beam commissioning schedule and staff p. emma accelerator readiness review dec. 4, 2008
DESCRIPTION
LCLS. Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008. Goals Radiation Surveys Manpower Organization. http://www-ssrl.slac.stanford.edu/lcls/commissioning/. Nov 2008…. Commission Jan-Aug 2008. Commission Mar-Aug 2007. LCLS Accelerator Layout. - PowerPoint PPT PresentationTRANSCRIPT
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20081
SLAC National Accelerator Laboratory
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff P. EmmaP. Emma
Accelerator Readiness ReviewAccelerator Readiness Review
Dec. 4, 2008Dec. 4, 2008
LCLSLCLS
GoalsGoals
Radiation SurveysRadiation Surveys
ManpowerManpower
OrganizationOrganization
http://www-ssrl.slac.stanford.edu/lcls/commissioning/http://www-ssrl.slac.stanford.edu/lcls/commissioning/
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20082
SLAC National Accelerator Laboratory
LCLSLCLS Accelerator Layout Accelerator Layout
SLAC linac tunnelSLAC linac tunnel research yardresearch yard
Linac-0Linac-0L L =6 m=6 m
Linac-1Linac-1L L 9 m9 m
rf rf 25°25°
Linac-2Linac-2L L 330 m330 mrf rf 41°41°
Linac-3Linac-3L L 550 m550 mrf rf 0° 0°
BC1BC1L L 6 m6 m
RR5656 39 mm39 mm
BC2BC2L L 22 m22 m
RR5656 25 mm25 mm DL2 DL2 L L =275 m=275 mRR56 56 0 0
DL1DL1L L 12 m12 mRR56 56 0 0
undulatorundulatorL L =130 m=130 m
6 MeV6 MeVz z 0.83 mm 0.83 mm 0.05 %0.05 %
135 MeV135 MeVz z 0.83 mm 0.83 mm 0.10 %0.10 %
250 MeV250 MeVz z 0.19 mm 0.19 mm 1.6 %1.6 %
4.30 GeV4.30 GeVz z 0.022 mm 0.022 mm 0.71 %0.71 %
13.6 GeV13.6 GeVz z 0.022 mm 0.022 mm 0.01 %0.01 %
Linac-Linac-XXL L =0.6 m=0.6 mrfrf= =
21-1b,c,d
...existinglinac
L0-a,b
rfrfgungun
21-3b24-6dX
25-1a30-8c
undulatorundulator
Commission Mar-Aug 2007Commission Mar-Aug 2007 Commission Jan-Aug 2008Commission Jan-Aug 2008 Nov 2008…Nov 2008…
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20083
SLAC National Accelerator Laboratory
LCLS Commissioning Web-PageLCLS Commissioning Web-Pageh
ttp
://w
ww
-ssr
l.sla
c.st
an
ford
.ed
u/lc
ls/c
om
mis
sio
nin
g/
htt
p:/
/ww
w-s
srl.s
lac.
sta
nfo
rd.e
du
/lcls
/co
mm
issi
on
ing
/
Phase-IIPhase-IIPhase-IPhase-I Phase-IIIPhase-III
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20084
SLAC National Accelerator Laboratory
Design and Typical Measured Parameters Design and Typical Measured Parameters (Aug. 2008)(Aug. 2008)
ParameterParameter symbolsymbol designdesign measuredmeasured unitunit
Final linac Final linac ee energy energy mcmc22 13.613.6 13.613.6 MeVMeV
Bunch chargeBunch charge QQ 11 0.250.25 nCnC
Initial bunch length (rms)Initial bunch length (rms) z0z0 0.90.9 0.750.75 mmmm
Final bunch length (rms)Final bunch length (rms) zfzf 2020 8-108-10 mm
ProjectedProjected emittance (injector) emittance (injector) xx,,yy 1.21.2 0.7-1.00.7-1.0 μμmm
SliceSlice emittance (injector) emittance (injector) ssxx,,yy 1.01.0 0.60.6 μμmm
ProjectedProjected emittance (linac end) emittance (linac end) LLxx,,yy 1.51.5 0.7, 1.6*0.7, 1.6* μμmm
Single bunch repetition rateSingle bunch repetition rate ff 120120 3030 HzHz
RF gun field at cathodeRF gun field at cathode EEgg 120120 115115 MV/mMV/m
Laser energy on cathodeLaser energy on cathode uull 250250 20-15020-150 μμJJ
Laser diameter on cathodeLaser diameter on cathode 22RR 1.51.5 1.21.2 mmmm
Cathode quantum efficiencyCathode quantum efficiency QEQE 66 0.7-70.7-7 101055
* horizontal slice emittance likely < 1 * horizontal slice emittance likely < 1 µµmm
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20085
SLAC National Accelerator Laboratory
GoalsGoals
1)1) Re-establish Linac OperationsRe-establish Linac Operations
2)2) Transport Transport ee to main dump (~14 GeV, to main dump (~14 GeV,
