baucau cement project - la'o hamutuk · 2020. 7. 9. · project 301012-02135 - baucau cement...

221
TL CEMENT, LDA Baucau Cement Project Limestone Mine Environmental Management Plan 301012-02135 – 301012-02135-EMP-003 3 February 2017 Venture Hotel - Rua Filomena De Camara Bidau Lecidere PO Box 7 Dili Timor Leste Telephone: +670 331 3238 & 331 3238 Facsimile: +670 772 8144 www.worleyparsons.com LPA 22548/MTCI/V/2011 © Copyright 2017 WorleyParsons (TL) LDA

Upload: others

Post on 26-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

Baucau Cement Project Limestone Mine Environmental Management Plan

301012-02135 – 301012-02135-EMP-003

3 February 2017

Venture Hotel - Rua Filomena De Camara Bidau Lecidere PO Box 7 Dili Timor Leste Telephone: +670 331 3238 & 331 3238 Facsimile: +670 772 8144 www.worleyparsons.com LPA 22548/MTCI/V/2011

© Copyright 2017 WorleyParsons (TL) LDA

Page 2: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

PROJECT 301012-02135 - BAUCAU CEMENT PROJECT

REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVAL

DATE CLIENT APPROVAL

DATE

1 FINAL – Rev1

A Jacobs

A Mratovich

D Hunter

3 Feb 2017

J Rhee

3 Feb 2017

Document No : 301012-02135-EMP-003 Page ii

Disclaimer

This report has been prepared on behalf of and for the exclusive use of TL Cement, LDA, and is

subject to and issued in accordance with the agreement between TL Cement, LDA and

WorleyParsons. WorleyParsons accepts no liability or responsibility whatsoever for it in respect of

any use of or reliance upon this report by any third party.

Copying this report without the permission of TL Cement, LDA and WorleyParsons is not

permitted.

Page 3: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page iii 301012-02135-EMP-003 Rev 1 : 3 February 2017

CONTENTS

A EXECUTIVE SUMMARY .................................................................................................... 9

B INTRODUCTION .............................................................................................................. 18

1.1 Environmental Management Framework .......................................................................... 18

1.2 Environmental Management Plan ..................................................................................... 18

1 PROJECT DESCRIPTION ............................................................................................... 20

1.1 Project Identification.......................................................................................................... 20

1.2 Details of Project Proponent ............................................................................................. 20

1.3 Project Environmental Impact Statement ......................................................................... 21

2 DETAILS OF EMP CONSULTANTS ............................................................................... 22

2.1 Local presence .................................................................................................................. 22

3 DESCRIPTION OF THE PROJECT ................................................................................. 29

3.1 Project component equipment and technology ................................................................ 29

3.1.1 Pre construction ................................................................................................... 29

3.1.2 Construction ......................................................................................................... 30

3.1.3 Operation ............................................................................................................. 32

3.1.4 Decommissioning ................................................................................................. 34

3.2 Project Location ................................................................................................................ 35

3.2.1 Nature of the project location ............................................................................... 36

3.3 EMP Endorsement ............................................................................................................ 37

4 LEGAL REQUIREMENTS ................................................................................................ 39

4.1 Legislation and legal framework ....................................................................................... 39

4.1.1 Environmental Legislation .................................................................................... 39

4.1.2 Biodiversity and protected areas legislation ........................................................ 40

4.1.3 Land legislation .................................................................................................... 41

4.1.4 Mineral Resources/Mining legislation .................................................................. 41

4.1.5 Labor legislation ................................................................................................... 42

4.2 Obligations ........................................................................................................................ 42

Page 4: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page iv 301012-02135-EMP-003 Rev 1 : 3 February 2017

4.3 Summary of Project Approvals ......................................................................................... 42

4.4 Summary of Environmental Standards ............................................................................. 43

5 INSTITUTIONAL ROLES AND RESPONSIBILITIES ...................................................... 45

6 SUMMARY OF IMPACTS ................................................................................................ 46

7 DESCRIPTION OF PROPOSED MITIGATION MEASURES .......................................... 54

7.1 Climate .............................................................................................................................. 54

7.2 Topography, Geology and Soils ....................................................................................... 55

7.3 Air Quality (including dust) ................................................................................................ 56

7.4 Noise and vibration ........................................................................................................... 58

7.5 Surface Water ................................................................................................................... 58

7.6 Groundwater ..................................................................................................................... 59

7.7 Flora .................................................................................................................................. 60

7.8 Fauna ................................................................................................................................ 61

7.9 Traffic ................................................................................................................................ 62

7.10 Infrastructure ................................................................................................................ 62

7.11 Employment.................................................................................................................. 63

7.12 Economic Use of Forestry and other Natural Resources ............................................. 64

7.13 Socio Economic Agriculture ......................................................................................... 65

7.14 Population and Community .......................................................................................... 65

7.15 Community Health ........................................................................................................ 66

7.16 Institutions, Schools and Health Facilities .................................................................... 67

7.17 Community and Family Structure ................................................................................. 67

7.18 Land Ownership and Land Rights ................................................................................ 68

7.19 Natural Resources Rights ............................................................................................ 68

7.20 Cultural Heritage, Archaeological and Sacred Sites .................................................... 69

7.21 Description of proposed mitigation measures .............................................................. 70

8 GOVERNING PARAMETERS ........................................................................................ 122

8.1 Environmental Quality Standards ................................................................................... 122

Page 5: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page v 301012-02135-EMP-003 Rev 1 : 3 February 2017

8.2 International Best Practice .............................................................................................. 122

8.3 Governing parameters .................................................................................................... 122

8.3.1 Emissions ........................................................................................................... 122

8.3.2 Ambient Water Quality Standards...................................................................... 122

8.3.3 Ambient Air Quality Standards ........................................................................... 123

8.3.4 Soil ..................................................................................................................... 124

8.3.5 Occupational Health and Safety Standards ....................................................... 125

8.4 Modelling or Engineering Calculations ........................................................................... 127

9 MONITORING PROGRAM ............................................................................................. 128

9.1 Climate ............................................................................................................................ 128

9.2 Topography and Soil ....................................................................................................... 129

9.3 Air Quality ....................................................................................................................... 129

9.4 Noise and vibration ......................................................................................................... 130

9.5 Surface water .................................................................................................................. 130

9.6 Groundwater ................................................................................................................... 131

9.7 Flora ................................................................................................................................ 131

9.8 Fauna .............................................................................................................................. 131

9.9 Traffic .............................................................................................................................. 132

9.10 Infrastructure .............................................................................................................. 133

9.11 Employment................................................................................................................ 133

9.12 Economic Use of Forestry and other Natural Resources ........................................... 133

9.13 Socio-Economic Agriculture ....................................................................................... 134

9.14 Population and community ......................................................................................... 134

9.15 Community Health ...................................................................................................... 134

9.16 Institutions schools and health facilities ..................................................................... 135

9.17 Community and Family Structure ............................................................................... 135

9.18 Land Ownership and Land Rights .............................................................................. 135

9.19 Natural Resources Rights .......................................................................................... 135

Page 6: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page vi 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.20 Cultural Heritage Archeological and Sacred Sites ..................................................... 136

9.21 Summary of monitoring program ................................................................................ 136

10 REPORTING REQUIREMENTS .................................................................................... 140

11 RESPONSIBILITIES FOR MITIGATION AND MONITORING ...................................... 147

12 EMERGENCY PLAN ...................................................................................................... 153

12.1 Purpose ...................................................................................................................... 153

12.2 Objective ..................................................................................................................... 153

12.3 Responsibilities .......................................................................................................... 153

12.4 Standards ................................................................................................................... 154

12.5 Incident Classification ................................................................................................. 154

12.6 Prevention .................................................................................................................. 155

12.7 Safety Data Sheets (SDS) .......................................................................................... 156

12.8 Spill Response ........................................................................................................... 157

12.8.1 Control ................................................................................................................ 157

12.8.2 Contain ............................................................................................................... 157

12.8.3 Clean Up ............................................................................................................ 157

12.9 Equipment .................................................................................................................. 158

12.9.1 Spill Response ................................................................................................... 158

12.9.2 First Aid Facilities and Personal Protective Equipment (PPE) .......................... 158

12.9.3 Fire Fighting Equipment ..................................................................................... 158

12.10 Training ....................................................................................................................... 159

13 DECOMMISSIONING PLAN .......................................................................................... 160

13.1 Preliminary Decommissioning Plan ............................................................................ 160

14 CAPACITY DEVELOPMENT AND TRAINING .............................................................. 167

15 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ................................. 168

15.1 Purpose of the consultation during the preparation of the EMP ................................ 168

15.2 Methodology and Approach ....................................................................................... 168

15.2.1 Identified Stakeholders ...................................................................................... 168

Page 7: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page vii 301012-02135-EMP-003 Rev 1 : 3 February 2017

15.2.2 Mechanism for Public Consultation.................................................................... 171

15.3 Summary of consultation activities carried out ........................................................... 171

15.4 Summary of main comments received from the public, community leaders, NGOs, local

officials, other stakeholders....................................................................................................... 175

15.5 Identify how those comments were taken into account ............................................. 179

15.6 Details of public participation activities ....................................................................... 179

15.7 Summarize the public acceptance or opinions on the proposed Project ................... 179

15.8 Related materials or activities .................................................................................... 180

15.9 Recommendations for future consultations ................................................................ 181

16 COMPLAINTS AND GRIEVANCES MECHANISM ....................................................... 182

17 WORK PLAN AND IMPLEMENTATION SCHEDULE .................................................. 185

18 COST ESTIMATES ........................................................................................................ 191

18.1 Infrastructure costs ..................................................................................................... 197

19 REVIEW OF THE EMP ................................................................................................... 198

20 NON-TECHNICAL SUMMARY ...................................................................................... 199

20.1 Introduction ................................................................................................................. 199

20.1.1 Purpose of this document .................................................................................. 199

20.1.2 Benefits of the project ........................................................................................ 199

20.1.3 Key project characteristics ................................................................................. 201

20.1.4 Operations .......................................................................................................... 201

20.2 Project Phases ........................................................................................................... 203

20.3 Key Potential Impacts and Mitigation Measures ........................................................ 207

20.4 Stakeholder Engagement Process ............................................................................. 212

21 REFERENCES ............................................................................................................... 215

22 ACRONYMS / ABBREVIATIONS .................................................................................. 219

Page 8: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page viii 301012-02135-EMP-003 Rev 1 : 3 February 2017

FIGURES

Figure 3-1 Example of excavator to be used to clear vegetation during pre-construction .................... 30

Figure 3-2 Example of excavator loading a dump truck ........................................................................ 31

Figure 3-3 Example of an open pit limestone mine ............................................................................... 31

Figure 3-4 Example of a topsoil stockpile ............................................................................................. 32

Figure 3-5 Example of a waste rock dump and stockpile ..................................................................... 32

Figure 3-6 Example of limestone blocks being mined .......................................................................... 33

Figure 3-7 Example of blasting of rock in an open pit of a mine ........................................................... 33

Figure 3-8 Example of a watering truck used for dust suppression ...................................................... 34

Figure 3-9 Example of decommissioning process (implosion of a power station) (Photo:

sandiegouniontribune.com) ................................................................................................................... 35

Figure 3-11 Example of revegetation process (Image : Google Images) ............................................. 35

Figure 3-11: Location of the Limestone Mine ........................................................................................ 36

Figure 13-1: Mine Closure Plan Success Criteria (Holtec, 2015a) ..................................................... 166

Figure 16-1: Grievance resolution framework ..................................................................................... 184

Figure 17-1 Overall work plan and implementation schedule ............................................................. 186

Figure 20-1: Location of Baucau Cement Project Limestone Mine .................................................... 200

Figure 20-2: The Baucau Cement Plant Project once in operation .................................................... 202

Figure 20-3: Stakeholder Engagement and Consultation ................................................................... 212

Page 9: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 9 301012-02135-EMP-003 Rev 1 : 3 February 2017

A EXECUTIVE SUMMARY

An Environmental Management Framework (EMF) sets the structure for managing environmental

risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the

following key approaches:

a. Select the Project option which has the lowest possible environmental footprint;

b. Reduce the environmental impact, as far as possible, through engineering and design

approaches;

c. Mitigate environmental impact, as far as possible, through engineering and design

approaches;

d. Manage the direct impacts and the risk of ongoing impact through management measures

and monitoring; and

e. Continuously improve the environmental management and monitoring measures through the

Project life cycle.

Two Environmental Management Plans (EMPs) were created for the TL Cement Project. One EMP

addresses impacts associated with the limestone mine site and the other addresses impacts

associated with the cement plant, jetty and other associated infrastructure. EMPs for the TL Cement

Project address:

1. Environmental impacts which are identified as ‘Medium’ or greater in the EIS document;

2. Mitigation measures for all aspects which are required in accordance with industry best

practice;

3. Monitoring measures and standards to be followed;

4. Trigger values or target values of measurement criteria;

5. Reporting requirements; and

6. Continuous improvement process.

This EIS and EMP is a component of the entire project and each component cannot be implemented

without the other. Where impacts have been assessed, they are generally cumulative impacts of the

entire operation which have been repeatedly documented in both of the Impact Assessments

submitted. This is significant when understanding the approach to implementation of the EIS and

EMP because the mitigation measures and monitoring actions as recommended in the EIS and EMP

are applicable to the overall project impact. All mitigation measures are applicable to occur once, for

the project as a whole; all monitoring events which are recommended are a single monitoring event,

which has been duplicated in the two separate documents. Similarly, all reporting to the regulator and

community are single reporting events.

Page 10: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 10 301012-02135-EMP-003 Rev 1 : 3 February 2017

Key impacts

Of all the aspects associated with the Project, key aspects are those with impacts identified in the EIS

as being ‘Medium’ or ‘High’ risk. These risks have been addressed through the Environmental

Management Plans (EMPs).

1. Displacement / Resettlement: Local people will be displaced and will require relocation in

order for this Project land to be acquired. This can cause a ‘High’ level of impact on local

people. Mitigation measures including resettlement and ongoing stakeholder consultation to

be undertaken by the Government of Timor-Leste will most likely result in a residual impact of

‘Medium’.

2. Cultural Heritage: Impacts of the mine on Cultural Heritage for the local area is significant with

a number of sacred heritage sites directly impacted by clearing and activities within the

Project footprint. Local area sites will be permanently impacted causing a ‘High’ impact,

however with the implementation of controlled relocation and removal of unavoidable

impacted sites, the residual impacts are ‘Medium’.

3. Traffic: An increase in heavy vehicle numbers and movements is likely to cause damage to

the condition of the local road network and also poses a ‘Medium’ safety risk for the local

road users and pedestrians. Mitigation measures including speed limits and road

improvements reduces this risk to 'Low' which is an acceptable level.

4. Noise: In accordance with the equations provided in AS 2436-2010 (AS 2436, 2010) the

predicted noise levels from a single 85dB at 1m emission source, is 45dB 100m away from

the source. This falls below the noise standard of 55 dB (A) (UNTAET, 2001). This represents

a ‘Medium’ level of impact. The residual impact from noise and vibration is ‘Medium’.

Monitoring

The monitoring requirements for the project have been developed to consider all project phases,

including; Pre-construction, construction, operation and decommissioning. Key monitoring

requirements are as follows:

1. Air quality monitoring at key receptors in the neighbouring settlements

2. Noise and vibration monitoring at the Plant and Mine site and sensitive receptors at the

neighbouring settlements

3. Water quality and quantity monitoring at rivers and groundwater sources including springs

adjacent to the mine and plant site

4. Recording of flora and fauna information during land clearing activities and ongoing

throughout the project life

5. Ongoing stakeholder and community consultation throughout the project life

Page 11: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 11 301012-02135-EMP-003 Rev 1 : 3 February 2017

Emergency Response Plan

The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak /

spillage of dangerous chemicals and hazardous wastes associated with the development and

operation of the Baucau Cement Plant Project.

The following will be adopted by the Project to prevent spillages and leaks from occurring:

• No tanks are to be filled prior to checking available tank volume;

• Tank filling and dispensing procedures shall be carried out only by appropriately trained

personnel and within designated and bunded area;

• The main outlet valve on tanks will be locked shut when unattended;

• Each tank/storage facility will be gauged and monitored daily;

• All chemical and hazardous materials are contained in bunded areas with an appropriate

holding capacity;

• Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is

not adversely affected by contact with the stored chemicals. It should be constructed in such

a way that permits full recovery of contents spilt from tanks and ensures that the lining

material is not damaged. The bund itself should be constructed of waterproof membrane,

reinforced concrete or an approved equivalent;

• The bunded compound shall have a minimum capacity of 110% of the capacity of the largest

tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be

affected during extreme rainfall events; and

• All marine-based spills and emergencies are to be managed in accordance with Regulation

37 Annex 1 of the International Convention for the Prevention of Pollution from Ships 1973.

This regulation deals with the management of accidental discharge and discharge of ballast

to sea.

Training

Training is essential for ensuring that the provisions of the EMPs are implemented efficiently and

effectively. Training needs will be identified based on the existing and available capacity of the site

and Project personnel (including the proponent, contractors and subcontractors) to undertake the

required management actions and monitoring activities.

EMP review

The EMP will be reviewed at the following key project milestones:

• Completion of the pre-construction phase and additional specialist studies;

• Completion of the construction phase;

• Award of the Operations contract to incorporate operator-specific information;

• Every 5 years at minimum during Operations phase.; and

• On finalization of the Mine Closure Plan.

Page 12: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 12 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

Pre Construction

Vehicles

movement

Equipment

operating

Clearing of

vegetation

Limit area to be cleared TL Cement

Construction

contractor

Check that clearing is within

the boundary

Weekly

reconciliation

Compensation per the Resettlement Plan :

$15,000 estimate

Monitoring and weed eradication costs:

$5.6M

Fauna relocation and monitoring, re-

introduction and elimination of pests: $670k

Rehabilitation costs (Labour and materials):

$?

Vehicles

movement

Equipment

operating

Air quality and

dust

Dust suppression

techniques include water

spraying and enclosing

equipment

TL Cement

Construction

contractor

PM10 and PM2.5

3 monitoring stations

Measurements

every 6

months

Compensation per the Resettlement Plan :

$15,000 estimate

Dust suppression sprayer and labour:

2000/month

Cost of illness and loss of productivity: $?

Page 13: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 13 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

Vehicles

movement

Equipment

operating

Generating

electricity

Noise Noise limitation

techniques include aprons

and enclosing equipment

TL Cement

Construction

contractor

Noise Levels

3 monitoring stations

Measurements

every 6

months

Compensation per the Resettlement Plan :

$15,000 estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles

movement

Equipment

operating

Water quality

and quantity

Rehabilitation in the event

of a spill or contamination

event

Spill and contamination

mitigation measures

TL Cement

Construction

contractor

Every 6 months

Flow meters / stream gauges

at the Bucoli River (1.6km

west) and at Uaimatabai,

Uaisa and Waino springs.

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring

receptors at

Waiono,

Uaimatabai

and Uaisa.

