bibiyana 03 addendum 03 with attachment

Upload: ammar-lateef-gakhar

Post on 03-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    1/28

    Addendum No. 03Memo No. 3022 -BPDB (Sectt)/Dev- 187/2007 date : 15 - 11 - 11

    Clarification/ amendment of the Tender document for Construction of Bibiyana300 -450 MWGas BasedCombined Cycle Power Plant

    Clarification/ amendment of theTender document for Construction of Bibiyana300 - 450 MWGas Based

    Combined Cycle Power Plant Project [Tender invitation no. 2100 -BPDB (Sectt)/Dev- 187/2007 date : 14-07-11; Addendum no. 1 ref: 2302-BPDB (Sectt)/Dev- 187/2007 date 08-08-11; Addendum no. 02 ref: 2800-

    BPDB (Sectt)/Dev- 187/2007 date 10-10-11] is hereby issued as mentioned below:

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    1. Eligibility ofTenderers/Experience

    of Project

    Implementation

    2, 12 Tendernotice sl. no.

    10;

    Clause 5.1of ITT, Vol.

    1;

    Addendum

    no. 02, sl.

    no. 9

    The Tenderer shall have the

    experience of supply,erection, installation, testing

    and commissioning on

    Turnkey basis of minimum2(two) Power Plant having

    each minimum 250 MWcapacity during last 15

    (fifteen) years. One of these

    projects have to be outside

    the tenderers country andone of these projects have to

    be combined cycle plant. In

    support of his experiences,

    the Tenderer shall submitwith his Tender for all work

    performed by him, detailedevidence that he himself and

    / or Lead partner of JVCAhave carried out the design,

    manufacture, supply,

    construction, erection,

    testing, commissioning and

    put into commercialoperation of power planthaving minimum capacity of

    250 MW. It is to be notedthat Subcontractors'

    The Tenderer shall have the

    experience of supply, erection,installation, testing and

    commissioning on Turnkey basis of

    minimum 2(two) Power Plant havingeach minimum 250 MW capacity (For

    Combined cycle plant, single blockcapacity having configuration 1:1:1 or

    2:2:1. For Non combined cycle plant,

    total capacity of maximum 02 no. of

    units) during last 15 (fifteen) years.One of these projects have to be

    outside the tenderers country and one

    of these projects have to be combined

    cycle plant. In support of hisexperiences, the Tenderer shall

    submit with his Tender for all workperformed by him, detailed evidence

    that he himself and / or Lead partnerof JVCA have carried out the design,

    manufacture, supply, construction,

    erection, testing, commissioning and

    put into commercial operation of

    power plant having minimumcapacity of 250 MW. It is to be notedthat if the tenderer himself/ lead

    partner of JVCA were not anindividual contractor or JVCA lead

    evsjv`k we`yr Dbqb evWBANGLADESH POWER DEVELOPMENT BOARD

    Office t

    Central Secretariate,BPDB, Dhaka.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    2/28

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    The Tenderer shall include at leasttwo (02) certificates from the end

    users on two (2) years satisfactoryperformance of the plants having

    minimum 250 MW capacity PowerPlants [One of these projects have to

    be outside the tenderers country andone of these projects have to be

    combined cycle plant] which weredesigned, supplied, constructed, tested

    & commissioned by the Tenderer to

    establish the Tenderer's minimumrequired experience to Tender. The

    certificates shall mention the name of

    power plant, number, capacity and

    commissioning date of the power

    plant (make, model) supplied by theTenderer; issue date, name and

    address (Telephone/Fax/e-mail) of theend user duly signed in the official

    pad. Without such certificates orwhere the certificates are un-

    satisfactory to BPDB, the Tender shall

    be considered technically non-responsive.

    These certificates must be notarizedand have authentication from the

    Chamber of Commerce of theTenderer's country or the

    Embassy/High commission of the endusers country situated in Dhaka. In

    absence of that, authentication isrequired from the Embassy/High

    Commission of tenderers country inDhaka.

    The Contractor shall arrange site visit

    of 03 (three) personnel of the

    Employer to the Premises of thePower Plants as mentioned in

    Experience Certificates. All living,

    accommodation, food, transport

    expenses of the personnel during the

    period of visit including air-fares,incidental expenses, medical

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    3/28

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    3. FinancialQualification

    13 Clause 5.2of ITT,

    Vol. 1

    --- The following is added in Clause 5.2of ITT, Vol. 1:

    The tenderer must have theexperience of completion of a Power

    plant Project through ECA/ Bankfinancing of minimum 150 million

    USD during last 15 years. Certificate/authenticated document shall have to

    be submitted in this regard. Withoutsuch Certificate/ authenticated

    document or where the Certificate/

    authenticated document are un-satisfactory to BPDB, the Tender

    shall be considered technically non-

    responsive. This certificate must be

    notarized and have authentication

    from the Chamber of Commerce ofthe Tenderer's country or the

    Embassy/High commission of thecertificate issuing authoritys country

    situated in Dhaka. In absence of that,authentication is required from the

    Embassy/High Commission of

    tenderers country in Dhaka.