200 pC, 200 pC, 10 Hz)10 Hz)
3)3) Verify all new components (BPMs, Verify all new components (BPMs,
screens, magnets, wires, software, etc)screens, magnets, wires, software, etc)
4)4) Verify all new photon diagnostics (FEE)Verify all new photon diagnostics (FEE)
5)5) Commission MPS & BCSCommission MPS & BCS
6)6) Fully characterize electron beamFully characterize electron beam
7)7) Align undulator using beam-based methodAlign undulator using beam-based method
8)8) Characterize X-ray radiationCharacterize X-ray radiation
9)9) Establish CD-4 flux level in FEEEstablish CD-4 flux level in FEE
http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/2009_commissioning-goals.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/2009_commissioning-goals.doc
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20086
SLAC National Accelerator Laboratory
Pre-Beam CheckoutPre-Beam Checkout1)1) Check magnet polaritiesCheck magnet polarities
2)2) Check cable connectionsCheck cable connections
3)3) Check component serial numbersCheck component serial numbers
4)4) Check component installation Check component installation
orientationorientation
5)5) Check controls function (power, Check controls function (power,
motion, readback, etc)motion, readback, etc)
6)6) Check water connectionsCheck water connections
7)7) Label all components, etc…Label all components, etc…
http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/pre-beam-check-list-2009.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/pre-beam-check-list-2009.doc
51 pages, 2000 checks, 70% done51 pages, 2000 checks, 70% done
Separate list for undulator…Separate list for undulator…204 pages, 7200 checks, 10% done?204 pages, 7200 checks, 10% done?
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20087
SLAC National Accelerator Laboratory
Radiation SurveysRadiation Surveys
http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/part1_uncominitial-11-13-08.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/part1_uncominitial-11-13-08.doc
1)1) Beam to D2 in BSY (done) – Beam to D2 in BSY (done) – survey BTHW, etc.survey BTHW, etc.
2)2) Beam to und. stopper – survey Beam to und. stopper – survey BTH head house, mazes, etc.BTH head house, mazes, etc.
3)3) 14-GeV beam to main dump – 14-GeV beam to main dump – survey bldg. 921, FEE-wall, etc.survey bldg. 921, FEE-wall, etc.
4)4) 4-GeV beam to main dump - 4-GeV beam to main dump - survey bldg. 921, FEE-wall, etc.survey bldg. 921, FEE-wall, etc.
>1 week required when first beam transported into new halls (BTH, UH, Dump)
DRAFT
DRAFT
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20088
SLAC National Accelerator Laboratory
ManpowerManpowerLCLS Commissioning Phase-III: Nov. 2008 through July 2009 (36 wks)LCLS Commissioning Phase-III: Nov. 2008 through July 2009 (36 wks)
3 shifts per day (1-2 physicists 8:00-16:00 & 16:00-24:00, with 3 shifts per day (1-2 physicists 8:00-16:00 & 16:00-24:00, with operations coverage 24:00-8:00, unless more required)operations coverage 24:00-8:00, unless more required)
21 LCLS Physicists (all with LCLS experience)
Axel Brachmann (ASD)Dave Dowell (consultant - available 1 week/month)Franz-Josef Decker (ASD)Yuantao Ding (PPA)Paul EmmaJoe FrischSasha Gilevich (laser)Steve Edstrom (laser)Greg Hays (laser)Philippe Hering (laser)Zhirong Huang (PPA)Cecile Limborg (on leave until May, 2009)Henrik LoosRick IversonHeinz-Dieter NuhnDaniel Ratner (graduate student/PPA)Jim TurnerJim WelchBill White (laser)Juhao WuDao Xiang (post-doc, PPA)
…plus new help from PEP-II and beyond
Kirk BertscheSasha NovokhatskiJerry Yocky
+ LBNLSasha ZholentsBill Fawley
+ TriesteSimone Spampanati
+ DESY, PSI, …?
