Benefits Realisation Guideline

Version 1.2

Thursday, June 30, 2011

Page 2: Benefits Realisation Guideline 2011

Department of Finance and Services 2

Benefits Realisation Guideline

Document Ownership Information

Document Owner ICT Policy Branch

Document Preparation S. Dey, M. Schniering

Document Confidentiality

Document Name and Version Control (Circulated versions only)

Document Name & Location www.services.nsw.gov.au

Version Date Author Changes Included

1.0 (First Release)

29 June 2010 S. Dey, M. Schniering First release based on drafts and feedback from reviewers.

1.1 23 March 20111 D Anspal Removed GCIO references

1.2 30 June 2011 D Anspal Updated contact details

Page 3: Benefits Realisation Guideline 2011

Department of Finance and Services 3

Benefits Realisation Guideline

Table of Contents

Table of Contents .................................................................................................................. 3

List of Figures ....................................................................................................................... 4

List of Tables ........................................................................................................................ 4

1 Introduction ................................................................................................................ 5

1.1 Document Purpose ................................................................................................. 5

1.2 The Case for Benefits Realisation ........................................................................... 5

1.3 Audience and User Guide ....................................................................................... 6

1.4 Challenges Typically Encountered in Benefits Realisation ...................................... 8

1.5 Applying this Guideline ........................................................................................... 9

2 Benefits Realisation Guideline .................................................................................. 10

2.1 Four Phases of Benefits Realisation ..................................................................... 10

2.2 Benefits Realisation Governance .......................................................................... 11

2.3 Understand Phase ................................................................................................ 12

2.4 Plan Phase ........................................................................................................... 14

2.5 Realise Phase ....................................................................................................... 16

2.6 Report Phase ........................................................................................................ 18

2.7 Roles and Responsibilities in Benefits Realisation ................................................ 21

3 Case Study 1 - Government Licensing Service ......................................................... 23

4 Case Study 2 – Electronic Medical Records ............................................................. 25

5 Appendix A – Articulating Benefits and Understanding how they are Delivered ........ 27

5.1 What is a Benefit? ................................................................................................. 27

5.2 Types of Outcomes and Benefits .......................................................................... 27

5.3 Understanding Outcomes and Benefits, and how they are derived ....................... 27

6 Appendix B - Potential Benefits Listed by Category .................................................. 34

6.1 Increased Effectiveness ........................................................................................ 34

6.2 Increased Efficiency .............................................................................................. 35

6.3 Enabling ................................................................................................................ 35

6.4 Survival ................................................................................................................. 36

6.5 Research and Development .................................................................................. 36

7 Appendix C – Template Benefits Realisation Plan .................................................... 37

8 Appendix D – Template Benefits Register ................................................................ 45

9 Appendix E – Suggested Further Reading ................................................................ 46

Page 4: Benefits Realisation Guideline 2011

Department of Finance and Services 4

Benefits Realisation Guideline

List of Figures

Figure 1 - User Guide ............................................................................................................ 7

Figure 2 - Benefits Realisation Phases ............................................................................... 10

Figure 3 - Benefits Realisation across the Program Lifecycle .............................................. 11

Figure 4 - Managing Outcomes for Business Change ......................................................... 12

Figure 5 - Example Report using Balanced Scorecard Format ............................................ 19

Figure 6 - Example Report using Benefits Register Extract ................................................. 20

Figure 7 - Example Report using Outcomes Dashboard Format ......................................... 20

Figure 8 - Example Benefits Pathway ................................................................................. 30

Figure 9 - Simplified Value Map .......................................................................................... 31

Figure 10 - Sample Value Map ............................................................................................ 33

Figure 11 - Report generated by completion of Benefits Register ....................................... 45

List of Tables

Table 1 - Table of Investment Type and Guideline Application .............................................. 9

Table 2 - RACI Table for Key Benefit Realisation Activities ................................................. 22

Page 5: Benefits Realisation Guideline 2011

Department of Finance and Services 5

Benefits Realisation Guideline

1 Introduction

1.1 Document Purpose

The Benefits Realisation Guideline (this Guideline) has been developed by the NSW Department of Finance and Services (DFS) to assist NSW Government Agencies manage benefits realisation. This includes the process of understanding, planning, realising and reporting both financial and non-financial benefits associated with ICT enabled and business change programs. This Guideline may also be used to establish a benefits management framework for other reform and transformation programs.

Effective benefits realisation is critical to the achievement of the business outcomes desired from investments. Benefits realisation is an important contributor of key information to the development of business cases, portfolio management, governance and decision making by Government.

This Guideline merges and updates the Benefits Management Plan Guideline (version August 2003) and Benefits Realisation Register Guideline (version March 2004). It has been developed after research of public and private sector models and in consultation with a number of NSW Government agencies. Several agencies have established processes to track the achievement of benefits throughout phases of the program lifecycle. Case studies and experiences from these agencies are included to illustrate the application of this Guideline.

This Guideline covers the steps involved in effectively understanding, planning, realising and reporting benefits of ICT enabled business change programs. It also provides inputs into the NSW Treasury Business Case and Total Asset Management (TAM) Guidelines. It does not cover areas such as the writing a business case, undertaking project or program management, portfolio management or governance.

Supporting this Guideline are two sample templates for Benefits Realisation:

1. The Benefits Realisation Plan is used as a key component in the development of business cases used to support proposals for new ICT enabled business change programs. This Plan describes the expected benefits or outcomes that will be realised from exploiting capabilities of an ICT enabled business change program.

2. The Benefits Register and Reporting are used to ensure that potential benefits are captured and realised. Reporting provides the Program Sponsor, Manager and Benefit Owners with the information vital to make the decisions required to ensure ICT enabled business change programs are successful in achieving the benefits articulated in their approved business cases.

1.2 The Case for Benefits Realisation

ICT enabled business change programs represent a large portion of spend for government. These programs are publicly funded; therefore it is ultimately the responsibility of agencies to ensure that taxpayers receive a positive return for their investment in the form of increased service delivery or decreased cost of service.

The NSW Government’s Total Asset Management (TAM) Guideline states that Post Implementation Reviews (PIR) should report on whether the desired benefits, expected in the business case have been realised. Additionally NSW Treasury Business Case Guideline TPP08-5 sets out the benefits requirements for business cases, which should be inextricably linked to the outputs of the Benefits Realisation process.

This Guideline provides a structured approach for agencies to manage and demonstrate the realisation of benefits from an ICT enabled business change program. It helps agencies

Page 6: Benefits Realisation Guideline 2011

Department of Finance and Services 6

Benefits Realisation Guideline

show the linkage between ICT investment and Government policy priorities, agency business objectives and service delivery outcomes.

This Guideline has been developed based on a number of well accepted good practice principles of benefits realisation. These are:

• Business change programs deliver benefits. Technology by itself does not deliver business benefits – technology delivers new capabilities which can be exploited to deliver business benefits. Organisations only realise business benefits through a coordinated, focused combination of changes in technology, organisation, people, processes and relationships with external suppliers, customers and partners.

• Benefits are not automatic. In addition to effective project management, delivery of desired business benefits requires active monitoring of program progress and the outcomes and benefits to be realised.

• Benefits need to be first understood as business outcomes. With an understanding of the holistic business change required to realise business outcomes, benefits can be planned, realised and reported.

• Benefits are dynamic. Benefits identified at the commencement of the investment‟s life cycle will almost certainly change over the life of the investment. They need to be regularly reviewed and updated, in response to changes in program scope, objectives and delivery.

• Intermediate outcomes are needed to realise business benefits. Achievement of and reporting on intermediary outcomes (those associated with the change along the way) are just as important as the benefits associated with final strategic outcomes.

• The ‘Business’ need to own the benefits. Benefits must be owned by appropriate business sponsors and managers, not by the project / program manager.

• Benefits are both financial and non-financial. Benefits realised and measured include both financial and non-financial outcomes.

• Change management is integral to benefit realisation. Change management is essential to the introduction of benefits realisation disciplines. Benefits realisation needs strong executive sponsorship across an agency to be successful.

Following these principles, benefits realisation becomes a critical value adding role in a business change program.

1.3 Audience and User Guide

This document is intended for the use of the agency and cross-agency roles involved in benefits realisation, including:

• Program Sponsors: the executive responsible for the program and its benefits.