    4. FinancialProposal

    19 Volume 1of 2 ITT

    Clause No

    14.0

    ----- The following is added:Grace Period will be minimum 03

    years, Repayment Period (excluding

    Grace period) will be minimum 10

    years, Repayment shall be made half-

    yearly.5. LTSA 19 Volume 1

    of 2 ITTClause No

    14 (vi)

    The Tenderer shall, in

    addition to essential spareparts and consumables for

    warrantee period also submit

    a price list of spare parts and

    services with OEM part no.for LTSA period (next 4

    years after warrantee period)

    which reflects the OEM'sguidelines and Tenderer'sexperience in the operation

    and maintenance of the typeof equipment proposed. ForLTSA period also the

    Contractor shall supply all

    The tenderer have to provide a

    price quotation from GT OriginalEquipment Manufacturer with

    confirmation that they agree to

    provide LTSA for GT for 5 years

    after the warranty period within theterms and condition of the

    quotation, which will be attached

    along with the tender. BPDB willsign a separate contract with OEMfor GT on the basis of quotation

    related LTSA.

    Without such confirmed quotation

    the tender will be rejected. It is to

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    4/28

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    6. Localtraining and

    Overseastraining

    during LTSAperiod

    - - - The following is included:

    LTSA provider personnel shall beresponsible for providing instruction

    and guidance to BPDB personnel inthe operation and maintenance of the

    equipment. During LTSA period, itshall also be the responsibility of the

    LTSA provider to train up (by on jobtraining) BPDB personnel adequately

    and properly in a planned manner so

    that they can take over theresponsibility of operation and

    inspection/ maintenance of the plant

    and equipment independently. As a

    part of on job training, BPDB

    personnel shall have to be engaged inthe schedule/ unscheduled

    maintenance of the equipment so thatthey could get a clear idea about

    inspection/ maintenance of theequipment.

    As mentioned below, LTSAprovider will provide overseas

    training to BPDB personnel and they(BPDB personnel) will witness

    manufacturing process and tests ofthe materials and spares (to be

    supplied under LTSA) atmanufacturers' works:

    For HGPI materials/ spares: 03person, 30 person-days (each person

    10 days excluding travel time);For MI materials/ spares : 06 person,

    60 person-days (each person 10 daysexcluding travel time).

    09(nine) round trip air fares fromDhaka, Bangladesh to the

    Manufacturer's factory, meals,

    lodging costs transport expenses of

    the BPDB personnel during the period

    of training including incidentalexpenses or medical expenses or

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    5/28

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    7. ServiceEngineers

    afterwarranty

    period;Maintenance

    during LTSAperiod

    116 ofVo. 1;

    20 ofVol. 2

    Part A

    Clause 27.1of PCC,

    Vol. 1;Clause 2.21

    of Vol. 2

    Part A

    The Contractor shall provideOne (1) Competent

    Operation Engineer who willbe in overall in charge of the

    Plant, one (1) Engineer forElectrical Maintenance &

    I&C, one (1) EngineerMechanical Maintenance

    (BOP), one (1) Engineer GasTurbine Maintenance and

    One (1) Engineers for Steam

    Turbine & HRSGMaintenance during 4 years

    LTSA period -----------

    LTSA provider shall provide One (1)Engineer for GT and One (1)

    Engineer for C&I during 5 yearsLTSA period -----------

    8. Evaluation 21 Clause 25.0of ITT,

    Vol. 1

    ------- Amended as mentioned in attachment01 of this addendum.

    9. Terms of

    Payment

    92-95 Clause

    61.03 and61.04 ofGeneral

    conditions,

    Vol. 1;

    Addendumno. 02, sl.

    no. 6 and 7

    -------- The following is added:

    If credit amount is 85% or higher ofthe EPC contract amount (for bothForeign currency and Local

    currency), advance payment of

    foreign currency will be 15% instead

    of 10%. Progress payment (paymentagainst receiving cum damage report/

    monthly invoice) percentage offoreign currency will be reduced

    accordingly.

    Credit repayment shall be made halfyearly.

    10. BangladeshIncome taxand VAT for

    Incomeearned in

    Bangladesh

    88 Clause51.01 (a) ofGeneral

    conditions,Vol. 1;

    ---------- For Tendererscredit financing, IncomeTax, VAT and all other taxes

    as mentioned above will beapplicable at the time of

    deferred payment on theprincipal and interest

    amount. -------------

    ---------- For Tenderers creditfinancing, Income Tax, VAT and allother taxes as mentioned above will

    be applicable at the time of deferredpayment on the principal amount. ---

    11. ExhaustSystem

    49 Clause

    4.3.2.10 of

    Vol. 2, Part

    A

    Gas turbine unit shall be

    equipped with an exhaust

    duct and a suitable by pass

    stack (not less than 40 m) ---

    Gas turbine unit shall be equipped

    with an exhaust duct and a suitable by

    pass stack (not less than 50 m) --------

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    6/28

    Sl.

    no.

    Subject of

    clarification/

    amendment

    TD

    Page

    no.

    Clause no. Mentioned in Tender

    document/ Addendum

    Clarification/ Amendment of

    Tender document

    work will not be required and pricefor this item will be deleted from the

    contract amount. But this price will beconsidered during evaluation.

    Revised Bill of Materials/Quantities& price schedules are enclosed asattachment 02 of this addendum.