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill:

$?

Construction

Vehicles

movement

Air quality and

dust

Dust suppression

techniques include water

spraying and enclosing

TL Cement

Construction

contractor

PM10 and PM2.5

3 monitoring stations

Measurements

every 6

months

Dust suppression sprayer and labour:

2000/month

Page 14: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 14 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

Equipment

operating

Generating

electricity

equipment

Cost of illness and loss of productivity: $?

Vehicles

movement

Equipment

operating

Generating

electricity

Noise Noise limitation

techniques include aprons

and enclosing equipment

TL Cement

Construction

contractor

Noise Levels

3 monitoring stations

Measurements

every 6

months

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles

movement

Equipment

operating

Water quality

and quantity

Rehabilitation in the event

of a spill or contamination

event

Spill and contamination

mitigation measures

TL Cement

Construction

contractor

Every 6 months

Flow meters / stream gauges

at the Bucoli River (1.6km

west) and at Uaimatabai,

Uaisa and Waino springs.

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring

receptors at

Waiono,

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill:

$?

Page 15: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 15 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

Uaimatabai

and Uaisa.

Operation

Vehicles

movement

Equipment

operating

Air quality and

dust

Dust suppression

techniques include water

spraying and enclosing

equipment

TL Cement

Operator

PM10 and PM2.5

3 monitoring stations

Measurements

every 12

months

Dust suppression sprayer and labour:

2000/month

Cost of illness and loss of productivity: $?

Vehicles

movement

Equipment

operating

Removal of

buildings

Generating

electricity

Noise Noise limitation

techniques include aprons

and enclosing equipment

TL Cement

Operator

Noise Levels

3 monitoring stations

Measurements

every 6

months

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Vehicles

movement

Equipment

Water quality

and quantity

Rehabilitation in the event

of a spill or contamination

event

TL Cement

Operator

Flow meters / stream gauges

at the Bucoli River (1.6km

west) and at Uaimatabai,

Every 6

months

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Page 16: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 16 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

operating

Mine dewatering

Spill and contamination

mitigation measures

Uaisa and Waino springs.

Monthly water quality and

quantity measurements at

monitoring boreholes, key

spring receptors at Waiono,

Uaimatabai and Uaisa.

Rehabilitation costs in the event of a spill:

$?

Decommissioning

Vehicles

movement

Equipment

operating

Air quality and

dust

Dust suppression

techniques include water

spraying and enclosing

equipment

TL Cement

Operator

PM10 and PM2.5

3 monitoring stations

Measurements

every 6

months

Dust suppression sprayer and labour:

2000/month

Vehicles

movement

Equipment

operating

Removal of

buildings

Generating

electricity

Noise Noise limitation

techniques include aprons

and enclosing equipment

TL Cement

Operator

Noise Levels

3 monitoring stations

Measurements

every 6

months

Compensation per the Resettlement Plan :

$15,000 estimate

Monitoring costs: $580k

Cost of illness and loss of productivity: $?

Page 17: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 17 301012-02135-EMP-003 Rev 1 : 3 February 2017

Stage Activity Potential Key

Impact

Mitigation Measure Responsibility Monitoring Measure Frequency of

monitoring

Cost of Mitigation Measure USD

Vehicles

movement

Equipment

operating

Revegetation

activity

Water quality

and quantity

Rehabilitation in the event

of a spill or contamination

event

Spill and contamination

mitigation measures

TL Cement

Operator

Flow meters / stream gauges

at the Bucoli River (1.6km

west) and at Uaimatabai,

Uaisa and Waino springs.

Monthly water quality and

quantity measurements at

monitoring boreholes, key

spring receptors at Waiono,

Uaimatabai and Uaisa.

Every 6

months

Water Quality Monitoring costs: $1,4M

Water Quantity Monitoring costs : $970k

Rehabilitation costs in the event of a spill:

$?

Page 18: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 18 301012-02135-EMP-003 Rev 1 : 3 February 2017

B INTRODUCTION

The TL Cement Project will be managed through the implementation of two Environmental

Management Plans. These plans are for the Cement Plant, Jetty and Other Associated Infrastructure

and the Limestone Mine. This EMP relates to the Limestone Mine.

1.1 Environmental Management Framework

An Environmental Management Framework (EMF) sets the structure for managing environmental

risks and impacts during the Project life cycle. The EMF for the TL Cement Project includes the

following key approaches:

a. Select the Project option which has the lowest possible environmental footprint;

b. Reduce the environmental impact, as far as possible, through engineering and design

approaches;

c. Mitigate environmental impact, as far as possible, through engineering and design

approaches;

d. Manage the direct impacts and the risk of ongoing impact through management measures

and monitoring; and

e. Continuously improve the environmental management and monitoring measures through the

Project life cycle.

1.2 Environmental Management Plan

As required by the Environmental Licensing Law the Environmental Management Plan (EMP) is a

separate stand-alone document from the Environmental Impact Statement (EIS).

The EMP is an essential tool for ensuring that mitigation of the negative impacts and enhancement of

the positive impacts is carried out effectively throughout the life of the Project. An EMP should be

systematically improved on a regular basis to ensure that best available technologies (BAT) and best

environmental management practices are implemented in a manner that is pragmatic, efficient and

cost-effective.

The EMP for the TL Cement Project Limestone Mine addresses:

1. Environmental impacts which are identified as ‘Medium’ or greater in EIS document;

2. Mitigation measures for all aspects which are required in accordance with industry best

practice;

3. Monitoring measures and standards to be followed;

4. Trigger values or target values of measurement criteria;

5. Reporting requirements; and

6. Continuous improvement process.

Page 19: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 19 301012-02135-EMP-003 Rev 1 : 3 February 2017

It should be noted that the any resettlement or compensation matters are the responsibility of the

Government of Timor-Leste and as such are not part of the EMP.

This EMP should be read in conjunction with the document, Baucau Cement Plant, Jetty and

Associated Infrastructure EMP. Under the instructions of the NDCEPI, the project environmental

impact statements were separated into two separate EIS and EMP’s i.e. Baucau Cement Plant & Jetty

and Associated Infrastructure and Limestone Mine. This EMP is a component of the entire project and

each component cannot be implemented without the other. Where impacts have been assessed, they

are generally cumulative impacts of the entire operation which have been repeatedly documented in

both of the Impact Assessments submitted. This is significant when understanding the approach to

implementation of the EMP because the mitigation measures and monitoring actions as

recommended in the EMP are applicable to the overall project impact. All mitigation measures are

applicable to occur once, for the project as a whole; all monitoring events which are recommended

are a single monitoring event, which has been duplicated in the two separate documents. Similarly, all

reporting to the regulator and community are single reporting events.

Page 20: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 20 301012-02135-EMP-003 Rev 1 : 3 February 2017

1 PROJECT DESCRIPTION

1.1 Project Identification

TL Cement LDA, a privately-owned company, proposes to construct a greenfield cement

manufacturing project in Baucau Municipality, Timor-Leste. The project will produce approximately

1.65 million tons per annum (mtpa) of Portland cement clinker. For the purposes of this EMP, the

components of the Baucau Cement Plant Project that relate to the construction and operation of the

limestone mine shall be referred to as the Project.

1.2 Details of Project Proponent

TL Cement LDA was registered in Timor-Leste as a new company to develop the Baucau Cement

Clinker Plant project. The contact details of the Project Proponent are given below:

Name: TL Cement LDA

Dili Office

Address: Rua Complexo

Hotel Ramelau

Aimutin Comoro, Dom Aleixo

Dili

Timor Leste

Phone: +670 331 1206

Perth Office

Address: Level 5, 22 Mount Street

Perth, Western Australia 6000

Phone: +61 8 9261 1965

Contact Person Mr. James Rhee

Managing Director

Mob: +61 400 317 811

Email: [email protected]

Contact Person Mr. James Rhee

Managing Director

Mob : +61 400 317 811

Email: [email protected]

Page 21: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 21 301012-02135-EMP-003 Rev 1 : 3 February 2017

1.3 Project Environmental Impact Statement

The Environmental Authority for this Project is the National Directorate for Pollution Control and

Environmental Impact (NDPCEI). WorleyParsons on behalf of the Project Proponent has consulted

with the NDPCEI with regards to obtaining the Environmental Licensing Certificate for the Project. The

Application for Environmental License and the Project Document were submitted to NDPCEI in June

2015. The Project Document was approved on 20 July 2015 and pursuant to Decree Law 5/2011, the

NDPCEI categorized the Baucau Cement Project as Category A.

Page 22: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 22 301012-02135-EMP-003 Rev 1 : 3 February 2017

2 DETAILS OF EMP CONSULTANTS

WorleyParsons is responsible for leading the environmental assessment process, conducting the

environmental and social baseline studies, and preparing the Environmental Impact Statement (EIS)

and Environmental Management Plans (EMPs).

Globally, WorleyParsons is a leading provider of professional services to the infrastructure and

resource industries. WorleyParsons has been involved in environmental management for decades

and has a proven track record of delivering innovative solutions for our customers. WorleyParsons

offers a full suite of environmental services, which cover all aspects from planning to detailed design

and implementation. Services include engineering and environmental services to assist in site

selection, site analysis, site layout, and design. One of the key differentiators to WorleyParsons’

environmental assessment approach is our ability assemble multi-disciplinary, in-house teams,

including but not limited to engineers, urban planners, GIS and mapping specialists, geotechnical

engineers, environmental scientists, social impact specialists, and hydrological engineers. These

teams are led by experienced environmental assessment professionals who are capable of

integrating the technical aspects of all disciplines into a tailored solution. Our ability to draw upon all of

these resources internally streamlines the project delivery process and ensures reliable quality for the

customer.

2.1 Local presence

WorleyParsons established an office in Timor-Leste in 2010 to provide our customers with the

advantages of local content and an ‘on-the-ground’ understanding of local conditions. WorleyParsons

Timor-Leste has delivered several major projects nationwide for the Government of Timor-Leste,

TIMOR GAP, and international development agencies, including engineering feasibility, engineering

design, and environmental assessment projects.

As a local company employing local staff, WorleyParsons is intimately familiar with the Timorese

environment and culture. Our local staff are fluent in Portuguese, Tetun, and other local languages

and are experienced in community engagement. Our multi-disciplinary team has extensive experience

in the delivery of environmental studies in Timor-Leste.

WorleyParsons is supported by the following specialist consultants, who have extensive experience in

Timor-Leste, including:

• Bita Bina Semesta (BBS): BBS is based in Bandung, Indonesia and maintains a locally-

registered project office in Dili, Timor-Leste. BBS specializes in 'front end' type works, including

planning and environmental studies for transport, resources, urban development, infrastructure

and industrial development. BBS has become a regional leader in the preparation of

environmental impact assessments that meets international standards. BBS recently worked

with WorleyParsons to deliver environmental studies in support of the Dili Drainage EIA for the

Ministry of Public Works.

Page 23: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 23 301012-02135-EMP-003 Rev 1 : 3 February 2017

• Nuno Oliviera: Dr. Nuno Oliveira is currently the Cultural Heritage Adviser for the Timor-Leste

Secretary of State for Arts and Culture where he has led development of cultural heritage

management programs and policies including the National Cultural Policy, Cultural Strategic

Plan, Resolution on Protection of Cultural Heritage and ratification of UNESCO’s main

conventions on cultural heritage. Prior to this role, Dr. Oliveira conducted extensive research in

Timor-Leste for the Australia National University (ANU), completing his dissertation on early

subsistence practices and agriculture in Timor-Leste. His research included extensive fieldwork

and excavations near the proposed project location.

• Dr Colin Trainor: During 1997-2002, Colin worked internationally as an ecologist with BirdLife

International, leading biodiversity assessments, particularly of forest birds, in Indonesia and

East Timor (Timor Leste) (Timor Leste) (Timor-Leste). In Timor-Leste (2002-2014), work

included a PhD thesis involving systematic survey of birds, mammals, reptiles, ants and trees

across a 2,000 km2 district, and consulting projects on transmission and proposed hydropower

works at Baucau and Iralalaro in Timor-Leste; shorebird and waterbird assessments; bird

species rediscoveries. In Timor-Leste has worked on establishment of a protected area, wrote

and published a field guide to the birds of East Timor (Timor Leste) and a site priority guide.

The environmental assessment has been undertaken by a team of specialists with world-class

expertise and extensive experience in Timor-Leste.

Page 24: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 24 301012-02135-EMP-003 Rev 1 : 3 February 2017

The development of the EIS and EMP has been led by Mr Daniel Hunter.

Key Personnel Qualifications and Experience

Daniel Hunter

EIA Specialist

B App Sci (Natural Resources Management), University of Melbourne

Dan is a Project Manager and Scientist with over 20 years’ experience predominantly in

the area of environmental assessment and management. He has extensive experience

in managing multidisciplinary projects, including the assessment and management of

cumulative environmental issues associated with large infrastructure projects such as

mine and port developments, roads, rail corridors, land developments, pipelines and has

worked pro-actively with environmental planning teams, project design teams,

government regulators, construction personnel, consultants and the community to

achieve environmental / sustainability objectives and the development of mitigation

strategies and consents in accordance with regulatory requirements. One of Dan’s major

roles on projects is to integrate environmental considerations into all aspects of decision

making, planning, design, construction and operational processes and drive for

sustainable outcomes.

Dan has previously managed and led a study of the Timor-Leste local industry capability

for ConocoPhillips.

The environmental assessment has been undertaken by a team of specialists with world-class

expertise and extensive experience in Timor-Leste.

Key Personnel Qualifications and Experience

Chris Serjak

Study Manager

MSc, Sustainable Development, University of London

Chris has 18 years of experience in environmental management, infrastructure

development, and sustainable international development. He has five years of

experience in Timor-Leste working on environmental projects, community-driven

development, local content, and offshore petroleum projects. Chris recently completed a

year-long study of the environmental licensing process in Timor-Leste and is an expert on

the local regulatory framework. He has led the Dili Airport Environmental and Social

Scoping Study and provided consulting services on the environmental licensing process

for the Suai Supply Base project. As a certified project-manager, Chris understands how

to manage interdisciplinary teams to deliver projects that meet client expectations.

Page 25: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 25 301012-02135-EMP-003 Rev 1 : 3 February 2017

Key Personnel Qualifications and Experience

Annette Jacobs

EIA Specialist

Lead Author

BSc (Hons) Geology; Diploma of Project Management

Annette is trained as an environmental scientist with 8 years’ experience in environment

and social impact assessment (ESHIA), management plan development, geology and

hydrogeology. Her technical experience includes numerical modelling, environmental

hydrogeology and advanced spatial analysis using geographic information systems (GIS).

Annette currently project manages all the large marine science projects at WorleyParsons

and understands the complexities and issues often encountered.

She has 5 years’ project management experience in all stages of the project life cycle.

Her project specific experience includes marine environmental hydrology, environmental

and groundwater management for the mining industry and infrastructure projects,

contaminated sites groundwater quality investigations, ESHIA project development and

implementation, and mitigation and management plans.

Alison Mratovich

Community Consultation

BA Geography and Environment Management, University of Johannesburg

Alison has over 10 years’ experience in stakeholder management providing consultancy

and advisory services to government agencies and private companies on environmental

and social impact assessments, community engagement and socio-economic baseline

assessments. Her focus is on social and environmental impact assessments, stakeholder

engagement programs and social investment strategies. Delivering assessments in

accordance with WA, International Finance Corporation (IFC) and World Bank Standards.

Lindsay Furness

Water Resources

MA, Hydrogeology and Engineering Geology

Mr Lindsay Furness has over 38 years’ experience in groundwater and water resource

management in 14 countries for ADB, WB, UNESCO, WHO, AusAID, NZAID. He is a

Fellow of the Australian Institute of Geosciences (Registered Professional Geoscientist),

a member of the International Association of Hydrogeologist and the National Association

of Ground Water Scientists and Engineers (US). Lindsay Furness made a preliminary

study of the caves and springs of the Baucau Aquifer in 2004 under an ADB water

resources assessment for Timor-Leste in relation to Agricultural irrigation. In 2010 he was

appointed as the Timor-Leste Water Resources and Climate Adaptation Specialist in the

National Department of Water Resources (DNGRA), where he was responsible for

carrying out several surveys of the Baucau geohydrology.

Page 26: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 26 301012-02135-EMP-003 Rev 1 : 3 February 2017

Key Personnel Qualifications and Experience

Stuart Atkinson

Water Resources

MEngSc, BEng (Hons), MIEAust

He has over 15 years’ experience in hydrology, hydrogeology and contaminated site

assessment gained in Australia, Africa, the Middle East, UK and New Zealand. Stuart’s

Master’s degree research included water balance modelling in wet and arid

environments.

He has worked as part of large multidisciplinary teams addressing all water resource

issues on major projects, and also managing smaller projects requiring specialist

technical expertise to resolve complex water resource problems. This has included

working through all project phases using a variety of project delivery.

Stuart’s technical experience includes numerous hydrological investigations aimed at designing flood protection measures for new mine sites, residential and commercial developments, mine water management, flood mapping, water balance modelling, environmental hydrology, dam design, drainage system design and the preparation of bridge and culvert schedules for railway, roads and pipelines with lengths in excess of 1,000km. Stuart’s experience solving complex surface and groundwater issues on mining projects allows him to identify and address project risks associated with surface and groundwater while also considering associated geotechnical and civil engineering issues.

Lekha Siraz

Water Resources

PhD Hydrogeology, BSc Geology, MSc. Geology (Hydrogeology)

Lekha’s fields of experience include groundwater assessments, environmental

hydrogeology, hydrogeological and contaminated site assessments and groundwater

modelling. She has worked on a number of hydrogeological reviews, feasibility / impact

assessments and compliance monitoring for mining and industrial customers in Australia.

Lekha’s expertise also includes hydrogeological Interpretation and conceptualisation

leading towards flow and contaminant transport Modelling. She has project managed and

reviewed hydrogeological and groundwater modelling projects for the Victorian and New

South Wales Government agencies, mining clients and waste management facilities.

Besides these, her other projects have included landfill liner and cover design using

industry standards such as the US EPA HELP model and alternate cover

conceptualisation and design for landfills using vadose zone modelling. She also

assisted a WA based contaminated sites auditor in audits of several sites, reviewing

assessments, reports and preparing contaminated sites audit reports.

Page 27: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 27 301012-02135-EMP-003 Rev 1 : 3 February 2017

Key Personnel Qualifications and Experience

Grant Hickson

Air Quality

BSc (Hons) Physics and Computer Science

Grant Hickson has more than five years of air quality consulting and professional

experience in environmental impact assessments. He is an Environmental Scientist

specialising in pollutant and particulate matter dispersion modelling from major industrial

works, emissions estimation / calculation, data analysis and management as well as data

validation and quality control for reporting purposes. Grant has undertaken numerous air

quality impact assessments in Australia and internationally. He has recently been the

primary author for the air quality, meteorology and noise assessments for the Tasi Mane

Environmental Impact Assessment project. In this assessment he was responsible for:

the on-site collection of air quality samples; meteorological and noise measurements;

location surveying; data management and interpretation; and reporting. All work was

conducted to International Standards across multiple sites and allowed the client to

assess any adverse environmental impacts from the proposed development.

