Beamline 8.3.2 Radiation ShieldingBeamline Design Review
17 April, 2006
Background
• Radiation leak discovered during annual white-light survey
• Surgical inspection revealed that:– Lead had shifted slightly– Corner section was not built
to specification
• Actions taken:– All lead lined hutches are to
be inspected and reviewed– All lead lined hutches moved
to Pre-Commissioned status
Shielding Inspection Criteria
• Verify that lead shielding is either:– Contiguous– Properly overlapped
• Ensure that shielding is secure and will not move
• Document and Archive
Shielding Defining Process
• Determine types of panels and shielding– Exploratory surgery– Compare to mfg drawings
• Develop repair plan:– Procedure for panel repair– Process for documentation
Shielding panel types
• Three types of shielding panels on the hutch:
–Structural (S)–Non-Structural (NS)–Corners (C)
• Additional regions–Doors–Support Structure over door
X-rays
PLAN VIEW
S
NS
C
NSNS
NSNS
NS
C
CC
S
S
Shielding Repair Approach
• Documentation– Generate tracking methods for each panel– Record panel information and repairs– Archive documents, drawings and photos.
• Three basic shielding repair “actions” to hutch panels:
– Skinning (structural & corners)– Securing (non-structural & doors)– Surveying (roof, H – panels, labyrinths)
8.3.2 Shielding Documentation
• Documentation note– Includes explanation– Defines numbering
system for panels and references drawing
– Provides repair forms for each panel
– Will serve to record repairs with forms and photos.
“Skinning” Example documentation
• Corner Panels– Fill out inspection sheet
– Photograph lead
– Re-skin with 5mm lead
– Cover with steel
“Skinning” Example documentation 2
• Door Support Structure– Fill out inspection sheet
– Re-skin with 5mm lead
– Photograph before install
– Cover with steel
“Securing” repair process
• Non Structural Panels– Inspect Lead– Photograph
• Overall Picture• Quadrants
– Install Support Bar– Install Cover Plate
“Securing” Inspection
A
B
C
D
“Securing” Support bar
“Securing” Assembly view
“Securing” Attachment view
“Securing” Example Documentation 2
• Doors– Remove doors – Cut into and Inspect lead– Photograph– Install Support Bars – Install Cover Plate– Re-install doors
“Surveying” Repair process
• Survey panels– Roof panels– H - panels– Labyrinths
• Survey Process– Inspect panels– Perform commissioning
survey per procedure– Complete forms
“Surveying” Commissioning checklist
“Surveying” Example documentation
• Roof panels– Inspect panels– Perform commissioning
survey per procedure– Complete forms
Open issues…..
• Complete documentation note with deails, process for repair and drawings for each panel on hutch
• Review of Commissioning radiation survey procedure – All concerns must be addressed regarding actual
process.
• Structural Calculations– INC is reviewing hutch design with added lead– If additional structure is needed a design could be
added to the corners
Plan of Attack
• Immediate Actions:–Non-Structural Panels
• Inspect/Repair/Secure–Doors
• Remove• Inspect/Repair/Secure
–Labyrinths• Remove/Inspect
–Roof Cover Plates• Fabricate Lead• Inspect/Install
– Inspect C-Channels on Joining Plates
• Near Term Actions–Structural Calculations–Re-Skin
• Structural Panels• Door Support
Structure• Corners
• During Re-Commissioning–Verify H-Channels on
Joining Plates–Survey All Panels
Questions?
Panels to be “Skinned”