    All other terms and condition shall remain unchanged.Signed.

    dt. 15.11.1011

    (Md. Azizul Islam)Secretary,

    Bangladesh Power Development Board

    WAPDA Building (1st

    Floor)

    Motijheel C/Area, Dhaka-1000,

    Bangladesh

    Fax : 880-2-9564765

    Memo No. 3022-BPDB (Sectt)/Dev- 187/2007 date : 15 - 11- 11Copy for information & necessary action to:

    1. Secretary, Power Division, Ministry of Power, Energy and Mineral Resources, Dhaka.2. DG, IMED, Planning commission, CPTU, Dhaka. He is requested to take necessary action for posting

    addendum No. 03 in the CPTU website.

    3. Member, Generation/ P&D/Finance, BPDB, Dhaka.4. Chief Engineer, Generation/ P&D/PSC, BPDB, Dhaka.5. Controller (Finance & Accounts), BPDB, Dhaka.

    6. P.S to Hon'ble Advisor to Prime Minister for Power, Energy and Mineral Resources, Dhaka.7. PS to Hon'ble State Minister, Ministry of Power, Energy and Mineral Resources, Dhaka.8. Project Director, Bibiyana 300-450 MW Combined Cycle Power Plant Project, BPDB.9. C.S.O to Chairman, BPDB, Dhaka.10.Director, Design & Inspection-1/ Design & Inspection-2/System Planning/Program/ Finance/ Contract

    & C.A, BPDB, Dhaka.

    11.Director, Purchase, BPDB, Dhaka. He is requested to send addendum No. 03 to those, who purchasedtender document and to enclose addendum No. 03 with the tender document before selling.

    12.Senior System Analyst, BPDB Dhaka. He is requested to post the addendum No. 03 in BPDB website.

    13.M/S ___________________________14.Office copy.

    Signed.

    dt. 15/11/11

    Sr. Section Officer (Dev)

    BPDB, Dhaka.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    7/28

    Attachment 01 of addendum no. 03 (page no. 7 to 11)

    EVALUATION

    The Technical Proposals submitted by the Tenderers shall be opened first in presence of the Tenderers. At

    the same time the envelope marked "Financial Proposal" submitted by the respective Tenderers will be

    noted for record and kept unopened in proper custody of the Secretary, Bangladesh Power Development

    Board, until the Technical Proposals are completely evaluated. Considering all the aspects ( in connection

    with specified work) offered by each Tenderer as well as the data and information submitted and on proper

    judgement of the capability of individual Tenderers, technically qualified proposals shall be selected

    amongst them and listed. The technical qualifications and overall capability of the Tenderer for carrying out

    the work as specified as well as the specifications of the equipment/materials offered and fulfilment of thekey dates/data shall be the essence for selection of technically qualified Tenderers.

    In the process of evaluation, tender may be considered as responsive only if it is submitted in compliancewith the mandatory requirements set out in the tender document, without material deviation or reservation.

    A material deviation or reservation is one -a) Which affects in any substantial way the scope, quality or performance of the works.b) Which limits in any substantial way, inconsistent with the tender document, the procuring entitys

    rights or the tenders obligations under the contract; orc) Whose rectification would affect unfairly the competitive position of other tenderers presenting

    responsive tenders.

    Total time from Contract Effective Date to Completion of ICO of the unit:

    Shall not exceed 660 Days for Simple Cycle OperationShall not exceed 900 Days for Combined Cycle Operation (Including 660 days for SC operation)

    Guarantee data shall have to be furnished with technical proposal as stated in guarantee schedule-A, vol. 2of 2 of tender document. The Tender shall be rejected if the Tenderers do not comply with thisrequirement.

    Data given by the Tenderer which significantly affect the result of evaluation shall be included in theContract as requirements tobe guaranteed and will be subject to verification at the cost of the Tendererand to the satisfaction of the BOARD.

    No proposal which offers less than 300 MW capacity (Net output at site condition) of Power Plant asspecified in Technical Requirements will be accepted. Excess Net output more than 450 MW at Siteconditions shall not be considered for evaluation of per KW cost stated hereunder.

    The "Financial Proposals" of those eligible Tenderers whose offers qualify in the "Technical Proposal" willb d i f th T d if d t t b tifi d l t If "T h i l P l"

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    8/28

    Financial Analysis:

    For the purpose of evaluation all costs shall be based on equivalent Bangladeshi Taka as of the date of theTender closing.

    The evaluation of the proposal would be done by Financial analysis method taking into account thefollowing:

    A. Tender Price (excluding LTSA cost)B. Initial costC. Debt servicing costD. Fuel costE. O & M cost.

    Initial cost of the proposals shall be determined by bringing the scope of works of all the proposals to acommon basis (Tender price plus average price of omitted equipment/ materials quoted by otherresponsive Tenderers).

    Debt servicing cost shall be calculated by considering Non credit amount, Credit amount, Annual interestrate, Re-payment Period, Grace period and others with a view to comparing different nature of CreditProposal to a equivalent status by applying Net Present Value @ 12 % discount factor.

    Example of Financial analysis for Debt servicing cost

    In this example, Credit portion is 80% of contract value (for both FC and LC), Non Credit portion is 20% ofcontract value (for both FC and LC), Annual interest rate i%, Grace period 03 years, Repayment period 10years are considered.