• Program Managers: responsible for the delivery of the program - its new capabilities and the environment in which successful business change will deliver the business benefits.

• Outcome/benefit owners: the officers who have the responsibility for realising the business outcomes/benefits.

• Benefits Realisation Manager: the officer responsible for the establishing, operating and maintaining of the benefits realisation disciplines outlined in these Guidelines. This role may be a specific function within the Program Management Office.

• Program Management Offices: the governance body responsible for co-ordinating and overseeing the delivery of the program, and has an oversight of the benefits realisation activities.

This Guideline consists of four phases. The next section of the document will break out and provide detail of each of these phases. As the users of this guideline will focus on different

Page 7: Benefits Realisation Guideline 2011

Department of Finance and Services 7

Benefits Realisation Guideline

elements of the framework for their roles, below is a guide to the relevant sections broken down according to the phases in the process.

Key Users:

Program Sponsors i i i

Program Managers i i

Benefit Owners i

Benefits Realisation Mgr i

PMO i i

Mandatory Reading for Each Phase:

1. Introduction

2.2 Governance

2.3 Understand Phase

2.7 Roles

Appendix A

Appendix B

1. Introduction

2.2 Governance

2.3 Understand Phase

2.4 Plan Phase

2.7 Roles

Appendix A

Appendix B

Appendix C

1. Introduction

2.2 Governance

2.5 Realise Phase

2.7 Roles

Appendix C

1. Introduction

2.2 Governance

2.6 Report Phase

2.7 Roles

Appendix C

Figure 1 - User Guide

Mandatory Reading i Suggested Reading

Page 8: Benefits Realisation Guideline 2011

Department of Finance and Services 8

Benefits Realisation Guideline

1.4 Challenges Typically Encountered in Benefits Realisation

This Guideline aims to increase successful benefits realisation. It addresses typical challenges encountered in benefits realisation, including:

• Benefits to be delivered by the program are not clear and/or agreed.

• The initiatives required to deliver the benefits are not defined nor linked to the outcomes/benefits that they deliver.

• The scope and objectives of the program are not clear and/or agreed.

• Linkage between the „actual‟ benefits delivered and the original business case is weak or unclear.

• The original (and approved) Business Case and Business Realisation Plan (BRP) developed at a project‟s conception are not updated throughout the project lifecycle to reflect better and more detailed planning; refinement of objectives, scope, cost and risk; and benefits expected to be delivered.

• Benefits are not measured or reported.

• Benefits measures not defined or measures at the beginning of the program. Objective comparisons of the changes and benefits realisation can not be easily identified and reported.

• Ownership and accountability for benefit realisation is not clear and/or agreed.

Page 9: Benefits Realisation Guideline 2011

Department of Finance and Services 9

Benefits Realisation Guideline

1.5 Applying this Guideline

Whilst the focus is on realising benefits from ICT enabled business change programs, these Guidelines can be applied to any investment where there is a desire to achieve specific business outcomes (and thus benefits). The following table provides some examples:

Type of Investment Primary Focus / outcomes

Investment Categorisation

Scope of the investment

Relevant Section in these Guidelines

ICT enabled business change program (at either agency of whole of government level)

e.g. Electronic Clinical Documentation Program

Changing the way the agencies work to achieve specific business outcomes

eg. Increased patient safety; Decreased costs of service

Transformation of the Business

People, process, organisation, technology, citizens, suppliers, etc

All

Reform and transformation initiatives of government

eg. Corporate and Shared Services Reform

Changing the way the agencies work to achieve specific business outcomes

eg. Decreased cost of service

Transformation of the Business

People, process, organisation, technology, citizens, suppliers, etc

All

Stand-alone ICT projects

eg. Virtualising servers or consolidating data centres

Focus is less on benefits, and more on managing delivery cost and risk, and maintaining core services.

eg. Decreased ICT cost

Core or Maintaining ICT Infrastructure

Technology Minimal – use of abridged Plan, Realise and Report for monitoring ICT cost reduction

Table 1 - Table of Investment Type and Guideline Application

Page 10: Benefits Realisation Guideline 2011

Department of Finance and Services 10

Benefits Realisation Guideline

2 Benefits Realisation Guideline

2.1 Four Phases of Benefits Realisation

The Benefits Realisation Guideline is a collection of steps, templates and frameworks designed to achieve the goal of realising business value from an ICT enabled business change program. It achieves this via four key phases, each with its own purpose and outputs. This document defines each phase and explains how, when carried out they combine to allow a program to successfully realise benefits.

Understand: Before we can plan or measure benefits, we must understand which outcomes are in fact the targets of such investment. The „Understand‟ phase is all about establishing the strategic intent and identifying the outcomes required to achieve this intent.

Plan: A plan is then created in which further develops the findings from the „Understand‟ phase. It includes additional details such as the owner, the target to be achieved and the units with which to measure progress. It also includes the necessary arrangements needed to be in place to realise the benefits. The outputs of the Plan phase form the basis for the benefits section of the program business case.

Realise: Realising the benefits is then achieved by monitoring progress towards the planned outcomes. Deviations from plan can be picked up early with the appropriate corrective action taken. Throughout this process the business case should be updated and maintained as there will inevitably be differences between what was initially proposed and what is attainable as the program progresses.

Report: Reporting of actual versus planned is provided to the Governance body in accordance with the plan, facilitating accountability of performance of the program.

Figure 2 - Benefits Realisation Phases

Page 11: Benefits Realisation Guideline 2011

Department of Finance and Services 11

Benefits Realisation Guideline

Benefits Realisation needs to be executed across the program lifecycle, from concept stage to benefits realisation. The figure below shows the 4 phases across the typical stages in a program lifecycle, from „Concept‟ to „Operate & Maintain‟. It shows that understanding the program scope and objectives is critical early in the lifecycle, as part of the initial business case development. Identifying and articulating the benefits at this point will inform the benefits in the business case. Initial definition of the benefits is then built upon with detailed benefits realisation planning. At this stage, the initial business case is updated and revised as the benefits to be realised are defined and ownership assigned. As soon as business change is delivered, benefit realisation activities are executed by the program and benefit owners. At the same time, benefits are measured and reported to track success of the program and benefit realisation.

Figure 3 - Benefits Realisation across the Program Lifecycle

2.2 Benefits Realisation Governance

As shown in Figure 2 Benefits Realisation Governance governs and supports the four phases of Benefit Realisation. In addition to the ownership and accountability reinforced by the Benefits Realisation Guidelines, three key principles of benefits governance should be followed:

1. Commitment and support at the senior leadership and executive level. Active support for the program will support and reinforce benefit ownership and realisation;

2. Clear and active program sponsorship and accountability. Sponsorship of the program, together with accountability for the benefits realised reinforces the benefits realisation process and framework; and

3. Program management and responsibility for defining, measuring and reporting benefits. Clear responsibility and accountability of the roles to deliver the four phases of the benefits realisation guideline are critical.

Benefits Realisation Governance

PMO

Benefits

Realisation

Managers

Program Sponsor

and

Benefits Owners

Program and

Project

Management

Concept Initiation/

Business

Case

Require-

ments and

Design

Prepare

for Go-Live

Stage gates

Realise

BenefitsUAT/

Deploy /

Migrate

Build &

Test

Operate &

Maintain

1. Understand

Program Scope

and Objectives

Initial

Business Case

Revised

Business CaseBenefit Tracking

2. Plan for Benefits Realisation

3. Realise Benefits

4. Report Outcomes

Realisation

Activities

Measurement

Ownership

Milestone Tracking

Page 12: Benefits Realisation Guideline 2011

Department of Finance and Services 12

Benefits Realisation Guideline

2.3 Understand Phase

The first step in benefits realisation is to identify and define potential outcomes and benefits. The goal is to explore and assess business ideas while maintaining focus on the proposed benefits – answering 'why we are doing this?' The process is continued by developing the initiatives and intermediate outcomes that will need to be delivered to realise the anticipated benefits.

This phase will distinguish outcomes from benefits. Outcomes are the capabilities created, changes made and results sought from the investment. Benefits are the specific outcomes where accountability can be assigned and measurement defined. Benefits are used for defining and declaring success of an investment. Benefits are the net positive changes resulting from outcomes. It is essential to understand the outcomes before we can define and declare them as benefits. The following example illustrates this distinction.

