Bond 2016 Community MeetingSam Houston High School
Chief Operations Officer Willie Burroughs
Bond 2016 - Input
2
Community Advisory Committee – Quarterly meetings, beginning June 14, 2017District 2 Committee Members• Darlyne Drummer• Christopher Green• Dimas Martinez
Project Advisory Team meeting – March 3, 2018• Dr. Mateen Diop, Principal• Pat Smith• Michelle Daniels• Mary King• Norma Rodriguez• Brenda Hardaway• Ryan Ortiz• Paul Pearson• Chris Sanchez• Jason Parks• Eduardo Munoz
• Ryan Ortiz• Paul Pearson• Jason Mims• Shannon Sanders• Ruth Munoz• Jason Cruz• Jason Mims• Shannon Sanders• Ruth Munoz• Oscar Vicks• Elias Gonzalez
Stakeholder meeting – August 30, 2018• James Howard, Trustee• Dr. Mateen Diop, Principal• Brenda Hardaway
• Darlyne Drummer• Patricia Smith• Norma Rodriguez
Bond 2016 - Scope
3
• Classroom spaces (general learning, science, special education)
• Restrooms• Cafeteria/kitchen• Auditorium• Heating, ventilation and air conditioning• Plumbing and electrical• Technology infrastructure for new and renovated spaces• Lighting• Fire sprinkler systems• Special needs accessibility in entryways, restrooms, and
other areas• Front-entry modifications to improve security• Athletic track re-coating• Tennis court fencing• Roofing, building exterior and site improvements
Total Project Budget: $33,190,150
Bond 2016 - Site
4
Athletics• New softball field• New fencing at tennis
courts
Bond 2016 – First floor
5
First floor renovations• New main entry with
secured vestibule• New windows throughout• Classroom renovations• New collaboration spaces• New multipurpose spaces• Locker removal
Bond 2016 – Main entry
6
• New main entry• Secured vestibule• New exterior windows
Bond 2016 – Auditorium
7
Auditorium renovations• Window infill• Mechanical upgrades• New ADA ramps and
stairs• New ceiling• New house lights• New stage lighting• New rigging• New sound system• Seat repair
Bond 2016 – Corridor
8
Corridor renovations• Locker removal• New finishes
• Flooring• Ceiling• Wall covering
• Mechanical upgrades• New lighting
Bond 2016 – Cafeteria
9
Cafeteria renovations• New kitchen equipment• New finishes
• Flooring• Ceiling• Wall covering
• Mechanical upgrades• New lighting
Bond 2016 – Second floor
10
Second floor renovations• New windows throughout• Classroom renovations• New collaboration spaces• New multipurpose spaces• Locker removal
Bond 2016 – Classroom
11
Classroom renovations• Upgraded mechanical and
electrical systems, including LED lighting
• Rightsize classrooms• Existing – Avg. 760sf• Renovated – 800 sf
• New exterior windows• New ceilings and finishes• New flexible furniture• Upgraded technology, including
new digital teaching wall
Bond 2016 – Collaboration spaces
12
New collaboration spaces• 4 New collaboration spaces• Upgraded mechanical and
electrical systems, including LED lighting
• New exterior windows• New ceilings and finishes• New flexible furniture
Bond 2016 – Schedule
13
Phase One• Areas D & H• Kitchen• Temporary serving line
March 2019 – December 2019
Phase Two• Areas E, F & J
October 2019 – March 2020
Phase Three• Area A
April 2020 – September 2020
B A
E
HFJ
CAFEKIT
AUD
Bond 2016 – Schedule
14
Phase Four• Areas B• Cafeteria• Roof replacement
June 2020 – August 2020
Phase Five• Auditorium
June 2020 – October 2020
B A
E
HFJ
CAFEKIT
AUD
Bond 2016
15
Bond 2016
16
Questions