Project Summary: Laurel Street W Narrative Description of Project: 2018-537 / Laurel Street W Labor Hours Labor Cost Equipment Cost Material Cost Contractor Cost Indirect Labor Total Cost AUDIT / Audit Project 0.5 $10.90 $0.00 $0.00 $0.00 $0.00 $10.90 HAUL / Hauling 23.0 $512.21 $216.66 $60.20 $0.00 $331.66 $1,120.73 RSDCL / Roadside Ditch - Cleanout 35.0 $797.95 $227.39 $38.06 $0.00 $517.60 $1,580.99 UTLOC / Utility locates 1.0 $24.70 $0.00 $0.00 $0.00 $13.23 $37.93 2018-537 / Laurel Street W Sub Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $2,750.55 Grand Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $2,750.55 Project improved 1,276 L.F. of drainage system. Cleaned out 1,276 L.F. of roadside ditch. Activity: Routine/Preventive Maintenance Duration: 10/18/17-10/24/17 Beaufort County Public Works Stormwater Infrastructure Project Summary Before During After

Upload: others

Post on 29-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Beaufort County Public Works Stormwater Infrastructure ... P… · 2018-537 / Laurel Street W Sub Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $ ... Activity: Routine/Preventive

Project Summary: Laurel Street W

Narrative Description of Project:

2018-537 / Laurel Street W LaborHours

LaborCost

EquipmentCost

MaterialCost

ContractorCost

Indirect Labor

Total Cost

AUDIT / Audit Project 0.5 $10.90 $0.00 $0.00 $0.00 $0.00 $10.90HAUL / Hauling 23.0 $512.21 $216.66 $60.20 $0.00 $331.66 $1,120.73RSDCL / Roadside Ditch - Cleanout 35.0 $797.95 $227.39 $38.06 $0.00 $517.60 $1,580.99UTLOC / Utility locates 1.0 $24.70 $0.00 $0.00 $0.00 $13.23 $37.932018-537 / Laurel Street W Sub Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $2,750.55Grand Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $2,750.55

Project improved 1,276 L.F. of drainage system. Cleaned out 1,276 L.F. of roadside ditch.

Activity: Routine/Preventive MaintenanceDuration: 10/18/17-10/24/17

Beaufort County Public WorksStormwater Infrastructure

Project Summary

Before During After

Page 2: Beaufort County Public Works Stormwater Infrastructure ... P… · 2018-537 / Laurel Street W Sub Total 59.5 $1,345.76 $444.05 $98.26 $0.00 $862.49 $ ... Activity: Routine/Preventive

PINE GROVE RD

LAUREL ST W

LAUREL ST E

SHANKLIN RD

LegendDrainage Type

Access PipeBleeder PipeChannel PipeChannelStreamCrossline PipeDriveway PipeLateralLateral PipeRiverRoad PipeRoadsideRoadside Pipe

®Project: LaurelStreet WActivity: Routine/Preventive MaintenaceProject #:2018-537Township/SW Dist:Port Royal Island/6Completed:October 2017

0 60 120 180 24030Feet 1 inch = 130 feet

Prepared By: BC Stormwater Management UtilityDate Print:04/11/18File:C:\project summaries map/Laurel Street W_2018-537

Cleaned out 649 LF of roadside ditch.

Cleaned out 627 LF of roadside ditch.