+ Operations, Controls, Power-conversion, RF, engineering, etc
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 20089
SLAC National Accelerator Laboratory
Physicist Commissioning Shifts SchedulePhysicist Commissioning Shifts Schedule
example
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 200810
SLAC National Accelerator Laboratory
With 36 total weeks, this distributes into the following weekly work load for each group (averaged over 36-week run).
LCLS Physicists: ~1 shift/wk (peak is higher depending on task)
Operators (3/shift): Operate accelerator and support commissioning
Chief Operator (EOIC): Leads operations crew during shift
Program Deputy: Makes daily decisions on program
Program Coordinator: (PE) Sets long-term program, shifts, access, etc.
Controls Deputy: Liaison to controls group to solve daily problems
Commiss’ng Engineer: Coordinate access/repair days and direct work
Manpower and OrganizationManpower and Organization
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 200811
SLAC National Accelerator Laboratory
Important Dates for 2008/2009 CommissioningImportant Dates for 2008/2009 Commissioning
Nov. 3, 2008:Nov. 3, 2008: Startup (establish beam to end of linac again)Startup (establish beam to end of linac again)
Dec. 10, 2008:Dec. 10, 2008: Install laser-heater undulator (1 day)Install laser-heater undulator (1 day)
Dec. 15, 2008:Dec. 15, 2008: First beam through LTU & to dump? (survey)First beam through LTU & to dump? (survey)
Dec. 19, 2008:Dec. 19, 2008: SLAC shuts down for holidaysSLAC shuts down for holidays
Jan. 5, 2009:Jan. 5, 2009: Startup again (establish beam in LTU & Startup again (establish beam in LTU &
dump)dump)
March 2, 2009:March 2, 2009: Install Install 25 undulators + PPS re-cert. (~2 wks)25 undulators + PPS re-cert. (~2 wks)
May 14, 2009:May 14, 2009: First x-ray beam in FEEFirst x-ray beam in FEE
July 2009:July 2009: Photons in NEHPhotons in NEH
August 2009:August 2009: Start AMO ExperimentStart AMO Experiment
December 2009:December 2009: Downtime for holidays + PPS re-cert. (~2 mo.)Downtime for holidays + PPS re-cert. (~2 mo.)
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 200812
SLAC National Accelerator Laboratory
Re-establishRe-establishee to SL2 to SL2
LTU/LTU/UndUnd
Comm. Comm.
Firs
t Li
ght
in
Firs
t Li
ght
in
FEE
FEE
Firs
t Li
ght
in F
EH
Firs
t Li
ght
in F
EH
NEH Ops & NEH Ops & CommissioningCommissioning
JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA
2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDownPPS
PPS
Linac/BC2 Linac/BC2 CommissioninCommissionin
g g FEL/FEEFEL/FEECommissioniCommissioni
ng ng Nov. 3, 2008Nov. 3, 2008
Inst
all
Inst
all U
ndula
tors
Undula
tors
MMDD
LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line
LTU
/Und
In
stall
LTU
/Und
In
stall
PEP-I
I ru
n
PEP-I
I ru
n
ends
ends
FEE/N
EH
In
stall
FEE/N
EH
In
stall
PPS C
ert
. LT
U/D
um
pPPS C
ert
. LT
U/D
um
p
CD-4
CD-4
(7
/31
/201
0)
(7/3
1/2
01
0)
X-R
ays
in N
EH
X-R
ays
in N
EH
DDDown?Down?
FEH
Hutc
h B
OFE
H H
utc
h B
O
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 200813
SLAC National Accelerator Laboratory
LTU/Undulator/FEE/FEL CommissioningLTU/Undulator/FEE/FEL Commissioning
H. TompkinsH. Tompkins
+ heater+ heater
Paul EmmaPaul Emma
Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu
Dec. 4, 2008Dec. 4, 200814
SLAC National Accelerator Laboratory
Beam Appears Bright Enough for FEL Saturation at 0.15 nmBeam Appears Bright Enough for FEL Saturation at 0.15 nm
Calculation based on measured end-of-linac Calculation based on measured end-of-linac projectedprojected emittance values, measured peak emittance values, measured peak current, and design undulator parameters (assuming undulator alignment and current, and design undulator parameters (assuming undulator alignment and 0.01% 0.01% rms slice energy spread – not yet measurable) rms slice energy spread – not yet measurable)
M. Xie method, with wakesM. Xie method, with wakes
FEL Power3D Gain Length
FEL Power3D Gain Length