bld 206 merged

Upload: viethungcao

Post on 02-Jun-2018

460 views

Category:

Documents


221 download

TRANSCRIPT

  • 8/11/2019 BLD 206 Merged

    1/54

    UNESCO-NIGERIA TECHNICAL &

    VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE II

    YEAR II- SEMESTER IV

    PRACTICAL

    Version 1: December 2008

    NATIONAL DIPLOMA IN

    BUILDING TECHNOLOGY

    WORKSHOP PRACTICE IV

    COURSE CODE: BLD 206

  • 8/11/2019 BLD 206 Merged

    2/54

    TABLE OF CONTENTS

    WEEK 1: REALI ZATION OF ONE WAY SWITCH CIRCUIT using PVC conduit

    WEEK 2: REALI ZATION OF two 2- WAY SWITCH CIRCUI T

    WEEK 3: REALIZATION OF TWO GANG SWITCH CIRCUIT

    WEEK 4: REALIZATION OF A LIGHTING CIRCUIT WITH INTERMEDIATE

    WEEK 5: REALIZATION OF A RADIAL USING P.V.C TRUNKING

    WEEK 6: SETTING OUT, EXCAVATION AND FOUNDATIONS

    WEEK 7: BLOCKWORK - SUPERSTRUCTURE

    WEEK 8: LINTELS AND ROOFBEAMS

    WEEK 9: ROOF STRUCTURE AND COVERING

    WEEK 10: CEILINGS AND NOGGINGS

    WEEK 11: METHOD OF FIXING PIPES FOR PLUMBING WORKS

    WEEK 12: FIXING OF DOORS AND WINDOWS

    WEEK 13: FINISHES

    WEEK 14: METHODS OF FIXING SANITARY FITTINGS

    WEEK 15: PAINTING

  • 8/11/2019 BLD 206 Merged

    3/54

    Week 1

    Title:

    REAL IZATION OF ONE WAY SWITCH CIRCUIT usi ng PVC co nduit

    Objective:

    To realize a circuit consisting of a one-way switch controlling two lamps in parallel

    Introduction:

    The most commonly used switch in domestic installation is the one way switch. It is used in

    domestic premises to control either a fluorescent lamp or an incandescent lamp. This ractical

    work familiarizes the student with the connection of the one way switch circuit and furtherimproves the student skill and ability to handle heavy gauge steel conduit.

    Equipment and tools:

    - PVC conduits and their accessories).

    - 2 end boxes (3/4 in.).

    - 1 steel conduit box with knockouts (3/4 in.).

    - 5 sockets and male bushes (3/4 in.).

    - 5 spacer bar saddles (3/4in.).

    - A pipe vice and a hacksaw.

    - Pipe reamer or half round file.

    - Stock and die set. >

    - Cutting oil or tallow.

    - A bending machine.

    - An electrician tool box.

  • 8/11/2019 BLD 206 Merged

    4/54

    Layout Diagram

    J.B

    General scheme

    Procedure:

    Step1:Draw the execution plan of the circuit.

    Step2:

    Layout the route of the conduits and the position of the boxes on the board.

    Step 3:

    Cut the conduits to the lengths given by the layout diagram.

    Step 4:

    Prepare and bend the conduit using bending spring.

  • 8/11/2019 BLD 206 Merged

    5/54

    Step6:

    Secure the conduits on the board by the saddles.

    Step7:

    Draw the cables in the fittings and ensure the terminals at the boxes long enough for

    connections.

    Step8:

    Strip the terminals and connect the circuit according to the layout.

    Step 9:

    Test the circuit for correct wiring by an ohmmeter.

    Step 10:

    Supply the circuit with power and ensure proper operation.

  • 8/11/2019 BLD 206 Merged

    6/54

    Week 2

    Title:

    REAL IZATION OF two 2- WAY SWITCH CIRCUIT

    Objective :

    To connect a 2 way switch circuit

    Introduction:

    Two 2 way switches are use whenever it is required to control a Lighting circuit from two

    position. This is useful in controlling the lighting of halls, stair cases and any room with two

    doors.fig.1.2 shows the circuit connection and the symbol representation of the switch.

    Wiring connection

    Load

    or

    Line

    Symbol

    representation

    Line

    or

    Load

    Equipment and tools:

    - P V C conduits and their accessories,

    Two 2 way swiches.

    One way switch.

    Ceiling rose.

    Lamp and lamp holders

    PVC cable 1.5mm.

    Hacksaw.

    PVC con duit bending spring.

    Electrcian tool box

    - An electrician tool box.

  • 8/11/2019 BLD 206 Merged

    7/54

    Layout Diagram

    J.B

    L1

    General scheme

    L 2

    C.R L3

    E E E

    E E

    E

    Controls the Lamp 1

    Controls the Lamp 1 & 2

  • 8/11/2019 BLD 206 Merged

    8/54

    Procedure:

    Step 1:Draw the execution plan of the circuit.

    Step2:Layout the route of the conduits and the location of the boxes on the board.

    Step 3:Cut the conduit according to the sizes given on the layout diagram.

    Step 4:Make the required 90 bends as shown on the layout diagram. See Fig. (1.3 a,b),for

    bending springs and methods of bending.

    Step 5:

    Secure the conduit ends to the boxes, use adopters where necessary.

    Step 6:Secure the conduits to the board by saddles.

    Step 7:

    Draw the cable and ensure the termina; in the boxes and project enough for connection

    Step 8:

    Strip the terminals in the boxes and connect up the circuit in a layout diagram.

    Step 9:

    Test the circuit for correct wiring using an ohmmeter

    Step 10:

    Supply the circuit with power and ensure proper operation.

  • 8/11/2019 BLD 206 Merged

    9/54

    Week 3

    Title:

    REAL IZATION OF TWO GANG SWITCH CIRCUIT

    Objective:

    To realize a circuit consisting of a one-way switch controlling two lamps in parallel

    Introduction:

    The most commonly used switch in domestic installation is the one way switch. It is used in

    domestic premises to control either a fluorescent lamp or an incandescent lamp. This ractical

    work familiarizes the student with the connection of the one way switch circuit and furtherimproves the student skill and ability to handle heavy gauge steel conduit.

    Wiring connectionSymbol

    representation

    Line Load 1

    Load 2

    Equipment and tools:

    - Heavy gauge steel conduit (3/4 in.).

    - 2 end boxes (3/4 in.).

    - 1 steel conduit box with knockouts (3/4 in.).

    - 5 sockets and male bushes (3/4 in.).

    - 5 spacer bar saddles (3/4in.).

    - A pipe vice and a hacksaw.- Pipe reamer or half round file.

    - Stock and die set. >- Cutting oil or tallow.

    - A bending machine.

    - An electrician tool box.

  • 8/11/2019 BLD 206 Merged

    10/54

    Layout Diagram

    J.B

    General scheme

    L 2

    L3

    E E E

    E E

    J.B

    L 1

    Controls the Lamp 1

    Controls the Lamp 1 & 2

  • 8/11/2019 BLD 206 Merged

    11/54

    Procedure:

    Step1:Draw the execution plan of the circuit.

    Step2:

    Layout the route of the conduits and the position of the boxes on the board.

    Step 3:

    Cut the conduits to the lengths given by the layout diagram.

    Step 4:

    Prepare and bend the conduit using bending spring.

    Step5:

    Secure the conduit ends to the boxes, use adapters where necessary.

    Step6:

    Secure the conduits on the board by the saddles.

    Step7:

    Draw the cables in the fittings and ensure the terminals at the boxes long enough forconnections.

    Step8:

    Strip the terminals and connect the circuit according to the layout.

    Step 9:

    Test the circuit for correct wiring by an ohmmeter.

    Step 10:

    Supply the circuit with power and ensure proper operation.

  • 8/11/2019 BLD 206 Merged

    12/54

    Week 4

    Title:

    REAL IZATION OF A L IGHTING CIRCUIT WITH INTERMEDIATE

    SWITCH USING P.V.C CONDUIT

    Objective:

    To connect an intermediate switch correctly in a lighting circuit and to improve the

    student skills in handling and using P.V.C conduit.

    Introduction:

    A lighting circuit can be controlled from any number of locations by the use of intermediate

    switches together with two 2-wayswitches. Two controls locations will be provided by the

    two 2-way switches and the other locations will be provided by the number of intermediate

    switches used in the circuit. See Fig.

    Wiring connection

    Load

    or

    Line

    Line

    or

    Load

    2 Way

    switch

    2 Way

    switch

    Any number of intermediate switches as

    required N number of locations of control

    Equipment and tools:

    - 20 mm P.V.Cconduits and their accessories.

    - One intermediate switch.

    - Two 2-wayswitches.

    - Two ceiling roses and two patten lamp holders.

    - Two lamp holders.

    - 1.5 mm2P.V.C cable (red, black and green/yellow).

    - Hacksaw.

    - Grip vice

    - Fishtape.

  • 8/11/2019 BLD 206 Merged

    13/54

    Layout Diagram

    J.B

    General scheme

    E E E

    EE

    E

    J.B

    L 1

    Controls the Lamp 1 & 2

    Controls the C.Rs

    J.B

    E

    E

    E

    L2

    C.RC.R

    &

  • 8/11/2019 BLD 206 Merged

    14/54

    Procedure:

    Step1:

    Draw the execution plan of the circuit.

    Step2:

    Layout the route of the conduits and the position of the boxes on the board.

    Step 3:

    Cut the conduits to the lengths given by the layout diagram.

    Step 4:

    Prepare and bend the conduit using bending spring.

    Step5:Secure the conduit ends to the boxes, use adapters where necessary.

    Step6:

    Secure the conduits on the board by the saddles.

    Step7:

    Draw the cables in the fittings and ensure the terminals at the boxes long enough for

    connections.

    Step8:

    Strip the terminals and connect the circuit according to the layout.

    Step 9:

    Test the circuit for correct wiring by an ohmmeter.

    Step 10:

    Supply the circuit with power and ensure proper operation.

    27

  • 8/11/2019 BLD 206 Merged

    15/54

    Week 5

    Title: REAL IZATION OF A RADIAL USING P.V.C TRUNKING

    Objective:

    To connect a radial circuit and to consolidate the student ability in using P.V.C trunking

    P.V.C conduit and connecting the intermediate switch correctly.

    Introduction:

    Socket outlets are widely used in residential installation. They are connected either as a

    radial circuit or as a ring circuit. Both of these circuits utilize 13A socket outlets.

    Two types of radial circuits,each with maximum number of six socket can be used.

    1. Wired with 2.5 mm2cable/protected by 20A circuit breaker and serves one room of

    maximum areas 20 m2,

    2. Wired with 4 mm2cable/protected by 30A circuit breaker and serves a maximum

    area of 50m2.

    EL

    N

    Execution

    30A

    Equipment and tools:

    - P.V.Cconduits (20 mm )with their accessories.

    - P.V.Ctrunking (25x16mm)-3 socket outlets (13A)

    - Two-way switches

    - Intermediate switch.

    - 1.5mm2P.V.C cables. Red/black,green/yellow.

    - 2.5 mm2P.V.C cables. Red,black/green/yellow.

    - 4 flash boxes (P.V.C) and one end box.

    - 3 surface boxes (P.V.C).

    - Hacksaw and grip vice.

    - Smooth file.

    - Bending spring.

    - Fish tape.- Electrician tool box.

  • 8/11/2019 BLD 206 Merged

    16/54

    Layout Diagram

    J.B

    General scheme

    E E E

    E

    E

    J.B J.B

    E

    EEE

    E E E

    E

    Procedure:

    Step 1:Draw the execution plan of the circuit.

    Step 2:Mark the routes of the conduits and trunking/as well as the locations of all boxes on the

    board.

    Step 3:Cut and prepare the trunkings/then fix them on the board according to the layout diagram.

    Step 4:

    Fix all boxes on the board/according to the positions and dimensions given to you.

    Step 5:

    Cut/prepare and bend the conduits then secure them to theboxes and board.

    Step 6:Install the 2.5 mm2cables in the trunkingand draw the 1.5 mm2 cables in the conduits as

    shown by the layout diagram.

    Step 7:Strip the terminals and connect up the circuits.

  • 8/11/2019 BLD 206 Merged

    17/54

    Step8:

    Test the circuit for correct wiring/using an ohmmeter

    Step 9:Supply thecircuit with powerand ensure operation.

    Safety no tg ;

    The student must not connect the circuit to the supply without the permission of his

    teacher.

  • 8/11/2019 BLD 206 Merged

    18/54

    WEEK 6: SETTING OUT , EXCAVATION AND FOUNDATIONS

    METHOD OF SETTING OUT

    In setting out simple building we may use one of the three methods.

    1. The 3, 4, 5 method2. The builderssquare method

    3. Leveling instruments.

    THE 3, 4, 5 METHOD (Fig 1)

    Mark out the building line from the road by measuring the required distance from the

    centre of the road, or by stretching a line along an existing building to the proposed site.

    The building line is then represented by a line known as the ranging line, which also

    marks the front wall of the buildings as shown.

    Mark out the overall length of the building by driving in pegs at A and B,

    along the ranging line.

    Procure two steel tape measures and mark out four equal distances on the ranging line

    starting from the corner peg at B. These distances may be in any unit of measurement, i.e.

    millimeters, meters, etc.

    Pull a tape measure from point B to C and ask an assistant to hold it, ready

    with a hammer and a peg.

    Pull the second tape from the fourth mark at D on the ranging line to point E on the first

    tape.

    The distance 5 m, if using meters, on tape DE should coincide with the point 3 m on tape

    BEC, to prove that the angle B is 90 (from Pythagoras' theorem). If this does not happen,

    the tape B C is either shifted outwards or inwards until 5 m on the second tape coincides

    with the 3 m mark on the first tape.

    Repeat the same procedures to obtain the right angle for BAF, and mark out the overall

    widths of the building.

    Establish corner pegs and erect profiles.

  • 8/11/2019 BLD 206 Merged

    19/54

    Mark the positions of partition walls on the profiles with either nails or saw cuts. Ranging

    lines are stretched through these nails and the corner pegs to mark the ground to indicate

    the line of excavation for the foundation trenches.

    Fig 1 3,4,5 method

    Advantages

    1. Simple to use, does not require any calculations. .

    2. Can be applied to large buildings.

    3. Accuracy of setting out is self-evident and adjustment in the event of error is simple andquick.

    Disadvantages

    1. Two tape measures are required, which may be difficult to obtain in rural areas.

    2. Effect of wind on tapes and line may lead to inaccurate work especially on long

    buildings.

    Note that the builder's square can only be used with accuracy for small buildings such as

    farmhouses and typical single room and parlour compound buildings.

    THE BUILDERS SQUARE METHOD(Fig 2)

    Set out the front of building line in the usual manner with pegs or marks at the required

    distances.

  • 8/11/2019 BLD 206 Merged

    20/54

    Place the builders square so that the front line touches one side of the square right

    through its length as shown.

    Stretch a line from the corner pegs so that it is parallel to the second side of the square

    and establish the third peg. A corner with an angle of 90 is thereby obtained.

    With the aid of a tape measure, mark out the length and breadth of the proposed building.

    Transferring the builders square to the remaining corners and repeating the above

    operations; a simple rectangular building can be set out.

    After establishing the four corner pegs, profiles, (separate or continuous) may be in the

    same way as described earlier.

    Fig 2 Builders Square Method

    Advantages

    1. Simple to use.

    2. Does not require any calculation.

    3. Can be very accurate when used for small rectangular buildings.

    4. Quick in application.

    Disadvantages

    1. Unseasoned timber can twist and warp leading to errors when used.

    2. Unsuitable for large buildings.

  • 8/11/2019 BLD 206 Merged

    21/54

    LEVELLING INSTRUMENTS THE SITE SQUARE

    When a right angle is to be set out, the corner of the angle is always known and also one side of

    the corner. One has only to find the position of the second side. The site square solves this

    problem in a very simple, quick and reliable way.

    The front or building line is set out in the usual manner, with pegs or marks at the

    required distances as shown

    Set up the tripod at No.2 peg so that the datum rod is directly over the peg or mark which

    represents the corner point. Make sure that the legs are firm on the ground.

    Release the spike screw and extend the spike so that it sits firmly on the nail or mark.

    Tighten the screw, as shown

    Before mounting the instrument on to the tripod head, ensure that the locking screw is

    tightened screw on the site square. Release the locking screw. By rotating the site square,

    point the lower telescope along the front or building line. Tighten locking screw.

    Check the circular bubble over the top of the instrument. This will probably be found to

    be 'off-centre'. To correct this, release tripod leg screws and adjust the instrument until

    the bubble comes into the centre of the black circle. When this is achieved, tighten the

    tripod leg screws. The instrument is now ready for use.

    Sight on to peg No.1 through the lower telescope to obtain the 'dead on' position by

    means of the fine setting screw which moves the telescope to the right or to the left and

    by tilting the telescope up or down as shown.

    When this position is obtained, measure the distance required to peg No.3. Now by

    sighting through the top telescope, taking care not to rotate the instrument to the right or

    left, signal an assistant to move the peg sideways until it is 'dead on'. Peg No.3 is now

    positioned at an angle of 90.

    By moving the site square to peg No.3 and 'lining up' on peg No.2 the remaining corner peg,

    No.4, can be set out using the procedures already given.

    Profiles can be marked easily by tilting the telescope upwards, having sighted on to the

    peg, and placing a nail in the 'dead on' position on the profile board.

  • 8/11/2019 BLD 206 Merged

    22/54

    EXCAVATION

    After setting out is completed by any of the processes above, the next step is to excavate.

    Excavation is done to receive the foundation that will be constructed for the building.

    Excavation can be done using any of the two methods:

    Manual method and

    Mechanical method

    The choice of the method of excavation depends on the size of work. In small construction, it

    is more economical to use the manual method, while for large works mechanical method will

    be economical for the execution.

    Tools Used in Manual Method of Excavation

    The manual method of excavation involves the use of the following tools

    pick-axes used to dig up the soil

    shovels to remove the dug up soil

    spades to level the bottom of the excavation and to load into the wheelbarrow,

    Wheelbarrows to convey the excavated soil away from the excavation area.

    FOUNDATIONS

    Shallow Foundations

    Shallow foundations transfer load of the building to a sub-soil at a level close to the surface.

    The common types of shallow foundations are

    Strip foundation

    Pad foundation

    Raft foundation.

    Strip Foundation

    The minimum thickness of a strip foundation is 150 mm. This may be of course, greater where the

    projection of the edge of the foundation from the base of the wall is greater than 150 mm. A typical

    strip foundation is as shown in figure below. The width of the strip should be at least equal to three

    times the thickness of the wall it supports.

  • 8/11/2019 BLD 206 Merged

    23/54

    Fig 3 Strip foundation

    PracticalProcedures;

    This week students are expected to set out a simple building using the 345 method.

    Tools and equipment required for setting out

    1. Wooden pegs

    2. Steel or fibre tape measures3. Builders line

    4. Hammer

    5. Digger(s)

    Result;

    At the end of the practical exercise students are expected to be able to set out a simple building.

  • 8/11/2019 BLD 206 Merged

    24/54

    WEEK 7: BLOCKWORK/SUPERSTRUCTURE

    Once the wall reaches ground level thought must be given to the positions of openings that will

    be formed in the wall, and the arrangement of the blocks in the chosen bond. The drawing should

    be properly studied well in advance so that all odd pieces of block and broken bonds are

    arranged to appear directly below the positions of the openings. When building with blocks in

    running bond little difficulty is experienced in setting out the bond for openings. With brickwork

    however, necessary precautions must be taken so that the bond at ground level is continued

    throughout the height of the wall. This means that the portends must be maintained throughout

    the height of the wall.

    Block/Brick walls are built in any one of the following forms;

    Stretcher bond

    English bond

    Flemish bond

    But for the purpose of this lesson the stretcher bond style is taken (Fig 1)

    Pre-cast window sills are built into the walls as the work proceeds. Where a wall has several

    window openings, it is good practice to bed the end sills first, and align all other sills to these.

    The bottom edge of the sills must give a true eye-line when finally bedded. If sills are to be castin-situ, adequate provision must be made to tie them into the wall. In brick walls, bricks equal in

    thickness to the sill are bedded in sand at the reveals, which are later removed. Blocks need to be

    cut to shape to provide for the sill before they are built into the wall. Window frames may be

    fixed into position as the work proceeds or fixed after the walls have been completed. Whichever

    way is adopted depends upon several factors, for instance, the availability of the frames at the

    time the wall is being built may be a deciding factor. Each method has it advantages and

    disadvantages. In theory, it is argued that the fixing of window frames while the work proceeds

    enables the frames to be fixed rigidly to the walls by using fixing lugs, cramps and similar

    devices. A major disadvantage in this method is that the frames need to be supported in position

    until the walls are built. This slows down the pace of the block layer as the bracing timber often

    extends to the scaffold platform, thereby obstructing the passage of wheelbarrows and labourers.

  • 8/11/2019 BLD 206 Merged

    25/54

    In practice, it has been found that frames fixed after the walls have been built do not suffer any

    structural weakness. After all, the plaster on the reveals serves to keep all frames rigid enough.

    When frames are not fixed as the work proceeds, the window reveals must be kept plumb. A

    pinch rod is usedto keep a constant check.

    Fig 1 Wall in stretcher bond

    Practical procedure;

    This week the students should build a brick wall in stretcher bond.

    Materialsandtoolsrequired

    1. Blocks or bricks

    2. Clean sharp sand

    3. cement

    4.

    Masons trowel

    5. Float and straight edge

    6. Builders line.

  • 8/11/2019 BLD 206 Merged

    26/54

    Result;

    At the end of this exercise, the students are expected to be able to build a wall in stretcher bond

    and to be conversant with the other bonds. The students should also know how openings areprovided in walls.

  • 8/11/2019 BLD 206 Merged

    27/54

    WEEK 8: LINTELS AND ROOF BEAMS

    LINTELS

    A lintel is a beam that spans across a horizontal opening and supports the load just above the

    opening. Lintels can be timber or concrete. Timber is fine for short spans but is not durable. For

    this reason most lintels are built from reinforced concrete.The lintel can be covered with skin decorative brickwork which needs support. This is done by:

    Bolting a galvanized steel angle to the concrete lintel.

    Building the decorative brickwork on the edge of the angle;

    Tying the brick joints to the lintel with metal ties.

    Constructing concrete lintels

    The following basic guidelines could be used to construct a lintel for domestic scale

    construction. Table 3.1 gives some basic requirements for smaller lintels.

    Lintels can be cast in situ or precast. The span will determine the height of the lintel, which

    should correspond to the height of full brick courses.

    Standard dimensions for lintels

    Span (mm) Depth (mm) Reinforcement sizes (mm)

    900 150 10

    1200 150 12

    1500 215 12

    1800 215 16

    The design of the lintel should use these additional requirements:

    the bearing of the lintel must be more than 150mm;

    at least 25mm of concrete must cover the bottom of the reinforcement bar;

    at least 50mm of concrete must cover the ends of the bar.

  • 8/11/2019 BLD 206 Merged

    28/54

    Fig 1 Construction of a concrete lintel

    ROOF BEAM

    This is otherwise known as head coarse, it is concrete casted in-situ at the end of the last coarse

    of block or brick to seal up the building and support the roof structure / roof covering.

    The process is by preparing the formwork to receive the wet concrete at the top of the last block

    work equal to the thickness of the block or brick and to height of a block coarse. The process is

    the same like that of a lintel construction with the only difference of position in building.

    Practical procedures;

    The students should prepare a formwork, fabricate and erect a reinforcement and cast the

    concrete for a lintel above an opening.

    1. Hammer

  • 8/11/2019 BLD 206 Merged

    29/54

    2. Nails

    3. 300mm x 300mm 3.6m planks

    4. Carpenters

    5.

    Saw and pinch bar

    6. Reinforcing rod

    7. Sharp sand, gravel and cement

    Result;

    At the end of this practical exercise the students are expected to be able to understand the process

    of making of a lintel above an opening.

  • 8/11/2019 BLD 206 Merged

    30/54

    WEEK 9: ROOF STRUCTURE AND OPENINGS

    ROOF COSTRUCTION

    The roof is perhaps the most important part of building. It shed water more quickly without

    leaking, it keeps out grit and dust, it provides shade and sometimes light, and insulate against

    heat and noise. It may also be used for re-creational purposes and for additional living space.

    Roof design involves a number of factors some of which are overhang, wind insulation,

    ventilation, lighting, movement of pest and disposal of water

    Pitch roof

    A pitch roof has one or more roof slopes at a pitch or slop of more than 10 to horizontal. The

    most common roof shape is the symmetrical pitch roof, pitched to central ridge with equal slope.

    A mono pitched roof has only one slope free standing vision lean to roof.A pitched roof is stable in most weather and its slope disposes of rainwater quickly. The main

    supporting structure is timber, which is easy to work and transport.

    Pitched roof construction

    This can be built in different ways depending on the loads and sizes. Below are the list of pitched

    roof that use different methods of construction.

    Types of pitch roofs

    Lean-to roof

    Couple roof

    Closed couple roof

    Collar roof

    Trussed rafters roof

  • 8/11/2019 BLD 206 Merged

    31/54

    Roof sheets covering

    This is covering the roof with sheeting materials like corrugated fibre cement, aluminum sheets,

    corrugated galvanized steel, etc.

    Fixing detail

    1. Position the first sheet in the bottom corner of the roof framework

    2. Drill through a sheet on top of the corrugations.

    3. Fix it to the purlins with galvanized iron drive screws or zinc roof nail

    4. Lay the next sheet so that it overlaps the first sheet by one corrugation

    5. Fix the ridge member and nailed to the sheets.

  • 8/11/2019 BLD 206 Merged

    32/54

    Practicalprocedures;

    The student should fabricate a simple purlin roof truss made of timber and fix some section of

    the covering.

    Materials and tools required

    1.

    Roofing sheets

    2. Nails or screws as required

    3. Hammer, saw and pinch bar

    4. Timbers for roof truss formation

    Result;

    At the end of this lesson the student should be able form roof trusses of small building, and

    should be able to know the process of fixing roof coverings.

  • 8/11/2019 BLD 206 Merged

    33/54

    WEEK 10: CEILING NOGGINGS AND COVERING

    CEILINGS

    Ceilings are generally classified into two major types i.e. the suspended and the non-suspended

    ceiling.

    Functions of ceilings

    The ceiling gives a definite demarcation of the room from the top.

    The ceiling provides support to lighting fittings and ceiling fans.

    The ceiling helps conceal service pipes, heating and cooling systems, which are regarded

    as unsightly features.

    The ceiling reduces the amount of heat transmission from the interior of the building (in

    case of fire) to the timber and /or steel roof members or suspended slab and beams

    Thermal insulation: The void created by the ceiling helps to regulate the transmission of

    heat from weather to the interior of the building.

    Dust proof: The ceiling prevents the effect of dust penetrating through roofing sheet laps

    and other into the building.

    Sound insulation: Depending on the type of materials used as the final finishing ceiling

    act as an insulator for sound in the room.

    Reducing in heating or cooling cost: By defining the limit of the room thus reducing the

    volume of air in room, the ceiling helps in reducing the cost of heating or cooling room

    when the need so arise.

    Appearance: The ceilings help in adding to the aesthetic of the interior of the room thus

    making the room comfortably habitable.

    Rain effect: In case of leakages on roof covering, the ceiling prevents the effect of direct

    dropping of rainwater into the room.

    Factors affecting the choice of ceiling construction

    It is an indisputable fact that the type of ceiling finish affects the construction and the factors that

    affect the choice of ceiling construction include the following:

  • 8/11/2019 BLD 206 Merged

    34/54

    Activities to be carried out in the building: The activities to be carried out in the building

    do affect the choice of ceiling thus affecting the construction. (e.g. a room which is meant

    to be used as conference room or music recording studio, where reverberation of sound

    produce will be detrimental to the activities being carried out in the room, ceiling with

    hard surface such as concrete finished carried out in the room, ceilings with hard surfaces

    surface such as concrete finished must be used, acoustic will be advisable). An additional

    example is the use asbestos in rooms that are prone to fire and POP (Plaster Of Paris) for

    functions same as the, and beauty.

    Availability of fund: It is only he that has money that thinks of the procedures of owning

    on whether there is available fund to select what ever type which consequently affect the

    construction.

    Suspended Ceiling

    The suspended ceiling can be defined as ceiling fixed to a frame work suspended form the main

    structure either by means of timber, aluminum or steel members, thus forming a void between

    the tow components. The choice of this type of ceiling depends on the aforementioned factors,

    through there are some situations where if ceiling must be constructed to a building, then it has tobe suspended ( i.e. when the frame structure is of timber roof members)

    Below are some notes that have to be carefully observed while constructing a suspended ceiling

    i. They should be easy to construct, repair, maintain and clean.

    ii. Should be designed in a form that an adequate means of access is provide to the void space for

    the maintenance of the suspension system and concealed services

    iii. Conform with the minimum requirement set out in the building regulations and in particular

    the regulations governing the restriction of spread of flame over surface of ceilings and the

    exceptions permitting the use of certain plastic materials.

    Classification of suspended ceiling

  • 8/11/2019 BLD 206 Merged

    35/54

    There is no standard method of classification since some are classified by their function such as

    illuminated and acoustic suspended ceiling; others are classified by materials used.

    However, classification by method of construction is also very popular. This method is simple

    since most suspended ceiling types can be place in one of the following groups:

    a. Jointless suspended ceiling

    b. Paneled suspended ceiling

    c. Decorative and open suspended ceiling

    Jointless suspended ceiling

    Jointless suspended ceiling are made with plaster of various sorts and sprayed asbestos, applied

    to a backing of expanded metal of 6mm size of the short way of the mesh, either galvanized steel

    or steel painted with asphalt, example of these materials are as shown of fig. below

    Paneled suspended ceiling

    This can be made with dry materials; consequently they are more quickly completed than the

    jointless types. The panels are pre-formed, made of fiberboard, plaster, asbestos materials, metal

    trays, cork, wood-wool and strawboard. The board is obtainable in thickness from 5 to 50mm

    and in sizes from 305mm square 1.2 x 4.2, panels 610mm square or 610 x 1200mm are

    commonly used. Some boards are perforated to within a short distance with small holes to

    improve sound absorption. Light gauge rustproof steel or aluminum channels, timber members

    or tee sections are used to support the sagging to the ceiling. The sections can be exposed or

    concealed and the panels should rest on flanges at least 16mm wide to allow for possible

    movement. Tees are often used supports, the main ones at 610mm centres with cross tees

    (noggin) at the end of the panel. Ideally 610mm square a panel gives the best result. The finished

    ceiling weighs from 10 to 12kg/m2

  • 8/11/2019 BLD 206 Merged

    36/54

    Fig 1 Typical Support Detain

    Practical procedures;

    This week the students should fix ceiling noggin to the hardwood tie beam and also fix the

    suspended paneled ceiling.

    Materials and tools required

    1. Ceiling sheets

    2. 50mm x 50mm Noggin and 10mm x 50mm batten in timber

    3. Hammer, saw and pinch bar

    4. Nails (75mm and 40mm) long

    Result;

    At the end of this practical exercise, students should be able to know different types of ceilings

    and there method of fixing. Also they should know the requirements for ceiling works.

  • 8/11/2019 BLD 206 Merged

    37/54

    Assignment

    1. List and describe the different types of ceiling covering

    2. Show using neat sketch the method of fixing paneled suspended ceilingd

    3. State the functions of ceiling.

  • 8/11/2019 BLD 206 Merged

    38/54

    WEEK 11: METHOD OF FIXING PIPES FOR PLUMBING WORKS

    Joints, bends or changes in direction of pipe work can be done using special purpose fittings and

    joints, but this can work out costly on big installations where you need a lot of fittings and some

    bends cannot be made-up easily using available fittings. In these cases you will have to bend the

    pipe yourself. The method chosen will be governed by the size and type of pipe used. Some

    bends on steel, copper and certain types of plastics, for example, can be done by heating. In most

    situations, however, the easiest way is to use a machine.

    Machine Bending to Mild Steel and Copper Pipes.

    Machine Bending to Mild Steel Pipe

    The easiest and most popular method of bending steel pipe is to use hydraulic pipe bender. There

    are several types available but the simplest is the hydraulic press bender which can bend pipes

    from 15mm diameters up to 100mm diameters. It consist of a hydraulic ram on which different

    sizes of former can be put to bend the pipe against a frame containing adjustable pins and stops.

    Figure 2.13.1: Hydraulic Press Bender

  • 8/11/2019 BLD 206 Merged

    39/54

    Using a Hydraulic Press-Bender to Make a 90 Bend

    To make a 90 bend from a fixed point, say 800 mm from the end of the pipe to the centre line of

    a bracket fixed on a wall.

    Tools Required

    1. Hydraulic press bender 7. Measuring tape rule

    2. Try-square 8. Sprit level

    3. Scriber 9. Hack saw

    4. Pipe reamer 10. Pipe vice

    5. File 11. Metal divider

    6. Pipe cutter 12. Straight edge

    Materials Required Any one of the following pipes can be bent using the procedure.

    1. Mild steel pipe.

    2. Galvanized iron pipe

    3. Steel pipe

    Produce a working drawing or template.

  • 8/11/2019 BLD 206 Merged

    40/54

    Fig. 2.13.2: Marking out for a 900bend from the working drawing

    Operational Steps

    1. Measure and cut the required length

    2. Mark the pipe 800 mm from the end.

    3. Deduct from this the diameter of the pipe, and make a fresh mark on the pipe, for

    example if you are using 35 mm diameter pipe, your new mark should be 800 minus 35,

    or 765mm from the end. This will now be the centre of the bend, to allow for the 'gain' in

    pipe length caused by a bend.

    4. Lift up the top bar of the frame on the machine and put the stops and pins in the correct

    position (35 mm) and put sand, the 35 mm former on the end of the hydraulic ram. Lower

    the bar on to the top of the pins.

    5. Position the pipe in the machine against the stops and with the centre line of the former in

    line with your mark on the pipe. Gently pump the ram until it locates against the pipe in

    the correct position and the pipe is held secure.

    The bleed valve on the hydraulic cylinder must be in the closed position otherwise it will

    not build up pressure to pump.

    6. Pump the machine carefully until the bend is almost at 90, and check this with a set-

    square or, template, To allow for " spring-back, you must bend the pipe a few degrees

    beyond 90, When the pressure is removed it will spring back to the desired angle.

    7. When you are happy that the bend is right, making the allowances mentioned, open the

    valve on the machine body to release the pressure and slowly pump the handle which will

    pull back the ram. The former will probably be jammed on the pipe, but do not remove it

    yet.

    8. Check with a set-square or working drawing that the angle is correct, then remove the

    former by holding it with one hand and striking the end of the pipe on a piece of wood on

    the f1oor; this should loosen it. If it needs bending more, simply return it to the machine

    and increase the bend. If you have bent it too much, it is possible to open the bend by a

    couple of degrees by securing one leg of the bend in a vice and carefully applying

    leverage to the other leg to pull it back slightly. This is not recommended if it needs

    pulling back much over 5, since it will deform the pipe wall.

  • 8/11/2019 BLD 206 Merged

    41/54

    Copper Pipe Machine Bending

    Several machines are available for bending light gauge copper pipe and most of them work on

    the same principle. One of the most popular for general site and workshop use is the floor

    mounted bender. This is suitable for all sizes up to and including 35mm.

    Fig.2.13.3: Floor-mounted copper pipe bending machine Fig. 2.13.4 making offset

    Fig. 2.13.5: Use of a floor-mounted copper pipe bending machine

  • 8/11/2019 BLD 206 Merged

    42/54

    Calculating the Heat Length for a 900Bend

    Mark off on the pipe the distance from a fixed point, say 5001 mm to the centre of the bend. This

    is the centre line of the projected bent leg of the pipe. This point will also be the end of the actual

    travel or length of the bend.

    For a 90 bend the actual length or travel of the bend should be a quarter of the circumference of

    a circle made to the radius of the given end. Unless a radius is specified. Use a radius equal to 4

    times the outside diameter of the pipe to be bent.

    If we assume the pipe is 28 mm, the radius will be 4 x 28, which is 112 mm. If the travel or

    length of bend is equal to a quarter of the circumference of a circle having a radius of 12mm the

    heat length will be:

    The circumference of the circle divided by a quarter or D, this will be 2 x 112 x 3.142 which is

    181mm, the calculated heat length, then is 181mm.

    Steel pipe can also bent by loading the pipe with dry sand, bearing it up in a furnace or with a

    large flame from a blowlamp or oxyacetylene torch, then bending it round a former or between

    steel pins on a bending table.

    From the centre line of the bend already marked out on the pipe (500mm), measure back towardsthe fixed point 181mm, the calculated heat length, and mark off on the pipe. This marks the

    position of the start of the bend.

    Fig. 2.13.12: Marking out the heat length on a pipe

  • 8/11/2019 BLD 206 Merged

    43/54

  • 8/11/2019 BLD 206 Merged

    44/54

    WEEK 12: FIXING OF DOORS AND WINDOWS

    A door is a moveable barrier used to cover an opening. Doors are used widely and

    are found in walls or partition of a building or space or in furniture such as

    cupboards, cages e.t.c. A door can be opened to give access and closed more or

    less securely using a combination of latches and locks. Doors are universal in

    buildings of all kinds, allowing passage between the inside and outside (external

    doors) and between internal rooms (internal doors). When open they also admit

    ventilation and light. Doors can be made of timber, glass, metal or plastic or any

    combination of these materials. They can also be designed to swing from one

    edge, slide, slide and fold, or roll close an opening. Classification of doors can

    also depend on their position in a building, their function or by their method of

    construction.

    On the other hand the primary functions of a window are to provide means for

    admission of natural daylight to the interior of building and to provide means of

    necessary ventilation of dwellings. Windows like doors can be made from a

    variety of materials or a combination of these materials, such as timber, metal and

    plastic.

    They can also be designed to operate in various ways, i.e to slide, pivot or swing

    or by being hung to one of the frame members.

    Frames of doors and windows are most important parts of our doors and windows.

    They are available in different sizes, heights, widths and shapes. Frames hold

    locks and hinges and support doors and windows to shut and open easily. Door

    frame or lining is attached to the opening in which a door is to be fitted, it

    provides a surround for the door and is the member to which a door is fixed or

    hung. Frames can be fixed to a wall by the following methods:-

    Built into the wall as the work proceeds by using L-shaped galvanized sheet ties

    or cramps. The ties are fixed to the back of the frame for building in at 450mm

    centres.

    Fixed into the opening at a late stage in the work to prevent damage to the frame

    during the construction period. This is a more expensive method and is usually

  • 8/11/2019 BLD 206 Merged

    45/54

    employed only when good quality timber and joinery or high quality materials are

    involved.

    Door linings are as wide as the wall including any wall finishes. They are usually

    only specified for internal doors. Linings are not built in but are fixed into an

    opening by nailing or screwing directly into walls or into plugs built in walls.

    Hanging doors and windows requires good carpentry skills and a set of good

    quality carpentry tools. It involves:

    Trimming the shape to fit the door swing (planning the edge)

    Reducing the height to fit the opening

    Fitting door closers

    Fitting hinges

    Fitting bolts

    Fitting latches and locks

    Fitting handles

    TASK

    Students are expected to carryout the fixing of the following:-

    i. A wooden casement window

    ii.

    A flush door

    The task includes the fixing of all ironmongery

    RESULT

    After the completion of the task, the student is expected to known the techniques

    and methods of fixing doors and windows. The task will also allow the student to

    know the function of the different types of ironmongery and the effectiveness and

    uses of different kinds of carpentry tools.

    ASSESSMENT

    i. Describe two methods of fixing frames to walls

    ii. Briefly describe the steps or procedures you followed in the fixing of any of the

    given items in the task carried out.

  • 8/11/2019 BLD 206 Merged

    46/54

    WEEK 13: FINISHES

    Walls constructed using the wet system requires surface finish of one type or another. A

    wall finish may consist of painting, plastering or rendering, pointing the joints, tiling etc. No

    matter what type of material is used or which method is adopted for a wall finish, the purposes

    tend to be common for all. Generally, finishes provide resistance to moisture and rain

    penetration, give a pleasant appearance and increase the fire, sound and thermal resistance of

    walls. This week, wall finishes will be restricted to plastering or rendering and wall tiling.

    Plastering or rendering refers to the application of wet mixes of fine cementing material and sand

    to the surfaces of walls, while tiling refers to the application of tiles to internal walls.

    STEPS

    1. Plastering or Rendering of walls (Task 1)

    Clean the wall surface thoroughly.

    Prepare plastering mixes by mixing cement and sand in the right ratio and addwater to make a suitable workable mix.

    Place plaster screeds at convenient distance to form guides for straightening the

    surface. These served are narrow hands of plastering mortar plumbed down.

    Apply the coat of plaster. Use the trowel to throw the mortar in an upward stroke

    to the wall. This technique spread the mortar in an almost even thickness.

    Use the straight edge to spread the mortar to a straight and even surface.

    Use the wooden float to work the surface to a sandy gently finish.

    Use the plastering trowel to make surface smooth.

    Clean up the working space.

    2. Wall tiling (Task 2)

    Hack the wall and clean thoroghlly if surface is smoth.

    Set out the work starting from a corner, making sure that all odd picies are placed at a

    corner, and at the base of the wall.

    Bed a flat piece of lath to a perfect level at the base of the wall to receive the first

    course of tiles.

    Soak the tiles in water.

    Mix mortar. Fixing of tiles is done with special mastics or a purely cement mix.

    Butler the tiles bed evenly with the mix and press on to the wall,tapping it slightly

    into position with a mallet.

    Allow as small a joint as possible between tilesensure plumb and flatness by using a

    spirit level and straight adge.

    Rub the joint flush with a piece of soft waste cloth.

    Clean the tile after setting and polish as a final oppration.

    Clean the tools and working area.

  • 8/11/2019 BLD 206 Merged

    47/54

    NB When odd pieces are required, a tile cutter or punches is needed to cut and shape tiles to

    appropriate sizes.

    TOOLS/EQUIPEMENT

    1.

    Plastering or Rendering (Task 1) Blocklayering Trowel

    Plastering Trowel

    Straight edge

    Spirit Level

    Wooden Float

    Cement

    Sand

    Water

    2. Wall tiling (Task 2)

    Steel Square

    Lath

    Container, preferable 20L bucket

    Mallet

    Trowel

    Spirit Level

    Waste cloth

    Tile Cuter

    Puncher

    Cement

    Water

    Tiles

    RESULT.

    These two tasks are expected to give the student a good knowledge about how to

    apply finishes to wall of building. On completion of the task, the student is also

    expected to be conversant with the techniques of plastering and tilling of walls.

    ASSESSMENT.

    1. State the main purposes of a wall finish.

    2. Explain the important of platerscreeds in plastering.

  • 8/11/2019 BLD 206 Merged

    48/54

    WEEK 14 : SANITARY APPLIANCES.

    Sanitary appliances are fittings used for the collection and discharge of soil or waste matter. This

    appliance may be grouped under soil appliances and waste water appliances. Soil appliances are

    used for the collection and discharge of excreta matter and they include water Closets (W.C.),

    Urinal etc. A sanitary appliances used for the collection and discharge of water after use is called

    water appliances and include drinking water from tanks, water hand basin, Kitchen sinks, bath

    tub etc. Sanitary fittings are necessary in buildings in order to enhance our convenience and use

    of the building.

    STEPS

    Task 1. Installation of water closet with siphonic action pan

    Place the W.C. pan on the flour.

    Fix the W.C. pan to the flour by using screws and plastic plugs.

    Place the flushing cistern on the W.C. pan.

    Align the holes to connect the cistern to W.C. pump.

    Insert bolt to the aligned holes.

    Tie the bolt and nut to connect the W.C. pan and the flush cistern.

    Connect water supply pipe to the flushing cistern.

    Clean the tools and working area.

    Task 2 Installation of wash hand Basins

    Type 1Bracket type

    Mark the position for the wash hand basin bracket.

    Drill a hole of the correct diameter and depths using a suitable masonry drill to receive

    plastic plug or ribbed plug.

    Insert the plug to the wall.

    Pan the screws through the item to be fixed and with the plug.

    Screw home the bracket until tight.

    Place the basin on the bracket.

    Connect the hot and cold water supply.

    Connect the water outlets. Clean the working space.

    Type 2Pedestal type

    Mark position for the bolt and nuts to hold the basin

    Place the basin to the wall and align the holes in the basin to the bolts.

  • 8/11/2019 BLD 206 Merged

    49/54

    Tight the bolts and nuts to hold the basin.

    Fix down the pedestal to the floor with basin screws to support the basin.

    Connect the hot and cold water supply.

    Connect the waste outlets.

    Clean up the working space.

    Task 3 Installation of Baths.

    Place the bath on the floor.

    Adjust the legs to make the bath slope to the outlet.

    Connect the hot and cold water supply.

    Connect the waste outlet.

    Clean up the working space.

    TOOLS/EQUIPMENT.

    Task 1.

    Hack saw

    Reamer

    Measuring tape

    Spirit level

    Hand drilling machine

    Screw driver

    Hammer

    File

    Chain pipe vice

    Heavy duty multiple cutter

    Caulking tools

    Drill

    Cold chisel

    Pliers

    Task 2.

    Measuring tape

    Pipe cutter

    Pipe vice

    Oil can

    Chisel

    Screw drivers

  • 8/11/2019 BLD 206 Merged

    50/54

    Open spanners

    File

    Spirit level Hack saw

    Reamer

    Threading machine Pipe wrench

    Hammer

    Adjustable spanner

    Scriber

    Pliers

    Task 3.

    Same as task 2.

    MATERIALS

    Task 1.

    Ceramic W.C. pan

    Flushing cistern

    Various pipes

    Simple rubber push-fit connectors

    Hemp

    Cement

    Plastic plug

    Putty

    Sand

    Gasket

    Flush pipe

    Brass screws

    Ribbed plug

    Task 2.

    Wash hand basins (Bracket or/and pedestal type)

    Mild steel pipe

    Plastic pipe

    Copper pipe

    Bran Screws

    Plastic plug

  • 8/11/2019 BLD 206 Merged

    51/54

    Cantilever basin bracket

    Pipe fittings

    Ribbed plug

    Bolt and nuts

    Task 3.

    Baths

    Copper pipe

    Pipe fitting

    Putty

    Mild steel pipe

    Plastic pipe

    Brass screws

    RESULT

    After the completion of these tasks, the student is expected to understand the methods of

    fixing sanitary appliances and their mode of connection to water supply. These task are also

    expected to give the student acknowledge about the requirement of sanitary accommodation, the

    differences between sanitary appliances, the use of these appliances and their mode of operation.

    ASSESSMENT

    1) Differentiate between soil and waste appliances.

    2) Explain the differences in the fixing of bracket type and pedestal type wash hand basins.

    3) Write a report to explain the type or types of tools used to achieve each step in any of the

    three tasks.

  • 8/11/2019 BLD 206 Merged

    52/54

    WEEK 15: PAINTING.

    Paint is a liquid that drives to form a protective film on the surface. Paints mainly consist of

    pigments, builders, additives and solvents. The pigments are fine particles that provide the

    colour. The builder holds the pigment together and glues them to the surface being painted. The

    additives are included to enhance different properties of the paint e.g. Splatter resistance, easier

    brushing, etc. The solvent could be water or natural plant oils

    There are generally two types of paints, i.e. the latex paint and the Alkyd paint. Latex paint are

    formulated with water as the main ingredient and are known as water base. Because its primary

    liquid is water, latex paint dries quickly, is almost odorless and is environmentally friendly.

    Alkyd paints use mineral spirits or paint thinner as a solvent. Since earlier paints use natural

    plant oils as a binder instead of alkyd resins this type of paint become known as oil base. Alkyd

    paints are used especially on interior trim. If is durable, stain resistant and dries with less brush

    marks. Both paint types have excellent qualities but are incompatible with each other. Alkyd or

    oil-based paint can be applied over latex or water-based paint, but never the other way round (oil

    over water- never water over oil).

    Painting is the art or process of applying paints to surfaces especially in building. With the use

    of right colours, a room can change its feel and become a more enjoyable living space.

    Paint is designed to be applied to clean and smooth surface, therefore a quality paint job

    beings with the preparation can amount to 50% or more of actual work involved in painting.

    Preparation involves removal of loose and peeling paint, washing away dust particles and spider

    webs, covering areas where you do not want to paint and protecting floors. The choice of the

    right type of ladder is also a very important aspect of preparation.

    Choosing the right type of paint for a job depends on the surface, the use of the surface, and

    the type of tools available for the work. Any type of paint chosen must be stirred thoroughly for

    about three minutes because paint and painting look better if the components are well mixed.

    In applying the paint to the surface, ceilings are the first area to receive the new colour.

    Ceilings are always a pain in the shoulders, therefore rolling is suitable for ceilings in small

    rooms and most area of the house. Painting the walls are next and by far the easiest. If the colour

    and sheen is identical to the ceiling, the same paint and application method can be used.

    Different paint will require a separate application method such as in large jobs the ceiling could

    be sprayed then the walls rolled. Next, it is the time for details like painting the windows, doors

    and trim. These areas require extra patience and attention to details. The choice of the right tools

    and painting technique will help with these projects.

  • 8/11/2019 BLD 206 Merged

    53/54

    TOOLS

    The tools needed for house painting can be separated into two categories i.e. preparation tools

    and application tools. Preparation tools consist of the following:-

    Pressure washer- used for washing the dust and spider webs of house prior topreparation.

    Paint scraper- for removing loose paint as well as other old materials.

    Power sanders, Wire brushes, Sandpaper- used to identify and remove additional loose

    and peeling paint.

    Drop cloth or Rags- for protecting floor to prevent messes.

    Masking machine, Masking tape- used for covering areas you do not want to paint.

    Putty Knife- for applying putty to cover depressions.

    Caulking gun.

    Extension and step ladders.

    Application tools consist of the following:-

    Paint brushes- most basic of all and it comes in different sizes and styles.

    Paint rollers- consist of roller cover, roller frame and roller pole and also comes in

    different sizes, shapes and styles.

    Powered painting tools- such as airless sprayer, HVLP sprayer, Power roller and pad

    applicators.

    Availability of painting tools saves a lot of time and additional effort and most tools are

    suitable for interior and exterior jobs.

    After painting the surfaces, the clean up stage involves removing paint stains and washing the

    tools water-based or latex paint cleans up with water while a paint thinner or TSP (Tri Sodium

    Phosphate) will be required to clean up oil-based or alkyd paints.

    TASK.

    After studying the explanation in the introduction, the student should carry-out a complete

    painting of room. This will involve the processes of preparation, application and cleaning of

    ceiling walls and trims. The types of tools available should guide the studentschoice of method

    of application.

  • 8/11/2019 BLD 206 Merged

    54/54

    RESULT.

    After the completion of the task, the student is expected to present a wall painted room.

    Furthermore, with this task the student is also expected to have acquired a good understanding of

    the processes involved and methods of painting a house.

    ASSESSMENT.

    The student should write a report. The report is expected to present an explanation of the step

    taken to complete the task in logical sequence and the tools used to achieve each step.