Dr. Kania Dewi

Air Quality

PhD, Environmental Engineering

Dr. Kania has 10 years’ experience as an Air Quality Expert conducting monitoring and

modelling of air quality impacts for EIAs and EMPs. She has extensive experience with

mining and hydrocarbons projects throughout Indonesia. Dr Kania has conducted

multiple pollutant and GHG emissions inventories and completed climate change

assessments. She has also completed modelling and assessment of impacts from

cement plants. Dr. Kania recently completed a baseline air quality assessment for the Dili

Drainage EIA environmental studies in association with WorleyParsons.

Dr. IB Ardhana Putra

Noise

PhD, Engineering

Dr. Ardhana has 16 years of experience in noise impact assessment, modelling, and

management. He has published nearly 40 papers on noise over the past 27 years and is

a former Head of Academic Development Program at Bandung Institute of Technology

and a current advisor to the Indonesian Ministry of Environment. He has extensive

experience with measurement, analysis and mapping of noise condition at oil and gas

facilities and power plants, as well as airports and roads.

Titi Liliani Soedirdjo

Traffic

MSc, Highway and Traffic Engineering

Ir Titi has 34 years of experience in traffic engineering, traffic surveys, and traffic impact

assessments. He has been a lecturer at Bandung Institute of Technology since 1981 and

a consultant on traffic and railways. He has been involved in several studies in Timor-

Leste, including modelling the traffic signalization and signage for Dili in 2002 and a traffic

impact assessment for the Dili Drainage EIA.

Page 28: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 28 301012-02135-EMP-003 Rev 1 : 3 February 2017

Key Personnel Qualifications and Experience

Dr. Hisyam Achmad

Social Impact

PhD, Anthropology

Dr. Hisyam has over 40 years’ experience in social sciences and anthropology. In the

past 10 years, Dr. Hisyam has worked for BBS completing several socio-economic and

resettlement impact studies for projects throughout Indonesia, including public

consultation, field surveys, and resettlement planning. He has extensive experience with

IFC Guidelines and Indonesian AMDAL. He recently completed a socio-economic and

resettlement impact assessment for the Dili Drainage EIA project.

Joana Belo

Public Consultation field

officer

BSc, Environmental Science (Management)

Joana is an HSE Professional with experience in Australia, Malaysia and Timor-Leste.

She has 7 years of experience health, safety and environment (HSE) including

conducting risk assessment, developing emergency procedures in hydrocarbon and

infrastructure industry. She also is participating in many environmental impacts and social

assessments including, Field Officer for Worley Parsons Timor-Leste working on Dili

Airport Environmental and Social Scoping Study, and Field officer for Tasi Mane EIA

Study.

These specialists are supported by a team of local Timorese staff including environmental specialists,

social specialists, and field surveyors. Field assistants have also been hired from the local area to

ensure access to local knowledge and to promote public consultation.

In addition, wherever possible, the environmental assessment process has involved participation from

local communities and mentoring of Timor-Leste university students, especially during field survey

activities.

Page 29: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 29 301012-02135-EMP-003 Rev 1 : 3 February 2017

3 DESCRIPTION OF THE PROJECT

3.1 Project component equipment and technology

For the purposes of the Environmental Licensing process, the NDPCEI has divided the Baucau

Cement Project into several major components, as follows:

1. Cement Plant, Conveyor Belt, Power Plant, Marine Jetty, and Associated Infrastructure;

2. Limestone Mine;

3. Clay Extraction; and

4. Road Improvements and New Roads.

All of the items included are critical to the success of the Baucau Cement Project. The Limestone

Mine will supply the product to be processed and exported. The cement plant will process the raw

materials to produce cement clinker for domestic use and international sale.

The jetty will be used to import raw materials not available locally including coal, iron ore, and gypsum

and to export the clinker product. The conveyor belt will be used to transport materials to and from

the marine jetty. The cement plant also includes a 30MW CFB power plant to provide electrical power

to the plant.

The Limestone Mine project comprises the following components in each phase.

3.1.1 Pre construction

During pre construction, excavators and graders will be used to clear vegetation and level the ground

for the construction phase. Refer to Figure 3-1 Example of excavator to be used to clear vegetation

during pre-construction

.

Page 30: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 30 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-1 Example of excavator to be used to clear vegetation during pre-construction

3.1.2 Construction

During construction, heavy plant and equipment will be used to construct the Limestone Mine and

Waste Rock Dump. Examples of this equipment is included inFigure 3-1 & Figure 3-2. Figure 3-3

shows an example of a comparable constructed limestone mine. Figure 3-4 shows an example of a

top-soil stockpile.

Page 31: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 31 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-2 Example of excavator loading a dump truck

Figure 3-3 Example of an open pit limestone mine

Page 32: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 32 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-4 Example of a topsoil stockpile

3.1.3 Operation

During operation, the mine will be operational and blasting and rock breaking will occur. Trucks and

other vehicles will be used around the site to transport material and people to and from the workplace.

Water trucks will also be used during operations to reduce dust impacts (Figure 3-8). An example of a

rock waste dump and stockpile is shown in Figure 3-5 below. Figure 3-6 shows an example of

limestone blocks being mined. Figure 3-7 shows an example of blasting of rock in an open pit mine.

Figure 3-5 Example of a waste rock dump and stockpile

Page 33: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 33 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-6 Example of limestone blocks being mined

Figure 3-7 Example of blasting of rock in an open pit of a mine

Page 34: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 34 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-8 Example of a watering truck used for dust suppression

3.1.4 Decommissioning

During decommissioning, equipment and buildings will be dismantled following consultation with the

community and GoTL. Figure 3-9 shows an example of a decommissioning program.

The area will be revegetated with native species. Figure 3-10 depicts a comparable revegetation

program.

Page 35: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 35 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-9 Example of decommissioning process (implosion of a power station) (Photo:

sandiegouniontribune.com)

3.2 Project Location

The proposed Baucau Cement Project is located in Suco Tirilolo, Aldeia Osso-ua, in the Baucau

administrative post of Baucau Municipality, Timor-Leste. The location is about 120 km east of Dili and

approximately 16 km west of Baucau.

Figure 3-10 Example of revegetation process (Image : Google Images)

Page 36: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 36 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 3-11: Location of the Limestone Mine

3.2.1 Nature of the project location

The overall site is dominated by a relatively uniform coastal Closed Tropical Forest (70%) which is

most likely a combination of existing forest and mature plantation trees. The remaining area (30%) is

cleared grazing land and residential farms. Overall, the site is a heavily modified plantation

environment with a severe infestation of Lantana camara throughout. The biological diversity at these

sites was very low and overall the site was not representative of a pristine coastal/beach forest

(Trainor & Easton, 2015).

No permanent rivers exist within the Project site. Some small ephemeral watercourses flow through

the area, mainly during the wet season. These tend to stop flowing in the dry season and are not

considered suitable as full time water sources.

The Project is located near the Caisido community of the Aldeias Parlemento, Caisido, Lialaileso, and

Osso-Ua. The total population of the Caisido area (the Project Site) is 2,387 or 38% of the Suco

Tirilolo population. There are 532 households in Caisido and the average size of a household is 5

people. Economic employment is mainly focused on agricultural sector. Most of the local populations

Page 37: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 37 301012-02135-EMP-003 Rev 1 : 3 February 2017

in the areas surrounding Baucau Cement Project site are farmers. A small number of these farmers

are also teachers, drivers and owners of small kiosks (vendors) within their villages/hamlets (BBS,

2015c).

The geographical coordinates of the Baucau Cement Project components are detailed in Table 1

below.

Table 1: Coordinates of Project components

Component Latitude Longitude

Cement Plant -8.4520 126.3424

Marine Jetty -8.4438 126.3433

Conveyor belt -8.4520 to -8.4438 126.3424 to 126.3433

Construction camp and Residential

area

Adjacent to cement plant Adjacent to cement plant

Limestone mine S 8 º.4 62’21.5 126 º 35 ’61.82”

3.3 EMP Endorsement

The Baucau Cement Project proponent, TL Cement, has endorsed this EMP/EIS in writing. A copy of

their written endorsement is included below.

Page 38: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 38 301012-02135-EMP-003 Rev 1 : 3 February 2017

Page 39: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 39 301012-02135-EMP-003 Rev 1 : 3 February 2017

4 LEGAL REQUIREMENTS

4.1 Legislation and legal framework

This section identifies the legislation and guidelines governing the conduct of the Environmental

Impact Assessment studies and preparation of the EIS and EMP. This section also identifies other

applicable laws, regulations, guidelines, and standards governing environmental quality, health and

safety, protection of protected areas and sensitive areas, protection of vulnerable and endangered

species, land use control, and other environmental and social issues.

4.1.1 Environmental Legislation

Decree Law 26/2012 Environment

Basic Law (EBL)

The EBL (also sometimes called the Environmental Framework Law)

sets the overall framework for environmental protection in Timor-Leste.

Articles 14, 15 and 16 of the Decree define the instruments for

environmental standards, environmental assessment and licensing and

environmental monitoring respectively for Environmental Assessment

(EA).

Decree Law 5/2011 Environmental

Licensing Law (ELL)

The object of the Decree Law is to create a system of environmental

licensing for public and private projects likely to produce environmental

and social impacts. This system of licensing is based on assessing the

size of the potential impacts of projects taking account of their nature,

size, technical characteristics and location. Decree-Law No. 5/2011

elaborates the licensing requirement and the EIA procedure in Timor-

Leste. Article 4 of the Decree defines the categories of projects and the

Type of EA procedure required. The classification of projects is made in

accordance with Annex I and II of the Decree. The proposed project has

been classified by the NDE as a ‘Category A’ project “that may

potentially cause significant environmental impacts, and [is] subject to

the procedure of Environmental Impact Assessment (EIA) and

Environmental Management Plan (EMP).”

Draft Ministerial Diploma for

General Regulations for

Environmental Assessment

The Asian Development Bank (ADB) has prepared detailed

requirements for Screening, Scoping and the Terms of Reference,

Environmental Impact Statements and Environmental Management

Plans for Environmental Assessment. Although these guidelines have

not been formally adopted, they are in practical use by NDPCEI.

Draft Ministerial Diploma

Regulation on the Public

Consultation Procedures

The ADB has prepared detailed requirements for Public Consultation

Procedures and Requirements during the Environmental Assessment

Process. Although these guidelines have not been formally adopted,

Page 40: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 40 301012-02135-EMP-003 Rev 1 : 3 February 2017

they are in practical use by NDPCEI.

4.1.2 Biodiversity and protected areas legislation

UNTAET Regulation 2000/19 on

Protected Places

UNTAET Regulation 2000/19 is still in force and used by the Forestry

Department, although it is intended to be replaced by a draft Decree

Law on Protected Areas, a draft Decree Law on Forestry, and the draft

Decree Law on Biodiversity. Section 3 provides for the protection of

endangered species and their habitats. The killing, injuring, harming,

taking or disturbing of any endangered species is prohibited. The

destruction in any way of the habitat of an endangered species is also

prohibited.

UNTAET Regulation 2000/17 on the

Prohibition of Logging Operations

and the Export of Wood from East

Timor

UNTAET Regulation 2000/17 also remains in force at present. Section 2

prohibits the cutting, removal, and logging of wood from land in East

Timor. It also prohibits the burning or any other destruction of forests.

These prohibitions are subject to Section 3 which allow for exemption to

be authorised for certain logging activities.

Draft Decree Law on Forest

Management, draft 7, received

August 2013

The cutting of “forest trees” and harvesting of other forest products in

any zone is prohibited unless specifically authorized by the National

Director of Forestry (Article 61). The Director may give authorization for

such cutting and harvesting if it would be in accordance with this law and

other legislation, any community guideline agreements or with the forest

management plan. The Director must take into consideration the forest

management plan, conservation of the soil and water of the area,

ecology and biodiversity of the area, and any other technical

specifications determined by the National Director. Article 61.2 allows for

community cutting of trees and harvesting other forest products without

authorization, when used for traditional purposes.

Article 67 provides for measures to prevent deforestation. No-one is

allowed to cut, damage, destroy, remove, transport, purchase, sell,

donate or otherwise acquire or dispose of any tree, unless that tree is

private property or the person has a Community Forestry Management

Agreement or a permit/authorization from the National Director.

It is an offence under Article 86 for any person to pollute or contaminate

land in any Protected Area with chemicals, industrial waste or organic or

other polluting substances.

Draft Decree Law on Biodiversity,

dated March 2012

When preparing an SEA, EIS, EMP or any other environmental

assessment, the proponent must include an assessment of the potential

impacts of the proposal on biodiversity and biological resources. This

Page 41: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 41 301012-02135-EMP-003 Rev 1 : 3 February 2017

assessment must include: (a) Impacts on any natural ecosystems and

habitats located within or near the proposed site, in particular the habitat

of any protected species and critical habitat; (b) Impacts on any legally

protected areas, as well as any areas the subject of cultural or traditional

protection mechanisms such as Tara Bandu; (c) Impacts associated with

invasive alien species on or near the proposed site; (d) The

sustainability of any proposed use of biological resources; and (e)

Proposed measures to avoid, minimize, or mitigate identified impacts,

and measures to offset or compensate for any affected biological

resources and impacts on biodiversity.

In analyzing any environmental assessment and before deciding to grant

an environmental license, the decision-maker must take into account

whether granting approval for the proposed activity would be consistent

with the purpose and principles of the draft Biodiversity Decree Law. In

particular, the Decision-maker must be satisfied that: (a) Any adverse

impacts and risks identified in the assessment are deemed satisfactory;

(b) Adequate measures to avoid, minimize, or mitigate identified adverse

impacts have been identified and will be implemented; (c) As a last

resort, adequate compensatory measures, which are designed to

achieve no net loss of biodiversity, have been identified and will be

implemented by the proponent to offset or compensate for any impacts

on biodiversity and affected biological resources; (d) The proponent has

prepared, in close consultation with affected local communities, a

comprehensive plan that includes details about all necessary remedial

and restoration efforts, and is satisfied that the plan will be implemented

at the proponent’s expense.

4.1.3 Land legislation

Draft Expropriation Law Property may only be expropriated for the public interest and upon

timely payment of fair compensation (Article 1). Only the State can order

expropriation (Article 5).

There must be public consultation on any project requiring expropriation

of private or community property (Article 13), and the documents made

available to the public for consultation and public hearings must include

any environmental, social or economic impact assessment studies

(Article 15.4).

4.1.4 Mineral Resources/Mining legislation

Ministerial Diploma 01/2008 on The diploma sets out the procedure for granting of licenses for

Page 42: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 42 301012-02135-EMP-003 Rev 1 : 3 February 2017

Licensing of Mining Activities exploitation of mineral resources related to the construction industry,

including sand, sandstone, and site, basalt, diorite, limestone, and

marble. The Environmental License for the project is a precondition of

granting the mining license. The diploma requires reasonable

environmental protection during the exploration process. The diploma

prohibits the extraction of beach sand. The diploma sets out

requirements for expropriation of private land or property.

Draft Mining Code A draft Mining Code has been prepared which is still in its preliminary

stages and has not yet been submitted for public consultation. It is

understood that the Mining Code, as drafted, contains provisions

requiring projects to adhere to the ELL and obtain an environmental

license.

4.1.5 Labor legislation

Law 4/2012 Labor Code The duties of the employer include providing workers with good working

conditions, prevention of risks from diseases and occupational

accidents, providing workers with information and equipment necessary

to prevent such risks.

The employer is under a general obligation to provide appropriate health

and safety conditions, to prevent accidents and dangers, and to reduce

risks.

Employers must ensure that workers are not exposed to risks that are

harmful to their health, and must promote awareness programs. Where

necessary, employers must provide safety equipment to workers.

4.2 Obligations

TL Cement is committed to developing this project in the region and complying with the regulations of

Timor Leste. Negotiations and discussions with stakeholders and regulators are ongoing.

4.3 Summary of Project Approvals

Activity Requirement Legislation

Clearing of

vegetation

Environment licence from DNSMA Decree law 5/2011 on environment

licensing law

Operating

limestone mine

Environment licence from DNSMA Decree law 5/2011 on environment

licensing law

Mining License Ministerial Diploma 01/2008 on

Page 43: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 43 301012-02135-EMP-003 Rev 1 : 3 February 2017

Licensing of Mining Activities

Internal roads Transport Decree law 2/2003 on basic law on the

road transport system

Employment of

labour

Labour Law 4/2012 Labor Code

4.4 Summary of Environmental Standards

Phase Aspect Standard

Pre Construction Air Quality World Health Organization (WHO), 2006:

Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise

(2002)

Water Quality WHO Drinking Water Standards (2000)

Construction Air Quality World Health Organization (WHO), 2006:

Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise

(2002)

Water Quality WHO Drinking Water Standards (2000)

Operation Air Quality World Health Organization (WHO), 2006:

Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise

(2002)

Water Quality WHO Drinking Water Standards (2000)

Vibration Regulation 11

Environmental Protection (Noise)

Regulations 1997

Decommissioning Air Quality World Health Organization (WHO), 2006:

Air Quality Guidelines (AQGs) for PM10

Noise UNTAET Guideline on Ambient Noise

(2002)

Water Quality WHO Drinking Water Standards (2000)

Vibration Regulation 11

Environmental Protection (Noise)

Regulations 1997

Page 44: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 44 301012-02135-EMP-003 Rev 1 : 3 February 2017

Page 45: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 45 301012-02135-EMP-003 Rev 1 : 3 February 2017

5 INSTITUTIONAL ROLES AND RESPONSIBILITIES

Phase Item Develop/Author Implement

Detailed Engineering

Design

Environmental

Management Plans

Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Mitigation Measures Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Monitoring Plans Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Construction Tender

Phase

Develop construction

specific

Environmental

Management Plans

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Develop construction

specific

Mitigation Measures

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Develop construction

specific

Monitoring Plans

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Page 46: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 46 301012-02135-EMP-003 Rev 1 : 3 February 2017

6 SUMMARY OF IMPACTS

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

Vehicles

movement

Operating

heavy

machinery

Power

generation

from Power

Plant

Climate Limited impact

on climate

change from

greenhouse

gases.

Limited impact

on climate

change from

greenhouse

gases.

Some impact

from

operation of

a power

plant for

operations.

Reduction in impact

with decommissioning

of plant

Vehicles

movement

Digging and

excavating

Clearing of

vegetation

using

equipment

Construction

of roads and

buildings

Vehicles

travelling on

site

Topography

Geology and

Soil

Reshaping and

excavation of

landforms in

order to

prepare for

construction

will impact the

current

topography

Vegetation

clearing

resulting in

increased

erosion and

run-off

Plant and

equipment may

leak oils and

hydrocarbons

which pollute

the soil

Increased

erosion and run-

off from a

bituminized area

will likely change

the water quality

of the ocean,

springs and

rivers

Plant and

equipment may

leak oils and

hydrocarbons

which pollute the

soil

Increased

erosion and

run-off from

a bituminized

area will

likely change

the water

quality of the

ocean,

springs and

rivers

Plant and

equipment

may leak oils

and

hydrocarbon

s which

pollute the

soil

Decommissioning will

involve the

rehabilitation of the

This is expected to

have a positive impact

on the soil resources

at the site.

