beam commissioning schedule and staff p. emma accelerator readiness review dec. 4, 2008

14
Paul Emma Paul Emma Beam Commissioning Schedule and Beam Commissioning Schedule and Staff Staff [email protected] [email protected] u Dec. 4, 2008 Dec. 4, 2008 1 SLAC National Accelerator Laboratory Beam Commissioning Schedule and Beam Commissioning Schedule and Staff Staff P. Emma P. Emma Accelerator Readiness Review Accelerator Readiness Review Dec. 4, 2008 Dec. 4, 2008 LCLS LCLS Goals Goals Radiation Surveys Radiation Surveys Manpower Manpower Organization Organization http://www-ssrl.slac.stanford.edu/lcls/commissioning/ http://www-ssrl.slac.stanford.edu/lcls/commissioning/

Upload: creola

Post on 23-Jan-2016

47 views

Category:

Documents


0 download

DESCRIPTION

LCLS. Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008. Goals Radiation Surveys Manpower Organization. http://www-ssrl.slac.stanford.edu/lcls/commissioning/. Nov 2008…. Commission Jan-Aug 2008. Commission Mar-Aug 2007. LCLS Accelerator Layout. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20081

SLAC National Accelerator Laboratory

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff P. EmmaP. Emma

Accelerator Readiness ReviewAccelerator Readiness Review

Dec. 4, 2008Dec. 4, 2008

LCLSLCLS

GoalsGoals

Radiation SurveysRadiation Surveys

ManpowerManpower

OrganizationOrganization

http://www-ssrl.slac.stanford.edu/lcls/commissioning/http://www-ssrl.slac.stanford.edu/lcls/commissioning/

Page 2: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20082

SLAC National Accelerator Laboratory

LCLSLCLS Accelerator Layout Accelerator Layout

SLAC linac tunnelSLAC linac tunnel research yardresearch yard

Linac-0Linac-0L L =6 m=6 m

Linac-1Linac-1L L 9 m9 m

rf rf 25°25°

Linac-2Linac-2L L 330 m330 mrf rf 41°41°

Linac-3Linac-3L L 550 m550 mrf rf 0° 0°

BC1BC1L L 6 m6 m

RR5656 39 mm39 mm

BC2BC2L L 22 m22 m

RR5656 25 mm25 mm DL2 DL2 L L =275 m=275 mRR56 56 0 0

DL1DL1L L 12 m12 mRR56 56 0 0

undulatorundulatorL L =130 m=130 m

6 MeV6 MeVz z 0.83 mm 0.83 mm 0.05 %0.05 %

135 MeV135 MeVz z 0.83 mm 0.83 mm 0.10 %0.10 %

250 MeV250 MeVz z 0.19 mm 0.19 mm 1.6 %1.6 %

4.30 GeV4.30 GeVz z 0.022 mm 0.022 mm 0.71 %0.71 %

13.6 GeV13.6 GeVz z 0.022 mm 0.022 mm 0.01 %0.01 %

Linac-Linac-XXL L =0.6 m=0.6 mrfrf= =

21-1b,c,d

...existinglinac

L0-a,b

rfrfgungun

21-3b24-6dX

25-1a30-8c

undulatorundulator

Commission Mar-Aug 2007Commission Mar-Aug 2007 Commission Jan-Aug 2008Commission Jan-Aug 2008 Nov 2008…Nov 2008…

Page 3: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20083

SLAC National Accelerator Laboratory

LCLS Commissioning Web-PageLCLS Commissioning Web-Pageh

ttp

://w

ww

-ssr

l.sla

c.st

an

ford

.ed

u/lc

ls/c

om

mis

sio

nin

g/

htt

p:/

/ww

w-s

srl.s

lac.

sta

nfo

rd.e

du

/lcls

/co

mm

issi

on

ing

/

Phase-IIPhase-IIPhase-IPhase-I Phase-IIIPhase-III

Page 4: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20084

SLAC National Accelerator Laboratory

Design and Typical Measured Parameters Design and Typical Measured Parameters (Aug. 2008)(Aug. 2008)

ParameterParameter symbolsymbol designdesign measuredmeasured unitunit

Final linac Final linac ee energy energy mcmc22 13.613.6 13.613.6 MeVMeV

Bunch chargeBunch charge QQ 11 0.250.25 nCnC

Initial bunch length (rms)Initial bunch length (rms) z0z0 0.90.9 0.750.75 mmmm

Final bunch length (rms)Final bunch length (rms) zfzf 2020 8-108-10 mm

ProjectedProjected emittance (injector) emittance (injector) xx,,yy 1.21.2 0.7-1.00.7-1.0 μμmm

SliceSlice emittance (injector) emittance (injector) ssxx,,yy 1.01.0 0.60.6 μμmm

ProjectedProjected emittance (linac end) emittance (linac end) LLxx,,yy 1.51.5 0.7, 1.6*0.7, 1.6* μμmm

