behind the learning curve: linking learning activities
TRANSCRIPT
BEHIND THE LEARNING CURVE: LINKINGLEARNING ACTIVITIES TO WASTE REDUCTION
byM. A. LAPRE*
A. S. MUKHERJEE**
andL.N. VAN WASSENHOVE t
98/66/TM (CIMSO 5)(Revised version of 96/24/TM)
* Professor at Boston University, School of Management, 595 Commonwealth Avenue, Boston, MA02215, USA.
** Arthur D. Little, Inc., Cambridge, MA.
t Henry Ford Chaired Professor of Manufacturing and Professor of Operations Management at INSEAD,Boulevard de Constance, 77305 Fontainebleau Cedex, France.
A working paper in the INSEAD Working Paper Series is intended as a means whereby a faculty researcher'sthoughts and fmdings may be communicated to interested readers. The paper should be considered preliminaryin nature and may require revision.
Printed at INSEAD, Fontainebleau, France.
Behind the Learning Curve: Linking LearningActivities to Waste Reduction
Michael A. Lapre • Amit Shankar Mukherjee • Luk N. Van Wassenhove
Boston University, School of Management, 595 Commonwealth Avenue, Boston, MA 02215
Arthur D. Little, Inc., Cambridge, MA
INSEAD, Boulevard de Constance, 77305 Fontainebleau Cedex, France
August 11, 1998
Abstract
This exploratory research on a decade of Total Quality Management in one factory opens
up the black box of the learning curve. Based on the organizational learning literature we
derive a quality learning curve that links different types of learning in quality improvement
projects to the evolution of the factory's waste rate. Quality improvement projects that
acquired both know-why and know-how accelerated waste reduction, while other projects
either impeded or did not affect waste reduction. In complex, dynamic production environ-
ments locally acquired knowledge is difficult to disseminate. The combination of know-why
and know-how facilitates its dissemination.
(Learning Curve, Organizational Learning, Quality, TQM, Technological Knowledge, Exper-
imentation, Knowledge Transfer)
1 Introduction
Knowledge has become a critical resource for competition. Firms have to manage organiza-
tional learning efforts directed at building knowledge they can use in the future (Adler 1989).
One approach which is particularly learning-oriented is to embark on a Total Quality Man-
agement (TQM) program. The link between learning and quality, however, is ill-understood.
Little is known about the learning processes in TQM programs and their impact on bottom-
line organizational performance (Hackman & Wageman 1995).
1
In a previous paper (Mukherjee et al. in press) we started to explore this link between
learning and quality. We analyzed 62 quality improvement projects undertaken in one factory
over a decade. We identified two dimensions of the learning process that took place in these
projects: conceptual and operational learning. Conceptual learning consists of assessing
cause-and-effect relationships and designing concepts in response, i.e. the acquisition of know-
why. Operational learning consists of implementing a concept and observing the results, i.e.
the acquisition of know-how. We found that conceptual and operational learning played a
crucial role in changing factory personnel's attention as a result of the project. For example,
projects which acquired know-why or know-how were more likely to yield new Standard
Operating Procedures or changes in Statistical Process Control.
This paper extends the link between learning and quality from a cross-sectional, project
level analysis to a longitudinal, factory level analysis. In it, we open up the black box of
the learning curve, explicitly introducing the knowledge acquired by quality improvement
projects. Given the role of conceptual and operational learning in changing factory person-
nel's attention after project completion, we use these two learning dimensions to identify
four different types of knowledge acquisition: firefighting, artisan skills, unvalidated theories
and operationally validated theories. We construct the cumulative number of projects of
each type. We then use these cumulative number of project variables to explain changes
in the factory's waste rate (measured by the ratio of wasted material to total material
released to the process). We show that projects which acquired both know-why and know-
how—operationally validated theories—accelerated waste reduction. Other projects either
impeded or did not affect waste reduction.
We explain our findings in the context of complex, dynamic production environments.
Learning in such environments is often impeded by dynamic complexity, ambiguity and
erroneous myths (Sterman 1994, March & Olsen 1975). If the production process is not
completely understood, dissemination of locally acquired knowledge is problematic. We
argue that the combination of know-why and know-how facilitates its dissemination.
2
The paper is organized as follows. In section 2, we review drawbacks of the traditional
learning curve and ideas from the organizational learning literature that will help us un-
derstand the learning process behind the learning curve. In section 3, we derive a learning
curve model for waste reduction that addresses the drawbacks of the traditional learning
curve mentioned above. Section 4 describes the research site, its quality improvement ef-
forts, our previous study of these efforts and the data collection. Section 5 describes the
econometric results. Sections 6 and 7 discuss implications for managers and scholars.
2 Behind the Learning Curve
The learning curve phenomenon has been observed frequently. Firms realize large cost
reductions as they gain experience in production (see reviews by Yelle 1979, Dutton &
Thomas 1984). The functional form which has traditionally been suggested for the learning
curve is the power form
—6,C = Coq , (1)
where c is the cost to produce the q-th unit; co the cost to produce the first unit; and b the
learning rate.
Despite its frequent use, scholars have established fundamental shortcomings of the power
form (1). It is an entirely empirical phenomenon (Levy 1965), and as Lieberman (1984) notes
the appropriate functional form of the learning curve has never been rigorously tested. This
is peculiar in light of the following observations that do not support (1).
• The traditional power form does not accomodate two often observed patterns: initial
downward concavity and the plateau effect: after some amount of production no further
improvements are made (Muth 1986).
• Estimated learning rates vary widely, within an industry, within a plant, and over
time (Levy 1965, Dutton & Thomas 1984, Hax & Majluf 1982). Therefore, Dutton
& Thomas (1984) have advocated that the learning rate be treated as a dependent
3
variable as opposed to a given constant. In dynamic production environments with in-
complete technological knowledge, factory personnel should deliberately try to enhance
improvement rates (Jaikumar & Bohn 1992).
• Investments have resulted in shifts to steeper learning curves, Hax & Majluf (1982)
observed. Mishina's (1992) study of Boeing's production of B-17 heavy bombers cor-
roborates the importance of investments. His findings indicate that the scale-up of
production triggers learning. His rationale is that learning occurs only if there is a
challenge. Scale-up of production provides such challenge. Mishina used proven effec-
tive capacity to measure learning by new experiences. Findings by Epple et al. (1996)
and von Hippel & Tyre (1995) are consistent with Mishina's results.
Probably the most important reason why the traditional power form does not accomodate
these observations is that it lacks an underlying theory. It does not provide any insight
into the learning process behind the results. It assumes that cumulative volume is the
only source of learning and it ignores deliberately undertaken learning efforts (Bohn 1994).