Vehicles

movement

Air Quality Dust from earth

moving and

vegetation

Dust from earth

moving and

vegetation

Direct

emissions

from vehicles

Direct emissions from

vehicles and plant in

the form of fuel

Page 47: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 47 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

Digging and

excavating

Clearing of

vegetation

using

equipment

Construction

of roads and

buildings

Vehicles

travelling on

site

clearing

activities;

Direct

emissions from

vehicles and

plant in the

form of fuel

combustion

(i.e. exhaust

fumes) and

brake wear.

clearing

activities;

Direct emissions

from vehicles

and plant in the

form of fuel

combustion (i.e.

exhaust fumes)

and brake wear.

and plant in

the form of

fuel

combustion

(i.e. exhaust

fumes)

combustion (i.e.

exhaust fumes)

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Blasting

Noise and

Vibration

Impact from

Vehicle

movements

and earthworks

Impact from

Vehicle

movements and

earthworks

Noise Impact

from mining

and blasting

activities

Impact from Vehicle

movements and

earthworks

Vehicles

movement

Digging and

excavating

Surface

Water

Changes to

drainage

behavior and

quality from

earthworks

Changes to

drainage

behavior and

quality from

earthworks

Changes to

drainage

behavior and

quality from

earthworks

Changes to drainage

behavior and quality

from earthworks

Vehicles

movement

Groundwater Changes to

spring flow and

Changes to

spring flow and

Changes to

spring flow

Long term changes to

spring flow and quality

Page 48: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 48 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

Digging and

excavating

Dewatering for

mining

quality from

earthworks

quality from

earthworks

and quality

from

earthworks

after decommissioning

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Vehicles

travelling on

site

Flora Direct loss of

vegetation due

to clearing

Positive impact

due to

revegetation

activity

Indirect loss

of vegetation

cover due to

depletion of

water

sources

Positive impact due to

revegetation activity

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Vehicles

travelling on

site

Fauna Direct loss of

habitat through

vegetation

clearing;

Harm/death/dis

placement of

individual IUCN

listed species;

Direct loss of

habitat through

vegetation

clearing;

Harm/death/displ

acement of

individual IUCN

listed species

Increased

susceptibility of

native fauna to

predation

Soil disturbance

and potential

refuge

destruction for

ground dwelling

animals

Changes to

natural drainage

Direct loss of

habitat

through

vegetation

clearing;

Harm/death/

displacement

of individual

IUCN listed

species

Increased

susceptibility

of native

fauna to

predation

Soil

disturbance

and potential

refuge

destruction

Positive impact with

rehabilitation

Page 49: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 49 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

affecting fauna

and their habitat;

Disturbance

fauna activities

due to noise,

vibration and

lightning impacts.

for ground

dwelling

animals

Changes to

natural

drainage

affecting

fauna and

their habitat;

Disturbance

fauna

activities due

to noise,

vibration and

lightning

impacts.

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Vehicles

travelling on

site

Traffic Increase in

traffic to the

area due to

pre-

construction

Increase in traffic

due to

construction

Limited

traffic

increase

during

operations,

mainly on

the project

site

Increase in traffic due

to decommissioning

Development

of the project

resulting in

economic

participation

Employment Some short

term

employment

and training

opportunities

Longer term

employment and

training

opportunities

Long term

employment

and training

opportunities

Reduction in

employment

opportunities as the

project

decommissions

Development

of the project

resulting in

infrastructure

Infrastructure Increasing

pressure on

existing

infrastructure

Reduced impact

on existing

infrastructure as

project

Positive

impact on

local

infrastructure

Long term positive

impact on local

infrastructure

Page 50: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 50 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

development

Development

of a training

center

e.g. roads and

water

infrastructure

construction has

commenced

Development

of the project

resulting in

infrastructure

development

Economic

Use of

Forestry

Loss of access

to land by

community

No further impact

during

construction

No further

impact

during

operations

Positive impact on

community who get

access to the

revegetated and

rehabilitated forests

Access

restrictions

due to site

fencing

People and

vehicles

movement

Digging and

excavating

Relocation of

people

Socio

Economic

Agriculture

Access

controls and

reduction in

available

agricultural

land

Access controls

and reduction in

available

agricultural land

Access

controls and

reduction in

available

agricultural

land

Positive impact with

removal of access

controls and increase

available agricultural

land

Access

restrictions

due to site

fencing

People

movement

Digging and

excavating

Relocation of

people

Population

and

Community

Resettlement

of affected

families

Influx of

workers to the

pre-

construction

site

Influx of workers

to the

construction site

Daily

movement of

some

employee

during

operations

Changes to the

income source of

people in the

community due to

project

decommissioning

Vehicles

movement

Digging and

Community

Health

Increase in

respiratory

ailments due to

Increase in

respiratory

ailments due to

Increase in

respiratory

ailments due

Positive reduction in

prevalence of

diseases and dust-

Page 51: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 51 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

excavating

Construction

of roads and

buildings

Vehicles

travelling on

site

an influx of

people

Increase in the

level of

respiratory

ailments due to

increased dust

Increase in

vector-related

ailments such

as malaria due

to increase in

population

density;

Increase in

sexually

transmitted

infections such

as the human

immunodeficie

ncy virus due

to population

influx

an influx of

people

Increase in the

level of

respiratory

ailments due to

increased dust

Increase in

vector-related

ailments such as

malaria due to

increase in

population

density;

Increase in

sexually

transmitted

infections such

as the human

immunodeficienc

y virus due to

population influx

to an influx

of people

Increase in

the level of

respiratory

ailments due

to increased

dust

Increase in

vector-

related

ailments

such as

malaria due

to increase

in population

density;

Increase in

sexually

transmitted

infections

such as the

human

immunodefici

ency virus

due to

population

influx

related ailments.

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Vehicles

Institutions

Schools and

Health

Facilities

Increased

pressure on

health services

infrastructure

Increase in the

level of

respiratory

ailments due to

increased dust

Increased

pressure on

health services

infrastructure due

to population

influx

Increased

pressure on

health

services

infrastructure

due to

population

influx

Increase in

Positive impact on

community health with

legacy investments

Page 52: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 52 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

travelling on

site

the level of

respiratory

ailments due

to increased

dust

Vehicles

movement

Digging and

excavating

Construction

of roads and

buildings

Vehicles

travelling on

site

Community

and Family

Structure

The acquisition

of land may

cause impacts

on the

community and

family structure

Impacts to

household

subsistence and

ability to

generate income

Impacts to

household

subsistence

and ability to

generate

income

Change of

employment status

may affect the

households income

Access

restrictions

due to site

fencing

People and

vehicles

movement

Digging and

excavating

Relocation of

people

Land

Ownership

and Land

Rights

The acquisition

of land may

cause conflict

around land

owners and

communities.

Limited ongoing

impact on land

rights during

construction

Limited

ongoing

impact on

land rights

during

construction

The change in land

use and

decommissioning may

potentially cause

conflict around land

owners and

communities.

Access

restrictions

due to site

fencing

People and

vehicles

movement

Natural

Resources

Rights

Limited impact

due to limited

use of the

vegetation area

The acquisition

of land may

potentially

No additional

impact once

construction

commences and

resettlement has

occurred.

No additional

impact once

operations

commences

and

resettlement

has

The change in land

use and

decommissioning may

potentially cause

conflict around land

owners and

communities.

Page 53: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 53 301012-02135-EMP-003 Rev 1 : 3 February 2017

Activitytivity Impact Pre

construction

Construction Operations Decommissioning

Clearing,

Digging and

excavating

Relocation of

people

cause conflict

around land

use and

harvesting of

wood before

clearing.

occurred.

Access

restrictions

due to site

fencing

People and

vehicles

movement

Relocation of

people

Cultural

Heritage and

Archeology

Some sites

destroyed as a

result of the

Limestone

Mine

Access to sites

may be

restricted for

safety reasons

Some sites

destroyed as a

result of the

Limestone Mine

Access to sites

may be restricted

for safety

reasons

Some sites

destroyed as

a result of

the

Limestone

Mine

Access to

sites may be

restricted for

safety

reasons

Positive impact, Sites

with restricted access

for safety reasons will

be lifted

Page 54: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 54 301012-02135-EMP-003 Rev 1 : 3 February 2017

7 DESCRIPTION OF PROPOSED MITIGATION MEASURES

The following section outlines the proposed mitigation measures for each of the aspect identified in

the EIS. The proposed mitigation measures are considered for each of the different Project phases;

i.e.:

• Pre-construction;

• Construction;

• Operation; and

• Decommissioning.

Note: Some mitigation measures are applicable across one or more project phases.

7.1 Climate

Objective To ensure the atmospheric emissions (i.e. carbon monoxide) are minimised as much

as practicable;

To ensure design of Project components accommodate climate change, including sea

level rise and severe weather events

Impacts Carbon dioxide emissions

Sea level rise impacts on infrastructure

Pre-construction Construction Operations Decommissioning

Design reviews to consider

equipment selection

Design reviews to implement

Alternative Fuels in

consideration of climate

change impacts

Adoption and

implementation of clean

technology

Ensure vehicles and

equipment are regular

serviced and maintained

Limit vehicle idling and keep

vehicles well maintained

Adoption and

implementation of clean

technology

Use of substitute Alternative

fuels (Biomass, RDF, used

tyres and solvents instead of

fossil based fuels in both

cement and power plant

Ensure vehicles and

equipment are regular

serviced and maintained

Limit vehicle idling and keep

vehicles well maintained

Implement Mine Closure

Plan

Limit vehicle idling and keep

vehicles well maintained

Page 55: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 55 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.2 Topography, Geology and Soils

Objective Maintain the integrity, ecological functions and environmental values of landforms,

geology and soil

Minimise permanent landform alterations

Ensure that the modifications to landforms are physically and environmentally stable

and sustainable

Impacts Soil contamination

Erosion and loss of value

Landform shape change

Pre-construction Construction Operations Decommissioning

Soil contamination should be

monitored through

maintaining records of spill

events

Contouring and establishing

drainage systems during

pre-construction phase

Off-site contamination

should be monitored as part

of the Water Quality

Monitoring Programme

Minimizing of excavation

during construction

Soil contamination should be

monitored through

maintaining records of spill

events

Management measures to

control run off and erosion at

the Topsoil Stockpile

Soil contamination should be

monitored through

maintaining records of spill

events

Mined soil to be stockpiled in

quarry for reuse during Mine

closure as part pf Mine

Closure Plan

Off-site contamination

should be monitored as part

of the Water Quality

Monitoring Programme

Implementation of the Mine

Closure Plan Landform

impacts minimized through

mine backfill and contouring

process

Page 56: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 56 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.3 Air Quality (including dust)

Objective To ensure that atmospheric emissions do not impact on the health, welfare and

amenity of the population and land uses and the environment.

To use all reasonable and practicable measures to minimise airborne dust

Impacts Dust impacts on human health

Combustion emissions impacts on human health

Emissions from vehicles

Pre-construction Construction Operations Decommissioning

All material excavated, stockpiled, or graded shall be sufficiently watered, treated, or covered

to prevent fugitive dust from leaving the property boundaries and causing a public nuisance

or a violation of an ambient air standard.

Watering should occur at least twice daily, with complete site coverage.

All land clearing, grading, earth moving, or excavation activities on a project should be

suspended as necessary to prevent excessive windblown dust when winds are expected to

exceed 20 mph.

All raw materials storage will be in enclosed structures

All materials transport will be by fully covered conveyor belts

Dust and bag filters will be installed at all critical emissions hoppers

All areas with vehicle traffic shall be watered or have dust palliative applied as necessary for

regular stabilization of dust emissions.

All on-site vehicle traffic shall be limited to a speed of 15 mph on unpaved roads.

All material transported off-site shall be either sufficiently watered or securely covered to

prevent public nuisance, and there must be a minimum of six (6) inches of freeboard in the

bed of the transport vehicle.

No vehicles or plant will be left idling unnecessarily.

Reduce the number of vehicle movements through better planning.

Set an appropriate speed limit on haul routes.

All heavy duty vehicles should meet certain emission regulation from local Environmental

Protection Agency.

Use a good quality of fuel (e.g. with low sulphur content).

Implement the Mine Closure

Plan

Page 57: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 57 301012-02135-EMP-003 Rev 1 : 3 February 2017

Engines and exhaust systems should be regularly serviced according to manufacturer’s

recommendations and maintained to meet statutory limits/opacity tests.

All workers onsite will undertake environmental awareness training to highlight potential

issues specific to air quality impacts associated with the project.

The contractor will provide appropriate personal protective equipment (PPE) to the workers

based on the nature of the work.

Ensure correct working methods are employed for the Project.

Page 58: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 58 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.4 Noise and vibration

Objective To ensure that noise emissions do not impact on the health, welfare and amenity of

the population, land uses and environmental values.

To ensure that noise emissions, both individually and cumulatively, comply with the

appropriate statutory requirements

Impacts Amenity

Human Health

Fauna

Pre-construction Construction Operations Decommissioning

Storage areas should be located away from sensitive receptors.

Haulage of goods and movement of vehicles/people and equipment can be scheduled.

Where required, noise barriers can be constructed to abate the noise impacts.

Alternative construction methods and selection of less noisy equipment to do the tasks.

Quarry activities to be planned during the hours of 7:00am to 7:00pm.

Blasting activities in the limestone mine should be limited to set hours.

7.5 Surface Water

Objective Maintain the integrity, ecological functions and environmental values of surface water.

Impacts Flooding behaviour.

Spring flows.

Water quality changes

Uncontrolled discharge of waste water

Pre-construction Construction Operations Decommissioning

Diversion drains up gradient from the mine area and stockpiles.

Drains down-gradient from the site to capture potentially contaminated surface water run-off.

Storm water design will be incorporated to manage extreme weather events

Accumulated pit water to be pumped out with sump pumps and used for dust suppression

Implement Mine Closure

Plan

Post closure water quality

monitoring of the water

reservoir established in the

Page 59: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 59 301012-02135-EMP-003 Rev 1 : 3 February 2017

and water sprinklers

Monitoring of surface water features for water quality impacts.

Spills management and pollution control through the Emergency Plan.

backfilled mine

7.6 Groundwater

Objective Maintain the integrity, ecological functions and environmental values of groundwater

Minimise the impact on the flow and quality of springs

Impacts Spring flows

Vegetation impacts

Water quality

Pre-construction Construction Operations Decommissioning

Detailed hydrological study

to establish baseline

groundwater monitoring

network including boreholes,

spring flow gauging and

water quality analysis

Groundwater modelling of

Water Supply borehole to

quantify drawdown impacts

Design for handling and

storage of potential

contaminants (including

fuels and chemicals) to

eliminate risk

Emergency Plan to deal with

spills and contaminants

Substitute ground water use

with make- up sea water

systems

Water sprinklers and dust

suppression management to

draw water from surface

accumulation and pits and

not drawn from ground water

Emergency Plan to deal with

spills and contaminants

Implement Mine Closure

Plan

Page 60: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 60 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.7 Flora

Objective Maintain the abundance, diversity, geographic distribution and productivity of flora at

the species and ecosystem levels through the avoidance or management of adverse

impacts.

Impacts Clearing

Soil erosion

Weeds

Pre-construction Construction Operations Decommissioning

Optimize design to prevent

un-necessary excavation

Undertake stripping and

stockpiling of topsoil

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Minimize site excavation as

much as possible

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Planting Green aprons

around developed areas

where possible

Dust suppression measures

(e.g. water sprinkling) at all

dust generating sites

Weed management

activities including spraying

Implement Mine Closure

Plan

Sequential rehabilitation

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project

Revegetation using native

vegetation types typical of

the Project area pre-

construction.

Page 61: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 61 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.8 Fauna

Objective Maintain the abundance, diversity, geographic distribution and productivity of native

fauna at the species and ecosystem levels through the avoidance or management of

adverse impacts

Impacts Clearing

Displacement of fauna

Pre-construction Construction Operations Decommissioning

Site clearing to be

conducted sequentially and

from one corner of the site to

the other, enabling highly

mobile fauna species to

leave the construction area

Monthly recording of fauna

impacts and mortality as a

result of project construction.

6-monthly reporting of fauna

impact data and

interpretation

Control of feral and pest

animals including frogs

Monthly recording of fauna

impacts and mortality as a

result of project operation.

6-monthly reporting of fauna

impact data and

interpretation

Control of feral and pest

animals including frogs

Implement Mine Closure

Plan

Sequential rehabilitation

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

project

Page 62: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 62 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.9 Traffic

Objective To protect the amenity and safety of nearby residents

Minimise disturbance to local traffic

Impacts Traffic volumes

Traffic types increased trucks and heavy machinery

Pre-construction Construction Operations Decommissioning

Planning to minimize vehicle movements (e.g. use of buses to transport workers and house in camps)

Limit reversing requirements

Traffic signage implementation

Speed limits and enforcement

Road widening

7.10 Infrastructure

Objective Prospective employees are provided with the necessary and appropriate skills

training

The expectation of employment clearly outlined minimising any potential conflicts

Existing employment sectors/source of livelihood are not adversely impacted.

Impacts Long term beneficial impact on local communities

Pre-construction Construction Operations Decommissioning

Identify and prioritize the upgrades and construction of new infrastructure required for the

construction and operation of the Project (e.g. water treatment and wastewater facilities;

roads and accommodation facilities).

Ongoing inspection, monitoring and maintenance programmes will be developed and

implemented for the relevant infrastructure during the operational phase of the Project to

ensure optimal operation.

Prior to decommissioning

and closure, consultation

with all stakeholders

(relevant authorities,

government and local

community)

Implement Mine Closure

Plan

Page 63: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 63 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.11 Employment

Objective Upgrades to existing or construction of new infrastructure for the project are designed

and built fit for purpose

Existing infrastructure are not adversely impacted by the development and operation

of the Project

Impacts Short term to long term finite increase in income

Training and development

Conflict as a result of employment practices

Pre-construction Construction Operations Decommissioning

Selection and management of employee applications by a specialist employee management

institution formed through a consultative process with sub-district and suco leadership

Prior to decommissioning

and closure, consultation

with all stakeholders

(relevant authorities,

government and local

community)

Page 64: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 64 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.12 Economic Use of Forestry and other Natural Resources

Objective Ensure the local communities access to forest and other natural resources for

economic usage are not adversely affected with the development of the Project; and

Maintain the abundance, diversity, geographic distribution and productivity of flora

and fauna at the species and ecosystem levels through the avoidance or management

of adverse impacts

Impacts Loss of firewood sources

Loss of income

Pre-construction Construction Operations Decommissioning

Minimise the disturbance footprint as far as practicable.