    Initial cost = m Bangladeshi Taka (BTk.)Installment payment duration = 06 months (half yearly)Discount rate = 12%Po = Total Net output at generator Step-up transformer HT terminals at Site Condition in kW

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    9/28

    TotalNet present value of Repayment amount (NT) will be calculated as shown in Table below:

    Slno.

    Principal amount(In Eq. BTk.)

    Interest(In Eq. BTk.)

    Repaymentamount

    (In Eq. BTk.)

    Net present value ofRepayment amount

    (In Eq. BTk.)

    0 F0 = Initial payments

    for loan effectiveness,such as commitmentfee, risk premium etc.

    - R0 = F0 N0 = R0

    Grace period payment

    1 P1 =0 I1 = (0.8m x i%)/ 2 R1 = I1 N1 = R1/ (1.12)0.5

    2 P2 =0 I2 = (0.8m x i%)/ 2 R2 = I2 N2 = R2/ (1.12)1

    3 P3 =0 I3 = (0.8m x i%)/ 2 R3 = I3 N3 = R3/ (1.12)1.5

    4 P4 =0 I4 = (0.8m x i%)/ 2 R4 = I4 N4 = R4/ (1.12)2

    5 P5 =0 I5 = (0.8m x i%)/ 2 R5 = I5 N5 = R5/ (1.12)2.5

    6 P6 =0 I6 = (0.8m x i%)/ 2 R6 = I6 N6 = R6/ (1.12)3

    Repayment periodpayment

    7 P7 = 0.8 m/ 20 I7 = (0.8m x i%)/ 2 R7 = P7 +I7 N7 = R7/ (1.12)3.5

    8 P8 =0.8 m/ 20 I8 = [{(19x0.8m)/20} x i%]/ 2 R8 = P8 +I8 N8 = R8/ (1.12)4

    9 P9 =0.8 m/ 20 I9 = [{(18x0.8m)/20} x i%]/ 2 R9 = P9 +I9 N9 = R9/ (1.12)4.5

    10 P10 =0.8 m/ 20 I10 = [{(17x0.8m)/20} x i%]/ 2 R10 = P10 +I10 N10 = R10/ (1.12)5

    11 P11 =0.8 m/ 20 I11 = [{(16x0.8m)/20} x i%]/ 2 R11 = P11 +I11 N11 = R11/ (1.12)5.5

    12 P12 =0.8 m/ 20 I12 = [{(15x0.8m)/20} x i%]/ 2 R12 = P12 +I12 N12 = R12/ (1.12)6

    13 P13 =0.8 m/ 20 I13 = [{(14x0.8m)/20} x i%]/ 2 R13 = P13 +I13 N13 = R13/ (1.12)6.5

    14 P14 =0.8 m/ 20 I14 = [{(13x0.8m)/20} x i%]/ 2 R14 = P14 +I14 N14 = R14/ (1.12)

    7

    15 P15 =0.8 m/ 20 I15 = [{(12x0.8m)/20} x i%]/ 2 R15 = P15 +I15 N15 = R15/ (1.12)7.5

    16 P16 =0.8 m/ 20 I16 = [{(11x0.8m)/20} x i%]/ 2 R16 = P16 +I16 N16 = R16/ (1.12)8

    17 P17 =0.8 m/ 20 I17 = [{(10x0.8m)/20} x i%]/ 2 R17 = P17 +I17 N17 = R17/ (1.12)8.5

    18 P18 =0.8 m/ 20 I18 = [{(09x0.8m)/20} x i%]/ 2 R18 = P18 +I18 N18 = R18/ (1.12)9

    19 P19 =0.8 m/ 20 I19 = [{(08x0.8m)/20} x i%]/ 2 R19 = P19 +I19 N19 = R19/ (1.12)9.5

    20 P20 =0.8 m/ 20 I20 = [{(07x0.8m)/20} x i%]/ 2 R20 = P20 +I20 N20 = R20/ (1.12)10

    21 P21 =0.8 m/ 20 I21 = [{(06x0.8m)/20} x i%]/ 2 R21 = P21 +I21 N21 = R21/ (1.12)10.5

    22 P22 =0.8 m/ 20 I22 = [{(05x0.8m)/20} x i%]/ 2 R22 = P22 +I22 N22 = R22/ (1.12)11

    23 P23 =0.8 m/ 20 I23 = [{(04x0.8m)/20} x i%]/ 2 R23 = P23 +I23 N23 = R23/ (1.12)

    11.5

    24 P24 =0.8 m/ 20 I24 = [{(03x0.8m)/20} x i%]/ 2 R24 = P24 +I24 N24 = R24/ (1.12)12

    25 P25 =0.8 m/ 20 I25 = [{(02x0.8m)/20} x i%]/ 2 R25 = P25 +I25 N25 = R25/ (1.12)12.5

    26 P26 =0.8 m/ 20 I26 = {(0.8m/20) x i%}/ 2 R26 = P26 +I26 N26 = R26/ (1.12)13

    TotalNet presentvalue ofRepaymentamount (NT) :

    26

    Nn =n=0

    TotalNet present value of Repayment amount (NT) will be added with non credit amount to find Total Debtservicing cost (DT). Hence, DT = NT + 0.2m

    Per unit Debt servicing cost (T1) in BTk. per kW will be found by dividing DT by net plant capacity Po in kWat site condition. Hence, T1 = DT / Po .