Figure 4 - Managing Outcomes for Business Change

Desired Business

Outcomes

Project delivery of

New Capability

Outcomes

Business Change

Outcomes

Strategic

Outcomes

Created

enabling

technology for

clinical

Documentation

Increased patient

safety

(decreased

adverse events)

Increased Multi-

discipline team

information

sharing and

communications.

Decreased use of

paper records

Created new

best practice

for clinical

delivery

Created new

behaviours with

staff to drive

clinical

docucmentation

Outcomes that will be designated as

“ benefits” of the program

Outcomes identified as part of the Program

Enables

Increased

information

based clinical

decision making.

Decreased

variations in

clinical practice

CreatesHelps

achieve

Page 13: Benefits Realisation Guideline 2011

Department of Finance and Services 13

Benefits Realisation Guideline

This process of understanding the outcomes and benefits should be integral to the development of the Initial Business Case (refer to Treasury Business Case Guidelines TPP08-5 and TAM planning processes). The identification and articulation of the benefits provides the „benefits side‟ of the business case, including the rationale and objectives of the program. Understanding the benefits and development of the Initial Business Case should go hand-in-hand.

2.3.1 Steps

The following steps should be undertaken in the Understand phase:

Obtain business context of the benefits:

Determine business drivers – what is the business problem we are trying to solve?;

Define the scope and objectives of the program;

Define business benefits anticipated to flow from the change outcomes;

Identify which benefits are considered strategic and align these with the Agency's Results and Services Plan;

Identify any potential risks associated with the achievement of the benefits; and

Analyse change and benefits impacts on key stakeholders.

Identifying and agreeing the outcomes/benefits:

Define the target business environment required to realise benefits, then;

Identify the change initiatives required to successfully execute the initiative;

Map the outcomes and benefits to the initiatives;

Define the intermediate and final outcomes required to realise the benefits; and

Ensure sponsorship buy-in and ownership of benefits.

For ideas on potential benefits split by category please see Appendix B

2.3.2 Tips

Please note the following suggestions:

Use workshops to engage with stakeholders. This will get everyone on “the same page” in terms of scope of the program, how the business change will occur, and how the benefits will be realised.

Be careful of interdependencies with other programs and claiming the same benefits. Clear understanding and definition of benefits will mitigate this risk.

“Negative” benefits should be considered. There may be outcomes that are a negative consequence of the program. These need to be managed.

Ensure resources with appropriate change management skills are available as business cases often lack adequate provision for these roles.

2.3.3 Techniques

Common techniques for completing the Understand phase are:

Listing Benefits;

Three Column Analysis;

Benefits Pathway; and

Value Mapping.

For more information on these techniques please see Appendix A

Page 14: Benefits Realisation Guideline 2011

Department of Finance and Services 14

Benefits Realisation Guideline

2.4 Plan Phase

The next step is to plan benefits realisation for the program. The Benefits Realisation Plan (BRP) documents in detail the intermediate and final outcomes/benefits identified during the Understand phase. This is performed in parallel with the development of the business case, and is a major contributor to the business case compilation.

The BRP is an important document as it specifies the size, timeframe, metrics, ownership and responsibility for each proposed benefit. These details are crucial in ensuring successful benefits realisation.

2.4.1 Steps

The following steps should be undertaken in the Plan phase:

Establish Benefits Realisation Governance:

Establish the Benefits Realisation Governance Framework that will apply to the program. This establishes who will be responsible for benefits realisation, the governance structures, processes, resources, information needs, etc.

Populate the Benefits Realisation Plan

Determine which benefits will be measured and specify these in the Preliminary Business Case. This will define success for the program;

Confirm the strategic link between the benefits identified and the Results and Services Plan (RSP);

Identify a business owner for each benefit;

Identify the baseline and target Key Performance Indicator (KPI)/measure for each benefit;

Identify and confirm timeframes and milestones for achievement of each benefit;

Define benefit realisation activities to be executed by the business;

Define risk mitigation strategies;

Consolidate and document the above into the BRP and obtain program sponsor/owner approval; and

Communicate to and engage stakeholders on the expected benefits of the program.

Inform the Business Case

Develop business case benefits based on the BRP.

For more detailed information on creating a Benefits Realisation Plan please refer to Appendix C

Page 15: Benefits Realisation Guideline 2011

Department of Finance and Services 15

Benefits Realisation Guideline

2.4.2 Tips

Please note the following suggestions:

Meet with front line staff to ascertain baseline metrics and level of buy in;

Delineate between the risks to the program benefits and project delivery;

All outcomes should be measurable. Measures for benefits can be either financial or non-financial;

Measure only selected outcomes. Focus on identifying the key outcomes that will clearly define success for the program in terms of benefits;

Be careful not to have too many measures. Select the key „markers‟ of success;

Select measures that will indicate success of this program specifically. For example, overall user satisfaction will be influenced by many initiatives and can be too broad a measure. Selecting specific questions from user satisfaction survey results will be more relevant.

Always look for existing measures for benefits. An agency may have an existing scorecard and performance reporting that identifies existing measures;

Include anecdotal informal indicators for success, they usually make great headlines; and

Consider „proxy‟ measures which will be closely linked to the outcome or benefit being measured, especially if it simplifies the measurement task.

Page 16: Benefits Realisation Guideline 2011

Department of Finance and Services 16

Benefits Realisation Guideline

2.5 Realise Phase

The Realise phase “takes the temperature" of how successfully the program outcomes are being achieved. A Benefits Register (BR) is the “tool” used to record and keep track of realising benefits set out in the plan.

The Realise phase continues over the entire life cycle of the program, and beyond ICT project closure. Strategic benefits are usually realised well beyond the program delivery life cycle. Benefits realisation process and governance continues beyond completion of program delivery. The program does not really end until the benefits have been realised.

2.5.1 Steps

Once the Benefits Realisation Plan has been agreed the following steps in the Realise phase should be undertaken:

Establish the Benefits Register:

Establish the benefits tracking regime and mechanisms outlined in the BPR;

Register all outcomes/benefits selected for measurement during the Plan phase into the Benefits Register populating the agreed key information; and

Ensure all business benefits owners have signed off their allocated outcomes / benefits.

Update the Benefits Register:

Identify from the Register the frequency and dates for measurement of outcomes/benefits;

Facilitate the benefits realisation review sessions with outcome/benefits owners and other stakeholders. Identify and address issues that may be inhibiting the realisation of benefits; and

Collect, collate and record the actual measurements for the benefits in the Benefits Register.

Update the Benefits deliverables:

Validate that the outcomes/benefits are still valid and achievable;

Consider program progress and external factors that may impact the program and its outcomes with the appropriate stakeholders;

Assess if there are outcomes/benefits that need to be deleted;

Capture emerging benefits of the program. Identify, describe and justify why they might be included as part of benefits realisation for the program; and

Update the Benefits Realisation Plan and Benefits Register with all changes identified and agreed with the stakeholders.

Page 17: Benefits Realisation Guideline 2011

Department of Finance and Services 17

Benefits Realisation Guideline

2.5.2 Key Realisation Information

The Benefits Register should contain the following key information:

Outcome/Benefit name

Outcome/Benefit description

Measurement metric – how progress will be tracked

Measurement source – where the measurement information will come from

Current baseline measurement – including date taken

Targeted measure – expected result

Target measure date – day the expected result is to be realised

Outcome/Benefit owner

First tracking date – day tracking of the outcome/benefit began

Last review date – day the status was last reviewed

Next review date

Status commentary – comments regarding the latest review including any actions taken

Action to be taken

For an example Benefits Register template, please refer to Appendix D

2.5.3 Tips

Please note the following suggestions:

Ensure all measurement and review activities are undertaken on a formalised basis, with regular formal meetings established.

To effectively understand benefit realisation progress and future realisation activities required, face to face conversations are important to gain a shared understanding of the current situation and actions required.

Capture any anecdotal “benefits” that arise from stakeholder discussions. Anecdotal items tend to be personal experiences of users, and therefore add considerable credibility to the success of a program. Consider formalising anecdotal benefits in the benefits processes (where practicable).

Recognise that benefits are dynamic and can change during the lifecycle of a program. Be alert for outcomes/benefits that need to be deleted if they are no longer relevant/achievable, consider the impact on the business case and update if required.