Undertake stripping and stockpiling of vegetation and topsoil

for reuse in the decommissioning and rehabilitation phase.

Preserve topsoil for rehabilitation by stripping soil during

construction.

Site clearing to be conducted sequentially.

Topsoil to be stock piled separately from

overburden/interburden for rehabilitation purposes and

protected against loss of run-off.

Control of alien invasive plants i.e. weed control

Control of alien invasive

plants

Implement the Mine Closure

Plan.

Sequential rehabilitation to

be conducted as soon as

possible at the completion of

operation.

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project.

Page 65: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 65 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.13 Socio Economic Agriculture

Objective Ensure the local communities access to agricultural land economic usage are not

adversely affected with the development of the Project

Impacts Loss of agricultural land

Pre-construction Construction Operations Decommissioning

The impact on community access to farmland during the

project will be addressed by resettlement and compensation

to be undertaken by the GoTL.

Sequential rehabilitation to

be conducted as soon as

possible at the completion of

operation.

Implement the Mine Closure

Plan.

The areas degraded during

the pre-construction and

construction phases shall be

restored to their natural, pre-

construction condition.

Afforestation and plantation

of local species in areas

degraded during the pre-

construction, construction

and operation phases of the

Project.

7.14 Population and Community

Objective Maintain communities and limit secondary impacts of population increase due to the

Project

Impacts Increase in population locally

Fragmentation of communities

Pre-construction Construction Operations Decommissioning

The impact on community during the project will be addressed by resettlement and compensation to be undertaken by the

GoTL.

Page 66: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 66 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.15 Community Health

Objective No adverse impacts to community health from the project

Impacts Illness and disease

Lifestyle diseases

Health services infrastructure

Pre-construction Construction Operations Decommissioning

Facilitate education and awareness programs throughout the lifespan of the Project;

Design roads and implement driver training to improve traffic safety.

Internal Project roads will be designed and constructed for all-weather, 24 hr capability.

Establish a secure buffer zone from activities posing safety risks to villages or scattered dwellings.

Develop an employee wellness programme

Page 67: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 67 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.16 Institutions, Schools and Health Facilities

Objective No adverse effects on community institutions, schools, and health facilities

Impacts 1 Air quality and noise impacts on local primary school, aldeia hall, and church.

2 Influx of jobseekers impacts on capacity of institutions, schools, and health facilities

Pre-construction Construction Operations Decommissioning

1 Refer to Section Air Quality and Section Noise and vibration for relevant mitigation measures

2 The impact on community access to institutions during the project will be addressed by

resettlement and compensation to be undertaken by the GoTL.

Decommissioning will

reduce demand for services

and should be coordinated

with the relevant line

Ministries in advance of

closure to address any

reduction in resources.

7.17 Community and Family Structure

Objective Avoid adverse effects on community and family structure

Impacts Conflicts over the status of land, conflicts over compensation values and systems,

conflicts over the dismantling of graves and customary / traditional houses,

population resettlement, and potential damage to local landowners’ subsistence

resources

Pre-construction Construction Operations Decommissioning

Implementation of the Complaints and Grievance mechanism Implementation of the

Complaints and Grievance

mechanism

Advance coordination with

stakeholders with respect to

land transfer

Advance coordination with

potential land users to

maximize productive use of

rehabilitated land

Page 68: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 68 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.18 Land Ownership and Land Rights

Objective Limit the long term impact of the project on Land Ownership / Land Rights

Impacts People financially and physically excluded from traditional lands

Pre-construction Construction Operations Decommissioning

TL Cement is currently working with the Directorate of Land, Property and Cadastral Services (DLPCS) to map affected

households, farmland, and other property. Once TL Cement has secured the mining license and environmental licenses

required for the Project, the GoTL will enter into discussions with those affected households and property owners.

7.19 Natural Resources Rights

Objective Maintain and protect natural resource rights near the Project site and/or within new

site as a part of resettlement plan.

Minimize potential impacts on surrounding environment

Impacts Reduced availability or quality of natural resources

Pre-construction Construction Operations Decommissioning

Implementation of the Complaints and Grievance

mechanism

An environmental education

programme to be developed

and implemented for all

employees

Implementation of the

Complaints and Grievance

mechanism

Implementation of the

Complaints and Grievance

mechanism

Page 69: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 69 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.20 Cultural Heritage, Archaeological and Sacred Sites

Objective Minimise the number of recorded heritage sites which are directly impacted by the

project

Ensure that the management of the relocation of known sites is undertaken in

accordance with best practice standards

Ensure transparency and consultation occurs in relation to the unavoidable impacts

on known heritage sites in the project area

Impacts Permanent loss of sites

Temporary loss of access to sites for safety reasons

Pre-construction Construction Operations Decommissioning

First to minimize encroachment on such sites identified by field surveys by revising boundary parameters- If site cannot be

avoided then initiate relocation.

Where safe access cannot be guaranteed, those sites which are located adjacent to the project should be fenced off, access

restricted for the project life or relocated.

All archaeological excavations within or adjacent to the study area should be authorised by the State Secretariat of Tourism,

Art and Culture and undertaken by a team of professional archaeologists

Ceremonial platforms or altars should be properly documented and eventually relocated to a different location;

Burial sites should be properly documented, excavated and relocated to an agreed upon site; and

Archaeological sites should be test excavated.

Page 70: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 70 301012-02135-EMP-003 Rev 1 : 3 February 2017

7.21 Description of proposed mitigation measures

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Design reviews to

consider

equipment

selection

Design reviews to

implement

Alternative Fuels

in consideration

of climate change

impacts

Design

Contractor

Prior to

construction

Throughout

project site

Incl. in

construction

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height,

if practicable.

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

Gas emissions

in accordance

with National

Greenhouse

and Energy

Reporting Act

2007.

$500,000

for

Automated

Weather

station

Monitoring

Costs $580k

Topography, Changes to Soil TL Cement / Prior to Throughout Incl. in Weed growth and As required Construction Incl. in

Page 71: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 71 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Geology and

Soils

topography and

increase in soil

erosion

contamination

should be

monitored

through

maintaining

records of spill

events

Contouring and

establishing

drainage systems

during pre-

construction

phase

Design

Consultant

construction project site and

where spills

occur

construction

contract cost

drainage behaviour

on the topsoil

stockpile

Contractor constructio

n contract

cost

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

critical emissions

hoppers

All areas with

vehicle traffic

TL Cement /

Design

Consultant

Prior to

construction

Throughout

project site and

outside of site

where

materials are

being

transported

Incl. in

construction

contract cost

At sensitive

receptors:

AQ3 – At the Jetty

AQ4 – Settlement

area at Aldeia Osso-

Ua

AQ5 - representing

the construction

area.

Every 6 months

measurements

at sensitive

receptors i.e.

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

TL Cement

Contractor

$500,000

Page 72: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 72 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

shall be watered

or have dust

palliative applied

as necessary for

regular

stabilization of

dust emissions.

All on-site vehicle

traffic shall be

limited to a speed

of 15 mph on

unpaved roads.

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of vehicle

movements

through better

planning.

Set an

appropriate speed

limit on haul

routes.

All heavy duty

vehicles should

meet certain

Page 73: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 73 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

emission

regulation from

local

Environmental

Protection

Agency.

Use a good quality

of fuel (e.g. with

low sulphur

content).

Engines and

exhaust systems

should be

regularly serviced

according to

manufacturer’s

recommendations

and maintained to

meet statutory

limits/opacity

tests.

Ensure correct

working methods

are employed for

the Project.

Noise and

Vibration

Increase in levels

of noise

Storage areas

should be located

away from

TL Cement /

Design

Consultant

Design Phase Throughout

project site and

in particular in

Incl. in

construction

contract cost

At sensitive

receptors:

NO3 – At the Jetty

Every 6 months

measurements

at sensitive

TL Cement

Contractor

$500,000

Page 74: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 74 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

the vicinity of

sensitive

receptors.

Local road

networks.

NO4 – Settlement

area at Aldeia Osso-

Ua

NO5 - representing

the construction

area.

receptors i.e.

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

streamflow

Drains down-

gradient from the

site to capture

potentially

contaminated

surface water run-

TL Cement /

Design

Consultant

Design Phase /

Prior to

construction

Throughout

project site

Incl. in

construction

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

TL Cement -

Collation of

results into

Annual

Environmental

Report to

$970,000

Page 75: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 75 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

off.

Storm water

design will be

incorporated to

manage extreme

weather events

Monitoring of

surface water

features for water

quality impacts.

Spills

management and

pollution control

through the

Emergency Plan.

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation

of data every 6

months.

NDCPEI

Groundwate

r

Decrease in flows

in springs

Changes in water

quality of springs

Detailed

hydrological study

to establish

baseline

groundwater

monitoring

network including

boreholes, spring

flow gauging and

water quality

analysis

Groundwater

modelling of

TL Cement /

Design

Consultant

Design Phase /

Prior to

construction

Monitoring at

water supply

boreholes,

design for

handling and

storage to be

implemented

across site.

Incl. in

construction

contract cost

Quality and quantity

measurements at key

spring receptors at

Uaimatabai, Uaisa

and Uaino.

Monthly water

quality and

quantity

measurements

Reporting and

interpretation

of data

quarterly

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Inc. Above

Page 76: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 76 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Water Supply

borehole to

quantify

drawdown

impacts

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals) to

eliminate risk

Flora Removal of

threatened plants

Optimize design

to prevent un-

necessary

excavation

Undertake

stripping and

stockpiling of

topsoil

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

TL Cement /

Design

Consultant

Design phase /

prior to

construction

Throughout

project site

Incl. in

construction

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Construction

contractor

$5.6M

Page 77: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 77 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

activities including

spraying

Fauna Removal of

threatened

animals

Site clearing to be

conducted

sequentially and

from one corner

of the site to the

other, enabling

highly mobile

fauna species to

leave the

construction area

TL Cement /

Construction

Contractor

Clearing Throughout

project site

Incl. in

construction

contract cost

Any incidents of

fauna injury and

death should be

recorded.

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

TL Cement $670k

Traffic Increase in

amount of traffic

on the roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits and

enforcement

Construction

Contractor /

Mine Operator

During planning

prior to

construction

Throughout

project site and

on local road

networks

Incl. in

construction

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document

traffic incidents

and mitigation

measures

implemented as

and when they

occur.

Construction

Contractor

$2000/mon

th

Page 78: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 78 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Road widening

Infrastructur

e

Increased

pressure on

existing

infrastructure

Identify and

prioritize the

upgrades and

construction of

new

infrastructure

required for the

construction and

operation of the

Project (e.g. water

treatment and

wastewater

facilities; roads

and

accommodation

facilities).

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

implemented for

the relevant

infrastructure

during the

operational phase

TL Cement /

Design

Consultant

Design phase,

ongoing

throughout

construction

and operation

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 79: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 79 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

of the Project to

ensure optimal

operation.

Employment Training and

development of

local people

Selection and

management of

employee

applications by a

specialist

employee

management

institution formed

through a

consultative

process with sub-

district and suco

leadership

TL Cement Prior to

construction

Selected

employment

management

institution

offices

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Economic

Use of

Forestry and

other

Natural

Resources

Training and

development of

local people

Minimise the

disturbance

footprint as far as

practicable.

Site clearing to be

conducted

sequentially.

TL Cement /

Construction

Contractor

Design phase,

planning phase

for site clearing

sequencing

Throughout

project site.

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Socio

Economic

Relocation to an

area where

The impact on

community access

GoTL Design phase,

prior to

Throughout

project site and

Incl. in

construction

Complaints and

Grievance records

Per the

Grievance

TL Cement

Manager

N/A

Page 80: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 80 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Agriculture people can farm to farmland

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL.

construction surrounding

area

contract cost review mechanism

Population

and

Community

Influx of new

people to the area

from outside

Baucau

The impact on

community during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

GoTL Prior to

construction

As determined

by

resettlement

facilitated by

GoTL

Incl. in

construction

contract cost

Maintain

communities and

limit secondary

impacts of population

increase due to the

Project

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Community

Health

Increase in injury,

disease and

infections due to

more people in

the area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads and

implement driver

training to

improve traffic

safety.

TL Cement Prior to

construction

and ongoing

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 81: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 81 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Internal Project

roads will be

designed and

constructed for

all-weather, 24 hr

capability.

Establish a secure

buffer zone from

activities posing

safety risks to

villages or

scattered

dwellings.

Develop an

employee

wellness

programme

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL. Refer

to Air Quality and

GoTL / TL

Cement

Prior to

construction

and ongoing

noise and air

monitoring

during

construction,

operation and

decommissioni

ng stage

Throughout

local region

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 82: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 82 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

Noise and

vibration for

relevant

mitigation

measures

Community

and Family

Structure

Relocation of

families may

impact structure

Implementation

of the Complaints

and Grievance

mechanism

TL Cement Prior to design

phase, during

design and prior

to construction

Throughout

wider area

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

TL Cement is

currently working

with the

Directorate of

Land, Property

and Cadastral

Services (DLPCS)

to map affected

households,

farmland, and

other property.

Once TL Cement

has secured the

mining license

and

environmental

licenses required

for the Project,

the GoTL will

GoTL / TL

Cement

Prior to

construction

Throughout

project area

and in

surrounding

vicinity

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be

addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Page 83: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 83 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

enter into

discussions with

those affected

households and

property owners.

Natural

Resources

Rights

Relocation of land

users will not

impact resources

rights

Implementation

of the Complaints

and Grievance

mechanism

TL Cement /

GoTL

Prior to design

phase and

ongoing

Throughout

project site and

surrounding

environment,

in particular at

identified

natural

resources

within and

near the

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be

addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Cultural

Heritage,

Archaelogica

l and Sacred

Sites

Relocation of land

users will not

cultural heritage

sites

First to minimize

encroachment on

such sites

identified by field

surveys by

revising boundary

parameters- If site

cannot be avoided

then initiate

relocation.

Where safe access

cannot be

Construction

Contractor

(during

construction

stage), Mine

Operator

Prior to

construction

and ongoing

throughout

construction,

operation and

decommissioni

ng

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

operation or

decommissioni

ng phase

Incl. in

construction

contract cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there

has been

unauthorised

impact on

cultural

heritage sites.

Page 84: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 84 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

guaranteed, those

sites which are

located adjacent

to the project

should be fenced

off, access

restricted for the

project life or

relocated.

All archaeological

excavations

within or adjacent

to the study area

should be

authorised by the

State Secretariat

of Tourism, Art

and Culture and

undertaken by a

team of

professional

archaeologists

Ceremonial

platforms or altars

should be

properly

documented and

Page 85: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 85 301012-02135-EMP-003 Rev 1 : 3 February 2017

Impact Mitigation Performance and Impact Monitoring

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Pre-Construction Stage –

Activity : Clearing the land and levelling, Vehicle movement

eventually

relocated to a

different location;

Burial sites should

be properly

documented,

excavated and

relocated to an

agreed upon site;

and

Archaeological

sites should be

test excavated.

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Design reviews to

consider

equipment

selection

Design reviews to

Construction

Contractor

During

construction

Throughout

project site and

on road

networks

Incl. in

construction

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

$500,000

for

Automated

Weather

station

Page 86: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 86 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

implement

Alternative Fuels

in consideration

of climate change

impacts

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height,

if practicable.

Gas emissions

in accordance

with National

Greenhouse

and Energy

Reporting Act

2007.

Monitoring

Costs $580k

Topography,

Geology and

Soils

Changes to

topography and

increase in soil

erosion

Soil

contamination

should be

monitored

through

maintaining

records of spill

events

Contouring and

establishing

drainage systems

during pre-

Construction

Contractor

During

construction

Throughout

project site and

in surrounding

area

Incl. in

construction

contract cost

Weed growth and

drainage behaviour

on the topsoil

stockpile

As required Construction

Contractor

Incl. in

constructio

n contract

cost

Page 87: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 87 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

construction

phase

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

critical emissions

hoppers

All areas with

vehicle traffic

shall be watered

or have dust

palliative applied

as necessary for

regular

stabilization of

dust emissions.

All on-site vehicle

traffic shall be

limited to a speed

of 15 mph on

unpaved roads.

Construction

Contractor

During

construction

Throughout

project site and

on local road

networks when

materials are

being

transported

Incl. in

construction

contract cost

A monitoring and

reporting program

implemented to

monitor the air

quality in the

following sensitive

receptors:

• AQ4 -

settlement area in

Aldeia Osso-ua.

• AQ5 -

representing the

construction area.

The monitoring

program should

assess and report on

the following air

quality parameters:

• PM10; and

PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Once every six

months during

construction

and operation

Construction

Contractor: The

monitoring

stations are

derived from

the BBS

Baseline Air

Quality

monitoring

survey (BBS,

2015b).

Page 88: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 88 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of vehicle

movements

through better

planning.

Set an

appropriate speed

limit on haul

routes.

All heavy duty

vehicles should

meet certain

emission

regulation from

local

Environmental

Protection

Agency.

Use a good quality

of fuel (e.g. with

low sulphur

content).

Engines and

exhaust systems

should be

Page 89: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 89 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

regularly serviced

according to

manufacturer’s

recommendations

and maintained to

meet statutory

limits/opacity

tests.

Ensure correct

working methods

are employed for

the Project.

Noise and

Vibration

Increase in levels

of noise

Storage areas

should be located

away from

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Construction

Contractor

During

construction

and pre

construction

(scheduling)

Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

construction

contract cost

At sensitive

receptors:

AQ4 – Settlement

area at Aldeia Osso-

Ua

AQ5 - representing

the construction

area.

Every 6 months

measurements

at sensitive

receptors i.e.

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Construction

Contractor

Incl. in

constructio

n contract

cost

Page 90: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 90 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

streamflow

Drains down-

gradient from the

site to capture

potentially

contaminated

surface water run-

off.

Monitoring of

surface water

features for water

quality impacts.

Spills

management and

pollution control

through the

Emergency Plan.

Construction

Contractor

During

construction

Throughout

project site and

down gradient

of project site

to capture

contaminated

surface run off

Incl. in

construction

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation

of data every 6

months.

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Groundwate

r

Decrease in flows

in springs

Changes in water

quality of springs

Detailed

hydrological study

to establish

baseline

groundwater

Construction

Contractor

During

construction

Throughout

project site

Incl. in

construction

contract cost

Water quality and

quantity

measurements at

key spring receptors

at Uaimatabai, Uaisa

Monthly water

quality and

quantity

measurements

Reporting and

TL Cement -

Collation of

results into

Annual

Environmental

Page 91: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 91 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

monitoring

network including

boreholes, spring

flow gauging and

water quality

analysis

Groundwater

modelling of

Water Supply

borehole to

quantify

drawdown

impacts

and Uaino.

interpretation

of data

quarterly

Report to

NDCPEI

Flora Removal of

threatened plants

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

activities including

spraying

Construction

Contractor

During

excavation and

construction

Throughout

project site

Incl. in

construction

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

End of phase TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Fauna Removal of

threatened

animals

Site clearing to be

conducted

sequentially and

from one corner

of the site to the

other, enabling

highly mobile

Construction

Contractor

During

construction

Throughout

project site

Incl. in

construction

contract cost

All fauna injury and

death records.

