NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 1
PRELIMINARY AND GENERAL(Applicable to the whole of the Works)
FIXED CHARGE ITEMS
1/1/1 Contractual requirements. SUM
Establishment of Facilities on the Site
Facilities for Engineer
1/1/2 Name boards. (In No. 2). SUM
Facilities for Contractor
1/1/3 Offices and storage sheds. SUM
1/1/4 Workshops. SUM
1/1/5 Laboratories SUM
1/1/6 Living accommodation. SUM
1/1/7 Ablution and latrine facilities. SUM
1/1/8 Tools and equipment. SUM
1/1/9 Water supplies, electric power, communications, dealing withwater, and access. SUM
1/1/10 Dealing with water SUM
1/1/11 Access SUM
1/1/12 Plant SUM
1/1/13 Density Tests SUM
1/1/14 Concrete Tests SUM
1/1/15 Other fixed charge obligations. SUM
Carried Forward R Section No. 1SECTION 1: PRELIMINARIES AND GENERALSBill No. 1PRELIMINARIES AND GENERAL
- 1 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
1/1/16 Complying with Health and Safety Specifications SUM
1/1/17 Complying with Environmental Management Programme Actand all other statutory environmental requirements SUM
1/1/18 Security for the works for duration of the contract SUM
1/1/19 Removal of site establishment. SUM
TIME RELATED ITEMS
1/1/20 Contractual requirements. SUM
Operation and Maintenance of Facilities on Site, for Duration ofConstruction, (unless otherwise stated)
Facilities for Engineer
1/1/21 Nameboards. (In No. 2). SUM
Facilities for Contractor
1/1/22 Offices and storage sheds. SUM
1/1/23 Workshops. SUM
1/1/24 LaboratoriesSUM
1/1/25 Living accommodation. SUM
1/1/26 Ablution and latrine facilities. SUM
1/1/27 Tools and equipment. SUM
1/1/28 Water supplies, electric power, communications, dealing withwater, and access. SUM
1/1/29 Dealing with water SUM
1/1/30 Access SUM
Carried Forward R Section No. 1SECTION 1: PRELIMINARIES AND GENERALSBill No. 1PRELIMINARIES AND GENERAL
- 2 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
1/1/31 Plant SUM
1/1/32 Density Tests SUM
1/1/33 Concrete Tests SUM
1/1/34 Supervision for duration of construction. SUM
1/1/35 Complying with Health and Safety Specifications SUM
1/1/36 Company and head office overhead costs for duration ofconstruction. SUM
1/1/37 Other time related obligations. SUM
1/1/38 Complying with Environmental Management Programme Actand all other statutory environmental requirements
SUM
1/1/39 Security for the works for the duration of the contract. SUM
DAYWORK
Existing services.
1/1/40 Supply or hire of specialist equipment for the detection of aparticular service. SUM
1/1/41 The use of equipment referred to in (a) above. SUM
1/1/42 Excavation by hand in soft material to expose Unknownservices m3
1/1/43 Temporary protection, as required in terms of the projectspecification and as directed by the Engineer
SUM
Carried to Final Summary R Section No. 1SECTION 1: PRELIMINARIES AND GENERALSBill No. 1PRELIMINARIES AND GENERAL
- 3 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 1
YARDSTONE
NOTE: Removing and replacing of yard stone is measured1m beyond outside border of new structures and will bepaid accordingly
2/1/1 Take up yardstone layer 100mm thick and stockpile for reuse. m2 800
2/1/2 Take from stockpile and re-place yardstone layer 100mm thickupon completion of the works, lightly compacted to set levels m2 800
Pitching of Surfaces (Provisional)
2/1/3 New yard stones to terrace. m2 240
Rubble disposal. (Provisional)
2/1/4 Transport all rubble from demolitions and the works to a nearbyRegistered Dump Site. Item
BARRICADE FENCING
Barricade fencing to be re-sed to cover the rest of thescope (Provisional)
2/1/5 Make provision for supply and install barricading fence 1.8mhigh around the working area, compliant to Eskom Safetyrequirements. m 100
2/1/6 Make provision for the necessary barricade fencing (shark net)to fence off the approved working area and hand over toSub-station EA after finalising of contract. m 100
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 1SITE CLEARANCE