Incorporate any new emerging benefits, consider the impact on the business case and update if required.

Page 18: Benefits Realisation Guideline 2011

Department of Finance and Services 18

Benefits Realisation Guideline

2.6 Report Phase

The final phase in Benefits Realisation is reporting of achievement against target. The monitoring, reporting and escalation of actual vs. targeted performance is undertaken by the benefits reporting function. It informs progress and corrective actions required.

Benefits Reporting is conducted when benefits start to be realised and measured. It is a continuous process that commences as soon as business change starts to be delivered. The focus early in the program life will be on reporting progress in achieving intermediary outcomes of the program e.g. new capabilities successfully delivered, change outcomes achieved, etc.

In the post implementation phase, reporting should continue beyond program closure. The focus is on the achievement of the desired business and strategic benefits, which are often realised after the program has closed.

2.6.1 Steps

The key steps in reporting outcomes/benefits are as follows:

Analyse the benefits:

Support and conduct measurement activities;

Record results in the Benefits Register against baseline and targets;

Analyse the Benefits Register and extract exception data. Make observations as to progress in realising benefits;

Assess benefits realisation effectiveness;

Seek explanation for deviation from targets. Discuss and collect suggested corrective actions with program manager and outcome/benefits owners. Corrective actions may involve further investment in the program and will need to be formally approved; and

Compile and document lessons and actions taken.

Report the results

Promptly escalate significant variations and suggested corrective actions with stakeholders;

Obtain approval of corrective action; and

Submit regular reports to stakeholders as per agreed schedule

Ensure corrective actions are implemented.

Throughout the process, review the benefits realisation plan, benefits register and business case and update if required.

2.6.2 Tips

Significant corrective actions may involve significant changes in the program scope and budget. Formal approval is required for any changes to program scope and budget.

Page 19: Benefits Realisation Guideline 2011

Department of Finance and Services 19

Benefits Realisation Guideline

2.6.3 Reporting Implications for Whole-of-Government Programs

These Guidelines are intended to apply equally to agency, cluster and/or whole-of-government programs. Whole-of-government programs include:

Large ICT enabled business change programs; and

Reform programs.

Whole-of-Government programs need to understand, plan, realise and report benefits at agency and aggregated whole-of-government levels. Having a consistent approach to the benefits realisation will enable government to have:

A common understanding of the outcomes/benefits to be delivered; and

Reporting in a standard format.

Central agencies will have the opportunity to inform agencies of their reporting requirements based on the consistent approach in these Guidelines.

2.6.4 Reporting Contents

The figure below provides an example of benefits reporting in a Balanced Scorecard format. This is one way of reporting the benefits, however the specific format of the report will depend on the specific program, agency requirements and alignment to Whole-of-Government guidelines.

Figure 5 - Example Report using Balanced Scorecard Format

Development, EmployeeDevelopment, Employee(are we increasing our capabilities, focusing on key value-added areas

and supporting growth?)

CS employee turnover

% of internal CS employees

% of CS budget devoted to internal employees

Training days per CS employee per year

CS spend on new IT investments vs. ongoing ops and

maintenance

Internal ProcessesInternal Processes(are our processes effective, efficient, and well controlled?)

% Projects Complete on Time/Budget

Defect rate

Tickets/change requests handled/period

% of enterprise process defects due to CS

Customer ServiceCustomer Service(are we meeting our customer‟s needs?)

% satisfied customers

Avg. # of inbound calls per service desk analyst per month

Avg. % first service desk call contact resolution

% strategic project begun without predefined, compelling business

cases

Financial Financial (is the cost/value of CS function managed appropriately?)

CS spend as % of company‟s revenue

CS operating budget as a % of revenue

CS capital budget as % of revenue

Adherence to Fiscal Plan/Budget

Development, EmployeeDevelopment, Employee(are we increasing our capabilities, focusing on key value-added areas

and supporting growth?)

CS employee turnover

% of internal CS employees

% of CS budget devoted to internal employees

Training days per CS employee per year

CS spend on new IT investments vs. ongoing ops and

maintenance

Internal ProcessesInternal Processes(are our processes effective, efficient, and well controlled?)

% Projects Complete on Time/Budget

Defect rate

Tickets/change requests handled/period

% of enterprise process defects due to CS

Customer ServiceCustomer Service(are we meeting our customer‟s needs?)

% satisfied customers

Avg. # of inbound calls per service desk analyst per month

Avg. % first service desk call contact resolution

% strategic project begun without predefined, compelling business

cases

Financial Financial (is the cost/value of CS function managed appropriately?)

CS spend as % of company‟s revenue

CS operating budget as a % of revenue

CS capital budget as % of revenue

Adherence to Fiscal Plan/Budget

Page 20: Benefits Realisation Guideline 2011

Department of Finance and Services 20

Benefits Realisation Guideline

An extract from the Benefits Register is shown in the figure below. Commentary on benefits including observations, variations and corrective actions and lessons learnt support reporting.

Figure 6 - Example Report using Benefits Register Extract

The figure below is an example of the outcomes/benefits set out in a dashboard format, showing level of achievement.

Figure 7 - Example Report using Outcomes Dashboard Format

Benefits Report

Project Name: xyz project Reporting Period:

Version: 0.01 Prepared by:

Variance Explanation Action Outcome ID

Outcome Description Measure Name

Current Total Cost of Operations

-10,000 High level of staff sick days this period provide vaccination facility

# or reams of paper consumed

25 - -

ex - 101 This is an example outcome.

Page 21: Benefits Realisation Guideline 2011

Department of Finance and Services 21

Benefits Realisation Guideline

2.7 Roles and Responsibilities in Benefits Realisation

A “RACI” (Responsible, Accountable, Consulted, Informed) table is used to define the roles involved and their level of accountability or participation in an activity. The table below has been used to define the activities across the understanding, plan, realise and report phases, the relevant roles and whether they are:

Responsible: this role is responsible for achieving the result of the activity;

Accountable: this role will be held accountable for the result of the activity;

Consulted: this role will be consulted during or in order to agree the result for that activity; or

Informed: this role will be informed of progress and/or the outcome of the activity.

Benefits Realisation Phase

High level Activity / Step

Program Sponsor

Program Manager

Outcome/ Benefits Owner

Benefits Realisation

Manager

Program Mgt Office

Understand Obtain Business Context

A R R C I

Identify and Agree Outcomes/Benefits

A R R C I

Define and Agree Program Scope and Objectives

A R C I I

Define Business Changes Required to Enable Benefits

A R C I I

Inform Business Case Development

A R C I I

Plan Establish Benefits Realisation Governance

A C C R C

Populate Benefits Realisation Plan

I C C R A

Inform Business Case Refinement

C C I R A

Obtain BRP Sign Off

C C I R A

Realise Establish Benefits Register

A I I R C

Page 22: Benefits Realisation Guideline 2011

Department of Finance and Services 22

Benefits Realisation Guideline

Benefits Realisation Phase

High level Activity / Step

Program Sponsor

Program Manager

Outcome/ Benefits Owner

Benefits Realisation

Manager

Program Mgt Office

Execute Benefit Realisation Activities

A R R C I

Establish Benefit Measurement

A C R R I

Update Benefits Register

A C C R C

Update Benefits Realisation Deliverables

A I I R C

Obtain Benefit Deliverables Sign Off

A I I R C

Report Measure Benefits A C R R I

Analyse Benefit Realisation

A C C R C

Report Benefit Realisation

A C C R C

Decide Corrective Action

A R C C I

Implement Corrective Action

A R C C I

Update Benefit Deliverables

I I I R A

Table 2 - RACI Table for Key Benefit Realisation Activities

Page 23: Benefits Realisation Guideline 2011

Department of Finance and Services 23

Benefits Realisation Guideline

3 Case Study 1 - Government Licensing Service

Program Description

Implementation of the Government Licensing Service (GLS) at the NSW Department of Industry and Investment, formerly Department of Primary Industries (DPI), was undertaken to improve the service of issuing fishing licences, while increasing the financial efficiency of the Agency.

Historically, licensing was not available online and licences were issued as one off (fixed term) paper licences without the option of renewal. The introduction of the GLS resulted in the introduction of plastic card fishing licences, with ability to renew at the time of expiry.

The program was completed over a five month period commencing in September 2008.