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    10/28

    Basis of Financial analysis for Fuel cost and O&M Cost

    For the purpose of Financial analysis, the following data would be considered:

    a. Plant life 20 years but for evaluation purpose 10 years O&M and fuel cost will be

    consideredb. Plant will operate on natural gasc. Considered plant factor = 80%d. Cost of natural gas, Tk per Nm3 = Tk 5.90 per Nm3

    (Fuel Calorific Value (LHV) of Gas fc = 35,350 kJ/Nm3)

    e. Heat rate to be used for weighted average of50%, 75% and 100 % load under SiteConditionSo H = H100% x 0.5 + H75% x 0.3 + H50% x 0.2 KJ per Kwh

    f. Operation and Maintenance cost - Tk. 0.20 per kWhg. Discount rate on capital investment - 12%

    Example of Financial Analysis for Fuel cost and O&M Cost:

    Po = Total Net output at generator Step-up transformer HT terminals (Delivery point) at SiteCondition in kW

    EP0 = Annual delivered energy at Delivery point in Kwh= P0 x 24 x 365 x 0.8 Kwh

    H = Average weighted heat rate of generating unit at Delivery point(100%, 75%and 50% load at Site Condition) in KJ / kWH

    = H100% x 0.5 + H75% x 0.3 + H50% x 0.2 KJ per Kwh

    Hc = Annual heat consumption at Delivery point= H x EP0 in KJ

    Fuel Calorific Value (LHV) of Gas fc = 35,350 kJ/Nm3

    Annual fuel consumption =Hc/ fc , Nm3 = Fa

    FAC = Annual fuel cost = Tk 5.90 Fa

    Ca = Annual operating and maintenance cost = Tk 0.20 x EP0

    d = Discount rate=12% perannum

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    11/28

    The Total Discounted Fuel and O&M cost, Te will be calculated as shown in Table below:

    Year Fuel CostIn Taka

    O&M Cost per yearIn Taka

    Discounted Fuel and O&M costper YearIn Taka

    1. Fac Ca (Fac+Ca)/(1+d)

    2. Fac Ca (Fac+Ca)/(1+d)2

    3. Fac Ca (Fac+Ca)/(1+d)3

    4. Fac Ca (Fac+Ca)/(1+d)4

    5. Fac Ca (Fac+Ca)/(1+d)5

    6. Fac Ca (Fac+Ca)/(1+d)6

    7. Fac Ca (Fac+Ca)/(1+d)7

    8. Fac Ca (Fac+Ca)/(1+d)8

    9. Fac Ca (Fac+Ca)/(1+d)9

    10. Fac Ca (Fac+Ca)/(1+d)10

    Te =

    Then Per unit Discounted Fuel and O&M cost (T2) in BTk. per kW will be found out by dividing Te by thenet plant capacity, Po in kW at Site conditions. Hence T2 = Te/ Po.

    Evaluated Price

    Finally Evaluated cost (T) in BTk. per kW will be found out by adding T1 and T2.Hence T = T1 + T2.

    The tenderer whose Tvalue is the lowest will be adjudged the lowest tenderer.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    12/28

    Attachment 02 of addendum no. 03 (Page 12 to 28 )

    Revised Bill of Materials/Quantities&

    Price Schedule

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    13/28

    Addendum 03, Bibiyana 300-450 MW 13

    The Tenderer shall fill-up the following table of prices and shall include the same in the financial proposal

    Schedule-1

    Supply of Equipment:Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1A-1 Packaged Gas Turbine Generating unitcompleted in all respect including allauxiliaries, instrumentation, grounding system

    and inter-connection piping, cabling, gas fueloperation, air intake filtration facilities, inletand exhaust silencing facilities, ducts andother ancillaries equipment.

    Gas Turbine2 nos. for2:2:1 Config.

    or1 no. for 1:1:1Config.

    Gas TurbineGenerator2 nos. for2:2:1 Config.or

    1 no. for 1:1:1Config.

    1A-2 Complete equipment for off base coolingsystem.

    1(one) Set

    1A-3 Complete equipment for off base natural gassupply system including gas treatment skid.

    1(one) Set

    1A-4 Gas Booster Compressor with all ancillary,auxiliary [3X60%]

    3(three) sets

    1A-5 GT (Bypass) Stack. 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.

    1A-6 15.75 KV Generator Switchgear(circuit breaker, isolators, earthing switches,CT, PT, surge capacitors, surge absorber

    assembly)

    2 (two) sets

    1A-7 Station Transformer, 6.6/0.415 KV. 4(four) Sets

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    14/28

    Addendum 03, Bibiyana 300-450 MW 14

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1A-8 Unit Auxiliary Transformer, 15.75/6.6 KV. 2(one) Sets

    1A-09 230/11/6.6 kV Transformer 1 (one) set

    1A-10 230 kV U/G cable, conductors 1 (one) Lot

    1A-11 230 kV switchgear, protection & meteringequipment etc.

    1 (one) Lot

    1A-12 Steel structures, insulators etc. for 230 kV 1 (one) Lot

    1A-13 11 kV switchgear, protection & metering

    equipment etc.