Reporting and

interpretation

every six

months

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 92: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 92 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

fauna species to

leave the

construction area

Traffic Increase in

amount of traffic

on the roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits and

enforcement

Road widening

Construction

Contractor /

Mine Operator

During planning

prior to

construction

and during

construction

Throughout

project site and

on local road

networks

Incl. in

construction

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document

traffic incidents

and mitigation

measures

implemented as

and when they

occur

Construction

Contractor /

Mine Operator

Costs to

Constructio

n

Contractor /

Mine

Operator

Infrastructur

e

Increased

pressure on

existing

infrastructure

Identify and

prioritize the

upgrades and

construction of

new

infrastructure

required for the

construction and

operation of the

TL Cement Update

priorities for

upgrade if

required

Throughout

project site

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 93: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 93 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

Project (e.g. water

treatment and

wastewater

facilities; roads

and

accommodation

facilities).

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

implemented for

the relevant

infrastructure

during the

operational phase

of the Project to

ensure optimal

operation.

Employment Training and

development of

local people

Selection and

management of

employee

applications by a

specialist

employee

management

Construction

Contractor

During

construction

At Employee

Management

Institution

Offices

Incl. in

construction

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 94: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 94 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

institution formed

through a

consultative

process with sub-

district and suco

leadership

Economic

Use of

Forestry and

other

Natural

Resources

Training and

development of

local people

Minimise the

disturbance

footprint as far as

practicable.

Site clearing to be

conducted

sequentially.

TL Cement /

Construction

Contractor

Stripping soil

and site

clearing.

Stockpile

topsoil

immediately

following

clearing.

Ongoing weed

control during

construction

Throughout

project site

Incl. in

construction

contract cost

Control of weed and

pathogen hygiene

practices

NA TL Cement /

Construction

Contractor

Socio

Economic

Agriculture

Relocation to an

area where

people can farm

The impact on

community access

to farmland

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL.

GoTL Access

established

prior to

construction

and managed /

mantained as

required

As determined

by

resettlement

facilitated by

GoTL

Incl. in

construction

contract cost

Control of weed and

pathogen hygiene

practices

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Population Influx of new The impact on GoTL Prior to As determined Incl. in Complaints and Per the TL Cement N/A

Page 95: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 95 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

and

Community

people to the area

from outside

Baucau

community during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

construction

and managed /

maintained as

required

by

resettlement

facilitated by

GoTL

construction

contract cost

Grievance records

Grievance

mechanism

Manager

Community

Health

Increase in injury,

disease and

infections due to

more people in

the area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads and

implement driver

training to

improve traffic

safety.

Internal Project

roads will be

designed and

constructed for

all-weather, 24 hr

capability.

Establish a secure

buffer zone from

activities posing

safety risks to

TL Cement Ongoing Throughout

project site and

in surrounding

area (secure

buffer zones)

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 96: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 96 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

villages or

scattered

dwellings.

Develop an

employee

wellness

programme

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL. Refer

to Air Quality and

Noise and

vibration for

relevant

mitigation

measures

GoTL / TL

Cement /

Construction

Contractor

Impact on

community

access

addressed prior

to construction.

Noise and

vibration

monitoring

ongoing

throughout

construction,

operation and

decommissioni

ng phases

As determined

by

resettlement

facilitated by

GoTL. Air and

Noise

monitoring at

selected

appropriate

locations and

near sensitive

receptors

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Community

and Family

Structure

Relocation of

families may

impact structure

Implementation

of the Complaints

and Grievance

mechanism

TL Cement /

Mine Operator

Impact on

community

addressed

construction

but complaints

and grievance

Throughout

project site and

wider area as

required

Incl. in

construction

contract cost

Complaints and

Grievance records

Per the

Grievance

mechanism

TL Cement

Manager

N/A

Page 97: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 97 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

records to be

maintained

throughout

project

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

TL Cement is

currently working

with the

Directorate of

Land, Property

and Cadastral

Services (DLPCS)

to map affected

households,

farmland, and

other property.

Once TL Cement

has secured the

mining license

and

environmental

licenses required

for the Project,

the GoTL will

enter into

discussions with

those affected

households and

property owners.

GoTL / TL

Cement

Ongoing Affected

households

and property

owners

Incl. in

construction

contract cost

Complaints and

Grievance records

Regular review

of records

To be

addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Natural Relocation of land Implementation TL Cement / Ongoing Throughout Incl. in Complaints and Regular review To be

Page 98: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 98 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Construction Stage

Activity : Clearing the land and levelling, Vehicle movement, excavating trenches, constructing buildings, constructing infrastructure, constructing the Limestone Mine

Resources

Rights

users will not

impact resources

rights

of the Complaints

and Grievance

mechanism

GoTL project site and

surrounding

environment,

in particular at

identified

natural

resources

within and

near the

project site

construction

contract cost

Grievance records

of records addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Cultural

Heritage,

Archaelogica

l and Sacred

Sites

Relocation of land

users will not

cultural heritage

sites

Where safe access

cannot be

guaranteed, those

sites which are

located adjacent

to the project

should be fenced

off, access

restricted for the

project life or

relocated.

Construction

Contractor

Prior to

construction for

planning and

design of

project, sites to

be fenced and

protected

throughout life

of project

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

operation or

decommissioni

ng phase

Incl. in

construction

contract cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there

has been

unauthorised

impact on

cultural

heritage sites

Page 99: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 99 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

Climate Atmospheric

emissions

(i.e. carbon

monoxide)

increase from

use of

vehicles

TL Cement During operation Throughout

project site and

on local road

networks

Incl. in

Operations

contract cost

Automated Weather

Station (AWS)

recording

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height,

if practicable.

Daily

measurements

TL Cement

Annual

reporting for all

project phases

of Greenhouse

Gas emissions

in accordance

with National

Greenhouse

and Energy

Reporting Act

2007.

$500,000

for

Automated

Weather

station

Monitoring

Costs $580k

Topography,

Geology and

Soils

Changes to

topography

and increase

in soil erosion

Soil

contamination

should be

monitored

through

maintaining

records of spill

TL Cement During operation Throughout

project site and

surrounding

area

Incl. in

Operations

contract cost

Water quality and

quantity

measurements at key

spring receptors,

Uaino, and in the

Water Reserve area.

Monthly

measurements.

Reporting and

interpretation

of data every 6

months.

Page 100: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 100 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

events

Contouring and

establishing

drainage

systems during

pre-

construction

phase

Air Quality Increase in

levels of dust

All raw

materials

storage will be

in enclosed

structures

All materials

transport will

be by fully

covered

conveyor belts

Dust and bag

filters will be

installed at all

critical

emissions

hoppers

All areas with

vehicle traffic

shall be

watered or

have dust

TL Cement During operation Throughout

project site

Incl. in

Operations

contract cost

A monitoring and

reporting program

implemented to

monitor the air

quality in the

following sensitive

receptors:

• AQ4 -

settlement area in

Aldeia Osso-ua.

• AQ5 -

representing the

construction area.

The monitoring

program should

assess and report on

the following air

quality parameters:

• PM10; and

PM2.5

• CO

Once every six

months during

construction

and operation

TL Cement: The

monitoring

stations are

derived from

the BBS

Baseline Air

Quality

monitoring

survey (BBS,

2015b).

Page 101: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 101 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

palliative

applied as

necessary for

regular

stabilization of

dust emissions.

All on-site

vehicle traffic

shall be limited

to a speed of 15

mph on

unpaved roads.

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of

vehicle

movements

through better

planning.

Set an

appropriate

speed limit on

haul routes.

All heavy duty

vehicles should

meet certain

• NO2

• SO2; and

• Ozone.

Page 102: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 102 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

emission

regulation from

local

Environmental

Protection

Agency.

Use a good

quality of fuel

(e.g. with low

sulphur

content).

Engines and

exhaust

systems should

be regularly

serviced

according to

manufacturer’s

recommendatio

ns and

maintained to

meet statutory

limits/opacity

tests.

Ensure correct

working

methods are

employed for

the Project.

Page 103: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 103 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

Noise and

Vibration

Increase in

levels of

noise

Haulage of

goods and

movement of

vehicles/people

and equipment

can be

scheduled.

Where

required, noise

barriers can be

constructed to

abate the noise

impacts.

Alternative

construction

methods and

selection of less

noisy

equipment to

do the tasks.

TL Cement During operation Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

Operations

contract cost

At sensitive receptors

(as per construction)

Once per year

measurements

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Surface Water Decrease in

flows in

streams

Changes in

water quality

of streamflow

Drains down-

gradient from

the site to

capture

potentially

contaminated

TL Cement During operation Throughout

project site and

drains down

gradient of site

Incl. in

Operations

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

TL Cement -

Collation of

results into

Annual

Environmental

Report to

$1.4M

Page 104: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 104 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

surface water

run-off.

Storm water

design will be

incorporated to

manage

extreme

weather events

Monitoring of

surface water

features for

water quality

impacts.

Spills

management

and pollution

control through

the Emergency

Plan.

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation

of data every 6

months.

NDCPEI

Groundwater Decrease in

flows in

springs

Changes in

water quality

of springs

Detailed

hydrological

study to

establish

baseline

groundwater

monitoring

network

including

boreholes,

TL Cement During operation Throughout

project site

Incl. in

Operations

contract cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

$1.4M

Page 105: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 105 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

spring flow

gauging and

water quality

analysis

Groundwater

modelling of

Water Supply

borehole to

quantify

drawdown

impacts

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals)

to eliminate risk

Interpretation

of data every 6

months.

Flora Removal of

threatened

plants

Dust

suppression

measures (e.g.

water

sprinkling) at all

dust generating

sites

Weed

management

activities

TL Cement Ongoing Throughout

project site

Incl. in

Operations

contract cost

The total area of

vegetation cleared

(habitat destruction)

at the end of phase

End of phase TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Page 106: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 106 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

including

spraying

Fauna Removal of

threatened

animals

Vehicles obey

speed limits.

TL Cement Ongoing Throughout

and

surrounding

project site

Incl. in

Operations

contract cost

All fauna injury and

death records.

Reporting and

interpretation

every six

months

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Traffic Increase in

amount of

traffic on the

roads

Planning to

minimize

vehicle

movements

(e.g. use of

buses to

transport

workers and

house in camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits

and

enforcement

Road widening

TL Cement Throughout life of

project

Throughout

project site and

on local road

networks

Incl. in

Operations

contract cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document

traffic incidents

and mitigation

measures

implemented as

and when they

occur.

Construction

Contractor /

Mine Operator

Costs to

Constructio

n

Contractor /

Mine

Operator

Page 107: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 107 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

Infrastructure Increased

pressure on

existing

infrastructure

Ongoing

inspection,

monitoring and

maintenance

programmes

will be

developed and

implemented

for the relevant

infrastructure

during the

operational

phase of the

Project to

ensure optimal

operation.

TL Cement Ongoing Throughout

project site

Incl. in

Operations

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Employment Training and

development

of local

people

Selection and

management of

employee

applications by

a specialist

employee

management

institution

formed through

a consultative

process with

sub-district and

TL Cement Ongoing as

required

Selected

Employment

Management

Institution

Offices

Incl. in

Operations

contract cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Page 108: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 108 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

suco leadership

Economic Use of

Forestry and

other Natural

Resources

Training and

development

of local

people

Minimise the

disturbance

footprint as far

as practicable.

Site clearing to

be conducted

sequentially.

TL Cement Ongoing Throughout

project site and

surrounding

area

Incl. in

Operations

contract cost

Control of weed and

pathogen hygiene

practices

NA TL Cement

Socio Economic

Agriculture

Relocation to

an area

where people

can farm

The impact on

community

access to

farmland during

the project will

be addressed

by resettlement

and

compensation

to be

undertaken by

the GoTL.

TL Cement At completion of

operation

Throughout

wider region

Incl. in

Operations

contract cost

Control of weed and

pathogen hygiene

practices

Population and

Community

Influx of new

people to the

area from

outside

Baucau

The impact on

community

during the

project will be

addressed by

resettlement

and

GoTL Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 109: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 109 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

compensation

to be

undertaken by

the GoTL.

throughout

project

Community

Health

Increase in

injury,

disease and

infections

due to more

people in the

area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

Design roads

and implement

driver training

to improve

traffic safety.

Internal Project

roads will be

designed and

constructed for

all-weather, 24

hr capability.

Establish a

secure buffer

zone from

activities posing

safety risks to

villages or

scattered

TL Cement Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

throughout

project

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 110: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 110 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

dwellings.

Develop an

employee

wellness

programme

Institutions,

Schools and

Health Facilities

No impact

anticipated

The impact on

community

access to

institutions

during the

project will be

addressed by

resettlement

and

compensation

to be

undertaken by

the GoTL. Refer

to Air Quality

and Noise and

vibration for

relevant

mitigation

measures

GoTL Impact on

community

addressed

construction but

complaints and

grievance records

to be maintained

throughout

project

Throughout

local region

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Community and

Family Structure

Transient

workers

families may

impact family

structures

Implementation

of the

Complaints and

Grievance

mechanism

TL Cement Impact on

community

addressed

construction but

complaints and

Throughout

local region

Incl. in

Operations

contract cost

Complaints and

Grievance records

Regular review

of records

Page 111: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 111 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environmental

Concern

Potential

Impact

Mitigation

Measures

(MM)

Responsible to

implement MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Operations

Activity : Vehicle movement, blasting, transporting material within the mine area, cement transport to/from Baucau

grievance records

to be maintained

throughout

project

Land ownership

and Land Rights

No impact

during

operations

Complaints and

Grievance records

Regular review

of records

Natural

Resources Rights

No impact

during

operations

Cultural

Heritage,

Archaeological

and Sacred Sites

No impact

during

operations

Page 112: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 112 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Climate Atmospheric

emissions (i.e.

carbon monoxide)

increase from use

of vehicles

Select equipment

with lowest

practical

emissions.

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Throughout

project site and

on local road

networks

Incl. in

Decommissioni

ng contract

cost

Maintain Automated

Weather Station

(AWS) per Operations

Phase

Daily

measurements.

TL Cement -

Annual

reporting for all

project phases

of Greenhouse

Gas emissions

in accordance

with National

Greenhouse

and Energy

Reporting Act

2007.

Topography,

Geology and

Soils

Changes to

topography and

increase in soil

erosion

Soil

contamination

should be

monitored

through

maintaining

records of spill

events

Contouring and

establishing

drainage systems

during

decommissioning

phase

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Throughout

project site

Incl. in

Decommissioni

ng contract

cost

Post closure

assessment of

rehabilitation success

and soil health

5 years after

closure

Page 113: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 113 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Air Quality Increase in levels

of dust

All raw materials

storage will be in

enclosed

structures

All materials

transport will be

by fully covered

conveyor belts

Dust and bag

filters will be

installed at all

critical emissions

hoppers

All areas with

vehicle traffic

shall be watered

or have dust

palliative applied

as necessary for

regular

stabilization of

dust emissions.

All on-site vehicle

traffic shall be

limited to a speed

of 15 mph on

unpaved roads.

No vehicles or

plant will be left

idling

unnecessarily.

Reduce the

number of vehicle

movements

through better

planning.

Set an

appropriate speed

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng, in particular

during

excavation,

stockpiling and

grading of

materials.

Throughout

project site

Incl. in

Decommissioni

ng contract

cost

Install Automated

Weather Station

(AWS) recording daily

measurements of:

Station identification

number;

Date and time of

record/observation;

Air, wet bulb and wet

dew point

temperatures.

Precipitation and

evaporation;

Relative humidity;

Wind speed and

direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height,

if practicable.

Daily

measurements

TL Cement -

Annual

reporting for all

project phases

of Greenhouse

Gas emissions

in accordance

with National

Greenhouse

and Energy

Reporting Act

2007.

Page 114: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 114 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Noise and

Vibration

Increase in levels

of noise

Storage areas

should be located

away from

sensitive

receptors.

Haulage of goods

and movement of

vehicles/people

and equipment

can be scheduled.

Where required,

noise barriers can

be constructed to

abate the noise

impacts.

Alternative

construction

methods and

selection of less

noisy equipment

to do the tasks.

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Throughout

project site and

in particular in

the vicinity of

sensitive

receptors.

Local road

networks

Incl. in

Decommissioni

ng contract

cost

At sensitive receptors

(as per construction)

Once per year

measurements

Results

interpretation

and review of

the EMP as

required.

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 115: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 115 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Surface

Water

Decrease in flows

in streams

Changes in water

quality of

streamflow

Drains down-

gradient from the

site to capture

potentially

contaminated

surface water run-

off.

Storm water

design will be

incorporated to

manage extreme

weather events

Monitoring of

surface water

features for water

quality impacts.

Spills

management and

pollution control

through the

Emergency Plan.

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Drains down

gradient of

site. Other

measures

throughout

project site

Incl. in

Decommissioni

ng contract

cost

Flow meters / stream

gauges at the Bucoli

River (1.6km west)

and at Uaimatabai,

Uaisa and Waino

springs

Monthly water

quality and

quantity

measurements

at monitoring

boreholes, key

spring receptors

at Waiono,

Uaimatabai and

Uaisa.

Interpretation

of data every 6

months.

TL Cement -

Collation of

results into

Annual

Environmental

Report to

NDCPEI

Groundwate

r

Decrease in flows

in springs

Changes in water

quality of springs

Design for

handling and

storage of

potential

contaminants

(including fuels

and chemicals) to

eliminate risk

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Throughout

project site

Incl. in

Decommissioni

ng contract

cost

NA NA NA NA

Page 116: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 116 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Flora Growth and

spread of weeds

Dust suppression

measures (e.g.

water sprinkling)

at all dust

generating sites

Weed

management

activities including

spraying

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Areas

degraded

during the life

of the project.

Incl. in

Decommissioni

ng contract

cost

Monitoring and

reporting of flora

species abundance

and coverage

5 years after

mine closure

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Fauna Removal of

threatened

animals

Planting of habitat

mimicking natural

environment.

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Areas

degraded

during the life

of the project

Incl. in

Decommissioni

ng contract

cost

Monitoring and

reporting of fauna

species abundance

5 years after

mine closure

TL Cement -

Collation of

results into

semi-annual

Environmental

Report to

NDCPEI

Page 117: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 117 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Traffic Increase in

amount of traffic

on the roads

Planning to

minimize vehicle

movements (e.g.

use of buses to

transport workers

and house in

camps)

Limit reversing

requirements

Traffic signage

implementation

Speed limits and

enforcement

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Througout

project site and

on local road

networks

Incl. in

Decommissioni

ng contract

cost

Traffic incidents and

mitigation measures

implemented

Update Safety

Management

System to

record and

document

traffic incidents

and mitigation

measures

implemented as

and when they

occur.