Agency Approach

GLS is a whole of government program spanning many different agencies. DPI had already been identified as a candidate for a GLS implementation and as such a number of the benefits attributed to GLS were applicable to DPI. DPI worked closely with the GLS team to submit a "Scoping Document and Process Improvement Plan", a summarised business case that asked individual agencies to analyse their fit relative to the generic GLS functions and expected benefits. This document included the following sections:

GLS features and benefits relevant for DPI;

Identification of process improvement for DPI and comparison to GLS estimates;

Impact on service delivery, licensing process costs, licensing fee structure and revenue;

Implementation constraints and risks, together with mitigation strategies;

KPIs that will form benchmarks to measure achievement of the program objectives;

Communications plan to gain internal and external stakeholder endorsement;

Issues relating to resources and skills required for implementation; and

Project plan, including work streams, milestones and responsibilities.

Once the plan was accepted, it then formed the primary document for governance of the GLS implementation at DPI. This plan was then actioned under the supervision of the GLS Program‟s governance body. In order, the structure was as follows:

Program Board - The highest decision making group, provided strategic guidance for the program and adjudicated issues not resolved by the Program Executive Council.

Program Executive Council - Operational guidance and decision making. Assisted with achieving program objectives as efficiently as possible.

Agency Steering Committee - Agency level decision making. Provided direction for achieving overall objectives and reported to the council on progress, risks and issues.

User Group - Managed common business processes and their requirements across the agencies. Responsible for user acceptance testing.

Project Team - Managed change initiatives within the Agency. Escalated project risks and issues.

Page 24: Benefits Realisation Guideline 2011

Department of Finance and Services 24

Benefits Realisation Guideline

Benefits Realisation

Benefits were measured at program commencement, completion and one year following completion. The Benefits Register was used to track program achievements against objectives. This process was performed twice during the project implementation and continued post completion. Results were reported to and actioned by the Governance Body.

GLS implementation was highly successful with benefits realised across three areas:

1. Financial

Increased revenue by 15% in the first year

Maintained recurrent costs at 10% of revenues collected

Leveraged existing printing capability for plastic licences

2. Environmental

Increased revenues collected were used to increase recreational fishing stocks

Decreased equipment power usage by 80% through sharing across agencies

Decreased required storage and paper usage by switching from paper to plastic

3. Social

Created 24/7 access to licensing services online

Decreased training and compliance costs through online access for Fisheries Officers

Implemented plastic cards which are more practical than paper in wet pockets

Created licence renewal capability, rather than replacing on expiry

Lessons Learnt

Governance

Early establishment of agency governance and project team is essential;

Nominate a single point of day-to-day accountability (project leader) and primary point of contact for interdependent programs to avoid conflicting decisions; and

Document and agree a detailed project plan and submit it to the appropriate governing body. Include resource requirements and dependencies, accounting for specific agency factors e.g. seasonal peaks.

Process

Training of agency staff should occur as the scope is confirmed. More training should be undertaken prior to user acceptance testing;

Allocate sufficient resources early on for data cleansing and mapping/conversion since this has significant impact on business process and the information available;

Maintain a single issues list and ensure all matters are closed out; and

Actively participate in any post implementation review process.

Change Management

Prepare a Change Management Plan to transform business processes, undertake legislative change and improve forms/correspondence;

Maintain regular communication with business users and customers;

Reuse/adapt resources from other agencies e.g. training materials; and

Account for initial drop in productivity due to tighter controls and user acceptance.

Page 25: Benefits Realisation Guideline 2011

Department of Finance and Services 25

Benefits Realisation Guideline

4 Case Study 2 – Electronic Medical Records

Program Description

The objective of the program was to replace traditional paper medical records with an electronic record throughout all major hospitals in NSW. Though this was a complex and significant program, NSW Health anticipated numerous long term benefits including patient safety, efficient use of resources and better access to services. The business case went through a number of submissions for funding over an eight year period. The final business case matched strategic health priorities in Emergency Departments and Operating Theatres together with a concurrent program addressing clinical redesign practices in these areas. The implementation approach was phased to take into account funding limitations and the change management required for over 70,000 clinicians.

“eMR” (Electronic Medical Records) captures information generated by clinicians in Emergency Departments, Operating Theatres and electronic orders for tests and associated results. It brings together patient clinical data from disparate information systems within a hospital (e.g. emergency, pathology, radiology, pharmacy and dietary) with other clinical data (e.g. diagnosis, allergies, alerts, clinical history, etc) to assist Clinicians to make informed decisions about managing a patient‟s care. It is linked to information sources that are evidence based to provide a powerful clinical decision support tool. It includes a series of „built-in‟ ordering rules, protocols, prompts and alerts that provide a standard clinical work flow for patient care and treatment, including:

Electronic test ordering and integration to Pathology and Radiology;

Decision support during the ordering process to provide key clinical information;

Duplicate orders checking;

Electronic results, abnormal results and verification process;

Emergency department electronic documentation and patient tracking;

Operating Theatre scheduling and electronic documentation;

Clinical assessments on admission including past and present medical history;

Discharge referrals and electronic notification to GPs;

Reminders when key data has been omitted;

The ability to share records across hospitals in the same area; and

Reporting facilities that support clinical audit, resource management, research and development, education and training.

Agency Approach

In order to ensure that the eMR system was implemented consistently and that all benefits were effectively tracked and managed, NSW Health developed the eMR Generic Benefits Realisation Framework (the Framework). The Framework was customised by each AHS to suit their individual needs and process reform efforts.

Whilst the business case articulated the strategic benefits of a complete eMR implementation, the revision to the business case divided the Program into phases. As a result, it was necessary to develop a more detailed measurement plan with a focus on the

intermediate benefits. Early in the life of the business case, a Benefits Pathway was used to highlight these intermediate benefits (refer to Appendix A for details on these techniques).

Page 26: Benefits Realisation Guideline 2011

Department of Finance and Services 26

Benefits Realisation Guideline

By associating accountabilities with initiatives and activities, the Benefits Pathway ensured that each stakeholder was unambiguously aware of their contribution to the achievement of the outcomes. The model was a graphical representation of these initiatives, activities, paths risks, and desired outcomes. A short version was developed for project teams and communication purposes. This summarised on one page the key business problems, critical business change and what has to be stopped in order for the benefits to be achieved.

Lessons Learnt

Business Case

Long delays in funding resulted in turnover of key staff and sponsors, as a result engagement of new sponsors and validation of benefits was critical;

The business case recognised the significant business change for clinicians in using a computer to document rather than the convenience of paper and provided funding for organisational change management as part of the solution;

Phasing of the program over a number of years (possibly 10 years) requires that the vision and expectations of each phase is properly managed. This mitigates the risk that clinicians expect that the current phase will deliver everything;

While the business case provided high level benefit targets it was necessary to adjust the benefit expectation to local conditions, for example reflecting the different environments of rural hospitals versus metropolitan hospitals;

Divide benefits into timeframes. Some of the benefits such as better decisions take time to realise due to the development of new reports and skills in extracting data; and

A number of the benefits were being impacted by other projects. Benefits Pathways and similar techniques help identify those contributions.

During Implementation

For benefits to be accepted and realistic, all hospitals were engaged to measure and report on the benefits at a local level;

A lack of information in existing systems required benefits data to be collected manually. Photographs were also used to bring the realisation process to life;

Satisfaction surveys used for qualitative measures uncovered new problems and potentials benefits;

“What‟s in it for me” (WIIFM) was used in conversations with stakeholders to explore potential value. It keeps the vision alive and provides a practical picture of the future;

Listening and observing „on the ground‟ provides real opportunities to spot new benefits; and

Sharing stories of quick wins and improvements on the baseline is a great way to build and maintain support for the program.

Post Implementation

Evidence was used with several external stakeholders to help them understand in practical terms the benefits realised, here simplicity was important;

Transition to Business as Usual (BAU) and ownership of on-going process improvement is critical. Typically the steering committee will retire after go-live. A governance body that maintains continuity between programs is the best way to manage this; and

Important to reserve funds and resources for post implementation User Groups to implement initiatives and the change required to realise the benefits.