Dutton & Thomas (1984) made this distinction between autonomous and induced learning.
Induced learning requires efforts or resources that are not present in the current operating
situation. These efforts are deliberately undertaken to create better knowledge. Autonomous
learning, on the other hand, does not involve deliberately undertaken learning efforts; it is
a much less cognitive process that occurs automatically "on-the-job". Levy (1965) and
Adler & Clark (1991) are the only two papers we are aware of that include learning process
variables, to measure induced learning, in a learning curve analysis. Yet, as the latter
authors acknowledge, variables like training hours and engineering activity are still proxies
of the actual induced learning process.
Levy (1965) assumed that for a new process, a firm has a maximum rate of output P it
would like to achieve. The rate of output after q units have been produced is Q(q) < P. His
crucial assumption is that the rate of improvement in Q(q) is proportional to the amount
4
the process can improve. From this assumption follows the adaptation curve:
Q(q) = P[1 — e-(a+Pq)],
where a represents the initial efficiency of the process, and it the process's rate of adaptation,
which can be affected by various factors y i , ... , yri like prior training and experience:
n
li = 00 + /3i i (2)i.i
Equation (2) is used to explain differences in learning rates across workers.
The adaptation curve overcomes many of the problems associated with the power form
(1). However, it does not address the dynamic nature of the learning rate and the impact
of changes in the production system. Furthermore, it raises new questions: (i) how should
the target level P be determined objectively, and (ii) what theory underlies the assumption
that the rate of improvement is proportional to the amount the process can improve?
One cannot obtain a value for P from estimation nor from hard data. Levy inferred
values for P from interviews. However, even the most ambitious values inferred for P can
be overtaken, thereby violating the assumption Q(q) < P. At Chaparral Steel, for exam-
ple, management sets targets for production rates "considerably beyond current production
capabilities." The company not only achieves these very ambitious goals, but continues to
improve performance unabated (Leonard-Barton 1992). Likewise, Boeing more than quadru-
pled the target it set initially at the planning stage (Mishina 1992).
Levy's assumption that the rate of improvement is proportional to the amount the pro-
cess can improve can be based on what the organizational learning literature refers to as
"performance gaps". A performance gap is the discrepancy between actual performance
and aspired performance (managerial targets). This performance gap induces organizational
members to search for alternative actions that might reduce the performance gap. March &
Simon (1958) postulated that a larger performance gap spurs organizations to intensify their
search efforts. Cangelosi & Dill (1965) confirmed that performance gaps trigger learning.
Yet, "learning is sporadic and stepwise rather than continuous and gradual." (p.175) Duncan
5
& Weiss (1979, p.52) noted that if the performance gap cannot be attributed to factors out-
side the locus of control or to improper implementation, "... it must be considered a failure
of organizational knowledge". Consequently, faced with a performance gap the organization
should obtain better knowledge about action-outcome relationships.
Adler & Clark (1991) found that two types of induced learning, engineering activity and
training activity, can be enhancing as well as disruptive. Their field research suggested some
explanations for their results, but they acknowledge that further research on identifying and
understanding induced learning variables is necessary. In prior work, we used research on
organizational learning to identify dimensions of the induced learning process. In this paper,
we use these dimensions to classify different types of induced learning.
Although there exist many different definitions of organizational learning, Fiol & Lyles
(1985) note that scholars typically distinguish two dimensions of the learning process: cog-
nitive development and behavioral development. They define organizational learing as the
process of improving actions through better knowledge and understanding. This process is
essentially a feedback process: "Decision makers compare ... information about the state
of the real world to goals, perceive [performance gaps], and take actions (they believe will)
cause the real world to move toward the desired state" (Sterman 1994, p.293) They revise
subsequent actions based on feedback received. Sterman identifies several barriers to learn-
ing that disrupt this feedback process in complex, dynamic environments. These include
dynamic complexity (separation of cause and effect in time and space), ambiguity (simulta-
neous existence of equally plausible but mutually contradictory explanations of a situation),
misperception of feedback, and poor inquiry and scientific reasoning skills. These barriers to
learning make it hard for people to create better knowledge about action-outcome relation-
ships. March & Olsen (1975), for example, discuss how ambiguity leads individuals to create
their own potentially inaccurate beliefs called "myths" (potentially inaccurate beliefs based
on subjective interpretations of data), and stick to these myths. They are skeptical of lo-
cally acquired knowledge. Dissemination of knowledge therefore becomes problematic. This
6
is further aggravated if all relevant knowledge is not fully understood and codified (Teece
Pisano 1994). In the next section, we enhance Levy's model using the organizational
learning ideas outlined above.
3 A Quality Learning Curve
In this section, we derive a learning curve model for quality improvement in a dynamic
production environment. We focus on waste, a key driver of both quality and productivity.
We make four modifications to Levy's (1965) model: a theoretical foundation; Mishina's
experience variable; a natural, objective aspiration level; and a dynamic learning rate.
Let xt be the production output in month t, zt = max,-< t XT the proven effective capacity
(Mishina's experience variable), W(z) the waste rate after z has been proven to be feasible
production output, and P the desired waste rate. W(z) — P is the performance gap. In our
context Levy's assumption becomes
dW(z) = /1 [W( z ) p],
dz
where y denotes the learning rate. However, instead of merely assuming (3), we can interpret
this equation in light of the organizational learning literature on performance gaps. The
performance gap W (z) — P induces the organization to search for alternatives to reduce
this gap. A larger discrepancy spurs the organization to exert more effort in searching for
better knowledge (e.g. March & Simon 1958). The effectiveness of acquiring new knowledge
is determined by the learning rate µ. Consequently, we can model the rate of improvement
as the product of the learning rate and the performance gap.
Mishina's findings suggest that scale-up of production triggers learning. In a dynamic
production environment scale-up of production can be achieved by adding new machines or
increasing machine speeds. In both cases factory personnel need to acquire new technological
knowledge on how to control their process in the changed production environment. We
therefore use Mishina's experience variable.
(3)
The TQM literature provides a natural choice for P: zero defects (Deming 1982). As our
research site aimed for zero defects, we will—without loss of generality—employ P = 0 in
the remainder of the paper (cf. Schneiderman 1986, 1988). Contrary to Levy's model, the
TQM context of waste reduction provides a value for P which is not subjective and which
can never be overtaken by actual performance.
