180) RECEPTACLES
20A
20A
20A
20A
(1000) RAP-120A
(1000) RAP-220A
(1000) RAP-320A
(1000) RAP-420A
ELECTRIC DOOR STRIKES (1200)20A
ELECTRIC DOOR STRIKES (1200)20A
ELECTRIC DOOR STRIKES (800)20A
RECEPTACLES (180)
RECEPTACLES (180)
(180) RECEPTACLES
(180) RECEPTACLES
(1000) SECURITY RACK20A
(1000) SECURITY RACK20A
SPARE
SPARE
SPARE
20A
20A
20A
20A
20A
20A
20A
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
A B C
50AT
100AF
SOLIDNEUTRAL
LOAD-VA
AN BN CNSUB TOT 100 3,500 1,000
TOTAL 4,600
UPS PANEL 4 UDP-4(GENERATOR ROOM)208Y/120V, 3PH, 4W, 12KA SCCR, 100A BUSALL CIRCUIT BREAKERS ARE 20A, 1PUNLESS NOTED OTHERWISE
SPARE SPARE
GSMCP (SCADA) (1500)
LVSCP (SCADA) (1000)
(500) NAP-M3
(500) NAP-M4
SPARE
SPARE
SPARE
(1000) RAP-5
20A20A
20A 20A
20A
20A
20A
20A
20A
20A
20ARESCUE ASSISTANCE POWER SUPPLY (100)
SPARE20A
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
11: 4
8:13
AM
NONE
E-51
LAN
PANELBOARD SCHEDULES - SHEET 3
490
ELECTRICAL
BRG
JFM
MAY 2016
1. REFER TO DEWATERING SYSTEMSPECIFICATION 70 96 55 AND BLOCKDIAGRAM ON DRAWING E-47 FORCIRCUIT BREAKERS TO BE CAPABLE OFSHUNT TRIP.
2. CONTRACTOR TO VERIFY BREAKER SIZEWITH DEWATERING SYSTEM CONTROLPANEL.
NOTES:
NO. DATE APPD DESCRIPTION1 07/15/16 NV ADDENDUM NO. 3
11
1
1
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
12: 0
2:50
PM
E-53
MTM
CABLE AND CONDUIT SCHEDULES - SHEET1
492
ELECTRICAL
BRG
JFM
MAY 2016
CABLE AND CONDUIT SCHEDULE - SHEET 1
CONDUITNUMBER
CONDUITSIZE
CONDUCTOR QUANTITY ANDSIZE FROM TO REMARKS
2MP2 1" 3 #8 & 1 #10 G PUMP NO.2 CONTROL PANEL P2CP PUMP NO.2 MOTOR MOTOR HEATER2MP3 2" 3 #8, 2#10, & 2 #10 G PUMP NO.2 CONTROL PANEL P2CP VARIABLE FREQUENCY DRIVE VFD-2 E-STOP/HEATER2MP4 2" 14-3/C#16 PUMP NO.2 CONTROL PANEL P2CP VARIABLE FREQUENCY DRIVE VFD-2 TEMPERATURE SENSORS2MP5 2" 11 - 2/C #16 TWSP PUMP NO.2 CONTROL PANEL P2CP VARIABLE FREQUENCY DRIVE VFD-2 VIBRATION AND SPEED
SENSORS
3MP1 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-3 PUMP NO.3 MOTOR3MP2 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-3 PUMP NO.3 MOTOR3MP3 1" 3 #8 & 1 #10 G PUMP NO.3 CONTROL PANEL P3CP PUMP NO.3 MOTOR MOTOR HEATER3MP4 2" 3 #8, 2#10, & 2 #10 G PUMP NO.3 CONTROL PANEL P3CP VARIABLE FREQUENCY DRIVE VFD-3 E-STOP/HEATER3MP5 2" 14-3/C#16 PUMP NO.3 CONTROL PANEL P3CP VARIABLE FREQUENCY DRIVE VFD-3 TEMPERATURE SENSORS3MP6 2" 11 - 2/C #16 TWSP PUMP NO.3 CONTROL PANEL P3CP VARIABLE FREQUENCY DRIVE VFD-3 VIBRATION AND SPEED
SENSORS
4MP1 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-4 PUMP NO.4 MOTOR4MP2 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-4 PUMP NO.4 MOTOR4MP3 1" 3 #8 & 1 #10 G PUMP NO.4 CONTROL PANEL P4CP PUMP NO.4 MOTOR MOTOR HEATER4MP4 2" 3 #8, 2#10, & 2 #10 G PUMP NO.4 CONTROL PANEL P4CP VARIABLE FREQUENCY DRIVE VFD-4 E-STOP/HEATER4MP5 2" 14-3/C#16 PUMP NO.4 CONTROL PANEL P4CP VARIABLE FREQUENCY DRIVE VFD-4 TEMPERATURE SENSORS4MP6 2" 11 - 2/C #16 TWSP PUMP NO.4 CONTROL PANEL P4CP VARIABLE FREQUENCY DRIVE VFD-4 VIBRATION AND SPEED
SENSORS
5MP1 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-5 PUMP NO.5 MOTOR5MP2 4" 3 - 350 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-5 PUMP NO.5 MOTOR5MP3 1" 3 #8 & 1 #10 G PUMP NO.5 CONTROL PANEL P5CP PUMP NO.5 MOTOR MOTOR HEATER5MP4 2" 3 #8, 2#10, & 2 #10 G PUMP NO.5 CONTROL PANEL P5CP VARIABLE FREQUENCY DRIVE VFD-5 E-STOP/HEATER5MP5 2" 14-3/C#16 PUMP NO.5 CONTROL PANEL P5CP VARIABLE FREQUENCY DRIVE VFD-5 TEMPERATURE SENSORS5MP6 2" 11 - 2/C #16 TWSP PUMP NO.5 CONTROL PANEL P5CP VARIABLE FREQUENCY DRIVE VFD-5 VIBRATION AND SPEED
SENSORS
CABLE AND CONDUIT SCHEDULE - SHEET 1
CONDUITNUMBER
CONDUITSIZE
CONDUCTOR QUANTITY ANDSIZE FROM TO REMARKS
COMED SERVICE NO.1, LINE NO.1 AND SERVICE NO.1, LINE NO.21U1 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.11U2 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.11U3 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.11U4 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.11U5 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.11U6 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-1 SERVICE NO.1COMED SERVICE NO.2, LINE NO.1 AND SERVICE NO.2, LINE NO.22U1 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.22U2 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.22U3 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.22U4 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.22U5 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.22U6 5" SEE NOTE 1 REMOTE COMED SWITCHGEAR COMED SWITCHGEAR USG-2 SERVICE NO.2MSG-1 SERVICE1UT1 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-1 