Page 27: Benefits Realisation Guideline 2011

Department of Finance and Services 27

Benefits Realisation Guideline

5 Appendix A – Articulating Benefits and Understanding how they are Delivered

5.1 What is a Benefit?

A benefit is a business outcome that delivers value to the organisation. Benefits include both financial (e.g. decreased cost of service) and non-financial (e.g. increased user satisfaction with agency services). An ICT enabled investment aims to deliver capabilities that can be exploited to enable business outcomes. Benefits deliver value to the agency when they contribute to achieving their strategic goals and objectives.

5.2 Types of Outcomes and Benefits

For ICT enabled investments, the expected business benefits should be assessed. Outcomes will broadly fit into:

Citizen benefits, usually represented from a social perspective, including:

Improved Service Delivery;

Decreased cost to citizens (time and effort; price of service);

Increased Business and Work opportunities (improved processes; reduced cost of servicing);

Increased community skills and knowledge (intuitive; easy to find information); or

More open government (policy familiarity; more transparency).

Agency and whole of government benefits, are usually represented with a strong financial perspective, including:

Decreased costs; or

Increased revenues.

Refer to Appendix B for illustrative outcomes, benefits and measures.

5.3 Understanding Outcomes and Benefits, and how they are derived

Understanding what and where the outcomes and benefits are can be ascertained by several means. Suggestions include:

Interviews/workshops with stakeholders to obtain expectations;

Reviewing other ideas papers/value assessments/business cases undertaken by the agency and beyond; and

Ascertaining best practice.

Page 28: Benefits Realisation Guideline 2011

Department of Finance and Services 28

Benefits Realisation Guideline

Workshops are a technique to draw key stakeholders together to discuss and validate the answers to the following questions. The answers form the basis for understanding outcomes and benefits and in turn, the benefits planning:

Why are we doing the program? What are the business drivers?

What are we going to get out of it? What are the strategic outcomes of the program?

What are the measurable benefits?

When do we obtain the benefits?

Who owns the outcomes? Who is the Outcome Owner and do they accept it?

Who is accountable for delivering benefits?

What is the mechanism that is required to achieve benefits?

To articulate the benefits for an ICT enabled investment, this Guideline recommends using the techniques detailed below. These 3 techniques represent escalating levels of sophistication and detail. The technique selected will depend on the time, resources and availability of information.

5.3.1 Technique 1: Listing Benefits

This is the “traditional” approach to identifying expected benefits from an investment, usually listing benefits by stakeholders. An example:

Stakeholders / Others

Benefits

Citizens Increased accessibility 24/7

Simplification of the process

Significantly reduced time to process transactions

Agency Resource savings when dealing with a growing market with peak load periods

Increased data integrity

Increased quality of reporting

Created a technical base to further expand online services

Page 29: Benefits Realisation Guideline 2011

Department of Finance and Services 29

Benefits Realisation Guideline

5.3.2 Technique 2: Three Column Analysis and Benefits Pathway

Another simple technique is the three column analysis. The analysis involves brainstorming answers to each of the four sections below and putting them into lists. A benefits pathway can be developed to graphically help facilitate the benefits understanding in one page. It should provide a representation of how the current business problems should be changed to achieve the desired benefits.

This technique is used by NSW Health to understand the contribution of changes needed to be made to the desired benefits (outcomes). This ensures a discussion with relevant stakeholders to understand and agree the current business problem, what has to change (and what must be stopped) and the benefits.

Page 30: Benefits Realisation Guideline 2011

Department of Finance and Services 30

Benefits Realisation Guideline

The figure below sets out a Benefits Pathway for a NSW Health change program.

Figure 8 - Example Benefits Pathway

Page 31: Benefits Realisation Guideline 2011

Department of Finance and Services 31

Benefits Realisation Guideline

5.3.3 Technique 3: Value Map

Similar to the Benefits Pathway approach, the Value Map is a graphical technique that helps represent how benefits will be realised. It draws the link between the initiatives (or projects) and the capabilities they deliver, use of that capability to change the way business is done, and contribution to strategic outcomes (or benefits).

The purpose and technique of the Value Map is similar to the Office of Government Commerce‟s Benefits Maps, and Cranfield‟s Benefits Dependency Models.

A Value Map has 4 elements (initiative, assumption, outcome and contribution), together becoming a clear way to represent the full scope of effort of an investment and specifically how the benefits will be realised.

Outcomes

An outcome is a „change of state‟ resulting from the contribution of initiatives and/or other outcomes. It includes intermediate outcomes, such as the delivery of a capability and final outcomes such as contribution to strategic objectives. In a Value Map, the circle represents an outcome, and is described to support measurement e.g. Increased patient safety.

Intermediate outcomes are capabilities created or change impacts achieved and they demonstrate the path to realise benefits. They articulate the specific changes and outcomes required to achieve the objectives of the investment, dispelling „miracle thinking‟. The figure below sets out a simplified Value Map.

Figure 9 - Simplified Value Map

Desired Business

Outcomes

Projects of the

Program

Capability

Outcomes

Business Change

Outcomes

Strategic

Outcomes

I-1

O-33

A-3

Legend for a Value Map

Initiative

Outcome

Assumption

Contribution

Implement

Patient Admin

software and

necessary

hardware

Created

enabling

technology for

clinical

Documentation

Implement new

clinician roles

and

responsibilities

Increased patient

safety

(Decreased

adverse events)

Increased Multi-

discipline team

information

sharing and

communications.

Decreased use of

paper records

Develop and

implement new

clinical

processes,

policies

Created new

best practice

for clinical

delivery

Created new

behaviours with

staff to drive

clinical

docucmentation

End OutcomesIntermediate OutcomesInitiatives

Assumption

that clinicians

will use the

new processes

Increased

information

based clinical

decision making.

Decreased

variations in

clinical practice

Page 32: Benefits Realisation Guideline 2011

Department of Finance and Services 32

Benefits Realisation Guideline

Initiatives

An initiative is the component project within a program – where the money is invested to deliver or support the implementation of a new capability. An initiative is represented by a square. The label describes the action e.g. „Implement new forecasting system‟ or ‘Deliver training to employees‟.

Contribution

A contribution is the role or part one component of a Value Map plays in the realisation of another. A contribution is represented as an arrow between initiatives and outcomes. Outcomes can also contribute to other outcomes.

Assumption

An assumption is an indication of uncertainty we have about a component in a Value Map. An assumption is represented in the model as a hexagon. Assumptions represent risks that must be either managed (or mitigated, e.g. by developing another initiative).

Developing a Value Map

Tips for the development of a Value Map:

The benefit of developing a Value Map is the conversations that it will facilitate and the clarity of logic that it forces. Development of the Value Map is where the benefit of the technique is derived; therefore it needs to be produced in consultation with key stakeholders.

Use workshop techniques (including the 3 column analysis described above) to facilitate discussion and obtain agreement with the stakeholders who will have knowledge of the outcomes, initiatives and assumptions surrounding the program.

Develop a “straw man” Value Map for validation with key stakeholders. Use the graphical image as an artefact to have a conversation.

Use the Value Map as the focus with stakeholders to ensure:

o All the stakeholders understand the scope, contribution and outcomes;

o All the risks/assumptions are out in the open;

o All the necessary initiatives have been identified; and

o All the aspects of people, process, organisation, technology, citizens, partners and suppliers have been considered. All are necessary to deliver business benefits.

Page 33: Benefits Realisation Guideline 2011

Department of Services, Technology & Administration 33

Benefits Realisation Guideline

The figure below sets out a sample Value Map for an Agency‟s Supply Chain Management ICT Enabled Change Investment.

Figure 10 - Sample Value Map

Page 34: Benefits Realisation Guideline 2011

Department of Finance and Services 34

Benefits Realisation Guideline

6 Appendix B - Potential Benefits Listed by Category

6.1 Increased Effectiveness

Community Expectation for Improved Service

It may be possible to quantify benefits in terms of time saved. If so, quantitative performance indicators and measures must be defined to demonstrate that benefits have been achieved. Benchmarking may be undertaken to achieve this, otherwise, it will be necessary to define qualitative indicators that can be assessed through methods such as customer satisfaction surveys.

Wider Range of Services

An investment in ICT to support a wider range of services must demonstrate that there is a demand for the additional services. It must identify how the service will contribute to the achievement of Government outcomes, and benefit the community in general. An additional tangible benefit to the agency may be in terms of cost avoidance.

