being the best we can be through working together
DESCRIPTION
This webinar is a template for partnering on a construction project. The concept of partnering is to create a collaborative process for project management in which all the parties have common goals and work as a team to achieve those goals. The partnering concept presented is not a "social science love fest" approach, but a reasoned structural approach for parties with sometimes diverse interests to use their resources collectively to work through conflicts to enhance the probability of success for the owner, designer, contractors and suppliers.TRANSCRIPT
1
Being the Best we Can beThrough
Working Together
June 14, 2012
www.frisbygroup.org
©Tom N. Frisby 2012Power Point Presentation by: Mendi Arnold
2
Agenda Introduction of Attendees by Attendee Introduction to Partnering – Facilitator Some Lessons Learned – Facilitator
Trust 25/10 Rule Communication Killer Bees Role of Field Personnel
Lessons Learned – Discussion Charter – Group Processes
Schedule Field Planning How to Handle Conflicts Dispute Resolution Tree Report Card
Wind‐Up Action Items What I Learned
3
Introductions:
4
Introduction to Partnering"Clearly, the best dispute resolution is dispute prevention. Acting to prevent disputes before they occur is key to building new cooperative
relationships. By taking the time at the start of a project to identify common goals, common
interests, lines of communication, and a commitment to cooperative problem solving, we
encourage the will to resolve disputes and achieve project goals."
LTG H. J. Hatch, Commander, U.S. Army Corps of Engineers Policy Memorandum 11, 7 August
1990“…cooperative problem preventing…”
5
Introduction to PartneringCONTRACT
A TEAM APPROACH…Working together to achieve or
exceed project goalsproject goals of all parties…
…within the contract
…within the law
FARsStatutes
Constitution
_________ _________
SEAL
6
Objectives Understand and commit to team, collaborative approach
Development of common goals‐charter
How to convert project from “completion of design” to construction project
Processes agreed upon
RFI’s
Changes
Coordination
Submittal Process
Safety
Dispute resolution
Back charges
The role of documentation
7
Objectives (cont.) Using schedule as a management tool
Development Updating Priorities for the first 25%‐challenges and rocks in the road
Planning meetings Time extension requests 20/20 foresight
The role of P‐I‐F and how it will be implemented Close‐out approach Improvement process Having fun
8
What is a Team?
With common measurable goals. Meeting common goals increases probability of meeting individual goals.
Each player can rely on the other players commitments. “I have your back!” (The doctrine of reliable promises or management commitment.)
Players have a plan to meet those goals.
Players work the plan together to meet those goals.
Players look ahead for obstacles, and ways to avoid them.
Players talk to each other in the huddle (communicate).
Coaches talk to players during game to correct problems.
Teams get better as the game is played.
They know they must win each game to stay in the play offs.
Qualified Players
9
Partnering ‐ intended to raise the bar of performance!
Will you rise to the challenge?
10
Kano Model of Quality
11
Introduction to Partnering
Raise the Bar of Performance by:
1+1=3
(sum plus arithmetic)
BUT FIRSTBUT FIRST
1+1=1
(unity)
12
Introduction to PartneringDisunity of Purpose
SO WHAT ARE OUR COMMON GOALS? WHAT IS THERE TO UNITE US?
13
Introduction to Partnering
Total Project Costs
Project Completion Time
Number of Claims
Profitability
Job Satisfaction
The Octagon Ring Doesn’t Work
Effective Effective Partnering (Team Work) DOES!CII Study of Partnered Projects
Item Results
Reduced ~ 10%
Reduced ~ 20%
Reduced ~ 83%
Increased ~25%
Increased ~30%
14
Some Lessons Learned ‐ Trust
Successful projects follow the level of trust of team members where
the calculus for trust is:
C+C+C+C=T C – Competence
C – Character
C – Communication
C – Consistently
T – Trust
15Lesson
s Learne
d ‐T
he Qua
ds IMakes MoneySafe PracticesSafe Execution
Knowing the right things Doing the right things
TeamCore Values
Trust (C+C+C+C=T)Content Conflict
ResolutionBuilt-In Quality
Decision MakingAccountability
Reliable Promises20 / 20 Foresight
IILoses Money
Re-WorkInspect and CorrectDecision Delaying
IIILoses Money
Relationship ConflictsDefensivenessNot AcceptingAccountability
Living in the Past
IVMakes Money
Raising the bar of PerformanceTraining
Lessons LearnedAssisting Others to do their Job
16
Lessons Learned ‐ Discussion
What are the key lessons for project success that you have
learned and want to implement on this project?