Our final modification to Levy's model concerns the learning rate Following Jaikumar
& Bohn (1992), we assert that the learning rate is fundamentally dynamic in nature. Factory
personnel in a dynamic production environment have to create new knowledge unabated to
adapt to new situations, and deliberately try to enhance rates of improvement.
Formally, let t be the time index. Let y it , , ynt be managerial factors that affect
the learning rate, like the cumulative number of quality improvement projects. The most
parsimonious formulation for the learning rate is
n
At = 00 +
(4)
i=1
Solving (3) with condition W(z) > P gives (recall P = 0)
W(z) = ea+Az, (5)
Substituting (4) in (5) and taking logarithms, we obtain
In W(zt) = a + (60 + E (3iYit)Zt• (6)i=1
Equation (6) can be estimated if we have data for the waste rate, production, and the
managerial factors yit . Estimating (6) is essentially an investigation of Dutton & Thomas's
(1984) autonomous/induced learning dimension (cf. Adler & Clark 1991): 0 0 measures the
autonomous part of the learning rate, whereas E7 oiyit measures the induced part.
Note that we do not restrict the range of p t , because the induced learning variables can be
enhancing as well as disruptive (Adler & Clark 1991). Moreover, Dutton & Thomas (1984)
observed both positive and negative learning rates. Equation (4) assumes that projects
conducted long ago do not lose their impact. In this paper we are not looking at forgetting.
8
We are, for now, merely interested in identifying factors that affect the rate of learning.
Future research could look at forgetting of both autonomous and induced learning.
Equation (5) is equivalent to Schneiderman's (1988) half-life curve specification if z is
replaced by t and it is kept constant. The assumption underlying the half-life curve is that
waste "decreases at a constant rate, so that when plotted on semi-log paper against time, it
falls on a straight line." (p.53) Not only do our field observations contradict this assumption,
the disappointing managerial implication is that the rate of waste reduction, i.e. the learning
rate, is given and cannot be accelerated. This is precisely what (4) allows for. Moreover, in
addition to the reasons for using z instead of t advanced above, z incorporates the Cangelosi
& Dill (1965) notion that learning is a stepwise process as opposed to a continuous process.
Finally, Scheiderman actually observes that depending on the scope of quality improvement
projects learning rates fall in different ranges. Our specification (6) allows for the learning
rate to change if quality improvement projects change over time. We now turn to the context
in which we estimate equation (6).
4 Research Design and Data
This methodology section discusses the research site, its quality improvement projects, mea-
surement of the learning constructs in the projects, and the longitudinal data. The first two
subsections are largely based on Mukherjee et al. (in press).
4.1 The Research Site
Several considerations prevailed in choosing a research site. First, the site had to provide
access to detailed data about the systems used to improve quality. Second, it had to have
incomplete knowledge so as to faciliate a study on knowledge acquisition. Third, for our
findings to be generalizable, the site had to have implemented standard TQM methods.
Fourth, it had to have an established record of successful quality improvement.
These considerations convinced us to choose N.V. Bekaert, S.A., a Belgian multinational
9
corporation. Bekaert is the world's largest independent producer of steel wire. In particular,
its Steel Cord Division, which hosted our research, produces about one-third of the world's
output of the steel wire (called "tire cord") used in the production of steel belted radial tires.
Our project received the enthusiastic backing of then CEO Karel Vinck and current CEO
Rafael Decaluwe, providing us with unlimited access to people and documents.
Bekaert's basic process flow is deceptively simple: Thick wire are pulled ("drawn")
through dies which progressively reduce their diameter. Very thin wire ("filaments") are
wrapped around each other to form tire cord. The simplest cord has two filaments; the most
complex, hundreds. See figure 1.
Figure 1 about here
Of course, reality is much more intricate. First, each plant has a handful of huge draw-
ing machines upstream and hundreds of small drawing and filament wrapping machines
downstream. Second, swimming pool sized soap pits supply lubricants (for the dies) to the
drawing machines downstream. Thus, while these machines are run independently, the soap
system links them to each other. Third, the wire is heat treated at two intermediate points
to make it ductile. At one of these points, a chemical process also coats the wires with brass.
Despite the use of sophisticated controls, wires which are heat treated and coated together
do not necessarily have identical properties. Fourth, Bekaert's suppliers, which include some
of the best known steel companies in Europe and Japan, cannot guarantee homogeneity of
properties across the thousands of tons of wire they deliver. Microscopic flaws in the wire
can cause fractures (the industry's biggest quality problem) at any process stage.
As a result, plant personnel have to contend with very high levels of dynamic complex-
ity and ambiguity (Sterman 1994). The former arises from the ease with which effects of
problems experienced at any machine or production stage could be transmitted to other
machines and stages. The latter arises as production personnel often disagree on causes
for a particular production problem like fractures. One person could blame raw materials,
another intermediate process settings, and there would be no way to tell who is right.
10
During the 1980s, Bekaert's customers—tire manufacturers—experienced traumatic
change, and responded by making simultaneous demands of high quality, short lead times,
low cost and product line flexibility. Bekaert responded by initiating a pilot quality improve-
ment program at its flagship Aalter plant (Belgium) in 1981. At that time, little scientific
knowledge existed concerning the production process of tire cord. However, over the next ten
years, it introduced and institutionalized among others a structured approach to problem
solving, a functional TQM organization, Statistical Process Control, Standard Operating
Procedures, TQM project teams, information systems providing standardized daily, weekly
and monthly production and quality data, process capability measures, and quality control
circles. Researchers on quality have long prescribed these methods (see e.g. Deming 1982,
Juran & Gryna 1993, Hackman & Wageman 1995).
In the late 1980s, Bekaert realized that central R&D laboratories lacked the charac-
teristics of the dynamic production environment encountered in the factory. It therefore
re-located process optimization to the factory. In 1988, Bekaert established a "Model Line"
at Aalter (MLA) for an important, representative product, and gave a senior R&D manager
the responsibility to create fundamental process control knowledge without sacrificing the
production of saleable wire.
Its diligent efforts seem to have borne fruit, for in 1990, CEO Karel Vinck won the first
European Foundation for Quality Management Leadership Award. Many people believed
that the jury was favorably impressed by his vision for quality exemplified by the innovative
practices at Aalter. Bekaert's second major recognition for quality came in 1992, when its
Burgos plant (Spain) won a European Quality Prize.
In sum, Bekaert provided access, was a dynamic production environment with incomplete
technological knowledge, used common TQM methods, and achieved considerable success.