Tailored Services

An agency providing direct service to the public may propose an ICT investment to enable it to provide a better, customer-focused service through tailoring its service delivery. Benefits would need to be related to Government outcomes, the Results and Services Plan and community benefits to the agency.

Geographic Access to Services

As extended hours of operation and maintaining remote location operations with traditional methods are expensive, an investment in an ICT solution may be efficient and effective. A key benefit is increased community services at an affordable cost. The cost avoided in providing equivalent services through traditional means is a valid tangible benefit that can and must be quantified. This can include delivering increased services with the same number of resources, in which case the service improvements should be defined.

New Legislation or Regulations Introduced

ICT investments are, at times, driven by new legislation or changes to existing legislation or regulations. Even though the development of systems may be seen as a mandatory result of the Government policy, it will still be necessary to identify the benefits associated with the use of ICT. This will ensure that the most appropriate and cost-effective solution is selected and that there are performance measures available against which the success of the implementation can be measured. The benefits can include decreased cost of service or increased service delivery with existing resources and budget.

Equity of Access Policies

For ICT investments which are intended to address equity of access issues it will be necessary to align them with current Government policies and desired program outcomes. As there may be limited overall benefit to the agency from such investments, it will be necessary to develop performance indicators related to the section of the community intended to benefit from the implementation of the system.

Page 35: Benefits Realisation Guideline 2011

Department of Finance and Services 35

Benefits Realisation Guideline

6.2 Increased Efficiency

Decreased Real Operating Budget

A reduction in annual operating budget may drive an agency to reduce the number of staff, close or otherwise limit service locations or alter the process by which services are delivered. An investment in ICT may allow these reductions to be achieved without a commensurate loss of service quality. The benefits from this are direct and realised through the ability to sustain budget reductions whilst maintaining an acceptable service level. Current operating costs (and performance indicators) need to be documented, as well as revised operating costs to show savings.

Competition for Resources

Competition for scarce resources may mean that an agency has to invest in systems which reduce the resources required to continue to operate one or more business processes. The benefit here is reduced operating costs in the business processes. This needs to be demonstrated by documenting current operating costs and performance indicators and predicted future operating costs and performance indicators. The realisation of the benefit is measured through reduced operating costs and/or maintained or improved performance indicators in the operational area supported by the system.

Demand Growing Faster Than Resources

If demand for a service is growing faster than the available resources to support the service it may be necessary to invest in ICT to allow greater levels of service delivery within constrained resources. The benefit in this instance is basically one of avoided cost. The investment in ICT is less than the avoided cost of making an alternative investment in other less effective technologies and / or greater staff numbers. The benefits can also include increased service delivery with existing resources and budget.

Changes in Technology Price/Performance

In order to identify the benefits of replacing equipment, it is necessary to document all costs of current equipment, costs of proposed equipment and the savings to be derived. Then it will be necessary to demonstrate how these savings will be realised. For example, will the savings be realised as a reduced recurrent budget, by repaying a loan for the original investment, or by increasing capacity to support extra services within the current budget.

6.3 Enabling

Infrastructure to Support Multiple Projects

An agency may need to invest in a replacement or major upgrade of its ICT infrastructure. There may not be a single project or business initiative which can be identified as the source of benefits to justify the investment. However, there could be a series of projects, related to specific business initiatives, which are relying on the development of the infrastructure to proceed. In this case there must be a clear strategic and business need for the ICT investment. The Asset Strategy and Total Asset Management Plan must also support the proposal. The benefits must be drawn from the specific business programs that will rely on the investment.

Support for Business Process Re-engineering

The benefits from Business Process Reengineering (BPR) are significant and generally include order of magnitude cost reductions. The identification of the tangible benefits should be clearly documented in terms of staff savings, operational cost reductions or other quantifiable performance measures.

Page 36: Benefits Realisation Guideline 2011

Department of Finance and Services 36

Benefits Realisation Guideline

6.4 Survival

Breakdown of Hardware or Software Supporting Core Business Services

There must be a very good case made to support the argument that the systems are crucial to continued operation and that breakdown is imminent if it has not already occurred. Replacement of such systems must also be consistent with the Asset Strategy and Total Asset Management Plan. In the case where breakdowns have occurred, a tangible benefit may arise from the minimisation of costs associated with operating alternate procedures (e.g., running systems on a commercial bureau at commercial rates) or repairs and ongoing maintenance costs.

Loss of Support for Hardware/Software on Which Core Business Processes Rely

The benefit of investing in changes of an ICT system in this instance is a reduction in business risk. Tangible benefits may be identified in terms of the possible costs associated with business disruption. These benefits will need to be appropriately adjusted to account for the probability of particular failure scenarios occurring, including any notice in writing from suppliers, vendors or maintenance providers, and the cost of disruption to service delivery.

6.5 Research and Development

Emerging Technology

The benefit deriving from an investment in emerging technology would need to take into account the potential benefits from adoption of the technology, the risks involved with early adoption and the costs related to delayed adoption. The benefits must still be consistent with and support the ICT Strategic Plan and strategic and business objectives and Results and Services Plan outcomes. Benefits need to be measured in terms of the business benefits (not technology outcomes).

Community Expectations

There may be community expectations that services will be delivered via new technologies similar to private sector services. Where pressure is exerted to adopt advanced ICT solutions in the public sector, it may be appropriate to undertake a pilot project. The pilot may be used to prove the concept, develop appropriate relationships with suppliers, and develop the expertise required for wider adoption. The benefits need to be treated in the same way as for piloting an emerging technology.

Changing Operational Environment

As technology evolves, an agency may find itself in a situation where it wishes to explore the benefits of moving from an older technology with a limited horizon to a newer, more stable technology. The agency, however, may be unwilling to commit to the change without first trialling the new environment on a minor application. It may not be possible to justify the costs associated with the move to the new environment solely on the benefits derived from the minor application. In these circumstances it may be possible to justify the investment on the basis of the Research and Development aspects of the pilot project. This would need to be clearly stated in terms of the goals of the program and/or project and the business benefits delivered.

Page 37: Benefits Realisation Guideline 2011

Department of Finance and Services 37

Benefits Realisation Guideline

7 Appendix C – Template Benefits Realisation Plan

Benefits Realisation Plan

For

<Program Name>

Page 38: Benefits Realisation Guideline 2011

Department of Finance and Services 38

Benefits Realisation Guideline

Document Ownership Information

Document Owner

Document Preparation

Document Confidentiality

Document Name and Version Control (Circulated versions only)

Document Name & Location

Version Date Author Changes Included

Distribution List

Name Title, Department

Page 39: Benefits Realisation Guideline 2011

Department of Finance and Services 39

Benefits Realisation Guideline

Document Purpose

For the <Insert Program Name> program, this document has two purposes:

1. To define the governance framework that will provide oversight for the whole benefits realisation life cycle; and

2. The plan to deliver the identified and agreed benefits

The approach to Benefits Realisation outlined in this Plan is based on the following fundamentals:

Benefits are net positive changes in outcomes. The program aims to deliver a number of outcomes (desired changes in state; being either intermediary or strategic outcomes) a number of which are identified as being the “benefits” to the organisation.

ICT is an enabler for business benefits. ICT provides technology capabilities, but is insufficient by itself to deliver business benefits. Technology enables changes to the way people work, with new processes and new ways, and this needs to be managed as a program of business change.

Benefits are not automatic. Benefits realisation is beyond project management, and requires active monitoring of the delivery of projects, the effectiveness of change and the achievement of outcomes.

Change management must be integrated. Benefits can not be delivered without business change. So there must be a strong linkage between change management and benefits realisation.

Benefits are long term. Benefits will flow over a period of time as people learn to use the new technology and systems and integrate it into business processes. Benefits realisation is a long-term process extending beyond the life of component projects.

Benefits will change. Benefits rarely occur as planned and the organisation has to establish a process for actively monitoring the benefits and actively managing the realisation of benefits, continuous process over the life of a program.

Benefits Realisation requires governance. The benefits realisation process will inform the program business case and program plan, and this needs to be synchronised. Benefits processes must be linked with program governance.

Defining the Benefits Realisation Governance Framework

For benefits realisation to be successful there must be established and maintained foundational governance structures, processes and responsibilities to ensure that the benefits will be managed though the whole life cycle of investment.