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.11UT2 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-1 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.11UT3 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-1 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.11UT4 4" EMPTY COMED TRANSFORMER UT-1 SWITCHGEAR MSG-1 SPARE2UT1 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-2 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.22UT2 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-2 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.22UT3 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-2 SWITCHGEAR MSG-1 SERVICE NO.1, LINE NO.22UT4 4" EMPTY COMED TRANSFORMER UT-2 SWITCHGEAR MSG-1 SPARE3UT1 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-3 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.13UT2 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-3 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.13UT3 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-3 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.13UT4 4" EMPTY COMED TRANSFORMER UT-3 SWITCHGEAR MSG-1 SPARE4UT1 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-4 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.24UT2 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-4 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.24UT3 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 #4/0 G COMED TRANSFORMER UT-4 SWITCHGEAR MSG-1 SERVICE NO.2, LINE NO.24UT4 4" EMPTY COMED TRANSFORMER UT-4 SWITCHGEAR MSG-1 SPAREMSG-1 FEEDERS1MS2 4" 3 # 4/0 & 1 # 3/0 G SWITCHGEAR MSG-1 TRANSFORMER T-1 (USS-1) UNIT SUBSTATION FEED NO.11MS4A 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS4B 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS4C 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS4D 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS4E 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS4F 4" SPARE SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.11MS6 4" 3 - 500 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-11MS8A 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS8B 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS8C 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS8D 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS8E 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS8F 4" SPARE SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.11MS12A 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-31MS12B 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-31MS17A 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-41MS17B 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-41MS21A 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-51MS21B 4" 3 - 350 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-51MS23A 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS23B 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS23C 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS23D 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS23E 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS23F 4" SPARE SWITCHGEAR MSG-1 TEMPORARY GENERATION TSG-1 FEED NO.21MS25 4" 3 - 500 KCMIL & 1 #3/0 G SWITCHGEAR MSG-1 VARIABLE FREQUENCY DRIVE VFD-21MS27 4" 3 # 4/0 & 1 # 3/0 G SWITCHGEAR MSG-1 TRANSFORMER T-2 (USS-1) UNIT SUBSTATION FEED NO.21MS29A 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.21MS29B 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.21MS29C 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.21MS29D 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.21MS29E 4" 3 - 350 KCMIL & 1 - 300 KCMIL G SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.21MS29F 4" SPARE SWITCHGEAR MSG-1 GENERATOR SWITCHGEAR GSG-1 GENERATOR FEED NO.2GSG-11GS2A 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-11GS2B 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-11GS4A 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-21GS4B 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-21GS8A 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-31GS8B 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-31GS10A 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-41GS10B 4" 3 - 350 KCMIL & 1 - 350 KCMIL N & 1 # 4/0 G GENERATOR SWITCHGEAR GSG-1 GENSET G-4
