Bloomsburg University's Facilities Master Plan is complete. The final projects proposed address the university’s existing and future space needs, including learning and non-learning areas. http://bloomu.edu/campus-master-planTRANSCRIPT
Bloomsburg University Council of Trustees Meeting
March 5, 2014
Campus Plan 2014
Agenda
1 Campus Plan Final Recommendations
2 Implementation Alternatives
3 Implementation Timeline
Final Recommendations
This plan is rooted in enrollment growth rather than time.
1
1,000+ Number of additional students the facilities can accommodate if this plan is implemented.
Facilities Impacts
ACADEMICS
New Waller Hall
New Academic on Quad
ADMINISTRATION
New President’s Residence
New Alumni / Gateway Center
New Waller Hall
Maintain Carver for Administration
STUDENT LIFE
New Student Union
New Dining at Swisher Village
STUDENT HOUSING
248 Minimum quantity of new beds needed to accommodate existing housing shortages.
Projected Bed Shortages (assumes no new construction / renovation)
248 284
320 357
394 431
469 507
546 585
0
100
200
300
400
500
600
700
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Bed
Sho
rta
ge
Qua
ntity
Year
Projections based on existing bed quantities, no new construction, and 1% enrollment growth per year.
New Swisher Village Housing
New Bookstore Housing
New Penn Village Housing
Renovate Montour
New West Village Apts.
New MPA Apts.
ATHLETICS
Recreation Field Upgrades
New Multipurpose Athletic Fields
Relocate Baseball Field
Relocate Track Throws
New Turf Field
Addition to Nelson Fieldhouse
New Air Structure & Fields
OPEN SPACE
West Village Quad
Swisher Village Quad
Penn Village Quad
Campus Gateway
INFRASTRUCTURE
New East Campus Parking Garage
Campus Loop Road
Ped. Bridge
Other Infrastructure Projects: • Lightstreet Road Intersection • Chiller Plants Lower Campus (east + west ends) • Modified Electrical Distribution to Upper Campus • Electrical Substation Replacement • Lower Campus Electrical Distribution Expansion • District Heating and Cooling on Upper Campus
New Facilities Maintenance Complex
Steam Plant Biomass CHP
Intersection Upgrade
Implementation Alternatives
Most projects can be completed within 15-20 years. Average capital costs are $54M per year.
2
3 Timeline Lower Campus Housing First