- 4 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 2
EARTHWORKS (PROVISIONAL)
Excavation
2/2/1 Excavate in all materials and use for backfill or dispose off asordered. m3 158
Extra over for:
2/2/2 Intermediate excavation m3 19
2/2/3 Hard rock. m3 9
Importation of Materials from Commercial Sources.(Provisional)
2/2/4 G5 Material from commercial sources in accordance with SABS1200 DM compacted to 95% Mod AASHTO density to beapproved by the Engineer. m3 80
Soil Poisoning
2/2/5 Approved weedkiller applied in strict accordance to themanufacturer's instructions. m2 84
Pitching of Surfaces (Provisional)
2/2/6 New yard stones to terrace. m3 84
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 2EARTHWORKS
- 5 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 3
CONCRETE (SMALL WORKS)
FORMWORK
Smooth
2/3/1 To sides of bases and stub columns m2 27
Boxing in special formwork to form
2/3/2 Form 20 x 20mm chamfer along top edge of exposed stubcolumn or base. m 18
REINFORCEMENT
Steel Bars
Mild steel reinforcement bars
2/3/3 8mm t 0.05
2/3/4 12mmt 1.76
2/3/5 25mm t 0.48
CONCRETE
Blinding layer in 15MPa/19mm concrete
2/3/6 Blinding layer 50mm minimum thickness. m2 84
Strength concrete, 25MPa/19mm
2/3/7 Bases and Stub Columns m3 66
Unformed Surface Finishes
2/3/8 Wood floated finish. m2 4
HOLDING DOWN BOLTS
Carried Forward R Section No. 2SECTION 2 : ARNOT SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 6 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
All HD bolts to be hot dipped galvanised bolts
Holding down bolts and miscellaneous metalwork (supplied andfixed by the Contractor)
2/3/9 HD bolts including nut and washer cast in position in concrete. kg 54.0
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 7 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 4
EARTHMAT (PROVISIONAL)
Earthing
Supply, deliver and lay copper earthmat equipmentearthing, earth straps, including excavation complete withrisks of collapse, bedding, backfill, compaction and testingat depth up to (See earthmat specification). All flat copperto be 50 x 3mm in accordance with BS 1432, picled andannealed black copper ().701 kg/m:
ELECTRICAL ( Provisional)
2/4/1 Clamp connection 50 x 3mm flat to 2 no. x 10mm diameterrods No 100
2/4/2 Crimp joints 10mm round to round (Refer sheets C5 to C8) No 99
2/4/3 1 x 10mm Diameter copper at 1,0m deep. m 99
ELECTRICAL
2/4/4 Excavate, search for and locate existing earthmat, includingexcavations complete with risk of collapse, backfill andcompaction Item
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 4EARTHING
- 8 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 5
HIGHMAST LIGHTING
Contractor to supply Certificate of Compliance for all electricalwork performed.
Concrete and structural steel measured under relevantsections.
Refer to drawing 0.54/4658 sheet 1-3 rev 0.
ELECTRICAL INSTALLATION (24M) LIGHT MAST
Contractor to supply and hot dipped galvanised 24m lightmast.
2/5/1 Complete electrical installation as per drawing No's26.41/40035 sheets 1 to 3 inclusive of all cabling, circuitbreakers, switches, connections equipment, cables and lightfittings complete to one no 24m flood light mast. No 5
LUMINAIRES AND LAMPS
Contractor to supply and install luminair and lamps fromGenlux Lighting.
2/5/2 400W Clear tubular high pressure Sodium luminaire. No 60
2/5/3 600W Clear tubular high pressure Sodium luminaire. No 60
CABLES
DIisconnecting,removal, Installation & Teminations for allcables required for floodmast .The rate price forterminating must include for all activities and items asspecified in cabling and earthing specification (i.e. earthingof spare cores).
2/5/4 BVX 4 KCV m 2 400
REFURBISH EXISTING YARD LIGHT MAST
Carried Forward R Section No. 2SECTION 2 : ARNOT SSBill No. 5ELECTRICAL WORK
- 9 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
This consist of the Mast distribution board, top of the mastjunction box and all cables.Clean, treat and paint wherenecessary.(Refer to drawing no 0.54/4658 note 4).