1MP1 4" 3 - 500 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-1 PUMP NO.1 MOTOR1MP2 1" 3 #8 & 1 #10 G PUMP NO.1 CONTROL PANEL P1CP PUMP NO.1 MOTOR MOTOR HEATER1MP3 2" 3 #8, 2#10, & 2 #10 G PUMP NO.1 CONTROL PANEL P1CP VARIABLE FREQUENCY DRIVE VFD-1 E-STOP/HEATER1MP4 2" 14-3/C#16 PUMP NO.1 CONTROL PANEL P1CP VARIABLE FREQUENCY DRIVE VFD-1 TEMPERATURE SENSORS1MP5 2" 11 - 2/C #16 TWSP PUMP NO.1 CONTROL PANEL P1CP VARIABLE FREQUENCY DRIVE VFD-1 VIBRATION AND SPEED
SENSORS
2MP1 4" 3 - 500 KCMIL & 1 #3/0 G VARIABLE FREQUENCY DRIVE VFD-2 PUMP NO.2 MOTOR
1. CABLE PROVIDED BY COMED.NOTE:
NO. DATE APPD DESCRIPTION1 07/15/16 NV ADDENDUM NO. 3
1
1
1
1
1
1
1
1
1
1
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7/
21/2
016
2:46
:32
PM
E-56
MTM
CABLE AND CONDUIT SCHEDULES - SHEET4
495
ELECTRICAL
BRG
JFM
MAY 2016
CABLE AND CONDUIT SCHEDULE - SHEET 5
CONDUITNUMBER
CONDUITSIZE
CONDUCTOR QUANTITYAND SIZE FROM TO REMARKS
5C2B 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 523B5C3A 1" 16 #14 & 1 - #14 G P5CP LUBE OIL SKID5C3B 3/4" 2/C #16 TWSP P5CP LUBE OIL SKID5C4 3/4" 2 #14 & 1 - #14 G P5CP SV 5705C5 3/4" 2 #14 & 1 - #14 G P5CP FS 570A5C6 3/4" 2 #14 & 1 - #14 G P5CP FS 570B5C7 3/4" 2 #14 & 1 - #14 G P5CP PSL 580A5C8 3/4" 2 #14 & 1 - #14 G P5CP PSL 580B5C9 3/4" 2 #14 & 1 - #14 G P5CP ZSH 580A5C10 3/4" 2 #14 & 1 - #14 G P5CP ZSL 580A5C11 3/4" 2/C #16 TWSP P5CP PIT 5045C12A 1" 16 #14 & 1 - #14 G P5CP HAV-55C12B 3/4" 2/C #16 TWSP P5CP HAV-55C13A 1" 16 #14 & 1 - #14 G P5CP DV-55C13B 3/4" 2/C #16 TWSP P5CP DV-55C14 3/4" 2/C #16 TWSP P5CP PIT 5505C15 3/4" 2/C #16 TWSP P5CP FT 5605C16 3/4" 6 #14 & 1 - #14 G P5CP FREIGHT ELEVATOR CP
N1A 3/4" 1 - CAT6e P1CP NAP-P1N1B 3/4" 1 - CAT6e P1CP NAP-P1N2A 3/4" 1 - CAT6e P2CP NAP-P2N2B 3/4" 1 - CAT6e P2CP NAP-P2N3A 3/4" 1 - CAT6e P3CP NAP-P3N3B 3/4" 1 - CAT6e P3CP NAP-P3N4A 3/4" 1 - CAT6e P4CP NAP-P4N4B 3/4" 1 - CAT6e P4CP NAP-P4N5A 3/4" 1 - CAT6e P5CP NAP-P5N5B 3/4" 1 - CAT6e P5CP NAP-P5N6A 3/4" 1 - CAT6e NAP-P1 NAP-P2N6B 3/4" 1 - CAT6e NAP-P1 NAP-P2N7A 3/4" 1 - CAT6e NAP-P2 NAP-P5N7B 3/4" 1 - CAT6e NAP-P2 NAP-P5N8A 3/4" 1 - CAT6e NAP-P5 NAP-M1N8B 3/4" 1 - CAT6e NAP-P5 NAP-M1N9A 3/4" 1 - CAT6e NAP-M1 NAP-P4N9B 3/4" 1 - CAT6e NAP-M1 NAP-P4N10A 3/4" 1 - CAT6e NAP-P4 NAP-P3N10B 3/4" 1 - CAT6e NAP-P4 NAP-P3N11A 3/4" 1 - CAT6e NAP-P3 NAP-P1N11B 3/4" 1 - CAT6e NAP-P3 NAP-P1N12A 3/4" 1 - CAT6e NAP-M1 HAS-1N12B 3/4" 1 - CAT6e NAP-M1 HAS-1N13A 3/4" 1 - CAT6e NAP-M1 HAS-2N13B 3/4" 1 - CAT6e NAP-M1 HAS-2N14A 3/4" 1 - CAT6e NAP-M1 VPS-1N14B 3/4" 1 - CAT6e NAP-M1 VPS-1N15A 3/4" 1 - CAT6e NAP-VFD V1CPN15B 3/4" 1 - CAT6e NAP-VFD V1CPN16A 3/4" 1 - CAT6e NAP-VFD V2CPN16B 3/4" 1 - CAT6e NAP-VFD V2CPN17A 3/4" 1 - CAT6e NAP-VFD V3CPN17B 3/4" 1 - CAT6e NAP-VFD V3CPN18A 3/4" 1 - CAT6e NAP-VFD V4CPN18B 3/4" 1 - CAT6e NAP-VFD V4CPN19A 3/4" 1 - CAT6e NAP-VFD V5CPN19B 3/4" 1 - CAT6e NAP-VFD V5CPN20 3/4" 1 - CAT6e NAP-VFD NAP-MSGN20A 3/4" 1 - CAT6e NAP-VFD NAP-MSGN21A 3/4" 1 - CAT6e NAP-MSG MSGCPN21B 3/4" 1 - CAT6e NAP-MSG MSGCPN22 3/4" 1 - CAT6e NAP-MSG NAP-M2N22A 3/4" 1 - CAT6e NAP-MSG NAP-M2N23A 3/4" 1 - CAT6e NAP-VFD NAP-M2N23B 3/4" 1 - CAT6e NAP-VFD NAP-M2N24A 3/4" 1 - CAT6e GSMCP GCP-1N24B 3/4" 1 - CAT6e GSMCP GCP-1N25A 3/4" 1 - CAT6e GSMCP GCP-2N25B 3/4" 1 - CAT6e GSMCP GCP-2N26A 3/4" 1 - CAT6e GSMCP GCP-3N26B 3/4" 1 - CAT6e GSMCP GCP-3N27A 3/4" 1 - CAT6e GSMCP GCP-4N27B 3/4" 1 - CAT6e GSMCP GCP-4N28A 3/4" 1 - CAT6e GSMCP NAP-M3N28B 3/4" 1 - CAT6e GSMCP NAP-M3N29A 3/4" 1 - CAT6e LVSCP NAP-M4N29B 3/4" 1 - CAT6e LVSCP NAP-M4N30A 1 1/2" 12 PAIR FIBER OPTIC CABLE SERVER RACK NAP-M1N30B 1 1/2" 12 PAIR FIBER OPTIC CABLE SERVER RACK NAP-M1N31A 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M1 NAP-M2N31B 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M1 NAP-M2N32A 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M2 NAP-M3N32B 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M2 NAP-M3N33A 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M3 NAP-M4N33B 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M3 NAP-M4N34A 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M4 SERVER RACKN34B 1 1/2" 12 PAIR FIBER OPTIC CABLE NAP-M4 SERVER RACKN35 3/4" 2/C #16 TWSP GPC LEGCP-1N36 3/4" 2/C #16 TWSP GPC LEGCP-2N37 3/4" 2/C #16 TWSP GPC LEGCP-3N38 3/4" 2/C #16 TWSP GPC LEGCP-4
CABLE AND CONDUIT SCHEDULE - SHEET 5
CONDUITNUMBER
CONDUITSIZE
CONDUCTOR QUANTITYAND SIZE FROM TO REMARKS