4.2 The Learning Process in Quality Improvement Projects
We had unlimited access to all of Aalter's records on improvement projects undertaken
throughout the 1980s. From these, we selected projects undertaken between 1982 and 1991
that (i) sought to improve product attributes or process control (as opposed to say, house-
keeping), (ii) had progressed (at least) past the testing stage, and (iii) had been adequately
documented. This selection left us with 62 projects.
We coded the projects on questions which dealt with their learning process and with their
performance. We structured these questions on the basis of the organizational learning lit-
erature and our experience with earlier exploratory research (Mukherjee & Van Wassenhove
1997). Questions were coded by giving a number or a response on a 5 point Likert scale.
Appendix A contains the questions relevant for the current paper. For each question, we in-
dicated how to determine the number or we gave typical examples for the extreme answers (1
or 5). To further improve reliability, we often developed typical answers for the intermediate
response categories as well. (See e.g. the question on the use of experiments in appendix A.)
These typical answers allowed one of us to objectively code the responses. For 55 projects,
he based his assessments primarily on the final project reports, which under a management
edict, contained fairly detailed information in a standardized format. Additionally, he re-
lied on any available interim reports. Finally, he resolved any ambiguity by discussing the
affected project with the plant's TQM coordinator, who had not only participated in all of
these projects, but had maintained his own notes about them. Data on 7 additional projects
came from a prior research effort (Mukherjee 1992).
We conducted a factor analysis on the questions which dealt with the learning process.
Two of the resulting factors are crucial for this paper; they mapped onto what Kim (1993)
calls conceptual learning and operational learning. The organizational learning literature has
proposed many different definitions for what Fiol & Lyles (1985) call cognitive development
and behavioral development. Figure 2 shows why we chose Kim's (1993) terminology. He
12
equates conceptual learning with assessing observed experiences and designing concepts in
response. The questions that loaded onto conceptual learning measured (i) the use of science
and statistical experiments to assess cause-and-effect relationships, and (ii) the level of detail
used in the designed solution. Kim equates operational learning with the implementation of
a concept and observation of the results. The questions that loaded onto operational learning
measured the modification of action variables and the follow-up of experimental results.
Figure 2 about here
While figure 2 helps to assess the content validity of conceptual and operational learning,
OLS regressions in Mukherjee et al. (in press) help to assess the criterion-related (predictive)
validity. We found that operational learning was a good predictor for achieving goals in TQM
projects, whereas conceptual learning was the key predictor of acquiring better technological
knowledge (measured on a scale that addressed Bohn's (1994) stages of knowledge).
Finally, we found that conceptual and operational learning during the project changed
organizational behavior measured by modifications of Standard Operating Procedures and
Statistical Process Control rules after the project. It is important to note, though, that in
our cross-sectional study (Mukherjee et al. in press), both learning and changed behavior
were measured in the limited boundaries of the project context (i.e., one production line,
one machine or an identified group of machines). Typically, a project did not even affect one
hundredth of the total plant waste.
Discussions with managers and engineers revealed that some of these local projects had
produced knowledge applicable to the entire plant. Some project insights were actually
transferred to other plants as well. Dissemination of local project knowledge, however,
was far from routine practice. The projects were scattered over time and space in the
factory. Often, project results did not even spread in the vicinity of the project context;
personnel in other parts of the factory would argue that a particular project finding would
not be transferable because of slight differences in machine types, product specifications, raw
materials, etc. Several managers and engineers commented on this notorious reluctance to
13
consider knowledge obtained elsewhere in the factory. This was particularly aggravated by
the lack of a scientific knowledge base of wire drawing. So, the Not Invented Here syndrome
Hayes & Clark (1985) observed between plants also exists within a plant.
Consequently, in this paper we study the impact of local project learning on global waste
reduction. Given the role of conceptual and operational learning in changing factory person-
nel's behavior locally, we want to investigate the impact of these two learning dimensions on
the plant's global learning curve. We now describe our longitudinal data to do so.
4.3 Longitudinal Data
In January 1984, the Aalter plant introduced a reporting system that provided standardized
waste and production data on a monthly basis.1
• Waste rate. For all major process stages, the plant reported the percentage of steel
wire scrapped because of irreparable defects. Let Wit denote this waste rate for process
stage i in month t. The yield rate for stage i is then 1 — Wit . Hence, the yield
rate for the entire factory is n ( 1 - Wit ) . (Cf. the probability that one ton of wire
passes flawlessly through all process stages.) Finally, we obtain the factory's waste
rate Wt 1 - - Wit ) . Figure 3 shows the waste evolution. We correct In
for seasonal patterns by subtracting the sample average for that month. Thus we
control for effects like increased waste levels due to start-ups in production months
that followed the holidays.
• Production. The factory's production volume x t was readily available in the re-
ports: the tonnage of wire produced in the last stage. The proven effective capacity is
constructed straightforwardly as zt = max,<tSee figure 4.
• Projects. For 50 projects the project reports provided the project completion dates.
The completion dates for the remaining 7 projects were recorded in Mukherjee (1992).
lAalter produces three product types. The waste and production data concern its most important product
type, tire cord. Five projects did not concern tire cord. Hence, we only retained the 57 projects that did.
14
For each project we had factor scores' for conceptual and operational learning at our
disposal from our previous study. A simple way of measuring knowledge accumulation
by projects would be to construct one variable Ct , the cumulative number of projects
completed up to month t. However, to investigate whether different ways of learning
had a differential impact, we compare the factor scores for conceptual and operational
learning with the median values in the sample of 57 projects, and classify each project
according to high (H C ) or low (LC ) conceptual learning and high (H°) or low (L°)
operational learning. This allows us to compute CL'14, the cumulative number of
projects with low conceptual learning and low operational learning completed up to
month t. Similarly, we compute CL'Il t̀', le14, and Cli cT. Thus, the projects split
up 14-14-14-15.
Figures 3 and 4 about here
Our sample includes 80 production months: January 1984 to March 1991 (there are 11
production months per year). By studying this time horizon, we control for learning through
both internal and external benchmarking as well as changes in technology. First, until 1991
Aalter pioneered Bekaert's TQM efforts, so it did not transfer knowledge from other Bekaert
plants. Second, the industry is very secretive, making it difficult to learn from competitors.
Moreover, during the 1980s Bekaert remained the leading, largest independent tire cord
producer. Third, the technology depicted in figure 1 remained stable during the 1980s.
It is important to point out the timing of events measured for each project. The items that
loaded onto conceptual learing measured assessments of cause-and-effect and detail in the
2 A factor analysis reduces a set of variables to a smaller set of new variables called factors. This set
accounts for the larger part of the variation in the original set. In standard factor analysis (principal
components followed by varimax rotation) the newly constructed factors are uncorrelated with one another.