Single bunch repetition rateSingle bunch repetition rate ff 120120 3030 HzHz

RF gun field at cathodeRF gun field at cathode EEgg 120120 115115 MV/mMV/m

Laser energy on cathodeLaser energy on cathode uull 250250 20-15020-150 μμJJ

Laser diameter on cathodeLaser diameter on cathode 22RR 1.51.5 1.21.2 mmmm

Cathode quantum efficiencyCathode quantum efficiency QEQE 66 0.7-70.7-7 101055

* horizontal slice emittance likely < 1 * horizontal slice emittance likely < 1 µµmm

Page 5: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20085

SLAC National Accelerator Laboratory

GoalsGoals

1)1) Re-establish Linac OperationsRe-establish Linac Operations

2)2) Transport Transport ee to main dump (~14 GeV, to main dump (~14 GeV,

200 pC, 200 pC, 10 Hz)10 Hz)

3)3) Verify all new components (BPMs, Verify all new components (BPMs,

screens, magnets, wires, software, etc)screens, magnets, wires, software, etc)

4)4) Verify all new photon diagnostics (FEE)Verify all new photon diagnostics (FEE)

5)5) Commission MPS & BCSCommission MPS & BCS

6)6) Fully characterize electron beamFully characterize electron beam

7)7) Align undulator using beam-based methodAlign undulator using beam-based method

8)8) Characterize X-ray radiationCharacterize X-ray radiation

9)9) Establish CD-4 flux level in FEEEstablish CD-4 flux level in FEE

http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/2009_commissioning-goals.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/2009_commissioning-goals.doc

Page 6: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20086

SLAC National Accelerator Laboratory

Pre-Beam CheckoutPre-Beam Checkout1)1) Check magnet polaritiesCheck magnet polarities

2)2) Check cable connectionsCheck cable connections

3)3) Check component serial numbersCheck component serial numbers

4)4) Check component installation Check component installation

orientationorientation

5)5) Check controls function (power, Check controls function (power,

motion, readback, etc)motion, readback, etc)

6)6) Check water connectionsCheck water connections

7)7) Label all components, etc…Label all components, etc…

http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/pre-beam-check-list-2009.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/pre-beam-check-list-2009.doc

51 pages, 2000 checks, 70% done51 pages, 2000 checks, 70% done

Separate list for undulator…Separate list for undulator…204 pages, 7200 checks, 10% done?204 pages, 7200 checks, 10% done?

Page 7: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20087

SLAC National Accelerator Laboratory

Radiation SurveysRadiation Surveys

http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/part1_uncominitial-11-13-08.dochttp://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/part1_uncominitial-11-13-08.doc

1)1) Beam to D2 in BSY (done) – Beam to D2 in BSY (done) – survey BTHW, etc.survey BTHW, etc.

2)2) Beam to und. stopper – survey Beam to und. stopper – survey BTH head house, mazes, etc.BTH head house, mazes, etc.

3)3) 14-GeV beam to main dump – 14-GeV beam to main dump – survey bldg. 921, FEE-wall, etc.survey bldg. 921, FEE-wall, etc.

4)4) 4-GeV beam to main dump - 4-GeV beam to main dump - survey bldg. 921, FEE-wall, etc.survey bldg. 921, FEE-wall, etc.

>1 week required when first beam transported into new halls (BTH, UH, Dump)

DRAFT

DRAFT

Page 8: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20088

SLAC National Accelerator Laboratory

ManpowerManpowerLCLS Commissioning Phase-III: Nov. 2008 through July 2009 (36 wks)LCLS Commissioning Phase-III: Nov. 2008 through July 2009 (36 wks)

3 shifts per day (1-2 physicists 8:00-16:00 & 16:00-24:00, with 3 shifts per day (1-2 physicists 8:00-16:00 & 16:00-24:00, with operations coverage 24:00-8:00, unless more required)operations coverage 24:00-8:00, unless more required)

21 LCLS Physicists (all with LCLS experience)

Axel Brachmann (ASD)Dave Dowell (consultant - available 1 week/month)Franz-Josef Decker (ASD)Yuantao Ding (PPA)Paul EmmaJoe FrischSasha Gilevich (laser)Steve Edstrom (laser)Greg Hays (laser)Philippe Hering (laser)Zhirong Huang (PPA)Cecile Limborg (on leave until May, 2009)Henrik LoosRick IversonHeinz-Dieter NuhnDaniel Ratner (graduate student/PPA)Jim TurnerJim WelchBill White (laser)Juhao WuDao Xiang (post-doc, PPA)

…plus new help from PEP-II and beyond

Kirk BertscheSasha NovokhatskiJerry Yocky

+ LBNLSasha ZholentsBill Fawley

+ TriesteSimone Spampanati

+ DESY, PSI, …?