1C1 3/4" 2 #14 & 1 - #14 G P1CP LS 2011C2 3/4" 2 #14 & 1 - #14 G P1CP LS 1101C3 1" 16 #14 & 1 - #14 G P1CP LUBE OIL CP1C3A 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 123A1C3B 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 123B1C4A 1" 16 #14 & 1 - #14 G P1CP LUBE OIL SKID1C4B 3/4" 2/C #16 TWSP P1CP LUBE OIL SKID1C5 3/4" 2 #14 & 1 - #14 G P1CP SV 1701C6 3/4" 2 #14 & 1 - #14 G P1CP FS 170A1C7 3/4" 2 #14 & 1 - #14 G P1CP FS 170B1C8 3/4" 2 #14 & 1 - #14 G P1CP PSL 180A1C9 3/4" 2 #14 & 1 - #14 G P1CP PSL 180B1C10 3/4" 2 #14 & 1 - #14 G P1CP ZSH 180A1C11 3/4" 2 #14 & 1 - #14 G P1CP ZSL 180A1C12 3/4" 2/C #16 TWSP P1CP PIT 1041C13A 1" 16 #14 & 1 - #14 G P1CP HAV-11C13B 3/4" 2/C #16 TWSP P1CP HAV-11C14A 1" 16 #14 & 1 - #14 G P1CP DV-11C14B 3/4" 2/C #16 TWSP P1CP DV-11C15 3/4" 2/C #16 TWSP P1CP PIT 1501C16 3/4" 2/C #16 TWSP P1CP FT 1601C17 3/4" 2/C #16 TWSP P1CP PIT 6002C1 3/4" 2 #14 & 1 - #14 G P2CP LS 2022C2 3/4" 2 #14 & 1 - #14 G P2CP LS 2102C3 1" 16 #14 & 1 - #14 G P2CP LUBE OIL CP2C3A 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 223A2C3B 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 223B2C4A 1" 16 #14 & 1 - #14 G P2CP LUBE OIL SKID2C4B 3/4" 2/C #16 TWSP P2CP LUBE OIL SKID2C5 3/4" 2 #14 & 1 - #14 G P2CP SV 2702C6 3/4" 2 #14 & 1 - #14 G P2CP FS 270A2C7 3/4" 2 #14 & 1 - #14 G P2CP FS 270B2C8 3/4" 2 #14 & 1 - #14 G P2CP PSL 280A2C9 3/4" 2 #14 & 1 - #14 G P2CP PSL 280B2C10 3/4" 2 #14 & 1 - #14 G P2CP ZSH 280A2C11 3/4" 2 #14 & 1 - #14 G P2CP ZSL 280A2C12 3/4" 2/C #16 TWSP P2CP PIT 2042C13A 1" 16 #14 & 1 - #14 G P2CP HAV-22C13B 3/4" 2/C #16 TWSP P2CP HAV-22C14A 1" 16 #14 & 1 - #14 G P2CP DV-22C14B 3/4" 2/C #16 TWSP P2CP DV-22C15 3/4" 2/C #16 TWSP P2CP PIT 2502C16 3/4" 2/C #16 TWSP P2CP FT 2602C17 3/4" 2/C #16 TWSP P2CP AIT 9012C18 3/4" 2/C #16 TWSP P2CP AIT 9022C19 3/4" 2/C #16 TWSP P2CP AIT 9033C1 3/4" 2 #14 & 1 - #14 G P3CP LS 3023C2 3/4" 2 #14 & 1 - #14 G P3CP LS 3103C3 1" 16 #14 & 1 - #14 G P3CP LUBE OIL CP3C3A 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 323A3C3B 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 323B3C4A 1" 16 #14 & 1 - #14 G P3CP LUBE OIL SKID3C4B 3/4" 2/C #16 TWSP P3CP LUBE OIL SKID3C5 3/4" 2 #14 & 1 - #14 G P3CP SV 3703C6 3/4" 2 #14 & 1 - #14 G P3CP FS 370A3C7 3/4" 2 #14 & 1 - #14 G P3CP FS 370B3C8 3/4" 2 #14 & 1 - #14 G P3CP PSL 380A3C9 3/4" 2 #14 & 1 - #14 G P3CP PSL 380B3C10 3/4" 2 #14 & 1 - #14 G P3CP ZSH 380A3C11 3/4" 2 #14 & 1 - #14 G P3CP ZSL 380A3C12 3/4" 2/C #16 TWSP P3CP PIT 3043C13A 1" 16 #14 & 1 - #14 G P3CP HAV-33C13B 3/4" 2/C #16 TWSP P3CP HAV-33C14A 1" 16 #14 & 1 - #14 G P3CP DV-33C14B 3/4" 2/C #16 TWSP P3CP DV-33C15 3/4" 2/C #16 TWSP P3CP PIT 3503C16 3/4" 2/C #16 TWSP P3CP FT 3604C1 3/4" 2 #14 & 1 - #14 G P4CP LS 4044C2 1" 16 #14 & 1 - #14 G P4CP LUBE OIL CP4C2A 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 423A4C2B 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 423B4C3A 1" 16 #14 & 1 - #14 G P4CP LUBE OIL SKID4C3B 3/4" 2/C #16 TWSP P4CP LUBE OIL SKID4C4 3/4" 2 #14 & 1 - #14 G P4CP SV 4704C5 3/4" 2 #14 & 1 - #14 G P4CP FS 470A4C6 3/4" 2 #14 & 1 - #14 G P4CP FS 470B4C7 3/4" 2 #14 & 1 - #14 G P4CP PSL 480A4C8 3/4" 2 #14 & 1 - #14 G P4CP PSL 480B4C9 3/4" 2 #14 & 1 - #14 G P4CP ZSH 480A4C10 3/4" 2 #14 & 1 - #14 G P4CP ZSL 480A4C11 3/4" 2/C #16 TWSP P4CP PIT 4044C12A 1" 16 #14 & 1 - #14 G P4CP HAV-44C12B 3/4" 2/C #16 TWSP P4CP HAV-44C13A 1" 16 #14 & 1 - #14 G P4CP DV-44C13B 3/4" 2/C #16 TWSP P4CP DV-44C14 3/4" 2/C #16 TWSP P4CP PIT 4504C15 3/4" 2/C #16 TWSP P4CP FT 4605C1 3/4" 2 #14 & 1 - #14 G P5CP LS 5055C2 1" 16 #14 & 1 - #14 G P5CP LUBE OIL CP5C2A 3/4" 2 #14 & 1 - #14 G LUBE OIL CP FS 523A
NO. DATE APPD DESCRIPTION1 07/15/16 NV ADDENDUM NO. 3
1
1
1
1
1
F9
WUH-52-21
WUH-62-21
WUH-72-21
WUH-82-21
LIGHTING/DISTRIBUTIONPANEL 2LDP-2
MAINTENANCEOBSERVATION
100
FL EL: 25.00
EXISTINGELEVATOR
B3
5
1LDP2
TO MCC-1
DEWATERINGCONTROL PANELDWP-1
1M13
SEE CONTINUATIONON DRAWING E-76
PULL BOXNEAREL +45.00SEE NOTE 2
ALARM ROTARYBEACON LIGHT FORDEWATERINGCONTROL SYSTEM(TYP)
TO UPS-1
DEWATERINGCONTROL CABINETDWCC-1(SEE NOTE 3)
CRANEDISCONNECTSWITCH
OVERHEAD DOOROCHD-1A
EXISTING ELEVATORDISCONNECT SWITCH
EXISTING WESTEXTERIOR LIGHTINGCONNECTION2-6
1M14
MLDT-2(WALL MOUNT ABOVEDISCONNECT SWITCH)
TO MCC-1TO MLDP-1
INSTALL CONDUITSABOVE WINDOWS (TYP)
1M15TO MCC-1
MAIN LIGHTING/DISTRIBUTIONPANEL 2MLDP-2
1M14A
1MP3, 1MP4, 1MP5
1MP1
1MP22MP3, 2MP4, 2MP5
1M8
OVERHEAD DOOROCHD-1B
1M16TO MCC-1
EXISTING WATER MONITORING PANELU1-11,12
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
11: 5
1:09
AM
3/16" = 1'-0"
E-73
MTM
AREA A - POWER PLAN AT EL +25.00
512
ELECTRICAL
BRG
JFM
MAY 2016
A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
SCALE: 3/16" = 1'-0"
AREA A - POWER PLAN AT EL +25.00
3/16"=1'-0"4 0 4 8 12 FT
1. CIRCUIT DESIGNATIONS ARE IDENTIFIED WITH #-#.THE FIRST NUMBER INDICATES THE PANEL ANDTHE SECOND NUMBER INDICATES THE CIRCUIT. I.E.2-25 INDICATES PANEL LDP-2 CKT 25.
