Drum PlantsConstruction 1
HMA Production
Senior/GraduateHMA Course
![Page 2: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/2.jpg)
Drum PlantsConstruction 2
What you will learn….
• How gradation is controlled in a drum-mixer• How asphalt is controlled in a drum-mixer• Different styles of drum-mixers• Using RAP with a drum plant
![Page 3: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/3.jpg)
Drum PlantsConstruction 3
Drum-Mix Production
Hot Mix Asphalt production characterized by:
• Gradation Control at Cold Feed• Measure aggregate flow with belt scale• Meter asphalt binder to aggregate flow• Produce HMA continuously
![Page 4: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/4.jpg)
Drum PlantsConstruction 4
![Page 5: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/5.jpg)
Drum PlantsConstruction 5
Cold Feed Proportioning
Composite gradation is controlled at cold feed by proportioning material from individual bins.
Gradation and quality of the individual materials is controlled at the quarry.
![Page 6: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/6.jpg)
Drum PlantsConstruction 6
![Page 7: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/7.jpg)
Drum PlantsConstruction 7
Cold Feed Proportioning
Variation in material flow from individual bins:
• Based on variable speed motor on belt• Adjustable manual gates help control
minimum and maximum flow
![Page 8: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/8.jpg)
Drum PlantsConstruction 8
Cold Feed Proportioning
• Accomplished by calibrating the feeders• Material output is charted against belt speed
in calibration charts• Different charts are created for different gate
settings on the same feeder
![Page 9: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/9.jpg)
Drum PlantsConstruction 9
![Page 10: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/10.jpg)
Drum PlantsConstruction 10
Cold Feed Gradation Control
Many styles of feeder controls found in field.
All can perform satisfactory proportioning.
![Page 11: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/11.jpg)
Drum PlantsConstruction 11
![Page 12: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/12.jpg)
Drum PlantsConstruction 12
Asphalt Binder Proportioning
Asphalt binder must proportion to aggregate flow.
First step in asphalt binder proportioning is measuring aggregate flow.
Belt scale is used.
![Page 13: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/13.jpg)
Drum PlantsConstruction 13
![Page 14: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/14.jpg)
Drum PlantsConstruction 14
How a Belt Scale Works
• Weigh bridge measures weight of aggregate.• Speed sensor measures speed of belt.• “Integrator / Totalizer” calculates aggregate
flow in ton (tonnes) per hour• “Integrator / Totalizer” reports flow rate to
plant control system
![Page 15: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/15.jpg)
Drum PlantsConstruction 15
![Page 16: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/16.jpg)
Drum PlantsConstruction 16
![Page 17: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/17.jpg)
Drum PlantsConstruction 17
Asphalt Binder Proportioning
Asphalt binder must proportion to aggregate flow.
Second step is regulating asphalt binder flow.
Asphalt binder pumping / metering unit is used.
![Page 18: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/18.jpg)
Drum PlantsConstruction 18
![Page 19: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/19.jpg)
Drum PlantsConstruction 19
![Page 20: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/20.jpg)
Drum PlantsConstruction 20
How the Asphalt Binder Proportioning System Works
• Controls system reads wet aggregate flow from belt scale.• Controls accepts moisture content entered by operator to
establish dry flow rate of aggregate• Control system accepts target asphalt content entered by
operator.• Control system drives pumping/metering unit flow control
device.• Control system adjusts asphalt binder flow control system
based on signal received back from meter
![Page 21: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/21.jpg)
Drum PlantsConstruction 21
![Page 22: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/22.jpg)
Drum PlantsConstruction 22
Plant Automation
Many types of systems and levels of complexity found in the field.
![Page 23: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/23.jpg)
Drum PlantsConstruction 23
![Page 24: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/24.jpg)
Drum PlantsConstruction 24
Drum-Mix Plant Calibration
![Page 25: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/25.jpg)
Drum PlantsConstruction 25
Step 1 - Calibrating Belt Scales
![Page 26: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/26.jpg)
Drum PlantsConstruction 26
Step 1 - Calibrate Belt Scale
• Verify belt scale reads zero per manufacturers guidelines
• Set the cold feed gates at an opening that will allow a good material feed
• Start main conveyor belt• Run the variable speed belt feeder for the coarse
aggregate bin - about 50% of desired production rate• Record the belt feeder speed and weight indicated on
the belt scale.
![Page 27: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/27.jpg)
Drum PlantsConstruction 27
Step 1 - Calibrate Belt Scale (cont.)
• Stop belt and remove a six foot section of material from the conveyor
• Weigh the material removed• Repeat process to get an average of two weights• Adjust instrument so that it reads correctly
![Page 28: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/28.jpg)
Drum PlantsConstruction 28
Example
• Conveyor is run at 225 feet per minute• Run the belt feeder until the digital readout reads 90
tons per hour• Weight of material on a six ft section of belt = 76 lbs
and 78 lbs for an average of 77 lbs
![Page 29: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/29.jpg)
Drum PlantsConstruction 29
Example - cont.