    1 (one) Lot

    1A-14 11 kV cable, conductors, insulators 1 (one) Lot

    1A-15 11/ 0.4 kV Transformers 1 (one) Lot

    1A-16 0.4 kV cable, conductors, insulators 1 (one) Lot

    1A-17 6.6 KV station switchgear. 1 (One) Lot

    1A-18 415 V switch gear and power centres 1 (One) Lot

    1A-19 Emergency Diesel Generator (EDG) (cap 1000kVA) with all ancillary and diesel storage tank.

    1 (one) set

    1A-20 Other miscellaneous equipment/materials 1 (One) Lot

    Sub-total : 1A

    1B-1 Heat Recovery Steam Generator(s) 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.

    1B-2 Structural Steels 1 (one) lot

    1B-3 Piping work 1 (one) lot

    1B-4 Valves 1 (one) lot

    1B-5 Instrumentation & Control facilities 1 (one) lot

    1B-6 Lagging & Cladding 1 (one) lot

    1B-7 On & Off-load Cleaning equipment 1 (one) set

    1B-8 Gas Duct 1 (one) lot

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    15/28

    Addendum 03, Bibiyana 300-450 MW 15

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1B-9 Hydraulic Diverted damper with hydraulic oilskid

    2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.

    1B-10 Motor operated Guillotine Damper 2 nos. for2:2:1 Config.or

    1 no. for 1:1:1Config.

    1B-11 HRSG Stack 2 nos. for2:2:1 Config.or1 no. for 1:1:1Config.

    1B-12 Chemical dozing system including pumps 01 (one) lot

    1B-13 Other miscellaneous equipment/materials 1(one) lot

    Sub-Total 1B

    1C-1 Steam Turbine & auxiliaries 1 (one) set

    1C-2 Steam Turbine Generator including excitationsystem, AVR & other auxiliaries

    1 (one) set

    1C-3 Surface condenser 1 (one) set

    1C-4 Deareator 1 (one) set1C-5 Air extraction system, ejector 1 (one) set

    1C-6 Air extraction system, Vacuum Pump 02 (two) Nos.

    1C-7 Closed loop cooling water system 1 (one) lot

    1C-8 Feed Water Pump 3 (three) nos.

    1C-9 Condensate water Pump 3 (three) nos.

    1C-10 Circulating water pump (cooling Tower Pump) 3 (three) nos.

    1C-11 Cooling Tower fans 1 (one) lot

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    16/28

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    17/28

    Addendum 03, Bibiyana 300-450 MW 17

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1E-2 6.6 KV XLPE power cable 1 (one) Lot

    1E-3 600 V power cable 1 (one) Lot

    1E-4 Control and Instrument cable 1 (one) Lot

    1E-5 Raceway Materials 1 (one) Lot

    1E-6 Grounding System 1 (one) Lot

    1E-7 Lighting and small power 1 (one) Lot

    1E-8 Battery (125 V DC Alkaline Ni-Cd battery)

    Battery Chargers

    2(two) sets

    1E-9 DC distribution board, switchgears, cables etc. 1 (one) Lot

    1E-10 2x 100% capacity Invertors with relatedswitchgears, cables etc.

    1 (one) Lot

    1E-11 Communication system

    PABX Telephone systemPaging system

    Power supplyTelemetering facilities, Communication &SCADA EquipmentCCTV System

    1(one) Lot1(one) Lot

    1(one) Lot1(one) Lot1(one) Lot1(one) Lot

    1E-12 Other miscellaneous equipment/materials 1(one) Lot

    Sub-total : 1E

    1F-1 Chemical water treatment plant including allreservoirs, storage tanks, pumps, valves,

    pipings, electrical and I&C system with allauxiliaries complete in all respect.

    1(one) Lot

    1F-2 Chemical laboratory with standard apparatusfor Combined cycle Power Plant

    1(one) Lot

    1F-3 Effluent Treatment Plant 1(one) Lot

    1F-4 Other miscellaneous equipment/materials 1(one) Lot

    Sub-total : 1F

    1G-1 GT Hall EOT Crane 1 (One) no.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    18/28

    Addendum 03, Bibiyana 300-450 MW 18

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1G-2 ST Hall EOT Crane(if ST is located in different hall or GT EOTcrane can not be used for ST)

    1 (One) no.

    1G-3 CWP House EOT Crane 1 (One) no.

    1G-4 GBC House EOT Crane 1 (One) no.

    1G-5 Mobile Crane 1 (One) no.

    1G-6 5 ton truck with 3 ton jib crane 1 (One) no.

    1G-7 5 ton fork lift 1 (One) no.1G-8 5 ton truck/ lorry 1 (One) no.

    1G-9 1 ton half truck 1 (One) no.

    1G-10 Hoist for EDG room, River intake pump house,Fire fighting pump house, Chemical plant

    1(one) Lot

    1G-11 Special tools and Special lifting and handlingappliances

    1(one) Lot

    1G-12 Other miscellaneous equipment/materials 1(one) LotSub-total : 1G

    1H-1 Fire Fighting Facilities 1(one) Lot

    1H-2 Special Maintenance tools including Boroscope 1(one) Lot

    1H-3 Electrical workshop tools 1(one) Lot

    1H-4 Machine Shop equipment & Tools 1(one) Lot

    1H-5 Laboratory Equipment (Testing Bench) 1(one) Lot

    1H-6 Transport:03 nos. of four wheel drive Jeep (3000 CC),04 nos. of sedan car (1600 CC), 04 nos. ofdouble cabin Pick up (2700 CC), 02 nos. ofmicrobus (2400 CC), 10 nos. of motorcycle(100 CC), 01 no. of ambulance.