Typically, each original variable is highly correlated with one factor, and relatively uncorrelated with the
other factors. For each observation factor scores can be constructed. A factor score for an observation on a
particular factor is a weighted average of the standardized responses to the original questions. The weights
are determined by the correlations between the original questions and the specific factor.
15
proposed design prior to final testing. The items that loaded onto operational learning dealt
with the final test results of the project. Finally, the date of project completion occurred
after the final test results of the project. The date of project completion denotes the time
when a project gets added to a cumulative number of projects variable, which subsequently
is linked to the waste evolution. This sequence of events is summarized in figure 5. The
longitudinal nature of the data will allow us to make inferences about the impact of the
learning constructs on waste reduction. We now turn to the econometric analysis.
Figure 5 about here
5 Quality Learning Curve Estimates
We first estimate the traditional learning curve with the various experience variables pro-
posed in the literature, time (t), cumulative volume (q), and proven effective capacity (z):
lnWt = a+blnt (7)
lnWt = a+blnqt (8)
ln Wt = a + b ln zt (9)
Next, we estimate the quality learning curve derived in section 3 with a learning rate that
is (i) constant, (ii) affected by projects assumed to be homogenous, and (iii) a function of
projects that differ in their learning processes:
In Wt = a + Oort (10)
In Wt = a + Po + OiCt)zt (11)
In Wt = a + (fio + Oi CLcift) + 02 CLcirt + )33CHcL7 + 04CHclinzt (12)
In each model, we allow for first order serial autocorrelation. The traditional learning curve
estimates confirm Mishina's findings (rows 1 to 3 in table 1). Maximum proven capacity
explains more variation. This particularly makes sense in Bekaert's production environment
16
where scale-up (increasing machine speeds and/or number of machines) forces factory per-
sonnel to learn how to produce good output in the changed operating conditions. As figure 4
shows, 50% of the scale-up during the 1980s occurred at the end of 1987 and the beginning of
1988. This scale-up coincided with a major reduction in the waste rate (figure 3). Nonethe-
less, for all traditional learning curve models the autocorrelation coefficients are statistically
significant indicating ill-specified models.
Table 1 about here
From rows 4 and 5 in table 1 one might conclude that the quality improvement projects
did not affect the learning rate. Both models show the same degree of autocorrelation and
explain the same amount of variation. The estimates for model (12) in row 6, however,
show that the implicit assumption in model (11) that all projects have the same impact on
waste reduction is erroneous. First, while model (11) suffers from autocorrelation indicating
an ill-specified model, model (12) does not. Second, the amount of variation explained is
significantly larger than either model (10) or (11). The corresponding F-statistics for testing
the 15% increments in R2 are 13.46 and 17.62 respectively. Both are highly statistically
significant. Third, two types of projects significantly affected the learning rate over time.
Consequently, even though model (12) requires estimating more parameters than the tradi-
tional models, it yields the insight that the learning rate is not constant, but dynamic in
nature affected by different ways of learning in TQM projects.3
We will argue that the impact of the different project types on the learning rate relates
to the transferability of project results. Before we do so, we need to rule out an alternative
explanation. Is it possible that the waste reduction resulted directly from local area efforts?
Four CI-IcII° projects were conducted on Aalter's model line spanning parts of all process
3Appendix B displays the table of correlations between the dependent and independent variables, and
discusses why the highly correlated cumulative project variables do not pose a multicollinearity problem.
This appendix also describes additional tests to demonstrate that the estimates in row 6 in table 1 are rather
robust.
17
stages. The other Cli cH° projects (which we defined as ClI cH°*) resembled the CL'Il°
projects in size—only a small part of one process stage. We re-estimated equation (12)
with the modified Cli c11°* variable. Again, Cli cH°* significantly enhanced waste reduction.
So, CI11-1°* and CI, c11° are two sets of local area efforts, which both yielded local results
(high operational learning). Yet, 14 of these combined (CUR') did not affect global waste
reduction, whereas 15 — 4 = 11 did. It seems therefore that the knowledge of the latter
11 projects must have been replicated in other areas of the plant to have had a significant
impact on global waste reduction. This also confirms discussions we had with the plant's
TQM coordinator who facilitated the local projects. His examples of projects that were
implemented elsewhere were all CHell°* projects. This result also rules out project size as
an alternative explanation for the significant estimate for 44 in equation (12). We will now
discuss each coefficient in turn.
• The insignificance of i3 indicates that projects with little conceptual and little opera-
tional learning (CUL') did not affect the learning rate. In these projects teams hardly
reflected on the causes of contingencies, implemented only minor changes, and con-
ducted little follow-up. We label these projects "firefighting." The lack of root cause
analysis and the lack of operational results lead other people to ignore these (local)
efforts.
• Projects with little conceptual learning but substantial operational learning (CLcil°)
generate know-how. Recall that operational learning basically means modifying pro-
cess variables and obtaining follow-up of the experimental results, i.e. these projects
generated successful solutions within the project context. However, the insignificance
of 42 suggests that they did not affect the learning rate. Due to the lack of conceptual
learning, the engendered know-how was not well understood. It was more art than
science. We therefore label these projects "artisan skills."
The lack of conceptual learning leaves a lot of room for ambiguity. Will the operational
learning apply to other areas of the factory as well? As mentioned in section 4.2,
18
personnel in other areas of the factory would argue that local project results would not
be applicable to their part of the factory because of slight differences in machine types,
product specifications, raw materials. As a result, the lack of conceptual understanding
of why something works makes artisan skills hard to transfer. Teece & Pisano (1994,
p.549) noted that "replication and transfer are often impossible absent the transfer
of people, though this can be minimized if investments are made to convert tacit
knowledge to codified knowledge." This was indeed the case at Bekaert; foremen
and supervisors who led these TQM projects were not transferred and the focus on
operational learning implied lack of codified knowledge.
• In projects with substantial conceptual learning and little operational learning (ClIcI,°)
teams assessed cause-and-effect relationships using science and statistics and came up
with a high level of detail in the designed solution. Yet, they failed to obtain opera-
tional results. Hence, we label these efforts "unvalidated theories" (we cannot distin-
guish between theories that were wrong and "correct" theories that were unsuccessfully
implemented). One would expect that the lack of local area operational results would
lead others to ignore these projects like the firefighting projects. However, rather sur-
prisingly, these projects actually had a significantly disruptive impact on the learning
rate (witnessed by the positive sign of g3). Unvalidated theories therefore must have
spread: production personnel elsewhere apparently took detrimental actions based on
conceptual ideas that had not been validated in a full scale manufacturing environment.