2. PROVIDE SEPARATE PULL BOXES FOR LOWVOLTAGE AND MEDIUM VOLTAGE CONDUCTORS.PROVIDE BARRIERS IN THE LOW VOLTAGE PULLBOX TO SEPARATE POWER AND CONTROL WIRING.
3. SEE SPECIFICATION SECTION 40 96 55DEWATERING CONTROL SYSTEM FOR ADDITIONALDETAILS.
4. ALL REQUIRED PULL BOXES AND CONDUIT BODIESARE NOT SHOWN FOR CLARITY BUT MUST BEPROVIDED IN ACCORDANCE WITH SPECIFICATION26 05 33.
NOTE:
NO. DATE APPD DESCRIPTION1 07/15/16 NV ADDENDUM NO. 3
1
D
C1
B2
6 6B 7A 8A 8B 9A 10A
11
11A 12A
PARTS ROOM
B103
FL EL: 11.00
CORRIDOR
B102
FL EL: 11.00
STAIR C
UP TO DISCONNECTSWITCH (TYP OF 8)
EAF-146-1
SUMP PUMPCONTROLPANEL SP-5
TO MCC-2
TO MCC-2
SUMP PUMP CONTROLPANEL SP-6
SP-6A SP-6B
TO MCC-3SCISSOR LIFTSL-1CONTROL PANEL
SP-5B
SP-5A
2
E-81
GFI (TYP OF ALLROOMS ANDCORRIDOR)
HVAC PLENUM
FL EL: 11.00
B3
3
E-81
4
E-81
SEECONTINUATIONONDRAWING E-70
SEECONTINUATIONON DRAWINGE-75
PULL BOX(SEE NOTE 1)
5
E-81
UP TO GSG-1(TYP OF 20)
10
10
10
8
8
10
10 8
8 6 4 2
4
2 2
2
4
22446
68
12
4
6
6
8
64
686
2
68
12
MS
6-1(EAF-14)
TO MCC-3
FOCP-2
UP TO MCC-2(TYP OF 4)
UP TO MCC-3(TYP OF 4)
2M22
3M7
3M5
2M17
PULL BOXPB-2(SEE NOTE 1)
WELDING STORAGE
B105
FL EL: 11.00
WELDING SHOP
B104
FL EL: 11.00
ELECTRICAL SHOP
B109
FL EL: 11.00
ELECTRICAL STORAGE
B109-B
FL EL: 11.00
MECHANICALSTORAGE
B110-B
FL EL: 11.00
MECHANICAL SHOP
B110
FL EL: 11.00
PIPE FITTER SHOP
B111
FL EL: 11.00
PIPE FITTER STORAGE
B111-B
FL EL: 11.00
STAIR B
SEECONTINUATIONONDRAWING E-77
PERMANENTGENERATOR DUCTBANK. SEECONTINUATION ONDRAWING E-3
SEECONTINUATIONOF CONDUITROUTE ONDRAWING E-86
CONDUITTRANSITIONAREA
FUEL RETURN TANKROOM
B115
FL EL: 11.00
3M20B
3M20A
8
MSPP-1MSLP-1
MST-1
TO MCC-3
3M20
TO MSPP-1
SEE NOTE 5 (TYPFOR ALL 3 PHASERECEPTACLES INBASEMENT SHOPS)
BOILER/GENERATOR B1
11.00'
BOILER/GENERATOR L1
27.50'
4 SPARES, 1MP3, 1MP4, 1MP5,2MP3, 2MP4, 2MP5, 4MP4, 4MP5, 4MP6
1US8A, 1US8B
1MP1, 1MS27, 1US7A, 1US7B, 3MP1, 3MP2, 4MP1, 4MP27 SPARES, 3MP3, 3MP4, 3MP5, 5MP4, 5MP5, 5MP6
2MP1, 1MS2, 1US5A, 1US5B, 1US6A, 1US6B, 5MP1, 5MP22 SPARES
BOILER/GENERATOR B1
11.00'
BOILER/GENERATOR L1
27.50'
2 SPARES, 4MP4, 4MP5, 4MP6
1MS4F1MS4E1MS4D
1MS29F1MS29E1MS29D
1MS4A1MS4B1MS4C
1MS29A1MS29B1MS29C
2 SPARES, 5MP4, 5MP5, 5MP64MP1, 4MP25MP1, 5MP2, 1GS2A, 1GS2B2 SPARES, 1GS3A, 1GS3B1US9, 1US10, 1GS4A, 1GS4B1GS5A, 1GS5B
BOILER/GENERATOR B1
11.00'
BOILER/GENERATOR L1
27.50'
1MP1, 1MS27, 1US7A, 1US7B, 3MP1, 3MP22MP1, 1MS2, 1US5A, 1US5B, 1US6A, 1US6B1US8A, 1US8B, 1US3A, 1US3B, 1US4A, 1US4B1US10, 1US9
3 SPARES, 1MP3, 1MP4, 1MP5, 2MP3, 2MP33 SPARES, 2MP4, 2MP5, 3MP3, 3MP4, 3MP5
BOILER/GENERATOR B1
11.00'
BOILER/GENERATOR L1
27.50'
1MS4F1MS4E1MS4D
1MS29F1MS29E1MS29D
1MS4A1MS4B1MS4C
1MS29A1MS29B1MS29C
1GS2A, 1GS2B1GS4A, 1GS4B1GS8A, 1GS8B1GS10A, 1GS10B
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
11: 5
4:34
AM
As indicated
E-81
MTM
AREA D - PARTIAL POWER PLAN AT EL+11.00
520
ELECTRICAL
BRG
JFM
MAY 2016
SCALE: 3/16" = 1'-0"
AREA D - PARTIAL POWER PLAN AT EL +11.00A
FILLMORE ST
CE
NT
RA
L P
AR
K A
VE
B
C
D E F
KEY PLAN
3/16"=1'-0"4 0 4 8 12 FT
SCALE: 3/8" = 1'-0"E-812 CONDUIT ROUTE
3/8"=1'-0"1 0 1 2 43 5 6 7 FT
SCALE: 3/8" = 1'-0"E-813 CONDUIT ROUTE
SCALE: 3/8" = 1'-0"E-814 CONDUIT ROUTE SCALE: 3/8" = 1'-0"E-81
5 CONDUIT ROUTE
1. PROVIDE SEPARATE PULL BOXES FOR LOWVOLTAGE AND MEDIUM VOLTAGE CONDUCTORS.PROVIDE BARRIERS IN THE LOW VOLTAGE PULLBOX TO SEPARATE POWER AND CONTROL WIRING.
