Bluewater Bio HYBACS Overview

Upload: others

Post on 04-Jan-2022

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bluewater Bio

Bluewater Bio

HYBACS Overview

Page 2: Bluewater Bio

6

BwB: HYBACS®

6

HYBrid ACtivated Sludge

• For rapid, simple upgrading of existing activated sludge plants

• Enables existing plants to treat double the load and/or achieve tighter standards (ammonia / N removal)

• Proven in UK (Ashbourne, 2012) • Proven up to 100 MLD / 400,000 PE • Full scale plants operating since

1999

Page 3: Bluewater Bio

31

HYBACS: Global Awards

Global Water Intelligence: Wastewater Project of the Year, 2014,

Highly Commended

Winner, Best Process Technology Water & Energy Exchange (WEX) Global Innovation Awards, 2014

Awarded by MoW in gratitude on the completion of the project

CIWEM W Mids. Innovations Showcase Winner – Best Value Innovation 2012

Page 4: Bluewater Bio

7

Small molecules

Conventional Activated Sludge 2

7

Macromolecules Particulates Hydrolysis (slow)

Hydrolysis (slow)

Oxidation Biomass Growth CO2

Cell Wall

Bacterial Cell

Assimilation (fast)

Types of COD in Wastewater

Page 5: Bluewater Bio

8

Small molecules

HYBACS®: How does it work? 2

8

Macromolecules Particulates

HYBACS: Hybrid Activated Sludge

Hydrolysis (accelerated)

Hydrolysis (accelerated)

Oxidation Biomass Growth CO2

Cell Wall

Bacterial Cell

High concentration of

Assimilation (fast)

Page 6: Bluewater Bio

9 of 20

HYBACS: Typical Configuration

Aeration Tank Anoxic Clarifier SMART

units

9

Aeration Tank

Conventional Activated Sludge HYBACS: HYBrid ACtivated Sludge

Page 7: Bluewater Bio

10 of 20

Hydrolysis in the SMART unit enables:

• Increased performance of aeration tanks

• Better sludge settlement

• Improved phosphorus removal

HYBACS: Typical Configuration

Aeration Tank Anoxic Clarifier SMART

units

10

Aeration Tank

Conventional Activated Sludge HYBACS: HYBrid ACtivated Sludge

Anaerobic

Page 8: Bluewater Bio

13

6

HYBACS: Powered by the SMART™ Unit 13

Page 9: Bluewater Bio

14

SMART™ Units

2 weeks

2

14

Standard, modular reactors • Installed offline

(no process interruption during construction) • Rapid deployment • Existing assets can be retained • Simple to commission • Each unit (4.5m long x 2.3m wide) pre-treats:

• Up to 3,000 m3/d • Equivalent to 6,000 - 10,000 PE

• Lease / rental options available

Presenter
Presentation Notes
Bluewater Bio worked with Severn Trent’s contractor, MWH, to deliver the upgrade. Construction was very simple; a flat concrete slab was built and the SMART units were delivered pre-assembled with their local control panels and local cabling. This enabled the units to be tested off-site to minimise risks during construction. The installation was completed within two weeks and the project was completed ahead of programme.
Page 10: Bluewater Bio

15

Case Study: Tubli WPCC, Bahrain

How do you increase the capacity of a plant which is highly overloaded and has limited space ?

15

Image © Google – CNES / Astrium, DigitalGlobe, taken 17 April 2014

Page 11: Bluewater Bio

16

16

TAeration

Lanes Clarifiers

16

• 2 aeration lanes upgraded from 40 to 100 MLD

• 4 clarifiers upgraded from 17 to 33 MLD each

• Contract value: US$ 20m(MBR alternative tendered for > US$ 100m)

• Performance targets of <3 mg/l ammonia,<10 mg/l TN have been achieved consistently

• Existing structures retained and minimaladditional land take

Case Study: Tubli WPCC, Bahrain

Page 12: Bluewater Bio

18

HYBACS: Tubli WPCC – Sludge Settlement

18

Page 13: Bluewater Bio

19

Floc Morphology 2

19

(Magnification x 200, phase contrast, unstained)

HYBACS advantages: • Large, dense flocs with few filaments • Settlement velocities up to 12 m/h • SVI typically 40-50 ml/g • Tubli clarifiers achieving <10 mg/l SS at 1.5 m3/m2.h and 7 kg/m2.h

Conventional Activated Sludge HYBACS Sludge

Page 14: Bluewater Bio

23 23

T

Before HYBACS

After HYBACS HYBACS: Proven Data, Performance & Technology

23

Page 15: Bluewater Bio

24 24

• Passed the Performance Test with no failures, despite very high influent COD loads

• HYBACS sludge is highly settleable

• Substantial power savings

• Simple, compact upgrade, maintaining full treatment during construction

Parameter Guaranteed value

Expected value

Actual performance

Flow (ML/d) 100 100 101 COD (mg/l) - 60 27 SS (mg/l) 20 15 9.5 Ammonia (mg/l) 35 3 0.58 Total nitrogen (mg/l) - 15 9.0 SSVI (ml/g) - 80 46 Power usage (MWh/d) 29.7 25 21

“The HYBACS plant performance and consistency have exceeded all our

expectations”, Project Manager, Ministry of Works

HYBACS at Tubli: Proven Performance

Performance Test Summary

24

Page 16: Bluewater Bio

• Chicken processor doubled discharge, increasing PE load from 25,000 to 35,000

• Four solutions compared namely: – new oxidation ditch – roughing filters – SAF plant – HYBACS

Existing PSTs

Existing oxidation

ditches

Existing FSTs

SMART units

New oxidation

ditch

Roughing filters

SAF units

9 HYBACS: Severn Trent, Ashbourne, UK

25

Page 17: Bluewater Bio

26

HYBACS: Ashbourne – Project Drivers 26

Page 18: Bluewater Bio

Item Unit HYBACS Additional oxidation

ditch Saving

Capital Cost1 £ k 1031 1438 28%

Operating Cost1 £ k/year 23 114 80%

Duration of site work2 weeks 8-10 24-40 70%

Embodied Carbon2 t CO2e 91 955 90%

Operational Carbon2 t CO2e/year 31 94 67%

Notes: 1 Severn Trent estimates, OPEX includes power, labour & business rates 2 Bluewater Bio estimates, using Environment Agency calculator

HYBACS: Ashbourne – Optioneering 27

Page 19: Bluewater Bio

28

HYBACS: IDI, Princeton Meadows, USA 28

Page 20: Bluewater Bio

29 29

HYBACS vs Competition 29

Comparison of options for upgrading an existing activated sludge plant:

Feature HYBACS MBBR Build more lanes and

clarifiers

Effective for biological N removal

Effective for biological P removal

Upgrade without affecting existing works operation

Minimal civil works needed

Short construction period

Compact footprint

Enhanced sludge settlement

Reduced aeration power

Page 21: Bluewater Bio

30 30

HYBACS: Future-Proofing Activated Sludge 30

• HYBACS is ideal for upgrading existing activated sludge plants for:

- increased capacity, and/or

- tighter standards

• Accelerated hydrolysis enables up to a 2.5-fold uplift in capacity

• Simple off-line installation, with minimal footprint

• Existing assets can be retained, reducing capital costs and project duration

• Easy to commission, operate and maintain

• 9 staff: Manager, 3 SCADA operators, 1 Mech Eng, 1 Elec Eng, 2 Labourers, 1 Safety

• As easy to operate as an activated sludge plant

• Sludge is highly settleable