    1(one) Lot

    1H-7 Other miscellaneous equipment/materials 1(one) Lot

    Sub-total : 1H

    1I-1 Local & Remote unit control desk Boards/ HMI 1(one) Lot

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    19/28

    Addendum 03, Bibiyana 300-450 MW 19

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    1I--2 15.75 KV common switchgear control deskboard including Gen. WH & VarH Recordingmeters

    1(one) Lot

    1I--3 Auxiliary power supply control desk board 1(one) Lot

    1I-4 420 KV control, metering and protectionpanels including delivery point WH & VarHRecording meters

    1(one) Lot

    1I--5 Synchronising panels (swing type)

    Plant Control System with on-line PlantPerformance Monitoring & OptimizationSystem

    1(one) Lot

    1I-6 Standard weather station 1(one) Lot

    1I-7 Continuous emission monitor module 1(one) Lot

    1I-8 Other miscellaneous equipment/materials 1(one) Lot

    Sub-total : 1I

    1J-1 Approx. 09 km Gas pipe line 1(one) Lot1J-2 Fuel gas regulating & metering station 1(one) Lot

    1J-3 Other Fuel Gas Handling facilities 1(one) Lot

    Sub-total : 1J

    1K-1 Spares for Warranty period 1(one) Lot

    1k-2 Consumables for Warranty period 1(one) Lot

    Sub-total : 1k

    1L-1 Simulator for Power Plant operation Training 1 (one) SetSub-total : 1L

    Sub-total : 1

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    20/28

    Addendum 03, Bibiyana 300-450 MW 20

    Schedule-2Erection & Commissioning

    Sl.No.

    Description Qty Erection & Commissioning Insurance forErection &

    Commissioning

    Foreigncurrency

    Bangladesh Taka Bangladesh Taka

    Rate Total Rate Total Rate Total

    2A Gas Turbine Generating unit Complete with auxiliary equipment 1 lot

    2B Heat Recovery Steam Generator complete with auxiliaryequipment

    1 lot

    2C Steam Turbine Generating unit complete with auxiliary equipment 1 lot

    2D Transformers, switchgears and other electrical equipment and

    materials

    1 lot

    2E Approx. 09 km Fuel gas pipe line 1 lot

    2F Fuel Gas regulating & metering station 1 lot

    2G Other Fuel handling facilities and Gas Booster compressor 1 lot

    2H Chemical Plant, Chemical lab, Effluent treatment plant 1 lot

    2I Cooling Tower 1 lot

    2J Fire fighting facilities 1 lot

    2K Communication system 1 lot

    2L Mechanical Auxiliary equipment 1 lot

    2M Maintenance facilities, Workshop facilities, EDG and other

    mechanical facilities

    1 lot

    2N Central control equipment 1 lot

    Sub-total : 2

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    21/28

    Addendum 03, Bibiyana 300-450 MW 21

    Schedule-3Civil & Building Works:

    Sl.No.

    Description Qty Civil & Building Works Insurance for Civil &Building Works

    Foreigncurrency

    Bangladesh Taka Bangladesh Taka

    Rate Total Rate Total Rate Total

    3A-1 Soil test, demarcation & serveying and Excavation 1 lot

    3A-2 Filling and Land development 1 lot

    3A-3 Others, if necessary (Tenderer shall specify those items) 1 lot

    Sub-total : 3A

    Site works

    3B-1 Internal Road, fencing, path and parking area 1 lot

    3B-2 Drainage system 1 lot

    3B-3 Sewage works 1 lot

    3B-4 Water works, deepwell and pumps (2X100%) 1 lot

    3B-5 Storage tank for fire-fighting 1 lot

    3B-6 Piping and others 1 lot

    3B-7 Landscaping, turfing, gravel surfacing 1 lot

    3B-8 Others (if any);Tenderer shall specify those items 1 lot

    Sub-total : 3B

    PilingTenderer shall specify kind of piles to be utilised

    3C-1 For Gas Turbine generating unit foundations 1 lot

    3C-2 HRSG unit foundations 1 lot

    3C-3 STG unit foundations 1 lot

    3C-4 For Transformers, switchgears, equipment etc. foundations 1 lot

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    22/28

    Addendum 03, Bibiyana 300-450 MW 22

    Sl.No.

    Description Qty Civil & Building Works Insurance for Civil &Building Works

    Foreigncurrency

    Bangladesh Taka Bangladesh Taka

    Rate Total Rate Total Rate Total3C-5 GBC, EDG and other equipment foundation 1 lot

    3C-6 For Building foundations 1 lot

    3C-7 For gantry, steel structure foundations 1 lot

    3C-8 Cooling Tower 1 lot

    3C-9 Permanent jetty/ platform for loading, unloading ofequipment

    1 lot

    3C-10 River Water Intake 1 lot

    3C-11 All storage Tanks 1 lot

    3C-12 For Others (if any) ;Tenderer shall specify 1 lot

    Sub-total : 3C

    Foundation

    3D-1 Gas turbine generating unit, HRSG, STG, GBC, EDG, Firefighting pumps and all associated equipment/auxiliaries

    1 lot

    3D-2 Transformers, switchgears, equipment foundations 1 lot

    3D-3 Gantry, steel structures foundations 1 lot

    3D-4 Buildings foundations 1 lot

    3D-5 Cooling Tower 1 lot

    3D-6 All storage Tanks 1 lot

    3D-7 Permanent jetty/ platform for loading, unloading ofequipment

    1 lot

    3D-8 River Water Intake 1 lot

    3D-9 Other foundation (if any) (Tenderer shall specify) 1 lot

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    23/28

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    24/28

    Addendum 03, Bibiyana 300-450 MW 24

    Schedule-4

    Services :Sl.