2. CIRCUIT DESIGNATIONS ARE IDENTIFIED WITH #-#.THE FIRST NUMBER INDICATES THE PANEL AND THESECOND NUMBER INDICATES THE CIRCUIT. I.E. 2-25INDICATES PANEL LDP-2 CKT 25.
3. ALL RECEPTACLES ON THIS DRAWING ARECONNECTED TO PANEL LDP-5. NUMBER ADJACENTTO RECEPTACLE REPRESENTS CIRCUIT NUMBER.
4. ALL REQUIRED PULL BOXES AND CONDUIT BODIESARE NOT SHOWN FOR CLARITY BUT MUST BEPROVIDED IN ACCORDANCE WITH SPECIFICATION26 05 33.
5. ALL THREE PHASE RECEPTACLES SHOWN ON THISDRAWING ARE NEMA L16-30 FED FROM THENEAREST PANELBOARD ON EL +11.00. COORDINATERECEPTACLE TYPE AND LOCATION WITH THECOMMISIONER'S REPRESENTATIVE.
NOTES:
NO. DATE APPD DESCRIPTION1 07/15/16 NV ADDENDUM NO. 3
1
SERVER ROOMAREA C AT EL +25.00
REFER TO DRAWING N-4 FORNETWORK CONFIGURATION DETAILS
EXISTING SERVER RACKREFER TO NOTE 1 SERVER RACKS A/B
PUMP ROOMAREA A AT EL -9.92
REFER TO DRAWING N-5 FORNETWORK CONFIGURATION DETAILS
PUMP NO. 4CONTROL PANEL
P4CP
NETWORKACCESS PANEL
NAP-P4
NETWORKACCESS PANEL
NAP-M1
VFD ROOMAREA E AT EL +21.58
REFER TO DRAWING N-6 FORNETWORK CONFIGURATION DETAILS
PUMP NO. 1 VFD CONTROL PANEL
V1CP
NETWORKACCESS PANEL
NAP-VFD
PUMP NO. 2 VFDCONTROL PANEL
V2CP
PUMP NO. 3 VFDCONTROL PANEL
V3CP
PUMP NO. 4 VFDCONTROL PANEL
V4CP
PUMP NO. 5 VFDCONTROL PANEL
V5CP
NETWORKACCESS PANEL
NAP-M2
MAIN SWITCHGEARCONTROL PANEL
MSGCP
NETWORKACCESS PANEL
NAP-MSG
GENSET MASTER CONTROL PANEL
GSMCP
GENSET 1CONTROLLER
GCP-1
NETWORKACCESS PANEL
NAP-M3
MEDIUM VOLTATGE SWITCHGEAR ROOMAREA E AT EL +21.58
REFER TO DRAWING N-6 FORNETWORK CONNECTION DETAILS
PARALLELING SWITCHGEAR ROOMAREA D AT EL +27.50
REFER TO DRAWING N-7 FORNETWORK CONNECTION DETAILS
LOW VOLTAGE SWITCHGEAR ROOMAREA B AT EL +33.00
REFER TO DRAWING N-7 FORNETWORK CONFIGURATION DETAILS
LV SWITCHGEAR CONTROL PANEL
LVSCP
NETWORKACCESS PANEL
NAP-M4
1
PUMP NO. 3CONTROL PANEL
P3CP
NETWORKACCESS PANEL
NAP-P3
1
PUMP NO. 1CONTROL PANEL
P1CP
NETWORKACCESS PANEL
NAP-P1
1
PUMP NO. 2CONTROL PANEL
P2CP
NETWORKACCESS PANEL
NAP-P2
1
PUMP NO. 5CONTROL PANEL
P5CP
NETWORKACCESS PANEL
NAP-P5
1
1 2 CONDUITS - 1 CAT 6e WIRE EACH
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2 CONDUITS - 12 PAIRS FIBER EACH