+ Operations, Controls, Power-conversion, RF, engineering, etc

Page 9: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 20089

SLAC National Accelerator Laboratory

Physicist Commissioning Shifts SchedulePhysicist Commissioning Shifts Schedule

example

Page 10: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 200810

SLAC National Accelerator Laboratory

With 36 total weeks, this distributes into the following weekly work load for each group (averaged over 36-week run).

LCLS Physicists: ~1 shift/wk (peak is higher depending on task)

Operators (3/shift): Operate accelerator and support commissioning

Chief Operator (EOIC): Leads operations crew during shift

Program Deputy: Makes daily decisions on program

Program Coordinator: (PE) Sets long-term program, shifts, access, etc.

Controls Deputy: Liaison to controls group to solve daily problems

Commiss’ng Engineer: Coordinate access/repair days and direct work

Manpower and OrganizationManpower and Organization

Page 11: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 200811

SLAC National Accelerator Laboratory

Important Dates for 2008/2009 CommissioningImportant Dates for 2008/2009 Commissioning

Nov. 3, 2008:Nov. 3, 2008: Startup (establish beam to end of linac again)Startup (establish beam to end of linac again)

Dec. 10, 2008:Dec. 10, 2008: Install laser-heater undulator (1 day)Install laser-heater undulator (1 day)

Dec. 15, 2008:Dec. 15, 2008: First beam through LTU & to dump? (survey)First beam through LTU & to dump? (survey)

Dec. 19, 2008:Dec. 19, 2008: SLAC shuts down for holidaysSLAC shuts down for holidays

Jan. 5, 2009:Jan. 5, 2009: Startup again (establish beam in LTU & Startup again (establish beam in LTU &

dump)dump)

March 2, 2009:March 2, 2009: Install Install 25 undulators + PPS re-cert. (~2 wks)25 undulators + PPS re-cert. (~2 wks)

May 14, 2009:May 14, 2009: First x-ray beam in FEEFirst x-ray beam in FEE

July 2009:July 2009: Photons in NEHPhotons in NEH

August 2009:August 2009: Start AMO ExperimentStart AMO Experiment

December 2009:December 2009: Downtime for holidays + PPS re-cert. (~2 mo.)Downtime for holidays + PPS re-cert. (~2 mo.)

Page 12: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 200812

SLAC National Accelerator Laboratory

Re-establishRe-establishee to SL2 to SL2

LTU/LTU/UndUnd

Comm. Comm.

Firs

t Li

ght

in

Firs

t Li

ght

in

FEE

FEE

Firs

t Li

ght

in F

EH

Firs

t Li

ght

in F

EH

NEH Ops & NEH Ops & CommissioningCommissioning

JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA

2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDownPPS

PPS

Linac/BC2 Linac/BC2 CommissioninCommissionin

g g FEL/FEEFEL/FEECommissioniCommissioni

ng ng Nov. 3, 2008Nov. 3, 2008

Inst

all

Inst

all U

ndula

tors

Undula

tors

MMDD

LCLSLCLS Installation and Commissioning Time-Line Installation and Commissioning Time-Line

LTU

/Und

In

stall

LTU

/Und

In

stall

PEP-I

I ru

n

PEP-I

I ru

n

ends

ends

FEE/N

EH

In

stall

FEE/N

EH

In

stall

PPS C

ert

. LT

U/D

um

pPPS C

ert

. LT

U/D

um

p

CD-4

CD-4

(7

/31

/201

0)

(7/3

1/2

01

0)

X-R

ays

in N

EH

X-R

ays

in N

EH

DDDown?Down?

FEH

Hutc

h B

OFE

H H

utc

h B

O

Page 13: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 200813

SLAC National Accelerator Laboratory

LTU/Undulator/FEE/FEL CommissioningLTU/Undulator/FEE/FEL Commissioning

H. TompkinsH. Tompkins

+ heater+ heater

Page 14: Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

Paul EmmaPaul Emma

Beam Commissioning Schedule and StaffBeam Commissioning Schedule and Staff [email protected]@SLAC.Stanford.edu

Dec. 4, 2008Dec. 4, 200814

SLAC National Accelerator Laboratory

Beam Appears Bright Enough for FEL Saturation at 0.15 nmBeam Appears Bright Enough for FEL Saturation at 0.15 nm

Calculation based on measured end-of-linac Calculation based on measured end-of-linac projectedprojected emittance values, measured peak emittance values, measured peak current, and design undulator parameters (assuming undulator alignment and current, and design undulator parameters (assuming undulator alignment and 0.01% 0.01% rms slice energy spread – not yet measurable) rms slice energy spread – not yet measurable)

M. Xie method, with wakesM. Xie method, with wakes

FEL Power3D Gain Length

FEL Power3D Gain Length