Construction

Contractor /

Mine Operator

Costs to

Constructio

n

Contractor /

Mine

Operator

Infrastructur

e

Increased

pressure on

existing

infrastructure

Ongoing

inspection,

monitoring and

maintenance

programmes will

be developed and

implemented for

the relevant

infrastructure

during the

decommissioning

phase

TL Cement Prior to

decommissioni

ng

Throughout

project site and

wider area

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

reviewed regularly

Regular Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 118: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 118 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Employment Training and

development of

local people

Redeployment

and training

opportunities to

offset loss of

employment on

closure

TL Cement Prior to

decommissioni

ng

Throughout

project site and

wider area

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

review

Stakeholder

consultation to check

progress

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement

Economic

Use of

Forestry and

other

Natural

Resources

Training and

development of

local people

Rehabilitation

with native

species

TL Cement /

Decommissioni

ng Contractor

Immediately

following

completion of

operation

Areas

degraded

during life of

project

Incl. in

Decommissioni

ng contract

cost

The total area of re-

vegetation and the

species used for

rehabilitation should

be recorded and

monitored

For a period of

5 years

following

decommissioni

ng.

TL Cement /

Decommissioni

ng Contractor

Socio

Economic

Agriculture

Returning to the

area

The impact on

community access

to farmland

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL.

TL Cement /

Decommissioni

ng Contractor

During

decommissioni

ng

Areas

degraded

during life of

project

Incl. in

Decommissioni

ng contract

cost

The total area of re-

vegetation and the

species used for

rehabilitation should

be recorded and

monitored

For a period of

5 years

following

decommissioni

ng.

Page 119: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 119 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Population

and

Community

Influx of new

people to the area

from outside

Baucau

The impact on

community during

the project will be

addressed by

resettlement and

compensation to

be undertaken by

the GoTL.

GoTL Impact on

community

addressed

construction

but complaints

and grievance

records to be

maintained

throughout

project

As determined

by

resettlement

facilitated by

GoTL

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of records

Community

Health

Increase in injury,

disease and

infections due to

more people in

the area

Facilitate

education and

awareness

programs

throughout the

lifespan of the

Project;

TL Cement Impact on

community

addressed

construction

but complaints

and grievance

records to be

maintained

throughout

project

Throughout

local region

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Page 120: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 120 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Institutions,

Schools and

Health

Facilities

No impact

anticipated

The impact on

community access

to institutions

during the project

will be addressed

by resettlement

and

compensation to

be undertaken by

the GoTL.

TL Cement /

Decommissioni

ng Contractor

Prior to

decommissioni

ng . Air quality

and noise

monitoring

during

decommissioni

ng.

Throughout

local region

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Community

and Family

Structure

Relocation of

families may

impact structure

Implementation

of the Complaints

and Grievance

mechanism

TL Cement Impact on

community

addressed

construction

but complaints

and grievance

records to be

maintained

throughout

project

Throughout

local region

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of Complaints

and Grievance

record

Regular

stakeholder

consultation

TL Cement N/A

Land

ownership

and Land

Rights

Relocation of land

users will not

impact land rights

Implementation

of the Complaints

and Grievance

mechanism

TL Cement /

GoTL

Ongoing Affected

households

and property

owners

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of records

To be

addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Page 121: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 121 301012-02135-EMP-003 Rev 1 : 3 February 2017

Environment

al Concern

Potential Impact Mitigation

Measures (MM)

Responsible to

implement

MM

Timing to

implement MM

Locations of

MM

Mitigation Cost Parameter to

Monitor

Frequency and

Variation

Responsible to

Monitor

Cost of

Monitoring

Decommissioning Stage

Activity : Clearing the land and levelling, rehabilitation, dismantling infrastructure

Natural

Resources

Rights

Relocation of land

users will not

impact resources

rights

Implementation

of the Complaints

and Grievance

mechanism

TL Cement /

GoTL

Ongoing Throughout

project site and

surrounding

environment,

in particular at

identified

natural

resources

within and

near the

project site

Incl. in

Decommissioni

ng contract

cost

Complaints and

Grievance records

Regular review

of records

To be

addressed by

resettlement

and

compensation

to be

addressed by

GoTL

Cultural

Heritage,

Archaeologic

al and

Sacred Sites

Relocation of land

users will not

cultural heritage

sites

TL Cement Prior to

construction

and ongoing

throughout

construction,

operation and

decommissioni

ng

Heritage sites

identified

through the EIA

as well as any

additional sites

discovered

during

construction,

operation or

decommissioni

ng phase

Incl. in

Decommissioni

ng contract

cost

Any and all

occurrences of

damage sites is to be

recorded.

Records to be

reviewed every

6 months.

TL Cement.

Process

improvements

are to be

implemented

where there

has been

unauthorised

impact on

cultural

heritage sites.

Page 122: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 122 301012-02135-EMP-003 Rev 1 : 3 February 2017

8 GOVERNING PARAMETERS

8.1 Environmental Quality Standards

The monitoring plan has been developed taking into account the best available measurement

standard for the relevant criteria. The standard is detailed in Section 8.3 (Governing Parameters)

below, alongside the applicable parameter.

8.2 International Best Practice

Where possible, the monitoring plan has been developed utilizing internationally-recognized

standards and emissions criteria. Standards used by the World Health Organization and the

International Finance Corporation have been used as first priority, followed by standards used in

Australia and elsewhere.

8.3 Governing parameters

8.3.1 Emissions

Emissions standards are determined based on the medium of transmission i.e. water or air and are

detailed further under Sections 8.3.2 and 8.3.3.

8.3.2 Ambient Water Quality Standards

Parameter International best

practice standard

Proposed limit value Comments

Fresh Water (Springs and streams)

e.Coli or Thermotolerant

coliform bacteria

WHO Drinking Water

Standards (2000)

0 mg/L in 100ml sample All water directly intended

for drinking

Nitrate WHO Drinking Water

Standards (2000)

50 mg/L All water directly intended

for drinking

Nitrite WHO Drinking Water

Standards (2000)

3 mg/L All water directly intended

for drinking

Chlorine WHO Drinking Water

Standards (2000)

5 mg/L All water directly intended

for drinking

Page 123: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 123 301012-02135-EMP-003 Rev 1 : 3 February 2017

Parameter International best

practice standard

Proposed limit value Comments

Copper WHO Drinking Water

Standards (2000)

2 mg/L All water directly intended

for drinking

Lead WHO Drinking Water

Standards (2000)

0.01 mg/L All water directly intended

for drinking

Nickel WHO Drinking Water

Standards (2000)

0.07 mg/L All water directly intended

for drinking

Manganese WHO Drinking Water

Standards (2000)

0.4 mg/L All water directly intended

for drinking

8.3.3 Ambient Air Quality Standards

Parameter International best practice standard Proposed interim target limit (µg/m3)

Carbon

monoxide

International Ambient Air Quality Standards

(IAAQS)

http://www3.epa.gov/ttn/naaqs/criteria.html

1 hour = 40,000 µg/m3

Not to be exceeded more than once per

year

Nitrogen

dioxide

International Ambient Air Quality Standards

(IAAQS)

http://whqlibdoc.who.int/hq/2006/WHO_SDE_PHE_

OEH_06.02_eng.pdf

1 hour = 200 µg/m3

Annual = 40 µg/m3

Photochemic

al oxidants

(as ozone)

International Ambient Air Quality Standards

(IAAQS)

1 hour = 235 µg/m3

Sulfur dioxide International Ambient Air Quality Standards

(IAAQS)

1 hour = 350 µg/m3

24 hour = 125 µg/m3

Particles as

PM2.5

International Ambient Air Quality Standards

(IAAQS)

24 hour = 75 µg/m3

Annual = 70 µg/m3

Page 124: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 124 301012-02135-EMP-003 Rev 1 : 3 February 2017

8.3.4 Soil

All the parameters below are obtained from the National Environment Protection Measure

(Assessment of Contamination) 1999 for the Groundwater Investigation Levels in Fresh Waters “Table

1C”. The measurement of soil contamination is typically taken from groundwater monitoring boreholes

located down-gradient from the suspected contamination.

Parameter Proposed discharge limit value

µg/L

Aluminium 55 µgL

Chromium IV 1 µgL

Nickel 11 µgL

Benzene 950 µgL

Phenol 320 µgL

Lead 3.4 µgL

Manganese 1900 µgL

Mercury (total) 0.06 µgL

Zinc 8 µgL

Ammonia (NH3-N) 900 µgL

Ethanol 1400 µgL

Page 125: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 125 301012-02135-EMP-003 Rev 1 : 3 February 2017

8.3.5 Occupational Health and Safety Standards

8.3.5.1 WORKPL ACE NOISE AND VIBRAT ION

Parameter International best

practice standard

Proposed discharge

limit value

Comments

Blasting

(Airblast level)

Regulation 11

Environmental Protection

(Noise) Regulations 1997

120 dBLz peak at

sensitive receptor

125 dBLz peak at non

sensitive receptor

Blasting carried out

between 7am and 6pm on

any day of the week

Noise and Vibration UNTAET, 2001

Residential, Institutional

and Educational

Receptors

50 – 55 dB(A)

8.3.5.2 DRINKING WATER

These standards are applicable for fresh water springs and streams.

Parameter International best practice

standard

Proposed limit value

E.Coli or Thermotolerant

coliform bacteria

WHO Drinking Water Standards

(2000)

0 mg/L in 100ml sample

Nitrate WHO Drinking Water Standards

(2000)

50 mg/L

Nitrite WHO Drinking Water Standards

(2000)

3 mg/L

Chlorine WHO Drinking Water Standards

(2000)

5 mg/L

Copper WHO Drinking Water Standards

(2000)

2 mg/L

Page 126: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 126 301012-02135-EMP-003 Rev 1 : 3 February 2017

Parameter International best practice

standard

Proposed limit value

Lead WHO Drinking Water Standards

(2000)

0.01 mg/L

Nickel WHO Drinking Water Standards

(2000)

0.07 mg/L

Manganese WHO Drinking Water Standards

(2000)

0.4 mg/L

8.3.5.3 SAFETY MANAGEMENT

Safety Management shall be undertaken in accordance with local labour laws and regulations.

8.3.5.4 COMMUNICATIVE DISEASES

Data and statistics on Communicative diseases will be confidentially collected through surveying of

the health providers to determine if adjustments to the Workplace Health and Safety Standard are

required. Communicative diseases include:

Infection control in the workplace aims to prevent pathogens from coming into contact with a person in

the first place. The basis of good infection control in the workplace is to assume that everyone is

potentially infectious. Proper procedures have to be followed at all times.

Good marketing of personal hygiene is the first line of defense. Infection control procedures relating to

good personal hygiene include:

• Hand washing;

• Covering cuts or abrasions with a waterproof dressing; and

• Gloves.

Many infections are food-borne. When preparing food, it is important to:

• Wash hands before and after handling food;

• Keep hot food hot and cold food cold;

• Use separate storage, utensils and preparation surfaces for cooked and uncooked foods; and

• Wash all utensils and preparation surfaces thoroughly with hot water and detergent after use.

Frequently, workplace illnesses are spread by droplet infection. Colds and flu are transmitted in this

way, and sharing telephones is an infection risk. If at all possible, users should have personal

headsets, and telephones should be regularly cleaned and sterilized.

Page 127: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 127 301012-02135-EMP-003 Rev 1 : 3 February 2017

8.4 Modelling or Engineering Calculations

Trigger values and monitoring upper limit guideline values have been based on published standard

and guideline values and no modelling was undertaken to derive them.

Page 128: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 128 301012-02135-EMP-003 Rev 1 : 3 February 2017

9 MONITORING PROGRAM

In designing the monitoring programme for each aspect identified in the EIS, this section details:

• the specific parameters;

• monitoring protocols;

• sampling locations and frequencies of monitoring; and

• how compliance with implementation of the EMPs and sub-EMPs will be checked and

reported.

The above information has been presented in table format for each phase of the Project; i.e. Pre-

construction; Construction; Operation; and Decommissioning.

9.1 Climate

Monitoring Programme : Climate

Pre-construction Construction Operations Decommissioning

Install Automated Weather Station (AWS) recording daily measurements of:

• Station identification number;

• Sate and time of record/observation;

• Air, wet bulb and wet dew point temperatures.

• Precipitation and evaporation;

• Relative humidity;

• Wind speed and direction;

• Solar radiation;

• Barometric pressure ;

• Visibility;

• Cloud cover; and

• Cloud ceiling height, if practicable.

Annual reporting for all project phases of Greenhouse Gas emissions in accordance with National Greenhouse

and Energy Reporting Act 2007.

Page 129: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 129 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.2 Topography and Soil

Monitoring Programme : Topography, Geology and Soil

Pre-construction Construction Operations Decommissioning

Weed growth and

drainage behaviour on

the topsoil stockpile

Monthly water quality and quantity measurements at

key spring receptors, Uaino, and in the Water

Reserve area.

Reporting and interpretation of data every 6 months.

5 years post closure

assessment of rehabilitation

success and soil health

9.3 Air Quality

Monitoring Programme : Air Quality

Pre-construction Construction Operations Decommissioning

A monitoring and reporting program (once every six months during construction and operation) should be

implemented to monitor the air quality in the following sensitive receptors:

• AQ4 - settlement area in Aldeia Osso-ua.

• AQ5 - representing the construction area.

The monitoring stations are derived from the BBS Baseline Air Quality monitoring survey (BBS, 2015b).

The monitoring program should assess and report on the following air quality parameters:

• PM10; and PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Page 130: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 130 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.4 Noise and vibration

Monitoring Programme : Noise and Vibration

Pre-construction Construction Operations Decommissioning

Every 6 months measurements at sensitive

receptors i.e.

1. AQ4 – Settlement area at Aldeia Osso-Ua

2. AQ5 - representing the construction area.

Results interpretation and review of the EMP as

required.

Collation of results into semi-annual Environmental

Report to NDCPEI

Once per year

measurements at

sensitive receptors (as

per Construction)

Results interpretation

and review of the EMP

as required.

Collation of results into

Annual Environmental

Report to NDCPEI

Once per year measurements

at sensitive receptors (as per

Operations)

Results interpretation and

review of the EMP as required.

Collation of results into semi-

annual Environmental Report

to NDCPEI

9.5 Surface water

Monitoring Programme : Surface Water

Pre-construction Construction Operations Decommissioning

Sampling and volume estimation of any water encountered in the open pit mine (quarry).

Flow meters / stream gauges at the Bucoli River (1.6km west) and at Uaimatabai, Uaisa and Waino springs.

Monthly water quality and quantity measurements at monitoring boreholes, key spring receptors at Waiono,

Uaimatabai and Uaisa.

Interpretation of data every 6 months.

Collation of results into Annual Environmental Report to NDCPEI

Page 131: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 131 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.6 Groundwater

Monitoring Programme : Surface Water

Pre-construction Construction Operations Decommissioning

Monthly water quality

and quantity

measurements at key

spring receptors at

Uaimatabai, Uaisa and

Uaino.

Reporting and

interpretation of data

quarterly

Sampling and volume estimation of any water

encountered in the open pit mine (quarry).

Monthly water quality and quantity measurements at

key spring receptors at Uaimatabai, Uaisa and

Uaino.

Reporting and interpretation of data quarterly

Collation of results into Annual Environmental Report

to NDCPEI

Monitoring of water quality in

the water reservoir remaining in

the footprint of the open pit

semi-annually for at least 5

years post decommissioning.

9.7 Flora

Monitoring Programme : Flora

Pre-construction Construction Operations Decommissioning

The total area of vegetation cleared (habitat destruction) at the end of phase

Collation of results into Annual Environmental Report to NDCPEI

Monitoring and reporting of

flora species abundance and

coverage 5 years after mine

closure

Collation of results into semi-

annual Environmental Report

to NDCPEI

9.8 Fauna

Monitoring Programme : Fauna

Pre-construction Construction Operations Decommissioning

Page 132: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 132 301012-02135-EMP-003 Rev 1 : 3 February 2017

Any incidents of fauna

injury and death

should be recorded.

Collation of results into

semi-annual

Environmental Report

to NDCPEI

Reporting and interpretation of fauna injury and

death records every 6 months.

Collation of results into Annual Environmental Report

to NDCPEI

Monitoring and reporting of

fauna species abundance 5

years after mine closure

Collation of results into semi-

annual Environmental Report

to NDCPEI

9.9 Traffic

Monitoring Programme : Traffic

Pre-construction Construction Operations Decommissioning

Safety Management System to record and document traffic incidents and mitigation measures implemented

Page 133: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 133 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.10 Infrastructure

Monitoring Programme : Infrastructure

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Regular Stakeholder consultation to check progress

9.11 Employment

Monitoring Programme : Employment

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Regular Stakeholder consultation to check progress

9.12 Economic Use of Forestry and other Natural Resources

Monitoring Programme : Economic Use of Forestry and other Natural Resources

Pre-construction Construction Operations Decommissioning

The total area of

vegetation cleared

during the pre-

construction and

construction phase

should be recorded.

Control of weed and pathogen hygiene practices The total area of re-vegetation

and the species used for

rehabilitation should be

recorded and monitored for a

period of 5 years following

decommissioning.

Page 134: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 134 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.13 Socio-Economic Agriculture

Monitoring Programme : Socio Economic Agriculture

Pre-construction Construction Operations Decommissioning

Complaints and

Grievance records

reviewed regularly

Control of weed and pathogen hygiene practices The total area of re-vegetation

and the species used for

rehabilitation should be

recorded and monitored for a

period of 5 years following

decommissioning.

9.14 Population and community

Monitoring Programme : Population and Community

Pre-construction Construction Operations Decommissioning

Maintain communities

and limit secondary

impacts of population

increase due to the

Project

Complaints and Grievance records reviewed regularly

9.15 Community Health

Monitoring Programme : Community Health

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

Page 135: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 135 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.16 Institutions schools and health facil ities

Monitoring Programme : Institutions, Schools and Health Facilities

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

9.17 Community and Family Structure

Monitoring Programme : Community and Family Structure

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

9.18 Land Ownership and Land Rights

Monitoring Programme : Land Ownership and Land Rights

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

To be addressed by resettlement and compensation to be addressed by GoTL

9.19 Natural Resources Rights

Monitoring Programme : Natural Resources Rights

Pre-construction Construction Operations Decommissioning

Complaints and Grievance records reviewed regularly

To be addressed by resettlement and compensation to be addressed by GoTL

Page 136: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 136 301012-02135-EMP-003 Rev 1 : 3 February 2017

9.20 Cultural Heritage Archeological and Sacred Sites

Monitoring Programme : Cultural Heritage, Archaeological and Sacred Sites

Pre-construction Construction Operations Decommissioning

Any and all occurrences of damage sites is to be recorded and the records to be reviewed every 6 months.

Process improvements are to be implemented where there has been unauthorised impact on cultural heritage

sites.

9.21 Summary of monitoring program

Pre - Construction

Environmental

Concern

Parameter to Monitor Frequency and Variation

Climate Automated Weather Station (AWS) recording measurements

of:

Station identification number;

Date and time of record/observation;

Air, wet bulb and wet dew point temperatures.