1
1
1
1
1
1
22
2
2
GENSET 2CONTROLLER
GCP-2
GENSET 3CONTROLLER
GCP-3
GENSET 4CONTROLLER
GCP-4
HAS-1 HAS-2 VPS-1 1
11GENERATOR ROOMAREA D AT EL +27.50
REFER TO DRAWING N-7 FORNETWORK CONNECTION DETAILS
SEE NOTE 5
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7/
21/2
016
3:09
:37
PM
NONE
N-3
MB
NETWORK OVERVIEW
586
INSTRUMENTATION
THP
THP
MAY 2016
SCALE: NONE
NETWORK OVERVIEW
1. MAINTAIN EXISTING SCADA NETWORK AFTERBEING RELOCATED, UNTIL EXISTING PUMPS ARETRANSFERRED TO NEW CONTROL SYSTEM.
2. FOR FIBER CONNECTION AND INSTALLATIONDETAILS REFER TO DRAWINGS N-31 AND 40 93 50.
3. PROVIDE FACTORY TESTED AND TERMINATEDCAT 6e CABLES FOR USE WITHIN PANELS.
4. NAP-M1, NAP-M2, NAP-M3, NAP-M4 ARE CORESWITCH PANELS.
5. TO JARDINE WPP VIA TELEPHONE BACKBOARD.6. ABBREVIATIONS:
NOTES:
- NAP: NETWORK ACCESS PANEL- HAS: HYDRAULIC ACCUMULATOR SYSTEM- VPS: VACUUM PRIMARY SYSTEM
NO. DATE APPD DESCRIPTION1 07/15/16 THP ADDENDUM NO. 3
1
1
1
1
1
1
1
1
O OO O O O O O O O O O O O O
O OO O O O O O O O O O O O O
O OO
OO
O OO
OO
O OO
OO
O OO
OO
O OO
OO
OO
O OO
OO
O OO
OO
O
OO
O OO
OO
OO
O OO
OO
OO
OO
O OO
OO
O
OO
O
OO
O OO
OO
O OO
OO
O OO
OO
O OO
OO
O OO
OO
O OO
OO
OO
O OO
OO
O
OO
O OO
OO
O OO
OO
O OO
OO
O OO
P5C
P I/
O
SHAFT
FOR CONTINUATIONSEE DRAWING N-2
M
DV-5CV-5
HS
540B
COHS
540A
LORHMS
540A
S
YL
540A
G
CLOSED
YL
540B
R
OPEN
YL
540C
A
FAULT
DV-5 ACTUATOR
FE
560
FT
560
VA
LVE
IN R
EM
OT
E O
PE
RA
TIO
N
VA
LVE
OP
EN
VA
LVE
FA
ULT
CLO
SE
VA
LVE
VA
LVE
CLO
SE
D
OP
EN
VA
LVE
FOR CONTINUATIONSEE DRAWING N-2
P5C
P-P
LC1
#
OIT
/HM
I
P5C
P
PIT
550
PU
MP
NO
. 5 C
UR
B P
RE
SS
UR
E
PU
MP
NO
. 5 D
ISC
HA
RG
E F
LOW
LS
510
VA
CU
UM
PR
IMIN
G R
EA
DY
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE
SPARE I/O AT P5CP-PLC1REFER TO I/O LIST ON DRAWING N-23
REFER TO DRAWING N-5FOR CONTINUATION
DIR
TY
OIL
FIL
TE
R 1
HIG
H O
IL T
EM
PE
RA
TU
RE
HIG
H O
IL P
RE
SS
UR
E P
UM
P 1
LOW
OIL
LE
VE
L
DIR
TY
OIL
FIL
TE
R 2
HIG
H O
IL P
RE
SS
UR
E P
UM
P 2
LOW
FLO
W T
O B
EA
RIN
GS
PU
MP
2 R
UN
NIN
G
PU
MP
1 R
UN
NIN
G
E-S
TO
P P
RE
SS
ED
SPARE
SPARE
SV-5
40"x42"INCREASER
YL
530A
G
CLOSED
YL
530B
R
OPEN
YL
530C
A
FAULT
REFER TO DRAWING N-17FOR CONTINUATION
48"
SPARE
SPARE
YA
501A
VF
D F
AU
LT
YI
501B
VF
D R
EA
DY
YI
501A
VF
D IN
RE
MO
TE
YI
501C
VF
D R
UN
NIN
G
SI
502A
PU
MP
SP
EE
D
YA
502A
HIG
H V
IBR
AT
ION
YA
502B
HIG
H T
EM
PE
RA
TU
RE
YA
502C
PU
MP
FA
ULT
YI
502A
PU
MP
RU
NN
ING
YI
540A
DV
-5 IN
RE
MO
TE
JIT
502A
ELA
SP
ED
RU
N T
IME
YI
540B
DV
-5 O
PE
N
YI
540C
DV
-5 C
LOS
ED
YA
540A
DV
-5 F
AU
LT
FI
560
PU
MP
NO
. 5D
ISC
HA
RG
E F
LOW
PI
550
PU
MP
NO
. 5C
UR
B P
RE
SS
UR
E
PI
600
ST
AT
ION
CU
RB
PR
ES
SU
RE
YA
521B
DIR
TY
FIL
TE
R 2
YA
520A
ES
TO
P P
RE
SS
ED
YA
522B
LOW
OIL
LE
VE
L
YA
521A
DIR
TY
FIL
TE
R 1
JIT
520A
PU
MP
1 R
UN
TIM
E
YA
520B
FA
ULT YA
523A
LOW
OIL
FLO
W A
LAR
M
JIT
520B
PU
MP
2 R
UN
TIM
E
YI
520B
PU
MP
2 R
UN
NIN
G
YA
705A
P5C
P-P
LC1
FA
IL
YA
705B
P5C
P-P
LC2
FA
IL
LUBE OIL SYSTEM
YI
510A
VA
CU
UM
PR
IMIN
G R
EA
DY
YA
570A
SE
AL
WA
TE
R L
OW
PR
ES
SU
RE
ALA
RM
YA
570B
SE
AL
WA
TE
R L
OW
PR
ES
SU
RE
ALA
RM
YI
570A
SE
AL
WA
TE
RF
LOW
AC
TIV
E
YI
570B
SE
AL
WA
TE
RF
LOW
AC
TIV
E
SEAL WATER SYSTEM PUMP NO. 5
YI
530A
CV
-5 O
PE
N
YI
530B
CV
-5 C
LOS
ED
YA
530A
CV
-5 F
AU
LT
CV-5 DV-5