2/5/5 18 meter mastNo 5
2/5/6 24 meter mast No 8
Removal
2/5/7 18 meter mast No 1
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 5ELECTRICAL WORK
- 1 0 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
ItemSABS Unit Quantity Rate AmountNoPay Ref
BILL No. 6
SANS 1200LC CABLE DUCTS
8.2.5 Sundries
2/6/18.2.5 Junction Boxes. All details to be as for thejunction box detail on Drawing 0.54/4713Sheet 1 revision 5,Sheet revision 2, 3 of 3revision 1 and 4 of 4 revision 1.(Provisional) No 1
2/6/28.2.5 New equipped distribution board as detailedin engineering specification 240-63471535. No 1
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 6CABLE DUCTS
- 1 1 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 7
STRUCTURAL STEELWORK (SMALL WORKS)
Notes to Tenderers:
The tenderer is to allow in the pricing of structuralsteelwork for all steelwork to be erected plumb and toinclude for all necessary steel packing pieces to achievesame.
Preparation of acceptable shop detail drawings:(Refer todrawing no 054/4658)
2/7/1 Prepare and submit to the Engineer acceptable shop detaildrawings and supporting calculations in terms of the projectspecifications.
SUM
Supply and Fabrication of steelwork:
Steelwork to be Hot Dipped Galvanised Grade 300W as perthe standard specifications, complete with all necessarycleats, brackets, gussets, packs, shop fasteners,baseplates and the like, including cleaning of steelwork,shop primming and loading ready for dispatch to site.
2/7/2 Tubular Structural Steelwork for Lightmast t 8.910
Delivery:
2/7/3 Delivery of normal loads of steelwork to site. t 8.910
Offloading and erection of steel on site.
2/7/4 Structural Steelwork. t 8.910
H.D. BOLTS AND MISCELLANEOUS METALWORK.
2/7/5 Grade 4.8 No 470
Carried Forward to Summary of Section No. 2 R Section No. 2SECTION 2 : ARNOT SSBill No. 7STRUCTURAL STEELWORK
- 1 2 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Section No. 2
SECTION 2 : ARNOT SS
SECTION SUMMARY - SECTION 2 : ARNOT SS
Bill Page AmountNo No
1 -4-SITE CLEARANCE
2 -5-EARTHWORKS
3 -7-CONCRETE,FORMWORK AND REINFORCEMENT
4 -8-EARTHING
5 -10-ELECTRICAL WORK
6 -11-CABLE DUCTS
7 -12-STRUCTURAL STEELWORK
Carried to Final Summary R Section No. 2SECTION 2 : ARNOT SS
- 1 3 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 1
YARDSTONE
NOTE: Removing and replacing of yard stone is measured1m beyond outside border of new structures and will bepaid accordingly
3/1/1 Take up yardstone layer 100mm thick and stockpile for reuse. m2 1 500
3/1/2 Take from stockpile and re-place yardstone layer 100mm thickupon completion of the works, lightly compacted to set levels m2 1 500
Pitching of Surfaces (Provisional)
3/1/3 New yard stones to terrace. m2 1 500
Rubble disposal. (Provisional)
3/1/4 Transport all rubble from demolitions and the works to a nearbyRegistered Dump Site. Item
BARRICADE FENCING
Barricade fencing to be re-sed to cover the rest of thescope (Provisional)
3/1/5 Make provision for supply and install barricading fence 1.8mhigh around the working area, compliant to Eskom Safetyrequirements. m 200
3/1/6 Make provision for the necessary barricade fencing (shark net)to fence off the approved working area and hand over toSub-station EA after finalising of contract. m 200
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 1SITE CLEARANCE
- 1 4 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 2
EARTHWORKS (PROVISIONAL)
Excavation
3/2/1 Excavate in all materials and use for backfill or dispose off asordered. m3 284
Extra over for:
3/2/2 Intermediate excavation m3 28
3/2/3 Hard rock. m3 14
Importation of Materials from Commercial Sources.(Provisional)
3/2/4 G5 Material from commercial sources in accordance with SABS1200 DM compacted to 95% Mod AASHTO density to beapproved by the Engineer. m3 105
Soil Poisoning
3/2/5 Approved weedkiller applied in strict accordance to themanufacturer's instructions. m2 151
Pitching of Surfaces (Provisional)
3/2/6 New yard stones to terrace. m3 200
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 2EARTHWORKS