Why can the implementation of unvalidated theories actually slow down the learning
curve? Several of these projects used insights obtained at central R&D. Pisano (1997,
p.44) notes that even if "... the technology developed and tested in the laboratory is
replicated nearly perfectly in the plant ... specific elements of the plant environment
(such as equipment configurations) can cause a deterioration in process performance.
This is not a problem of technology transfer, but one of technology development."
Similar problems arise with technology transfers within a plant where areas differ in
19
elements like equipment configurations. At Aalter, instead of first fine tuning R&D
insights locally, plant personnel transferred unvalidated theories to other parts of the
factory. Often, this process was aided by centrally issued directions.
• The negative and significant sign of 444 implies that projects with both substantial
conceptual and operational learning (Cli c1-1°) enhanced the learning rate. In these
projects, teams used scientific models and statistical experiments to develop theories
that explained the occurrence of process interruptions. Based on these theories, the
teams implemented changes and obtained empirical evidence of performance. There-
fore, we label these projects "operationally validated theories."
Conceptual learning guides the team in determining the key variables to modify.
Instead of changing variables by trial-and-error, the team applies scientific principles
to develop falsifiable hypotheses and build models of cause-and-effect. Therefore, the
team is less likely to make erroneous links of cause-and-effect. According to Teece &
Pisano (1994) it is often difficult to replicate organizational processes (here operational
results), because all relevant knowledge is not fully understood and codified. In opera-
tionally validated theories, conceptual learning enhances the build-up of deep process
understanding and codification of the results obtained with operational learning. It is
particularly powerful in isolating the principles from specific contexts. I.e., notwith-
standing differences in machine types, product specifications, raw materials etc., con-
ceptual learning helps to identify the principles that are transferable. Consequently, it
becomes easier to replicate these project results.
So, in order for successful TQM solutions to spread and thus to accelerate the learning
rate both conceptual and operational learning are required. In the next section, we explore
whether plant management can consistently produce both.
20
6 Implications
"In too many TQM programs ... science is fading, the slogans are staying, and the implica-
tions are worrisome." (Hackman & Wageman 1995, p.338) Our findings show the limitations
of solely relying on operational learning. We do not dispute that artisan skills can yield use-
ful solutions for local problems. However, in a production environment characterized by
dynamic complexity and ambiguity such locally acquired know-how does not affect other
people's strongly held beliefs, or myths. It takes conceptual learning to challenge myths.
Our findings suggest that accelerating learning for quality improvement requires both know-
why and know-how. Operationally validated theories are capable of overturning received
wisdom. Furthermore, their codification makes them are easier to disseminate.
The question arises, however, whether the adoption of conceptual learning will generate
desired results. At Aalter some projects with high conceptual learning were able to yield
the corresponding operational results whereas others were not. Can one a priori avoid the
potentially disruptive unvalidated theories? Certainly, with a single learning curve study we
cannot give the ultimate answer. However, we do have some encouraging case evidence.
Five projects in our dataset were conducted on the "Model Line" at Aalter (MLA). The
MLA was a fundamentally new organizational structure at Bekaert. Typically, Bekaert steel
cord factories organized personnel and machines by functional departments corresponding
to the stages in the production process depicted in figure 1. The MLA, on the contrary, was
an integrated line corresponding to a product cutting across all stages. People and machines
were dedicated to a product, and managed by a team led by a senior R&D manager. The
MLA team set goals for productivity and quality improvement based on both R&D and
production experience. It collected data on any product/process variable deemed relevant.
Through its unique information processing system, it was able to link data across process
stages. The MLA team typically solved problems by building scientific models from which
it derived testable hypotheses. These hypotheses were tested with natural and controlled
21
experiments (i.e. conceptual learning). The resulting regression output was then used to
modify limits for Statistical Process Control (based on operational learning). The MLA was
essentially a learning laboratory in the factory (Leonard-Barton 1992).
Four out of five model line projects were operationally validated theories. (The fifth
was an artisan skill directly below the median.) So it seems that Bekaert had created an
organizational structure that facilitated the learning rate enhancing mix of conceptual and
operational learning. One key reason for the strength of the MLA cited by Bekaert's man-
agement was the dedication of resources to the MLA. Pisano (1997, p.46) confirms that
because of the "complex and sometimes chaotic environments" encountered in factories,
"... slight, but unavoidable batch-to-batch differences in raw materials, equipment work-
ers, equipment settings, and other process parameters will reduce the signal-to-noise ratio
of factory experiments." The organizational structure of the MLA, therefore, provided a
controlled environment that enhanced the signal-to-noise ratio of factory experiments. This
leads us to speculate that it is possible to avoid the disruptive unvalidated theories as well
as firefighting projects that do not accelerate the learning rate. By careful project selection
in a factory environment with controlled conditions, a plant can save a lot of resources.
To appreciate the magnitude of the estimates in table 1 one might ask, how much does
one additional project of type i change the initial learning rate 0 0 ? For each type of project
we calculated 132 d30 x 100% to measure this effect. Table 2 shows that one additional oper-
ationally validated theory would improve the learning rate by 3.6%, whereas one additional
unvalidated theory would worsen the learning rate by 3.2%.
Table 2 about here
With 14 unvalidated theories, 15 operationally validated theories, and the estimates in
table 2, one can compute that the learning rate in 1991 was not very different from what it
was in 1984. Do these numbers imply that TQM did not pay off?
First of all, there were times when the learning rate was accelerated because of oper-
ationally validated theories. This resulted in faster waste reduction. So, it is wrong to
22
conclude that TQM did not pay off. The plant, however, was unable to keep these gains in
the learning rate due to unvalidated theories. Clearly, the plant would have been better off
without these. Also, it could have saved the resources spent on firefighting projects. It is
key to carefully select the right projects, and provide the right environment (organizational
structure) to produce the right learning (which is both conceptual and operational).
7 Conclusion
Our contribution to the learning curve literature is the introduction of learning process vari-
ables into the learning curve. Instead of merely linking production and cost improvement,
we use proxies for the learning process to classify different types of knowledge acquisition.
Moreover, we provide empirical evidence for Dutton & Thomas's (1984) assertion: the learn-
ing rate is definitely not constant, in fact, it can be modelled as a dependent variable, and
autonomous and induced learning are important explanatory variables for the learning rate.