Precipitation and evaporation;

Relative humidity;

Wind speed and direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height, if practicable.

Daily measurements for project life

Topography, Geology

and Soils

Weed growth and drainage behaviour on the topsoil stockpile As required

Air Quality At sensitive receptors:

AQ3 – At the Jetty

AQ4 – Settlement area at Aldeia Osso-Ua

AQ5 - representing the construction area.

Every 6 months measurements at sensitive

receptors i.e.

Results interpretation and review of the EMP

as required.

Collation of results into semi-annual

Environmental Report to NDCPEI

Noise and Vibration At sensitive receptors:

NO3 – At the Jetty

NO4 – Settlement area at Aldeia Osso-Ua

NO5 - representing the construction area.

Every 6 months measurements at sensitive

receptors i.e.

Results interpretation and review of the EMP

as required.

Collation of results into semi-annual

Environmental Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west)

and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity

measurements at monitoring boreholes, key

spring receptors at Waiono, Uaimatabai and

Uaisa.

Interpretation of data every 6 months.

Page 137: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 137 301012-02135-EMP-003 Rev 1 : 3 February 2017

Flora The total area of vegetation cleared (habitat destruction) at

the end of phase

TL Cement - Collation of results into Annual

Environmental Report to NDCPEI

Fauna Any incidents of fauna injury and death should be recorded.

TL Cement - Collation of results into semi-

annual Environmental Report to NDCPEI

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record

and document traffic incidents and mitigation

measures implemented as and when they

occur.

Social Complaints and Grievance records review

Stakeholder consultation to check progress

Regular review of Complaints and Grievance

record

Regular stakeholder consultation

Cultural Heritage,

Archaeological and

Sacred Sites

Any and all occurrences of damage to sites is to be recorded. Records to be reviewed every 6 months.

Construction

Environmental

Concern

Parameter to Monitor Frequency and Variation

Climate Automated Weather Station (AWS) recording measurements

of:

Station identification number;

Date and time of record/observation;

Air, wet bulb and wet dew point temperatures.

Precipitation and evaporation;

Relative humidity;

Wind speed and direction;

Solar radiation;

Barometric pressure ;

Visibility;

Cloud cover; and

Cloud ceiling height, if practicable.

Daily measurements for project life

Air Quality A monitoring and reporting program implemented to monitor

the air quality in the following sensitive receptors:

• AQ4 - settlement area in Aldeia Osso-ua.

• AQ5 - representing the construction area.

The monitoring program should assess and report on the

following air quality parameters:

• PM10; and PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Once every six months during construction

Noise and Vibration At sensitive receptors:

AQ4 – Settlement area at Aldeia Osso-Ua

AQ5 - representing the construction area.

Every 6 months measurements at sensitive

receptors i.e.

Results interpretation and review of the EMP

as required.

Collation of results into semi-annual

Environmental Report to NDCPEI

Surface Water Flow meters / stream gauges at the Bucoli River (1.6km west)

and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity

measurements at monitoring boreholes, key

spring receptors at Waiono, Uaimatabai and

Uaisa.

Interpretation of data every 6 months.

Page 138: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 138 301012-02135-EMP-003 Rev 1 : 3 February 2017

Groundwater Water quality and quantity measurements at key spring

receptors at Uaimatabai, Uaisa and Uaino.

Monthly water quality and quantity

measurements

Reporting and interpretation of data quarterly

Flora The total area of vegetation cleared (habitat destruction) at

the end of phase

End of phase

Fauna All fauna injury and death records. Reporting and interpretation every six months

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record

and document traffic incidents and mitigation

measures implemented as and when they

occur

Social Complaints and Grievance records review

Stakeholder consultation to check progress

Regular review of Complaints and Grievance

record

Regular stakeholder consultation

Cultural Heritage,

Archaeological and

Sacred Sites

Any and all occurrences of damage to sites is to be recorded. Records to be reviewed every 6 months.

Operations

Climate

Air Quality A monitoring and reporting program implemented to monitor

the air quality in the following sensitive receptors:

• AQ4 - settlement area in Aldeia Osso-ua.

• AQ5 - representing the construction area.

The monitoring program should assess and report on the

following air quality parameters:

• PM10; and PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Once every six months during construction

and operation

Noise and Vibration At sensitive receptors (as per construction) Once per year measurements

Results interpretation and review of the EMP

as required.

Collation of results into Annual Environmental

Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west)

and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity

measurements at monitoring boreholes, key

spring receptors at Waiono, Uaimatabai and

Uaisa.

Interpretation of data every 6 months.

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record

and document traffic incidents and mitigation

measures implemented as and when they

occur.

Social Complaints and Grievance records review

Stakeholder consultation to check progress

Regular review of Complaints and Grievance

record

Regular stakeholder consultation

Cultural Heritage,

Archaeological and

Sacred Sites

Any and all occurrences of damage sites is to be recorded. Records to be reviewed every 6 months.

Decommissioning

Topography, Geology

and Soils

Post closure assessment of rehabilitation success and soil

health

5 years after closure

Page 139: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 139 301012-02135-EMP-003 Rev 1 : 3 February 2017

Air Quality A monitoring and reporting program implemented to monitor

the air quality in the following sensitive receptors:

• AQ4 - settlement area in Aldeia Osso-ua.

• AQ5 - representing the construction area.

The monitoring program should assess and report on the

following air quality parameters:

• PM10; and PM2.5

• CO

• NO2

• SO2; and

• Ozone.

Once every six months

Noise and Vibration At sensitive receptors (as per construction) Once per year measurements

Results interpretation and review of the EMP

as required.

Collation of results into semi-annual

Environmental Report to NDCPEI

Water Flow meters / stream gauges at the Bucoli River (1.6km west)

and at Uaimatabai, Uaisa and Waino springs

Monthly water quality and quantity

measurements at monitoring boreholes, key

spring receptors at Waiono, Uaimatabai and

Uaisa.

Interpretation of data every 6 months.

Flora Monitoring and reporting of flora species abundance and

coverage

5 years after mine closure

Fauna Monitoring and reporting of fauna species abundance 5 years after mine closure

Traffic Traffic incidents and mitigation measures implemented Update Safety Management System to record

and document traffic incidents and mitigation

measures implemented as and when they

occur.

Social Complaints and Grievance records review

Stakeholder consultation to check progress

Regular review of Complaints and Grievance

record

Regular stakeholder consultation

Cultural Heritage,

Archaeological and

Sacred Sites

Any and all occurrences of damage to sites is to be recorded. On completion of closure

Page 140: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 140 301012-02135-EMP-003 Rev 1 : 3 February 2017

10 REPORTING REQUIREMENTS

Based on the monitoring programs outlined in Section 9 (Monitoring Program), this section (Table 2)

outlines the reporting frequencies and types of reports to be prepared for each aspect identified in the

EIS. Details of the reporting requirements include:

1. Monitoring limit or trigger which would dictate the need for reporting;

2. Frequency of reporting for internal and/or external purposes;

3. Incident, accident and emergency reporting;

4. Identification of the appropriate authorities/regulator to which the report is to be provided;

5. Measuring performance indicators and interpreting and acting on the indicators; and

6. Training programs required for employees/contractors.

Page 141: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 141 301012-02135-EMP-003 Rev 1 : 3 February 2017

Table 2 Monitoring reporting requirements

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Climate Daily N/A Automated Weather

Station

National Meteorological

Service

NDPCEI

Minister of Commerce and

Environment

Soil Monthly, in the event

of leak / spillage of

dangerous chemicals

and hazardous

wastes

Various AS/NZS 5667:1:1998

Water Quality Sampling

Water samples

Laboratory Analysis

6-monthly NDPCEI

Minister of Commerce and

Environment

Page 142: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 142 301012-02135-EMP-003 Rev 1 : 3 February 2017

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Air Quality

(including Dust)

6-monthly 25 µg/m3

(Maximum

concentration in 24

hours, 1 day

averaging period)

AS/NZS 3580.1.1:2007

Methods for the sampling

and analysis of ambient air

– Guide to siting air

monitoring equipment.

Air monitoring

equipment and dust fall

out containers

Annually Local suco chief

NDPCEI

Minister of Commerce and

Environment

Noise and

Vibration

6-monthly 50dB Exceedance

greater than 10%

of the time not

permitted (LA10)

AS/NZS 1269.1

Occupational noise

management

Noise and vibration

monitors

Annually Local suco chief

NDPCEI

Minister of Commerce and

Environment

Water – in the pit As water intersected

until the water flows

in the pit cease

Various AS/NZS 5667:1:1998

Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months

and

incorporated

into the Annual

Environmental

report to

NDPCEI

DWRQC

NDPCEI

Directorate of Mines

Minister of Commerce and

Environment

Page 143: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 143 301012-02135-EMP-003 Rev 1 : 3 February 2017

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Groundwater –

springs

Monthly during pre-

construction,

construction and

operations.

Flows <10%

variance pre-

development

Quality – below

limits

AS/NZS 5667:1:1998

Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months,

subject to

stabilizing, then

potentially every

6 months.

DWRQC

NDPCEI

Minister of Commerce and

Environment

Groundwater –

monitoring

boreholes

Monthly Levels <10%

variance pre-

development

Quality – below

limits

AS/NZS 5667:1:1998

Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months,

subject to

stabilising

Results

collation every 6

months,

reporting

annually to

NDPCEI

DWRQC

NDPCEI

Minister of Commerce and

Environment

Page 144: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 144 301012-02135-EMP-003 Rev 1 : 3 February 2017

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Groundwater –

supply

boreholes

Monthly Levels <10%

variance pre-

development

Quality – below

limits

AS/NZS 5667:1:1998

Water Quality Sampling

Water samples

Laboratory Analysis

Every 3 months,

subject to

stabilizing

Results

collation every 6

months,

reporting

annually to

NDPCEI

DWRQC

NDPCEI

Minister of Commerce and

Environment

Flora Monthly during pre-

construction,

construction

<55ha Surveyor standard Accurate survey of

cleared lands

Monthly

reconciliation

against planned

clearing,

clearing below

approved limit

NDPCEI

Directorate of Mines

Minister of Commerce and

Environment

Page 145: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 145 301012-02135-EMP-003 Rev 1 : 3 February 2017

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Fauna Monthly during pre-

construction and

construction

Annually during

operations

Fauna Fatalities <

1 per month

Data capture in the EMS Monthly

reconciliation

and adjustment

of clearing

approach if

exceeded

NDPCEI

Directorate of Mines

Minister of Commerce and

Environment

Traffic 4 weeks at the start

of each phase

N/A Traffic enumerators At conclusion of

survey,

continuous

improvement

MOPW DBRFC

Minister of Commerce and

Environment

Health Annually Stakeholder survey

Grievances mechanism

Year on year

variance

Continuous

improvement

process

Ministry of Health

Minister of Commerce and

Environment

Page 146: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 146 301012-02135-EMP-003 Rev 1 : 3 February 2017

Aspect Frequency of

monitoring

Limit / Trigger Method/Standard for

monitoring

Method of monitoring Frequency of

Internal

Reporting

External reporting

(Authority/Regulator)

Cultural Heritage Monthly during pre-

construction and

construction

Zero incidents of

non-agreed

disturbance

Escalation and

reporting of every

instance of

unknown sites

encountered

N/A Cultural Heritage

Monitors / Supervisors

Grievances mechanism

Monthly pre-

construction

and

construction

Secretariat of Arts and Culture

Minister of Commerce and

Environment

Page 147: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 147 301012-02135-EMP-003 Rev 1 : 3 February 2017

11 RESPONSIBILITIES FOR MITIGATION AND MONITORING

This section clearly identifies the responsibilities of the various parties involved in the implementation

of mitigation and monitoring requirements as outlined in Sections 7 and 9, respectively, of this EMP.

The following are the key managerial roles applicable to the Project during the following phases:

• Pre-Construction and Construction:

o Project Manager – TL Cement LDA;

o Project Engineer – Detailed Design and Mine Planning;

• Operation:

o Mine Manager

The Mine manager may delegate to his personnel for various functions, including the Health, Safety

Quality Manager/Officer function.

The responsibility for the development, implementation and monitoring of the success of; and review

and update of mitigation measures is illustrated in the table below.

Table 3 Responsibility for implementation of this EMP

Phase Item Develop/Author Implement Monitoring

Detailed Engineering

Design

Environmental

Management Plans

Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Mitigation Measures Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Monitoring Plans Lead Engineer from

the Engineering

provider with approval

by Project Manager –

TL Cement LDA

Lead Engineer from the

Engineering provider

Construction Tender

Phase

Develop construction

specific

Environmental

Management Plans

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Page 148: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 148 301012-02135-EMP-003 Rev 1 : 3 February 2017

Phase Item Develop/Author Implement Monitoring

Develop construction

specific

Mitigation Measures

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Develop construction

specific

Monitoring Plans

Civil works contractor

with approval by

Project Manager – TL

Cement LDA

Civil works contractor

Phase Item Develop/Author Implement External review

Pre-Construction Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Monitoring

activities

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Compliance

monitoring

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Compliance

reporting

Civil works

contractor with

approval by

Project Manager

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Minister of Commerce

and Environment

NDPCEI

Page 149: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 149 301012-02135-EMP-003 Rev 1 : 3 February 2017

– TL Cement

LDA

Construction Environmental

Management

Plans

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Mitigation

Measures

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Monitoring

activities

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Compliance

monitoring

Site Supervisor

from TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Compliance

reporting

Civil works

contractor with

approval by

Project Manager

– TL Cement

LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Minister of Commerce

and Environment

NDPCEI

Operations (Year

1 to 5, Year 6 to

end)

Environmental

Management

Plans

Environmental

Engineer

supervised by

the Mine

Manager – TL

Cement LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Year 6-end: TL Cement

Page 150: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 150 301012-02135-EMP-003 Rev 1 : 3 February 2017

Health, Safety Quality

Manager/Officer

Mitigation

Measures

Environmental

Engineer

supervised by

the Mine

Manager – TL

Cement LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Year 6-end: TL Cement

Health, Safety Quality

Manager/Officer

Monitoring

activities

Environmental

Engineer

supervised by

the Mine

Manager – TL

Cement LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Year 6-end: TL Cement

Health, Safety Quality

Manager/Officer

Compliance

monitoring

Environmental

Engineer

supervised by

the Mine

Manager – TL

Cement LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Year 6-end: TL Cement

Health, Safety Quality

Manager/Officer

Compliance

Reporting

Environmental

Engineer

supervised by

the Mine

Manager – TL

Cement LDA

TL Cement nominated

EPC management firm

Health, Safety Quality

Manager/Officer

Year 6-end: TL Cement

Health, Safety Quality

Manager/Officer

Minister of Commerce

and Environment

NDPCEI

Decommissioning Environmental

Management

Plans

Environmental

Engineer

supervised by

the Project

Manager – TL

Cement LDA

TL Cement Health,

Safety Quality

Manager/Officer

Page 151: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 151 301012-02135-EMP-003 Rev 1 : 3 February 2017

Mitigation

Measures

Environmental

Engineer

supervised by

the Project

Manager – TL

Cement LDA

TL Cement Health

Engineering Manager

Monitoring

activities

Environmental

Engineer

supervised by

the Project

Manager – TL

Cement LDA

TL Cement Health,

Safety Quality

Manager/Officer

Compliance

monitoring

Site Supervisor

from TL Cement

LDA

TL Cement Health,

Safety Quality

Manager/Officer

supervising the Civil

works contractor

Compliance

Reporting

Environmental

Engineer

supervised by

the Project

Manager – TL

Cement LDA

TL Cement Health,

Safety Quality

Manager/Officer

Minister of Commerce

and Environment

NDPCEI

Page 152: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 152 301012-02135-EMP-003 Rev 1 : 3 February 2017

This page has been intentionally left blank.

Page 153: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 153 301012-02135-EMP-003 Rev 1 : 3 February 2017

12 EMERGENCY PLAN

12.1 Purpose

The Emergency Plan (EP) outlines the approach for managing the handling, storage and leak /

spillage of dangerous chemicals and hazardous wastes associated with the development and

operation of the Baucau Cement Plant Project Limestone Mine.

The purpose of the EP is to identify appropriate management strategies, procedures and processes

to ensure that in the event of a spill / leak it is dealt with quickly and efficiently to ensure it is:

• Stopped at the source;

• Contained and collected; and

• If necessary, the site is remediated.

12.2 Objective

The objective of the EP is to:

• Reduce the risk of contamination and pollution to water and land from any dangerous

chemicals or hazardous wastes;

• Respond effectively and quickly to all spills and leaks, regardless of the size / volume; and

• Minimise the risk exposure of any dangerous chemicals or hazardous wastes to all

employees and contractors and subsequent health impacts.

12.3 Responsibil ities

TL Cement Safety and Quality Officer/Manager:

• Regular review and updating of the EP;

• Ensure the EP is effective and drills are conducted;

• Notify the regulatory authority of any major spills within the required timeframes;

• Ensure all employees are provided with the necessary training, PPE and equipment to deal

with spills;

• Notify and coordinate emergency services, if required;

• Oversee incident reporting and investigation process and ensure an adequate investigation is

undertaken, if required;

• Ensure the Safety Data Sheets (SDS) is maintained and current for all of the chemicals and

hazardous materials used and stored on the Project site; and

• Ensure spill kit materials are adequately stored and restocked following any spill or leak.

All employees and contractors are responsible for:

• Cleanup and removal of spills, if it is safe to do so;

• Reporting all spills to the TL Cement Mine Manager using the appropriate procedure;

Page 154: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 154 301012-02135-EMP-003 Rev 1 : 3 February 2017

• Participate in emergency drills; and

• Ensure appropriate PPE is used when dealing with the cleanup and removal of spills.

12.4 Standards

The storage, management of and handling of all dangerous chemicals or hazardous wastes will be

undertaken in accordance with the requirements of the following standards and legislation:

• Australian National Standard for the Storage and Handling of Workplace Dangerous Goods

[NOHSC: 1015 (2001)]; and

• Australian Standards AS 1940-2004: The storage and handling of flammable and combustible

liquids.

12.5 Incident Classification

All spills, leaks and or uncontrolled release of materials, regardless of the size / volume are classified

as an event, which needs to be reported to the TL Cement Environment Manager/Officer.

An incident includes a spill, leak or uncontrolled release of any of the following substances to water

sources, ground; bitumen; bunded areas (concrete or plastic lined); concrete pads; and spill trays:

• Hydrocarbons;

• Chemicals;

• Saline water;

• Powdered chemicals;

• Oily waste water;

• Tailings;

• Sewage;

• Drilling mud;

• Concrete washout; and

• Bitumen.

The following table outlines the potential ‘Incident Types’ which may be applicable to the Project.

Page 155: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 155 301012-02135-EMP-003 Rev 1 : 3 February 2017

Table 4: Incident Classifications

Level 1

Minor

Level 2

Moderate

Level 3

Medium

Level 4

Major

Minor uncontrolled spill or

release of materials within

a bunded or contained

area* that may:

• