Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association of America (CMAA)

Upload: wilfred-matthews

Post on 17-Jan-2016

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

Ben Jong Transportation Program Manager

Highway Program

LA Metro’sHighway Program

LA Metro’sHighway Program

May 29, 2014

Construction Management Association of America (CMAA)

Page 2: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

Highway ProjectsHighway Projects

2

Page 3: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

3Possible problem Major issue!On targetOK

State Route 710 NorthState Route 710 North

Construction CompleteConstruction CompleteCurrent

2029Current

2029Forecast

2029Forecast

2029

SCHEDULESCHEDULE

Alternatives Analysis Dec 2012Draft EIR/EIS Feb 2015Public Hearing Spring 2015Final EIR/EIS Fall 2016Record of Decision Fall 2016

Total Cost ($ mil.)Total Cost ($ mil.)

Current$780

Current$780

Forecast$2.6 – 5.4B*

Forecast$2.6 – 5.4B*

BUDGETBUDGET

Secured Funds: Measure R - $780MUnsecured Funds: $1.82B – $4.62B*Potential P3 Opportunity

!

* Denotes a range of cost for several higher cost alternatives

OK

Page 4: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

• Alternatives Analysis – completed in Dec. 2012• http://www.dot.ca.gov/dist07/resources/envdocs/docs/710s

tudy/

• Alternatives:– No Build– Transportation System Management/Transportation

Demand Management (TSM/TDM) – Bus Rapid Transit (BRT)– Light Rail Transit (LRT)– Freeway Tunnel

4

State Route 710 NorthState Route 710 North

Page 5: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

State Route 710 North Build State Route 710 North Build AlternativesAlternatives BRT LRT Freeway Tunnel*

5

Page 6: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

6Possible problem Major issue!On targetOK

Cost

Interstate 710 South EIR/EIS*Interstate 710 South EIR/EIS*

Construction CompleteConstruction CompleteCurrent

2028Current

2028Forecast

2028Forecast

2028

SCHEDULESCHEDULE

Draft REIR/REIS 2016 2016 Public Hearing 2016 2016 Final REIR/REIS 2017 2017 Record of Decision 2017 2017

Multiple Early Action Study Projects with various schedules

Total Cost ($ mil.)Total Cost ($ mil.)

Current$395

Current$395

Forecast$6.75B

Forecast$6.75B

BUDGETBUDGET

Secured Funds: Measure R - $395MUnsecured Funds: $6.36B – TBD*Potential P3 Opportunity

!

Begin Construction 2021 2021

*Some of these funds will be utilized for I-710 Early Action Projects

OK

Page 7: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

7Possible problem Major issue!On targetOK

I-710 Early Action ProjectsI-710 Early Action Projects

Total Cost ($ mil.)Total Cost ($ mil.)

Current$30.6

Current$30.6

Forecast$30.6

Forecast$30.6

BUDGETBUDGET

SCHEDULESCHEDULE

various (see below)

Completed 0 $ 000 N/AOngoing 1 $10,400 2014Future 6 $20,200 2018

TOTAL* 7 $30,600 2030

#APPR. PROJECTSBUDGET

(000’S) COMPLETION

*Multiple projects to be programmed with various schedules through 2030

Page 8: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

8Possible problem Major issue!On targetOK

Cost

High Desert Corridor (Environmental)High Desert Corridor (Environmental)

Total Cost ($ mil.)Total Cost ($ mil.)

Current$65

Current$65

Forecast$65

Forecast$65

BUDGETBUDGET

Funds include: STIP (GF), Measure R, Measure I, and federal earmarks• Scope includes Project Approval and Environmental Document (PA/ED) only

Environmental Document CompleteEnvironmental Document Complete

Current2015

Current2015

Forecast2015

Forecast2015

SCHEDULESCHEDULE

Draft ED CirculationPublic Hearing Final EDRecord of Decision

20142014Spring 2015Winter 2015

OK OK

Page 9: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

9Possible problem Major issue!On targetOK

Total Cost ($ mil.)Total Cost ($ mil.)

Forecast$600

Forecast$600

BUDGETBUDGET

Funds include: Measure R, Toll Revenues and SHOPP

OK

Construction CompleteConstruction CompleteForecast

2019Forecast

2019

SCHEDULESCHEDULE

RFQRFP

OK

Mid 2015 Late 2015

I-5 High Occupancy Vehicle/Toll Lane I-5 High Occupancy Vehicle/Toll Lane

Page 10: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

10Possible problem Major issue!On targetOK

Construction CompleteConstruction CompleteCurrent

2026Current

2026Forecast

2026Forecast

2026

SCHEDULESCHEDULEOK

• Multiple projects to be programmed with various schedules through 2030

• Completed Feasibility Study 2012

• Project Study Report 2013 - 2015

• Environmental Phase 2014-2019

Total Cost ($ mil.)Total Cost ($ mil.)

Current$590M*Current$590M*

Forecast$3.2 B*

Forecast$3.2 B*

BUDGETBUDGET

Secured Funds: Measure R - $590MUnsecured Funds: $ 2.6B

*Denotes current secure funding and not expected to cover Feasibility Study improvement needs. Project costs to be determined post Feasibility Study

I-605 Corridor “Hot Spot” I-605 Corridor “Hot Spot” InterchangesInterchanges

Page 11: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

1111Possible problem Major issue!On targetOK

Completed 1 $ 700 2014Ongoing 17 $ 33,278 2020Future 18 $ 26,366 2020

TOTAL 36 $60,344 2020

Measure R provides $170.0 Million over 30 years of which $60.3 Million has been programmed in the Subregion for FYs 2010-2020. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$60.3

Current$60.3

Forecast$170

Forecast$170

BUDGETBUDGET SCHEDULESCHEDULE

various (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

Arroyo Verdugo COG Measure R Operational Arroyo Verdugo COG Measure R Operational Improvements ProgramImprovements Program

Page 12: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

1212Possible problem Major issue!On targetOK

Completed 0 $ 0 N/AOngoing 12 $ 46,961 2018Future 9 $ 59,790 2020

TOTAL 21 $106,751 2020

Measure R provides $175.0 M over 30 years, $106.751 Million has been programmed for the Subregion by the Metro Board for FY’s 2010-17. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$106.75Current$106.75

Forecast$175

Forecast$175

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

COMPLETIONBUDGET

(000’S)#APPROVED PROJECTS

Las Virgenes/Malibu COG Measure R Operational Las Virgenes/Malibu COG Measure R Operational Improvements ProgramImprovements Program

Page 13: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

1313Possible problem Major issue!On targetOK

COG Admin/Development N/A $ 13,375 2020Contingency/Reserves N/A $ 15,500 2020Completed 6 $ 5,927 2014Ongoing 27 $ 135,422 2020Future 17 $ 65,469 2020

TOTAL 50 $ 235,693 2020

Measure R provides $906.0 Million over 30 years of which $235.7 Million has been programmed in the Subregion for FYs 2012-2020. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2014.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$235.7

Current$235.7

Forecast$906

Forecast$906

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

South Bay (I-405, I-110, I-105 and SR-91) Ramp and South Bay (I-405, I-110, I-105 and SR-91) Ramp and Interchange Operational Improvements ProgramInterchange Operational Improvements Program

Page 14: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

Upcoming Procurements Upcoming Procurements A&E Professional ServicesA&E Professional Services

14

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Page 15: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

Highway Projects in ConstructionHighway Projects in Construction

15

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Page 16: Ben Jong Transportation Program Manager Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 29, 2014 Construction Management Association

Questions?Questions?