Set the gold standard for highly successful projects.
17
Our Game Plan What Makes a Good Project
Good plans and specifications
Cleaning up plans in office, not field
Timely decision making
Open communication
Everyone doing their job
Good scheduling & schedule updating
Good planning
Good work force
Safe environment
Built‐in quality, not inspect & correct
Resolve problems early before they become costly
Commitment Non‐adversarial relations
Subcontractors being on a team
C+C+C+C=TC+C+C+C=T Fair response to change order
requests
Doing what the contract says to do
Treating others with respect
Accountability
Fair change order pricing
Creative thinking
Looking ahead for problems –telescopic vision
Claim avoidance
Resolution by the parties – not the lawyers
On‐site, real time mediation
Leadership
18
CharterCommon Goals• On time delivery
• Within budget
• Quality
• Safety
• No lost time
• Better yet NO incident
• No claims
• No litigation
• Decrease paperwork
Guiding Principles / Values• Team approach
• Trust (C+C+C+C=T)
• Open / honest communication
• Effective use of management tools
• Mutual respect
• The Quad
• Enjoy
• Have fun
• Be proud of accomplishments
19
Appendix FHPW Partnering Charter
20
21
CommunicationHow do we make it happen?
Seek first to understand Listen Do not accept that you understand until you can repeat to the other
party what he / she has said, and how you believe that person feels about it – and the other person agrees that this is what was said and meant
Attack issues – never peopleWe can always resolve content conflicts. It is the relationshipWe can always resolve content conflicts. It is the relationship
conflicts which are difficult, if not impossible, to resolve.conflicts which are difficult, if not impossible, to resolve. Provide adequate and timely information Agree that you will never walk out of a meeting saying: “I wish I said”
or “I should have said” SAY IT! Be prepared with reliable information Agree now that gossip and backbiting will not be permitted in your
organization Find reasons to say good things about people – find reasons to
celebrate.
22
Some Lessons Learned
The 25/10 Rule:
If you meet the goals of the first 25%, the probability of the last 10% becoming 12% ‐
15% greatly decreases.
(Corps calls last 25% red zone!)
See www.frisbygroup.org/webinars/the25/10concept
23
Lost Man Hours Per Craftsman Per Week
Due to Rework vs. Project Completion Stage
0
1
2
3
4
5
6
7
8
25% 50% 75% 100%
Lost man hoursper craftsmanper weekLo
st M
an Hou
rs
Percent Complete
24
Lost Man Hours Per Craftsman Per Week
Due to Overcrowded Work Area vs. Project Completion Stage
0
1
2
3
4
5
6
7
8
25% 50% 75% 100%
Lost man hoursper craftsmanper week
Lost M
an Hou
rs per
Craftsman
per week
Percent Complete
25
The 25/10 Rule
26
Some Lessons Learned: 25/10 RulePareto Principle
‐Convert project completion of design to construct ASAP
‐Clean up drawings (Desk top reviews)‐Submittal process complete
‐Establish short term goals / priorities / decisions / challenges
‐Establish process for close out
20% of the issues cause80% of the impact
27
Project Close‐Out Process
28
Project Close‐Out Process
29
Project Close‐Out Process
30
ProcessesSchedule
Review by general contractor and discussion by all team members. Identify key priorities and goals of first 25%; assign responsibilities; require decisions and actions
Identify challenges and obstacles and develop team approaches and actions.
Let’s hear from the subs: Mr. General Contractor, how can you do a better job of scheduling?