This foundational benefits realisation governance must be developed with a practical eye as to the size of the investment (both its spend and potential benefits), and the capability of the agency‟s business sponsor and staff to effectively manage the benefits realisation process.

Page 40: Benefits Realisation Guideline 2011

Department of Finance and Services 40

Benefits Realisation Guideline

Purpose and Objective of the Benefits Realisation Plan

The Benefits Realisation Plan (BRP) is used to define the benefits of the overall program of work and responsibilities for their realisation, measurement and reporting.

The objective of the Benefits Realisation Plan is to ensure those involved in the implementation (and a wider audience as required) have:

A common understanding of the expected strategic outcomes of the program;

Identified the key implementation outcomes and secondary/intermediate outcomes, who will be accountable for the outcomes‟ benefits and how they will be measured;

Record which initiatives will be required to ensure the delivery of the expected outcomes, who will be accountable for their implementation and their completion timeframe;

Captured the detail of the overall program outcomes that can be referenced and broken into more detail in the individual project business cases; and

Identified key assumptions and risks around the delivery of the expected outcomes, the strategies that will be implemented to mitigate them and who will be accountable to implement those strategies.

The Benefits Realisation Plan includes high level information about the proposed types of benefits applicable for the key outcomes and where possible, it will also include detailed metrics, including targets, baselines and timelines for the benefits to be measured.

A diagrammatic view of the linkages and delivery of the outcomes from the successful implementation of the program is documented using the „Value Map‟ approach. Appendix A contains the Value Map for <Insert Program>, that has been prepared through broad stakeholder consultation and input.

A Benefit Register is contained in a separate document. This is brief documentation for each outcome on the Value Map. Where applicable, the benefit metric information will be recorded, but for the majority of outcomes that will not be tracked as part of the Benefit Realisation Plan, this is just a brief summary of the outcome.

Roles and Responsibilities for Benefits Realisation:

Identify who will be Accountable for the Benefits Realisation for this program.

Identify who will be Responsible for managing and undertaking the realisation of the benefits from this program.

Structure within which Benefits Realisation will be managed:

Identify and briefly explain the governance structure within which the Benefits Realisation function will reside (e.g. PMO, other governance bodies).

Benefits Realisation Processes to be used:

Identify the specific benefits realisation monitoring processes that will be used for this program.

Confirm at what aspects of the program life cycle these processes will be applied e.g. updating the business case periodically.

Page 41: Benefits Realisation Guideline 2011

Department of Finance and Services 41

Benefits Realisation Guideline

Resources and budget identified to undertake Benefits Realisation

Identify the (named) resources who will undertake the benefits realisation activities for this program.

Confirm these resources have sufficient time to complete the tasks and have the capability to undertake the tasks.

Are there other types of resources needed?

Confirm there is sufficient budget for these resources to undertake the tasks.

Assumptions, Issues and Constraints

Describe the assumptions, known issues and constraints associated with the realisation of the benefits.

Benefits Delivery Plan

This plan outlines for each key outcome (considered a benefit) of the program:

Baseline and target measurements to be achieved for each outcome (the benefit);

A description of how each benefit will be measured;

The expected delivery schedule for each benefit;

An overview of the monitoring capabilities required to measure each specified benefit, along with details explaining how each capability will be delivered;

An explanation of the risks that may threaten the achievement of each benefit and how the threat will be handled.

This section presents the documentation for each of the key outcomes and the metrics that may be used for measuring their success. Where appropriate, other outcomes from the Value Map, not deemed essential to measure, will be incorporated into a key outcome as an additional metric and labelled using both outcomes numbers.

It is not expected that all metrics will be measured, baselined and tracked. The summary of the outcomes in this BRP below sets out the outcomes that are recommended for tracking.

Please note the first draft of the BRP will not have some sections completed. These will be completed as part of the Benefits Realisation Process.

Complete this section for each key outcome and benefit identified.

Page 42: Benefits Realisation Guideline 2011

Department of Finance and Services 42

Benefits Realisation Guideline

[Key Outcome / Benefit #1 – Insert Benefit Name Here]

Outcome Summary

Objective: Outcome Name

Organisational Goal:

Organisational Goal/Metric this benefit contributes to

Description: A Brief description of the outcome (benefit) to be achieved.

Outcome Category: As per the Value Map legend for type/colours of the outcomes.

Incl. in Business Case?

Select from: Yes / No Will the outcome be documented in the business case?

Tracked Status?

Select from: Yes / No / Unsure Will the outcome be measured and tracked? The result of the metric assessment will be included in the business case.

Benefit Type:

Financial Status:

Select from: Financial / Non-Financial / Milestone

Financial: Can be translated into dollars, but may not be reflected in the current balance sheet.

Non-Financial: Provides a view of successful delivery of an outcome, but is not translated into financial metrics, e.g. customer satisfaction. This will also cover defined intermediate outcomes.

Milestone: An outcome that will be reflected in the program plan.

Continuity Status:

Select from: Lasting / Increasing / Once-Off

Lasting benefit: A benefit that is achieved early and continues, e.g., software maintenance fee no longer required

Increasing benefit: A benefit that develops further over time, e.g., customer adoption of new capabilities.

Once-Off Benefit: A benefit that only occurs once, e.g. a one off cost saving or milestone.

Page 43: Benefits Realisation Guideline 2011

Department of Finance and Services 43

Benefits Realisation Guideline

Measurement Detail and Capabilities

# Measurement Description Baseline Measure

Target Measure

Target Start Date

Frequency Target Finish Date

1 Description of measurement The

current state

The target state

Start measure when?

How often?

Finish measure when?

Outcome Realisation Capability and Measurability

Realisation: Major activities required to finalise and formalise the realisation of the outcome. This will be documented as part of the Benefit Realisation process.

Measurability: Specific tasks and infrastructure required to quantify and measure the metrics for this outcome.

Dependencies: Other outcomes and/or other projects that are linked to this outcome.

Roles and Responsibilities

Responsibility Name Title and Business Unit

Outcome Owner

Measurement of Outcome

Reporting of Outcome

Other

Page 44: Benefits Realisation Guideline 2011

Department of Finance and Services 44

Benefits Realisation Guideline

Monitoring Capabilities:

Outline the capabilities required, addressing the following:

What needs to be developed to get the measurement information?

Who will develop and implement the monitoring capability and how will it be developed and implemented (is this represented as a task in any of the projects/initiatives within the program)?

What (if any) cost is involved in providing the monitoring capability?

What actions need to be taken on a regular basis to provide the information?

Who will be responsible for these actions?

Risks

What factors could threaten the achievement of this outcome or benefit? Under what circumstances could these factors arise? What will be done to mitigate these risks?

Notes

Include dependencies and other notes here. Delete this section if not required.

Page 45: Benefits Realisation Guideline 2011

Department of Finance and Services 45

Benefits Realisation Guideline

8 Appendix D – Template Benefits Register

Attached below is a template Benefits Register. This tool will need to be tailored to the particular program and benefits to be tracked. Please see section 2.5.1 for detailed steps on how to complete this template.

GCIO Benefits Register.xls

Completion of the Benefits Plan in the Benefits Register template will automatically generate the following Benefits Report.

Figure 11 - Report generated by completion of Benefits Register

Benefits Report

Project Name: xyz project Reporting Period:

Version: 0.01 Prepared by:

Variance Explanation Action Outcome ID

Outcome Description Measure Name

Current Total Cost of Operations

-10,000 High level of staff sick days this period provide vaccination facility

# or reams of paper consumed

25 - -

ex - 101 This is an example outcome.

Page 46: Benefits Realisation Guideline 2011

Department of Finance and Services 46

Benefits Realisation Guideline

9 Appendix E – Suggested Further Reading

Bartlett, John , „Managing Programs of Business Change’, Project Manager Today Publications 1998, 3rd edition

John Ward and Elizabeth Daniel, „Benefits Management – Delivering Value from IS and IT Investments’ Cranfield, 2006

Murphy, Tony „Achieving Business Value from Technology’ Gartner 2002

Managing Successful Programs: Office of Government Commerce, UK web site.

Thorp, John, ‘The Information Paradox - Realizing the Business Benefits of Information Technology’, McGraw-Hill 1998, Revised 2003. The book can be downloaded from http://www.fujitsu.com/ca/en/news/publications/books/ip.html