This paper also sheds new light on Adler & Clark's (1991) findings. They found that
induced learning can disrupt as well as facilitate the learning process. Our analysis confirms
this. However, we offer a systemic explanation based on the dimensions of the learning
process. Induced learning that yields both know-why and know-how enhances the learning
rate, whereas induced learning that only yields know-why can disrupt the learning process.
In Mukherjee et al. (in press) we suggested future research concerning the reproducibility
of our work and the development of more rigorous definitions of conceptual and opera-
tional learning. Here, having confirmed our project level findings at the factory level, we
re-emphasize the importance of researching the organizational systems for consistently pro-
ducing and supporting conceptual and operational learning. Further study of sophisticated
experimentation in the factory could build on Bohn's work on experimentation (1987).
This paper focuses on the autonomous/induced learning dimension from Dutton &
Thomas's (1984) framework. Future research should include their endogenous/exogenous
dimension. This requires the study of multiple production units. Which types of knowledge
23
are easier to transfer? Argote, Epple and others have studied the transfer of learning by
doing (e.g. Argote et al. 1990), yet the transfer of different types of knowledge has received
little attention in empirical learning curve research.
The current learning curve study focuses on a quality measure. Another important area
for future research would be the development and estimation of learning curve models for
productivity/cost measures with a theoretical footing. We believe that answers to these
questions will enhance firms' efforts to manage and measure their learning curve processes.4
Appendix A: Learning Process Questions
1. Use of statistical experimentation in the project
1 none, 2 moderate use of seven statistical tools, 3 extensive use of seven statistical
tools and/or ad hoc experiments, 4 natural experiments, 5 controlled experiments
2. Use of scientific models or R&D/engineering staff
1 none ... 5 extensive
3. Detailed design
Number of levels in the Ishikawa diagram used in the final solution
4. Degree of modification of action variables or Ishikawa diagram
1 no change ... 5 major change/primary variable dropped or added
5. Follow-up of experimental results, in the testing stage of the project
1 no sufficient follow-up nor improvement in the mean or the variance of the focal
variable ... 5 for sufficient follow-up (large period, or large sample size) a distinct
improvement in the mean and/or the variance of the focal variable
4We gratefully acknowledge the thoughtful comments made by Roger Bohn, Melissa Schilling, Ludo Van
der Heyden, an associate editor and three anonymous referees. We thank the management and employees
of N.V. Bekaert, S.A. for their unstinting cooperation. This research was supported by INSEAD, and (for
part of the field research) the Harvard Business School Division of Research. The work by Michael Lapre
was supported by Arthur D. Little, Inc., N.V. Bekaert, S.A., INSEAD and the Sasakawa Foundation.
24
Appendix B: Correlations and Robustness Tests
In W
In t
In q
hat
—0.779
lnq
—0.796
0.999
lnz
—0.898
0.881
0.899Correlations for the traditional learning curve models
z Cxz CUL° x z CL cir x z ClicL° x z Cli cli° x z
In W
z
Cx z
CUL° x z
CUFF x z
Cli cL° x z
—0.898 —0.848
0.932
—0.871
0.954
0.991
—0.854
0.937
0.997
0.990
—0.770
0.875
0.981
0.954
0.970
—0.859
0.921
0.993
0.981
0.987
0.964Correlations for the quality learning curve models
As can be expected, the cumulative project variables are highly correlated. This, however,
does not pose a multicollinearity problem if there are periods with faster project accumu-
lation of one type associated with accelerated waste reduction, and/or if for another type
faster project accumulation coincides with slower waste reduction. Two project types were
significant in model (12): Cli cli° and Cli c11°. These are graphed in figure 6. Cli cli° grew
faster in mid 87-mid 88 and early 90, two periods of accelerated waste reduction (figure 3).
ClicL° grew faster in mid 88-mid 89, during which waste flattened (figure 3). So even though
the independent variables are highly correlated, this does not prevent different patterns of
project knowledge accumulation from explaining changes in the rate of waste reduction.
Figure 6 about here
We also tested the robustness of row 6 in table 1. The projects were categorized in a 2 x 2
matrix defined by the median values for conceptual and operational learning. We lowered the
25
split up value for conceptual learning until one project jumped from one category to another.
We further lowered the split up value until the next project switched to another category.
This gave us two alternative categorizations. We obtained two more by increasing the split
up value instead of lowering it. Likewise, we obtained four alternative categorizations by
changing the split up value for operational learning. For all eight categorizations, we re-
defined the four cumulative project variables and re-estimated equation (12). The R es varied
between 0.777 and 0.792 (cf. 0.790 in table 1). /3, and 1j2 were never statistically significant
at 0.05. 43 was always positive and significant at 0.05, f34 was always negative and 7 out of
8 times significant at 0.05, only once did the p-value go up to 0.07. From these additional
tests it seems that the estimates in row 6 in table 1 are rather robust.
