bobwhite-manatee transmission line project
DESCRIPTION
Bobwhite-Manatee Transmission Line Project. Longleaf Environmental Consulting Steven Goodman, Project Manager (UWF GIS4043/L) April 28, 2014. Arbor Day Foundation . Bobwhite-Manatee Transmission Line Project. Background Phase. Arbor Day Foundation . Project Goals and Objectives. - PowerPoint PPT PresentationTRANSCRIPT
Bobwhite-Manatee Transmission Line
ProjectLongleaf Environmental ConsultingSteven Goodman, Project Manager
(UWF GIS4043/L)April 28, 2014
Arbor Day Foundation
Bobwhite-Manatee Transmission Line Project
Background Phase
Arbor Day Foundation
Project Goals and Objectives• Goal: Select optimal
transmission line route based on four primary factors:• Proximity to schools and
daycares• Environmental impact• Proximity to individual homes
and land parcels• Length and cost of line
Study Area and Data• Role of GIS •Manatee and Sarasota Co.• Basemap layers• Data needs• Data acquisition and source• Data limitations
Cartographic Model• Defines goals and objectives• Broken down by criteria• Lists data requirements• Lists GIS approaches and
tools• Illustrates feedback loops,
including public comment
Bobwhite-Manatee Transmission Line Project
Analysis and Results Phase
Arbor Day Foundation
Environmental Analysis•Minimize impact• Study area location• Impacted conservation lands• Impacted uplands• Impacted wetlands• GIS process and tools• Other potential analysis
Environmental AnalysisConservation Land Types Impacted AcresWater Managenent Land 10State Recreation Area 63Conservation Easement 91Manatee County 0Sarasota County 0City Managed 0Manatee Audubon Society 0Mosaic Fertilizer 0National Audubon Society 0Selby Botanical Gardens 0FWC Lands 0Historic Site 0Recreation Area 0State Preseve 0State Park 0
General Habitat Types Impacted AcresRiverine 1Lacustrine 11Palustrine 903Upland 5652
Schools and Daycare• Research on adverse effects
on children• Avoid locating line within
400ft• GIS process and tools• No schools or daycares
within 400ft of line
Impacted Homes•Minimize impact• Balancing act• 20 houses within corridor• 26 houses within 400 Ft.
buffer•Most homes along current
lines and right-of-ways
Impacted Parcels•Minimize number impacted• Future value• Current land uses• GIS processes and tools• 162 within corridor• 93 within buffer
Estimated Line Length• Use of existing Roads•Manatee River/Lake• Engineering/cost related to
line length• Estimated length = 24.5 • Cost per mile
Conclusion•Were overall goals and objectives met?•Balancing the four criteria•Community participation and buy-in•Conservation opportunities•Additional capabilities•Role of GIS and ArcMap software
Arbor Day Foundation
Works CitedFeychting. M and A. Ahlbom. 1993. Magnetic Fields and Cancer in Children Residing Near Swedish High-voltage Power Lines. American Journal of Epidemiology 138(7): 467-481.
Florida Power and Light Company. 2014. FAQs: Planning for a Brighter Future; the Role Power Lines Play. http://www.fpl.com/environment/lines/brighter_future.shtml
Florida Power and Light Company. 2014. FPL’s Bobwhite-Manatee Power Line. http://www.fpl.com/environment/lines/bobwhite.shtml
Klein, Mel. 2006. “November 3, 2006 letter.” Florida Power and light Company.
Bobwhite-Manatee Transmission Line ProjectQuestions?