• Determine the aggregate weight in lbs per minute.WR r
where Q = weight of aggregate, lbs/min
W = wt of agg measured, lbs
R = speed of belt
r = length of belt from which material was removed
Q =
![Page 30: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/30.jpg)
Drum PlantsConstruction 30
Example - cont
• Therefore the aggregate weight in lbs/min is:
q = WR/r = 77 x 225 = 2887.5 lbs/min
• To convert to tons per hour (q x 60)/2000
2887.5 x 60 = 86.63 tph < 90 tph
6
2000
![Page 31: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/31.jpg)
Drum PlantsConstruction 31
Example - cont
• Adjust instrument per manufacturer’s guidelines so that next test it reads 86.63
• Repeat test, adjust, until two consecutive readings are within acceptable tolerance
(Unlike batch plant no department spec on this scale tolerance - because mix purchased from silo weigh tickets)
![Page 32: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/32.jpg)
Drum PlantsConstruction 32
Step 1 - AlternateCalibrating Belt Scale
• Verify belt scale reads zero per manufacturers guidelines
• Set the cold feed gates at an opening that will allow a good material feed
• Start main conveyor belt• Run the variable speed belt feeder for the coarse
aggregate bin - about 50% of desired production rate• Starting with empty belt run material in tared truck
and stop material flow to end with empty belt
![Page 33: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/33.jpg)
Drum PlantsConstruction 33
Step 1 - AlternateCalibrating Belt Scale
• Record the total weight indicated on the belt scale.• Compare weight total on belt scale with actual weight
on truck.• Following manufacturers guidelines, adjust belt scale
instrument based on weight difference.• Repeat test, adjusting instrument, until two
consecutive tests are within tolerance.
![Page 34: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/34.jpg)
Drum PlantsConstruction 34
Example
• Start belt scale and verify reads zero• Tare empty truck at 22,375#• Record belt scale totalizer at 437897.65• Start feeder at approximately 50% flow • Fill truck and stop and empty belt• Record belt scale totalizer at 437906.87• Calculate tonnage on scale at 9.22 tons (437906.87 -
437897.65 = 9.22 tons)
![Page 35: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/35.jpg)
Drum PlantsConstruction 35
Example - cont.
• Weigh truck at 41,401#• Calculate weight in truck at 9.51 ton (41,401- 22,375
= 19,026 ÷ 2,000 = 9.51 ton) • Recall “span” value of instrument at 897654• Adjust span value by 1.0314 (9.51 ÷ 9.22 = 1.0314)• New span value = 925,840 (897654 x 1.0314 =
925,840)• Re-test, re-adjust, until two tests pass
![Page 36: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/36.jpg)
Drum PlantsConstruction 36
Asphalt Binder Distribution in Drum-Mix Plants
![Page 37: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/37.jpg)
Drum PlantsConstruction 37
Asphalt Binder Distribution
Understanding asphalt binder distribution…..
• Calculating Flow Requirements• Calibrating Asphalt Binder Meter
![Page 38: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/38.jpg)
Drum PlantsConstruction 38
Asphalt Binder DistributionCalculating AC Flow
Need to know the number of gallons/minute of asphalt binder that is to be delivered
R = P x T x 2000 x 1
Where R = asphalt binder to be delivered, gpm P = optimum asphalt binder
T = production rate, tons per hourW = unit weight of asphalt binder (typically about 8.4 lb/gal)
W 60100
![Page 39: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/39.jpg)
Drum PlantsConstruction 39
This example, Asphalt Binder target is 6.0% of 200 tons per hour
R = P x T x 2000 x 1
Where R = asphalt binder to be delivered, gpm
P = 6
T = 200
W = 8.4
W 60
Example – Asphalt Binder Flow Required
100
![Page 40: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/40.jpg)
Drum PlantsConstruction 40
This example, Asphalt binder target is 6.0% of 200 tons per hour
R = 6 x 200 x 2000 x 1
Where R = asphalt binder to be delivered, gpm
P = 6
T = 200
W = 8.4
8.4 60
Example – Asphalt Binder Flow Required
100
![Page 41: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/41.jpg)
Drum PlantsConstruction 41
This example, Asphalt Binder target is 6.0% of 200 tons per hour
R = .06 x 200 x 238.095 x .0167
R = 47.71 gpm
Example – Asphalt Binder Flow Required
![Page 42: Block 16 Drum Plants 13](https://reader038.vdocuments.mx/reader038/viewer/2022103116/558e46d91a28ab5d268b46c8/html5/thumbnails/42.jpg)
Drum PlantsConstruction 42
QUESTIONS ?