References
Adler, P.S, "When Knowledge is the Critical Resource, Knowledge Management is the
Critical Task," IEEE Transactions on Engineering Management, 36, 2 (1989), 87-94
Adler, P.S. and K.B. Clark "Behind the Learning Curve: A Sketch of the Learning Process,"
Management Science, 37 (1991), 267-281
Argote, L., S.L. Beckman and D. Epple, "The Persistence and Transfer of Learning in
Industrial Settings," Management Science, 36 (1990), 140-154
Bohn, R.E., Learning by Experimentation in Manufacturing, HBS Working Paper 88-001,
1987
Bohn, R.E., "Measuring and Managing Technological Knowledge," Sloan Management Re-
view, (Fall 1994), 61-73
Cangelosi, V.E. and W.R. Dill, "Organizational Learning: Observations Toward a Theory,"
Administrative Science Quarterly, 10 (1965), 175-203
Deming, W.E., Quality, Productivity, and Competitive Position, MIT Center for Advanced
Engineering Study, Cambridge, 1982
Duncan, R. and A. Weiss, "Organizational Learning: Implications for Organizational De-
26
sign," Research in Organizational Behavior, 1 (1979), 75-123
Dutton, J.M. and A. Thomas, "Treating Progress Functions as a Managerial Opportunity,"
Academy of Management Review, 9 (1984), 235-247
Epple, D., L. Argote and K. Murphy, "An Empirical Investigation of the Micro Struc-
ture of Knowledge Acquisition and Transfer Through Learning by Doing," Operations
Research, 44 (1996), 77-86
Fiol, C.M. and M.A. Lyles, "Organizational Learning," Academy of Management Review,
10 (1985), 803-813
Hackman, J.R. and R. Wageman, "Total Quality Management: Empirical, Conceptual, and
Practical Issues," Administrative Science Quarterly, 40 (1995), 309-342
Hayes, R.H. and K.B. Clark, "Exploring the Sources of Productivity Differences at the
Factory Level," in The Uneasy Alliance, K.B. Clark et al. (Eds.) HBS Press, 1985
Hax, A.C. and N.S. Majluf, "Competitive Cost Dynamics: The Experience Curve," Inter-
faces, 12, 5 (1982), 50-61
Jaikumar, R. and R.E. Bohn, "A Dynamic Approach to Operations Management: An
Alternative to Static Optimization," International Journal of Production Economics,
27 (1992), 265-282
Juran, J.M., and F.M. Gryna, Quality Planning and Analysis, McGraw-Hill, 1993
Kim, D.H., "The Link between Inidividual and Organizational Learning," Sloan Manage-
ment Review, (Fall 1993), 37-50
Leonard-Barton, D., "The Factory as a Learning Laboratory," Sloan Management Review,
(Fall 1992), 23-38
Levy, F.K., "Adaptation in the Production Process," Management Science, 11 (1965), B-
136-B-154
Lieberman, M.B., "The Learning Curve and Pricing in the Chemical Processing Industries,"
RAND Journal of Economics, (Summer 1984), 213-228
March, J.G. and J.P. Olsen, "The Uncertainty of the Past: Organizational Learning under
27
Ambiguity," European Journal of Political Research, 3 (1975), 147-171
March, J.G. and H.A. Simon, Organizations, Wiley, 1958
Mishina, K., "Learning by New Experiences," HBS Working Paper 92-084, 1992
Mukherjee, A.S., The Effective Management of Organizational Learning and Process Con-
trol in the Factory, Unpublished Doctoral Dissertation, HBS, Boston, 1992
Mukherjee, A.S., M.A. Lapre and L.N. Van Wassenhove, "Knowledge Driven Quality Im-
provement," Management Science, (in press)
Mukherjee, A.S. and L.N. Van Wassenhove, "The Impact of Knowledge on Quality," in
The Practice of Quality Management, P.J. Lederer and U.S. Karmarkar (Eds.), Kluwer
Academic Publishers, 1997
Muth, J.F., "Search Theory and the Manufacturing Progress Function," Management Sci-
ence, 32 (1986), 948-962
Pisano, G.P., "The Development Factory: Unlocking the Potential of Process Innovation,"
HBS Press, 1997
Schneiderman, A.M. "Optimum Quality Costs and Zero Defects: Are They Contradictory
Concepts?," Quality Progress, (November 1986), 28-31
Schneiderman, A.M., "Setting Quality Goals," Quality Progress, (April 1988), 51-57
Sterman, J.D., "Learning in and about Complex Systems," System Dynamics Review, 10
(1994), 291-330
Teece, D. and G. Pisano, "The Dynamic Capabilities of Firms: an Introduction," Industrial
and Corporate Change, 3, 3 (1994), 537-556
Von Hippel, E. and M.J. Tyre, "How Learning by Doing is Done: Problem Identification
in Novel Process Equipment," Research Policy, 24 (1995), 1-12
Wadsworth, H.M., K.S. Stephens and A.B. Godfrey, Modern Methods for Quality Control
and Improvement, Wiley, 1986
Yelle, L.E., "The Learning Curve: Historical Review and Comprehensive Survey," Decision
Sciences, 10 (1979), 302-328
28
Traditional Learning Curve Estimates
In t In q In z p R2
(1) -0.18* -0.66* 0.246
(-5.01) (-7.75)
(2) -0.18* -0.65* 0.279
(-5.46) (-7.49)
(3) -1.32* -0.43* 0.631
(-11.5) (-4.14)
Quality Learning Curve Estimates
z C x z CUL° x z CL c 1-1° x z CH cL° xz Clic li° xz p R2
(4) -323' -0.42* 0.636
(-11.6) (-4.05)
(5) -289* 0.27 -0.42* 0.639
(-3.96) (-0.51) (-4.01)
(6) -227* -0.93 -0.65 7.33* -8.23* -0.20 0.790
(-3.15) (-0.19) (-0.13) (2.71) (-2.26) (-1.70)Dependent variable In W. Sample size 80.
Coefficient estimates for independent variables in rows (4)-(6) x 10-6.
T-statistics in parentheses. * signifies significant at 0.05 in a 2-tail test.
Table 1: Learning Curve Estimates
29
Dry Drawing Heat treatment Wet Wire Drawing BunchingBrass coating
$41:111411102Process
0 q q q 0 0 q q q qq q q 0 q q q q q q
—k- q 0 q 0 q -0-00 q 00q q 0 q 0 q q q 0 q0 0 0 0 0 q 0 0 0 0
I 1
I I
unvalidated theories operationally validated
high (CI-I'L') theories (CI-1'11°)
+3.2% * —3.6%*
firefighting artisan skills
low (CUL') (CL'I-1°)
n.s. n.s.
low high
conceptual
learning
operational learning
Table 2: Impact of four types of induced learning: percentage change in the initial learning rate
by adding one project (a negative sign means faster waste reduction). * signifies significant at 0.05
in a 2-tail test. n.s. means not significant.
Factoryfloor
Figure 1: Simplified, schematic process flow of a Bekaert factory. In reality several steps are
repeated. An example of dynamic complexity is incomplete knowledge of the effects of upstream
process settings on downstream quality. Incomplete knowledge combined with heterogeneous inputs
and hundreds of process variables to control often gives rise to ambiguity concerning causes of
production problems.
30
Conceptual
use experiments (.81)
Learning use science (.70)
detail offinal design
(.65)
modify actionvariables (.66)
follow-upof results
(.91)
OperationalLearning
Figure 2: Mapping of factors onto Kim's (1993) conceptual and operational learning (factor
loadings in parentheses)
' _w 1
1984
1985
1986
1987
1988
1989
1990
1991
Figure 3: Waste evolution (W). To protect Bekaert's proprietary data, we do not report the scale
on the vertical axis, nor do we report the estimate of the intercept.
31
E
O
E
E
es
E
O
1984
1985
1986
1987
1988
1989
1990
1991
Figure 4: Production (x) and scale-up (z) history
Time
Conceptual Operational Project Link tolearning learning completion waste
Figure 5: Timeline of events measured for each project
16—
14 m
"2
12 —ca.
``a 10-Lm.ctE 8-c=
6 —
4 —E
2—
0
CHLCHH
1 1984 1985 1986 1987 1988 1989 1990 1991
Figure 6: Evolution of unvalidated theories (CIFL°) and operationally validated theories (C1-19.1°)
32