YA
502D
PU
MP
WA
RN
ING
ALA
RM
YI
520A
PU
MP
1 R
UN
NIN
G
YA
521D
HI O
IL P
RE
SS
UR
E P
UM
P
YA
521C
HI O
IL P
RE
SS
UR
E P
UM
P
YA
522A
HI O
IL T
EM
PE
RA
TU
RE
PI
504A
DIS
CH
AR
GE
PR
ES
SU
RE
TO CURBPRESSURERING
HMS
520A
ES
YL
520B
W
CONTROLPOWER
ON
YL
520A
A
FAULT
LUBE OIL CONTROL PANEL
LUBE OIL SKID
PSH
521A
PSH
521B
PSH
521C
PSH
521D
LSL
522A
TSH
522B
OILTANK
FS
FS
523B
FS
FS
523A
TO PUMPBEARINGS
FROM LUBEOIL SYSTEM
FROM LUBEOIL SYSTEM
LS
TO AIR RECIEVER TANKREFER TO DRAWING M-7
FOR CONTINUATION
FROM PUMPREFER TO DRAWING M-7
FOR CONTINUATION 48"40"
MVS
PUMP NO. 5
SE
501
TE
503A
MO
TO
R S
HA
FT
SP
EE
D
TA
IL E
ND
SH
AF
T B
EA
RIN
G T
EM
PE
RA
TU
RE
DR
IVE
EN
D S
HA
FT
BE
AR
ING
TE
MP
ER
AT
UR
E
TA
IL E
ND
SH
AF
T B
EA
RIN
G T
EM
PE
RA
TU
RE
DR
IVE
EN
D S
HA
FT
BE
AR
ING
TE
MP
ER
AT
UR
E
TE
501A
VE
501A
MO
TO
R V
IBR
AT
ION
MO
TO
R V
IBR
AT
ION
MO
TO
R V
IBR
AT
ION
MO
TO
R V
IBR
AT
ION
MO
TO
R B
EA
RIN
G T
EM
PE
RA
TU
RE
MO
TO
R B
EA
RIN
G T
EM
PE
RA
TU
RE
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
MO
TO
R W
IND
ING
TE
MP
ER
AT
UR
E
TE
501B
TE
502A
TE
502B
TE
502C
TE
502DTE
502ETE
502F
VE
501B
VE
501C
VE
501D
TE
503B
TE
503C
TE
503D
XKT
501
PIT
504
PU
MP
NO
. 5 D
ISC
HA
RG
E P
RE
SS
UR
E
FROM SEALWATER SUPPLY
S
FI570A
PI
570A
PSL
570A
FS
FS
570A
TO PUMPSEAL
FI570B
PI
570B
PSL
570B
FS
FS
570B
TO PUMPSEAL
TO DRAIN
OP
EN
/CLO
SE
SE
AL
WA
TE
R S
OLE
NO
ID
SE
AL
WA
TE
R L
OW
PR
ES
SU
RE
ALA
RM
SE
AL
WA
TE
R F
LOW
AC
TIV
E
SE
AL
WA
TE
R L
OW
PR
ES
SU
RE
ALA
RM
SE
AL
WA
TE
R F
LOW
AC
TIV
E
VA
LVE
CLO
SE
D
VA
LVE
OP
EN
CLO
SE
VA
LVE
OP
EN
VA
LVE
EM
ER
GE
NC
Y C
LOS
E V
ALV
E
VA
LVE
FA
ULT
LS
205
YA
205A
HIG
H L
EV
EL
ALA
RM
INS
UM
P P
IT 4
LOCATED IN SUMP PITWITH SP-4
HIG
H L
EV
EL
ALA
RM
IN S
P-4
YA
715A
V5C
P-P
LC1
FA
IL
YA
715B
V5C
P-P
LC2
FA
IL
HYDRAULIC ACTUATOR CABINETHAV-5
ZSH
580A
ZSL
580AS
UC
TIO
N V
ALV
E O
PE
N
SU
CT
ION
VA
LVE
CLO
SE
D
YI
580A
SU
CT
ION
VA
LVE
OP
EN
YI
580B
SU
CT
ION
VA
LVE
CLO
SE
D
SV-5
SV
570
LUB
E O
IL T
EM
PE
RA
TU
RE
ES
501
EM
ER
GE
NC
Y S
TO
P
FREIGHTELEVATORCONTROL
PANEL
YA
801A
FR
IEG
HT
ELE
VA
TO
RA
LAR
M
YA
802A
PA
SS
EN
GE
R E
LEV
AT
OR
ALA
RM
PU
MP
2 F
AU
LT
PU
MP
1 F
AU
LT
VA
LVE
PO
SIT
ION
VA
LVE
PO
SIT
ION
692
CENTRAL PARK PUMPING STATIONELECTRIFICATION
DRAWN
DWG
SHEET OF
FIL
E:
DEPARTMENT OF WATER MANAGEMENTBUREAU OF ENGINEERING SERVICES
CITY OF CHICAGO
CHECKED
APPROVED
DATE
SCALE
CONTRACT NO. 13 - 102
REVISIONS
PROJECT NO.
100 SOUTH WACKER DRIVE, SUITE 1400 CHICAGO, ILLINOIS 60606-4003
C:\U
sers
\och
avez
\Doc
umen
ts\1
2354
-CP
PS
-GC
MH
PE
I_oc
have
z.rv
t7 /
21/2
0 16
12: 1
1:16
PM
NONE
N-12
MB
PUMP NO. 5 P&ID
595
INSTRUMENTATION
THP
THP
MAY 2016
SCALE: NONE
PUMP NO. 5 P&ID
NOTES:
SEE TO NOTE 1 AND 2
1. I/O IS ONLY SHOWN FOR PLC1. PLC2 IS REDUNDANTPLC. CONFIGURE BOTH PLC1 AND PLC2 TO OPERATEWITH REDUNDANT PROGRAM. UTILIZE SAMETERMINALS AND RELAYS PLC2 I/O AS PLC1 I/O.
2. SIGNALS GENERATED AT P5CP THAT NEED TO BESHOWN ON OTHER OITs AND HMIs TO BE MAPPED VIANETWORK SWITCHES.
3. RECALIBRATE EXISTING DP CELL. VERIFY SCADA ISRECEIVING ACCURATE SIGNAL.
4. REQUIREMENTS FOR OIT SHOWN APPLY TOASSOCIATED VFD PANEL, HMI APPLIES TO SCADACOMPUTER (TYP).
SEE NOTE 3
NO. DATE APPD DESCRIPTION1 07/15/16 THP ADDENDUM NO. 3
1