The Challenge
Bilfinger Salamis UK were asked to come up with a solution for replacing compromised bulkhead penetrations. The bulkhead penetrations needed to be wind and water tight, as well as satisfying HSEQ minimum standards for fire rated bulkheads. Operations could not provide forecasts for future use, so the bulkhead had to be able to cope with various sizes of cables and pipes.
The Solution
It was agreed with the client that Bilfinger Salamis should proceed with the manufacture, supply and installation of a set of bespoke bulkhead penetration assemblies.
The bespoke items comprised of the following:
• Agalvanisedplatetoretainfireinsulationatthecompromisedbulkhead.
• Abulkheadmountingframeweldedtoaroundtransitframe.
• Aroundexpansionframewithasquarepackingspace.
• Modularversatilepackersforfuturepenetrationrequirements.
Designedforeaseofinstallation,theonlyinvasiveactivityrequiredoffshorewastodrillfourboltholesfordirectmountingtothedamagedbulkheads.Anapprovedfireseal gasket was used to provide fireproof integrity between the transit frame and bulkhead.
Future proofing was achieved by using modular components with removable inner layers, designed for a flawless adaptation to various cable or pipe sizes.
01
BILFINGER SALAMIS UK
––––––
BULKHEADPENETRATIONS––––––
BESPOKE DESIGN AND INSTALLATION OF INTERCHANGEABLE COMPONENTS
Minor ModificationsSpecialist Services
ClientChevron
LocationCaptain FPSO, North Sea
01 - Bilfinger Salamis UK designed and fitted a bespoke solution for bulkhead penetrations which is water and wind resistant
The bespoke design
Bilfinger Salamis UK
4 Greenhole Place · Bridge of Don Aberdeen · Scotland · AB23 8EU Phone +44 1224246000 [email protected] www.salamis.bilfinger.com
Bulkhead Penetrations
05 -Typical internal arrangement of penetrations through bulkhead fire insulation. (Inset - the removable inner layers of the modular components allow for various cable and pipe sizes.)
02 - The previous engine room bulkhead penetration.03 - Bespoke future-proof solution installed for various cable combinations.
The Outcome
BilfingerSalamiswereabletosatisfytheclientsrequirements,byprovidinganinnovative, neat, and HSEQ compliant solution for bulkhead penetrations, which can be adapted for future use.