Discuss updating process – Is a schedule a management tool or a billing document? Is it used to measure performance? How to handle time extension requests?
How to use schedule at “Red Zone” (last 25%)
31
Short Term Priorities – Action List
B.
A.
5. Resources Needed
B.
A.
4. Installation
B.
A.
3. Deliveries
B.
A.
2. Approvals
B.
A.
1. Decisions
Comment / Status(Ball in Court)
ResponsibilityScheduleItem
32
The Role of Field Personnel Schedulers know how to use software Field supervisors know how to build the project. Field supervisors (including subcontractors and key suppliers) should be involved deeply in initial
planning process and continuously throughout the project.
The Role of Real Collaboration at the Field Level: Flow of work Short interval objectives developed by all trades working together.
3 – 6 week look ahead; 1 week look ahead; daily Another opportunity to “clean up drawings”
Measurable performance goals Coordination of craft contractors State of readiness Method of resolving conflicts
Priority conversations Focus meetings for improvement Waste management goals
Workmanship Back charge avoidance Finding problems in office, not in field Material handling Maintaining production flow (for all trades)
Managing home office
33
Concepts of the Planning ProcessThe Process is about: Thinking about best way to build, best way to avoid problems, best way to
overcome problems A network of promises
And promises fulfilled “My crew will be there Monday” – and it is! “This area will be ready for your crew” – and it was!
Conversations, skull sessions Continuous information, preparation
Creativity and Improvement How can we build an Empire State Building in 13 months rather than
living in status quo? Planning and Execution (PLEX)
Promise to do it! Do it! Mood
Mood of ambition or role of despair
34
Processes
•Field Planning•How to achieve effective coordination•The role of planning meetings•How to Maintain Production Flow•What if you are directed to work overtime and you do not believe you are the reason for schedule slippage.•How to improve quality of field labor
35
Safety
Too important to be Mixed into the Brew!
36
Processes
Conflicts – How to handle:COE’s denial of contractor’s request for a change order or time extension.
What is approach to pricing changes?How to handle subcontractor whose schedule workmanship performance is less than desirable.
How to manage back charges?
37
Some Lessons Learned
38
Crash Curve
39
40
Dispute Resolution Ladder
WORK IT OUT!!!
Superintendents, ForemanWorking relations between trades in the field
Project Managers, SuperintendentsField Planning
Project Managers, A/E, Owner’s Rep.Schedule, scope of work disputes
StakeholdersUnresolved conflicts Step 1
MediationUnresolved conflicts Step 2
Team
Buil
ding C
onflic
ts
41
Establish overall plans, goals, and standards
Project and contract administration
Work planning and performance
Crew, execution of work
Dispute Resolution Tree
Mission statement, schedules, Q&A, safety
plans, planning
and coordination
DOING IT!!!
Stakeholders, facilitator,
project managers,
(champions), superinten-
dents, foreman and
craftsmen Look Ahead! Prevent Problems.
Identify conflict before damage is incurred. Resolve conflict at the lowest level it can be resolved. Use a facilitator in
“real time – on site”
42
Appendix ESample Resolution Ladder
43
Report Card
Evaluate Team Performance
Establish key monthly milestones and
achievements; attach to report card.
44
5. Built‐In Quality
4. Finding problems in office, not in field
3. Coordination
2. Scheduling
1. Leadership
CommentsScore
(0‐10)
Item
Report Card
45
10. Common goal attainment
9. Team approach
8. Working things out
7. Accountability
6. Safety
CommentsScore
(0‐10)
Item
Report Card
11. Security
46
Comments
Schedule
Who has secondary responsibility
Who has primary responsibility:
What is test of completion:
What is to be done:Priority Matrix
47
Processes
Item How to HandleRFI ‐Changes ‐Submittals ‐Time extension requests ‐Coordination ‐Back charges ‐Documentation ‐Dispute Resolution ‐
48
Wind ‐ UpAction Items
Item Response Schedule
Next Meeting
49
Wind ‐ UpWhat is the most important
thing that came of this session that you will
definitely implement during the course of the project.