    No.

    Description Qty Services

    Foreign currency Bangladesh TakaRate Total Rate Total

    4A DESIGN AND ENGINEERING 1 lot

    4B WORKSHOP TESTS INCLUDING TEST WITNESSING 1 lot

    TRAINING

    4C1 Training at manufacturers factory 1 lot

    4C2 Traveling charges, ____ persons 1 lot

    4C3 Living allowance, ____Man-Month 1 lot

    4C4 Training at the site 1 lot

    4D DOCUMENTS (DRWINGS, OPERATION MANUALS,

    STANDARDS etc.)

    1 lot

    4E Service for Execution of Schedule maintanance (Firstinspection, HGPI etc.) during 2 years warranty period

    1 lot

    4F Operation and maintenance services after satisfactory

    performances test. (warrantee engineers for 2 yearswarranty period).

    1 lot

    Sub-total : 4

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    25/28

    Addendum 03, Bibiyana 300-450 MW 25

    Schedule-5A

    Spare parts for Long Term Service Agreement (LTSA) for 5 years after warrantee period: [Will not be considered in

    Evaluation]

    Sl.No

    Item Name Qty Foreign Currency Bangladesh TakaFOB Price Freight Insurance Insurance for

    Transportationup to Site

    Custom Clearanceand Inland

    Transportation

    Rate Total Rate Total Rate Total Rate Total Rate Total

    5A-1 Spare parts & consumables for the 1st year ofLTSA

    1(one) Lot

    5A-2 Spare parts & consumables for the 2

    nd

    year ofLTSA 1(one) Lot

    5A-3 Spare parts & consumables for the 3rd year ofLTSA

    1(one) Lot

    5A-4 Spare parts & consumables for the 4th year ofLTSA

    1(one) Lot

    5A-5 Spare parts & consumables for the 5th year ofLTSA

    1(one) Lot

    Sub Total of 5AN.B: In preparation of the list the tenderer have to consider plant factor as 80%.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    26/28

    Addendum 03, Bibiyana 300-450 MW 26

    Schedule-5B

    Service for Long Term Service Agreement (LTSA) for 5 years after warrantee period: [Will not be considered in

    Evaluation]

    Sl.No.

    Description Qty Foreign currency Bangladesh Taka

    Rate Total Rate Total

    5B.1 Service for the 1st year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)

    1(one) Lot

    5B.2 Service for the 2nd year of LTSA (with break-up cost for required

    service personnel including no. of visits, per-diem cost and expectedman-days)

    1(one) Lot

    5B.3 Service for the 3rd year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)

    1(one) Lot

    5B.4 Service for the 4th year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)

    1(one) Lot

    5B.5 Service for the 5th year of LTSA (with break-up cost for requiredservice personnel including no. of visits, per-diem cost and expectedman-days)

    1(one) Lot

    Sub-total : 5B

    N.B: In preparation of the list the tenderer have to consider plant factor as 80%.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    27/28

    Addendum 03, Bibiyana 300-450 MW 27

    Schedule 5 : Total Prices for 5 years LTSA

    Sch.No.

    Description Foreign currency Bangladesh Taka

    FOB Insurance

    & Freight

    Service/

    Erection,Commissioning

    , Civil &Building works

    Insurance Customs

    Clearance &Inland

    transportation

    Erection,

    Commissioning, civil and

    building works

    Transportation

    upto site

    Erection

    commission-ing, civil &building works

    Sch. 5A Supply of Spares

    Sch. 5B Services

    Total of Schedule 5

    Note: For gas turbine maintenance at least 1 (One) CI, 1 (One) HGPI and 1 (One) MI within the LTSA period have tobe considered.

  • 7/28/2019 Bibiyana 03 Addendum 03 With Attachment

    28/28

    Addendum 03, Bibiyana 300-450 MW 28

    Summary of Prices:Sch.

    No.

    Description Foreign currency Bangladesh Taka

    FOB Insurance& Freight

    Service/Erection,

    Commissioning, Civil &Building works

    Insurance CustomsClearance &

    Inlandtransportation

    Erection,Commissioning,

    civil and buildingworks

    Transportation

    upto site

    Erection

    commission-ing, civil &building works

    Sch. 1 Supply ofEquipment

    Sch. 2 Erection &Commissioning

    Sch. 3 Civil and Buildingworks

    Sch. 4 Services

    VAT & TAX for thework except CIF

    Value of permanent

    materials (@10.5%)

    Grand Total

    Sch. 5 LTSA

    VAT & TAX for thework except CIF

    Value of permanentmaterials (@10.5%)

    Total