  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.

    1/6

    OPEXCOM MEMORANDUM

    1.0 INTRODUCTION :Maintenance attempt to execute the job of replacement of perforated 3 service air

    line as requested by Production Lubes in the first instance was unsuccessful because,

    available pipes issued from the Ware House were rejected by ETSD (I& T) on report

    number 2445 of November 24, 2010. Action was then initiated through MRF to

    enable MMD replace the 14 lengths of pipes needed to execute this job. Necessary

    fittings were sourced as a prelude for execution of this job.

    When it became obvious that available in-house welders were engaged in

    identical/emergency jobs plant-wide, KRPC Management was entreated to approve

    invitation to competent service providers in this job area to bid for its execution.

    The request was granted by management and the bids returned are herein analyzed.

    2.0 PROCEDURE/ SCOPE OF WORK:The scope of work includes but is not limited to the following:

    Cut and remove perforated pipes

    Prefabricate new pipes.

    Install prefabricated piping

    Complete welding of new pipes.

    Provision of welding machine.

    Provision of crane (KRPC to provide).

    Provision of grinding machines (big and small)

    Provision of scaffolds (KRPC to provide).

    Provision of cutting discs (180 X 3 X 22.23 mm)-20 pcs

    Provision of cutting discs (115 X 3 X 22.23 mm)-25 pcs

    Provision of grinding discs (180 X 3 X 22.23 mm)-25 pcs)

    Provision of grinding discs (115 X 3 X 22.23 mm) -25 pcs

    Provision of welding electrodes (LB52-E7018-3.2 mm)-10pkts

    Provision of welding electrodes (LB52-E7018.2.6 mm)-10pkts

    Provision of oxyacetylene gas set (KRPC to provide)

    Provision of pick-up towing van/staff transportation.

    Provision of 3 (14 lengths) STD pipes (KRPC to provide).

    Provision of 3 x 90deg Elbows STD 4pcs (KRPC to provide)

    Provision of 3 x 150# flanges 3sets (KRPC to provide)

    Provision of 3 equal Tee 1pc (KRPC to provide)

    Provision of 1 boss (KRPC to provide)

    Provision of 1 boss (KRPC to provide)

    3 end flange 1 (KRPC to provide)

    Provision of Labour.

    Mobilization/Demobilization.

    Housekeeping.

    Testing and commissioning of lines.

  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.

    2/6

    3.0 IN-HOUSE COST ESTIMATE:

    The in-house cost estimate, which is exclusive of costs of radiography, and

    hydrostatic pressure test is N933,350.00 was derived from NNPC standard rate on

    labour and equipment hiring (see detailed attachment1). The radiography andhydrostatic tests are statutory functions of ETSD which are to be performed after

    job execution.

    4.0 BIDS BENCH-MARKING:

    Find in the table below the BIDS returned by the approved short-listed servicecompanies in ascending order with the in-house estimate ofN933,350.00 also

    indicated.

    S/N NAME OF

    BIDDERS

    COMPLIANCE

    WITH

    W/SCOPE

    QUOTATION

    (N)

    MOBILIZATION

    PERIOD

    COMPLETION

    PERIOD

    VALIDITY

    QUOTATION

    1. PARSOULVENTURES.

    - 344,100.00 1 DAY 5 DAYS 30 DAYS

    2. IKEDIOBIIRON &

    STEEL

    OKAY 678,900.00 1DAY - -

    3. SAUKOENGRG

    - 709,020.00 - - -

    4. OKORO

    METAL

    OKAY. 817,000.00 - 5 DAYS 60 DAYS

    5. LAFO

    ENGG

    OKAY 1,272,700.00 - 10 DAYS 60 DAYS

    6. IN-HOUSE

    ESTIMATE

    N/A 933,350.00 N/A 5DAYS N/A

    5.0 BIDS ANALYSIS

    The sum ofN344,100.00 returned by Messrs PARSOUL VENTURES was the lowest price

    quoted for this job. The sum ofN678,900.00 was returned by Messrs IKEDIOBI IRON

    AND STEEL VENTURES as second lowest, while the third lowest quotation of

    N709,020.00 was submitted by Messrs SAUKO ENGINEERING AND CONSTRUCTION

    LTD. The highest quotation ofN1,272,700.00 was returned by Messrs LAFOENGINEERING LTD. The in-house estimate ofN933,350.00 was derived from NNPCstandard rate on labour and equipment.

    Analysis of the bids shows that Messrs PARSOUL VENTURES who returned the lowest

    cost estimate ofN344,100.00 for this job were thelowest bidders.All the companies are adjudged equally competent.

  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.

    3/6

    6.0 NOTATION:

    Management is invited to kindly note;

    That in- house Maintenance teams were engaged in identical start-up jobs in

    other locations of KRPC at the time. Only coded Welders and coded Fitters who pass KRPC statutory test shall be

    allowed to work.

    That the IN-HOUSE cost estimate of N933,350.00 was derived from NNPCCorporate Labour and Equipment hiring rate.

    That the N344,100.00 submitted by Messrs PARSOUL VENTURES as cost

    of executing this job not convincing, considering the quotations submitted byother companies on the one hand and the in-house estimate on the other.

    That PARSOUL VENTURES should be requested to re-confirm their

    quotation in writing prior to final contract award.

    7.0 PRAYER:

    OPEXCOM is prayed to consider and approve award of contract for the replacement of

    perforated 3 service air line in LUBES Area 5 in favour of MessrsPARSOUL

    VENTURES at their quoted price of N344,100.00 subject to a written re-confirmation

    letter from the Service Company to that effect.

    MAINTENANCE MANAGEMENT

  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.

    4/6

    KADUNA REFINING AND PETROCHEMICAL COMPANYLIMITED

    (A Subsidiary of Nigerian National PetroleumCorporation)

    INTERNAL MEMORANDUM

    KRPC THE PRIDE OF THE NATION

    TO: CHAIRMAN PC REF: KRPC/MTCE/MM/019

    FROM: MANAGER MAINTENANCE DATE: SEPTEMBER 25, 2011.

    RE- replacement of perforated 3 service air line in LUBES Area 5.

    Please, find attached OPEXCOM MEMORANDUM on award of contract

    for replacement of perforated 3 service air line in LUBES Area 5for your

    review and endorsement to OPEXCOM.

    Award is recommended in favour of MessrsPARSOUL VENTURES at

    their quoted price ofN344,100.00 subject to a written re-confirmation letter

    from the Service Company to that effect.

    ENGR S. A. GARBA.

  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.

    5/6

    OPEXCOM MEMORANDUM

    FORREPLACEMENT OFPERFORATED 3 SERVICE

    AIR LINE IN LUBES AREA 5.

    SEPTEMBER, 2011

  • 8/2/2019 Bids Analysis for Replacement of Perforated Service Air Pipe Line in Area 5 - Update.