- 1 5 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 3
CONCRETE (SMALL WORKS)
FORMWORK
Smooth
3/3/1 To sides of bases and stub columns m2 48
Boxing in special formwork to form
3/3/2 Form 20 x 20mm chamfer along top edge of exposed stubcolumn or base. m 32
REINFORCEMENT
Steel Bars
Mild steel reinforcement bars
3/3/3 8mm t 0.10
3/3/4 12mmt 3.16
3/3/5 25mm t 0.86
CONCRETE
Blinding layer in 15MPa/19mm concrete
3/3/6 Blinding layer 50mm minimum thickness. m2 151
Strength concrete, 25MPa/19mm
3/3/7 Bases and Stub Columns m3 120
Unformed Surface Finishes
3/3/8 Wood floated finish. m2 7
HOLDING DOWN BOLTS
Carried Forward R Section No. 3SECTION 3: DUVHA SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 1 6 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
All HD bolts to be hot dipped galvanised bolts
Holding down bolts and miscellaneous metalwork (supplied andfixed by the Contractor)
3/3/9 HD bolts including nut and washer cast in position in concrete. kg 97.2
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 1 7 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 4
EARTHMAT (PROVISIONAL)
Earthing
Supply, deliver and lay copper earthmat equipmentearthing, earth straps, including excavation complete withrisks of collapse, bedding, backfill, compaction and testingat depth up to (See earthmat specification). All flat copperto be 50 x 3mm in accordance with BS 1432, picled andannealed black copper ().701 kg/m:
ELECTRICAL ( Provisional)
3/4/1 Clamp connection 50 x 3mm flat to 2 no. x 10mm diameterrods No 100
3/4/2 Crimp joints 10mm round to round (Refer sheets C5 to C8) No 99
3/4/3 1 x 10mm Diameter copper at 1,0m deep. m 99
ELECTRICAL
3/4/4 Excavate, search for and locate existing earthmat, includingexcavations complete with risk of collapse, backfill andcompaction Item
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 4EARTHING
- 1 8 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 5
HIGHMAST LIGHTING
Contractor to supply Certificate of Compliance for all electricalwork performed.
Concrete and structural steel measured under relevantsections.
Refer to drawing 0.54/4658 sheet 1-3 rev 0.
ELECTRICAL INSTALLATION (24M) LIGHT MAST
Contractor to supply and hot dipped galvanised 24m lightmast.
3/5/1 Complete electrical installation as per drawing No's 0.08/18596sheets 1 to 3 inclusive of all cabling, circuit breakers, switches,connections equipment, cables and light fittings complete toone no 24m flood light mast. No 9
LUMINAIRES AND LAMPS
Contractor to supply and install luminair and lamps fromGenlux Lighting.
3/5/2 400W Clear tubular high pressure Sodium luminaire. No 78
CABLES
DIisconnecting,removal, Installation & Teminations for allcables required for floodmast.The rate price forterminating must include for all activities and items asspecified in cabling and earthing specification (i.e. earthingof spare cores).
3/5/3 BVX 4 HCV m 1 700
REFURBISH EXISTING YARD LIGHT MAST
Carried Forward R Section No. 3SECTION 3: DUVHA SSBill No. 5ELECTRICAL WORK
- 1 9 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
This consist of the Mast distribution board, top of the mastjunction box and all cables.Clean, treat and paint wherenecessary.(Refer to drawing no 0.54/4658 note 4).
3/5/4 24 meter mast No 5
Removal
3/5/5 14 meter mast No 1
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 5ELECTRICAL WORK
- 2 0 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
ItemSABS Unit Quantity Rate AmountNoPay Ref
BILL No. 6
SANS 1200LC CABLE DUCTS
8.2.5 Sundries
3/6/18.2.5 Junction Boxes. All details to be as for thejunction box detail on Drawing 0.54/4713Sheet 1 revision 5,Sheet revision 2, 3 of 3revision 1 and 4 of 4 revision 1. No 1
3/6/28.2.5 New equipped distribution board. No 1
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 6CABLE DUCTS
- 2 1 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 7
STRUCTURAL STEELWORK (SMALL WORKS)
Notes to Tenderers:
The tenderer is to allow in the pricing of structuralsteelwork for all steelwork to be erected plumb and toinclude for all necessary steel packing pieces to achievesame.
Preparation of acceptable shop detail drawings:(Refer todrawing no 054/4658)
3/7/1 Prepare and submit to the Engineer acceptable shop detaildrawings and supporting calculations in terms of the projectspecifications.
SUM
Supply and Fabrication of steelwork:
Steelwork to be Hot Dipped Galvanised Grade 300W as perthe standard specifications, complete with all necessarycleats, brackets, gussets, packs, shop fasteners,baseplates and the like, including cleaning of steelwork,shop primming and loading ready for dispatch to site.
3/7/2 Tubular Structural Steelwork for Lightmast t 16.038
Delivery:
3/7/3 Delivery of normal loads of steelwork to site. t 16.038
Offloading and erection of steel on site.
3/7/4 Structural Steelwork. t 16.038
H.D. BOLTS AND MISCELLANEOUSMETALWORK(provisional)
3/7/5 Grade 4.8 No 846
Carried Forward to Summary of Section No. 3 R Section No. 3SECTION 3: DUVHA SSBill No. 7STRUCTURAL STEELWORK
- 2 2 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Section No. 3
SECTION 3: DUVHA SS
SECTION SUMMARY - SECTION 3: DUVHA SS
Bill Page AmountNo No
1 -14-SITE CLEARANCE
2 -15-EARTHWORKS
3 -17-CONCRETE,FORMWORK AND REINFORCEMENT
4 -18-EARTHING
5 -20-ELECTRICAL WORK
6 -21-CABLE DUCTS
7 -22-STRUCTURAL STEELWORK
Carried to Final Summary R Section No. 3SECTION 3: DUVHA SS
- 2 3 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 1
YARDSTONE
NOTE: Removing and replacing of yard stone is measured1m beyond outside border of new structures and will bepaid accordingly
4/1/1 Take up yardstone layer 100mm thick and stockpile for reuse. m2 100
4/1/2 Take from stockpile and re-place yardstone layer 100mm thickupon completion of the works, lightly compacted to set levels m2 100
Pitching of Surfaces (Provisional)
4/1/3 New yard stones to terrace. m2 100
Rubble disposal. (Provisional)
4/1/4 Transport all rubble from demolitions and the works to a nearbyRegistered Dump Site. Item
BARRICADE FENCING
Barricade fencing to be re-sed to cover the rest of thescope (Provisional)
4/1/5 Make provision for supply and install barricading fence 1.8mhigh around the working area, compliant to Eskom Safetyrequirements. m 150
4/1/6 Make provision for the necessary barricade fencing (shark net)to fence off the approved working area and hand over toSub-station EA after finalising of contract. m 150
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 1SITE CLEARANCE
- 2 4 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 2
EARTHWORKS (PROVISIONAL)
Excavation
4/2/1 Excavate in all materials and use for backfill or dispose off asordered. m3 41
Extra over for:
4/2/2 Intermediate excavation m3 3
4/2/3 Hard rock. m3 3
Importation of Materials from Commercial Sources.(Provisional)
4/2/4 G5 Material from commercial sources in accordance with SABS1200 DM compacted to 95% Mod AASHTO density to beapproved by the Engineer. m3 20
Soil Poisoning
4/2/5 Approved weedkiller applied in strict accordance to themanufacturer's instructions. m2 35
Pitching of Surfaces (Provisional)
4/2/6 New yard stones to terrace. m3 100
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 2EARTHWORKS
- 2 5 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 3
CONCRETE (SMALL WORKS)
FORMWORK
Smooth
4/3/1 To sides of bases and stub columns m2 5
Boxing in special formwork to form
4/3/2 Form 20 x 20mm chamfer along top edge of exposed stubcolumn or base. m 2
REINFORCEMENT
Steel Bars
Mild steel reinforcement bars
4/3/3 8mm t 0.01
4/3/4 12mmt 0.35
4/3/5 25mm t 0.10
CONCRETE
Blinding layer in 15MPa/19mm concrete
4/3/6 Blinding layer 50mm minimum thickness. m2 17
Strength concrete, 25MPa/19mm
4/3/7 Bases and Stub Columns m3 9
Unformed Surface Finishes
4/3/8 Wood floated finish. m2 2
HOLDING DOWN BOLTS
Carried Forward R Section No. 4SECTION 4: HENDRINA SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 2 6 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
All HD bolts to be hot dipped galvanised bolts
Holding down bolts and miscellaneous metalwork (supplied andfixed by the Contractor)
4/3/9 HD bolts including nut and washer cast in position in concrete. kg 10.2
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 2 7 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 4
EARTHMAT (PROVISIONAL)
Earthing
Supply, deliver and lay copper earthmat equipmentearthing, earth straps, including excavation complete withrisks of collapse, bedding, backfill, compaction and testingat depth up to (See earthmat specification). All flat copperto be 50 x 3mm in accordance with BS 1432, picled andannealed black copper ().701 kg/m:
ELECTRICAL ( Provisional)
4/4/1 Clamp connection 50 x 3mm flat to 2 no. x 10mm diameterrods No 100
4/4/2 Crimp joints 10mm round to round (Refer sheets C5 to C8) No 99
4/4/3 1 x 10mm Diameter copper at 1,0m deep. m 99
ELECTRICAL
4/4/4 Excavate, search for and locate existing earthmat, includingexcavations complete with risk of collapse, backfill andcompaction Item
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 4EARTHING
- 2 8 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 5
HIGHMAST LIGHTING
Contractor to supply Certificate of Compliance for all electricalwork performed.
Concrete and structural steel measured under relevantsections.
Refer to drawing 0.54/4658 sheet 1-3 rev 0.
ELECTRICAL INSTALLATION (24M) LIGHT MAST
Contractor to supply and hot dipped galvanised 24m lightmast.
4/5/1 Complete electrical installation as per drawing No's 0.15/8318sheets 1 to 3 inclusive of all cabling, circuit breakers, switches,connections equipment, cables and light fittings complete toone no 24m flood light mast. No 1
LUMINAIRES AND LAMPS
Contractor to supply and install luminair and lamps fromGenlux Lighting.
4/5/2 600W Clear tubular high pressure Sodium luminaire. No 82
CABLES
DIisconnecting,removal, Installation & Teminations for allcables required for floodmast.The rate price forterminating must include for all activities and items asspecified in cabling and earthing specification (i.e. earthingof spare cores).(Provisional)
4/5/3 BVX 4 HCV m 60
4/5/4 BVX 4 LCV m 1 300
REFURBISH EXISTING YARD LIGHT MAST
Carried Forward R Section No. 4SECTION 4: HENDRINA SSBill No. 5ELECTRICAL WORK
- 2 9 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
This consist of the Mast distribution board, top of the mastjunction box and all cables.Clean, treat and paint wherenecessary.(Refer to drawing no 0.54/4658 note 4).
4/5/5 14 meter mast No 2
4/5/6 24 meter mast No 12
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 5ELECTRICAL WORK
- 3 0 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
ItemSABS Unit Quantity Rate AmountNoPay Ref
BILL No. 6
SANS 1200LC CABLE DUCTS
8.2.5 Sundries
4/6/18.2.5 Junction Boxes. All details to be as for thejunction box detail on Drawing 0.54/4713Sheet 1 revision 5,Sheet revision 2, 3 of 3revision 1 and 4 of 4 revision 1. No 1
4/6/28.2.5 New equipped distribution board. No 1
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 6CABLE DUCTS
- 3 1 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 7
STRUCTURAL STEELWORK (SMALL WORKS)
Notes to Tenderers:
The tenderer is to allow in the pricing of structuralsteelwork for all steelwork to be erected plumb and toinclude for all necessary steel packing pieces to achievesame.
Preparation of acceptable shop detail drawings:(Refer todrawing no 054/4658)
4/7/1 Prepare and submit to the Engineer acceptable shop detaildrawings and supporting calculations in terms of the projectspecifications.
SUM
Supply and Fabrication of steelwork:
Steelwork to be Hot Dipped Galvanised Grade 300W as perthe standard specifications, complete with all necessarycleats, brackets, gussets, packs, shop fasteners,baseplates and the like, including cleaning of steelwork,shop primming and loading ready for dispatch to site.
4/7/2 Tubular Structural Steelwork for Lightmast t 1.782
Delivery:
4/7/3 Delivery of normal loads of steelwork to site. t 1.782
Offloading and erection of steel on site.
4/7/4 Structural Steelwork. t 1.782
H.D. BOLTS AND MISCELLANEOUS METALWORK.
4/7/5 Grade 4.8 No 94
Carried Forward to Summary of Section No. 4 R Section No. 4SECTION 4: HENDRINA SSBill No. 7STRUCTURAL STEELWORK
- 3 2 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Section No. 4
SECTION 4: HENDRINA SS
SECTION SUMMARY - SECTION 4: HENDRINA SS
Bill Page AmountNo No
1 -24-SITE CLEARANCE
2 -25-EARTHWORKS
3 -27-CONCRETE,FORMWORK AND REINFORCEMENT
4 -28-EARTHING
5 -30-ELECTRICAL WORK
6 -31-CABLE DUCTS
7 -32-STRUCTURAL STEELWORK
Carried to Final Summary R Section No. 4SECTION 4: HENDRINA SS
- 3 3 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 1
YARDSTONE
NOTE: Removing and replacing of yard stone is measured1m beyond outside border of new structures and will bepaid accordingly
5/1/1 Take up yardstone layer 100mm thick and stockpile for reuse. m2 900
5/1/2 Take from stockpile and re-place yardstone layer 100mm thickupon completion of the works, lightly compacted to set levels m2 900
Pitching of Surfaces (Provisional)
5/1/3 New yard stones to terrace. m2 900
Rubble disposal. (Provisional)
5/1/4 Transport all rubble from demolitions and the works to a nearbyRegistered Dump Site. Item
BARRICADE FENCING
Barricade fencing to be re-sed to cover the rest of thescope (Provisional)
5/1/5 Make provision for supply and install barricading fence 1.8mhigh around the working area, compliant to Eskom Safetyrequirements. m 100
5/1/6 Make provision for the necessary barricade fencing (shark net)to fence off the approved working area and hand over toSub-station EA after finalising of contract. m 95
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 1SITE CLEARANCE
- 3 4 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 2
EARTHWORKS (PROVISIONAL)
Excavation
5/2/1 Excavate in all materials and use for backfill or dispose off asordered. m3 284
Extra over for:
5/2/2 Intermediate excavation m3 28
5/2/3 Hard rock. m3 14
Importation of Materials from Commercial Sources.(Provisional)
5/2/4 G5 Material from commercial sources in accordance with SABS1200 DM compacted to 95% Mod AASHTO density to beapproved by the Engineer. m3 105
Soil Poisoning
5/2/5 Approved weedkiller applied in strict accordance to themanufacturer's instructions. m2 151
Pitching of Surfaces (Provisional)
5/2/6 New yard stones to terrace. m3 100
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 2EARTHWORKS
- 3 5 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 3
CONCRETE (SMALL WORKS)
FORMWORK
Smooth
5/3/1 To sides of bases and stub columns m2 48
Boxing in special formwork to form
5/3/2 Form 20 x 20mm chamfer along top edge of exposed stubcolumn or base. m 324
REINFORCEMENT
Steel Bars
Mild steel reinforcement bars
5/3/3 8mm t 0.10
5/3/4 12mmt 3.16
5/3/5 25mm t 0.86
CONCRETE
Blinding layer in 15MPa/19mm concrete
5/3/6 Blinding layer 50mm minimum thickness. m2 151
Strength concrete, 25MPa/19mm
5/3/7 Bases and Stub Columns m3 120
Unformed Surface Finishes
5/3/8 Wood floated finish. m2 7
HOLDING DOWN BOLTS
Carried Forward R Section No. 5SECTION 5: ROCKDALE SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 3 6 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Brought Forward R
All HD bolts to be hot dipped galvanised bolts
Holding down bolts and miscellaneous metalwork (supplied andfixed by the Contractor)
5/3/9 HD bolts including nut and washer cast in position in concrete. kg 91.8
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 3CONCRETE,FORMWORK AND REINFORCEMENT
- 3 7 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 4
EARTHMAT (PROVISIONAL)
Earthing
Supply, deliver and lay copper earthmat equipmentearthing, earth straps, including excavation complete withrisks of collapse, bedding, backfill, compaction and testingat depth up to (See earthmat specification). All flat copperto be 50 x 3mm in accordance with BS 1432, picled andannealed black copper ().701 kg/m:
ELECTRICAL ( Provisional)
5/4/1 Clamp connection 50 x 3mm flat to 2 no. x 10mm diameterrods No 100
5/4/2 Crimp joints 10mm round to round (Refer sheets C5 to C8) No 99
5/4/3 1 x 10mm Diameter copper at 1,0m deep. m 99
ELECTRICAL
5/4/4 Excavate, search for and locate existing earthmat, includingexcavations complete with risk of collapse, backfill andcompaction Item
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 4EARTHING
- 3 8 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 5
HIGHMAST LIGHTING
Contractor to supply Certificate of Compliance for all electricalwork performed.
Concrete and structural steel measured under relevantsections.
Refer to drawing 0.54/4658 sheet 1-3 rev 0.
ELECTRICAL INSTALLATION (24M) LIGHT MAST
Contractor to supply and hot dipped galvanised 24m lightmast.
5/5/1 Complete electrical installation as per drawing No's 0.08/20503sheets 1 to 3 inclusive of all cabling, circuit breakers, switches,connections equipment, cables and light fittings complete toone no 24m flood light mast. No 9
LUMINAIRES AND LAMPS
Contractor to supply and install luminair and lamps fromGenlux Lighting.
5/5/2 400W Clear tubular high pressure Sodium luminaire. No 63
CABLES
DIisconnecting,removal, Installation & Teminations for allcables required for floodmast.The rate price forterminating must include for all activities and items asspecified in cabling and earthing specification (i.e. earthingof spare cores).
5/5/3 BVX 4 HCV m 20
5/5/4 BVX 4 LCV m 1 000
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 5ELECTRICAL WORK
- 3 9 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
ItemSABS Unit Quantity Rate AmountNoPay Ref
BILL No. 6
SANS 1200LC CABLE DUCTS
8.2.5 Sundries
5/6/18.2.5 Junction Boxes. All details to be as for thejunction box detail on Drawing 0.54/4713Sheet 1 revision 5,Sheet revision 2, 3 of 3revision 1 and 4 of 4 revision 1. No 1
5/6/28.2.5 New equipped distribution board. No 1
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 6CABLE DUCTS
- 4 0 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Item Quantity Rate AmountNo
BILL No. 7
STRUCTURAL STEELWORK (SMALL WORKS)
Notes to Tenderers:
The tenderer is to allow in the pricing of structuralsteelwork for all steelwork to be erected plumb and toinclude for all necessary steel packing pieces to achievesame.
Preparation of acceptable shop detail drawings:(Refer todrawing no 054/4658)
5/7/1 Prepare and submit to the Engineer acceptable shop detaildrawings and supporting calculations in terms of the projectspecifications.
SUM
Supply and Fabrication of steelwork:
Steelwork to be Hot Dipped Galvanised Grade 300W as perthe standard specifications, complete with all necessarycleats, brackets, gussets, packs, shop fasteners,baseplates and the like, including cleaning of steelwork,shop primming and loading ready for dispatch to site.
5/7/2 Tubular Structural Steelwork for Lightmast t 16.038
Delivery:
5/7/3 Delivery of normal loads of steelwork to site. t 16.038
Offloading and erection of steel on site.
5/7/4 Structural Steelwork. t 16.038
H.D. BOLTS AND MISCELLANEOUS METALWORK.
5/7/5 Grade 4.8 No 846
Carried Forward to Summary of Section No. 5 R Section No. 5SECTION 5: ROCKDALE SSBill No. 7STRUCTURAL STEELWORK
- 4 1 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
Section No. 5
SECTION 5: ROCKDALE SS
SECTION SUMMARY - SECTION 5: ROCKDALE SS
Bill Page AmountNo No
1 -34-SITE CLEARANCE
2 -35-EARTHWORKS
3 -37-CONCRETE,FORMWORK AND REINFORCEMENT
4 -38-EARTHING
5 -39-ELECTRICAL WORK
6 -40-CABLE DUCTS
7 -41-STRUCTURAL STEELWORK
Carried to Final Summary R Section No. 5SECTION 5: ROCKDALE SS
- 4 2 -
2017/07/12 09:32:54 AM
NE GRID VARIOUS SS YARD LIGHTING UPGRADEMIDDLEBURG CLN
FINAL SUMMARY
Section Page AmountNo No
1 -3-SECTION 1: PRELIMINARIES AND GENERALS
2 -13-SECTION 2 : ARNOT SS
3 -23-SECTION 3: DUVHA SS
4 -33-SECTION 4: HENDRINA SS
5 -42-SECTION 5: ROCKDALE SS
Carried to Form of Tender R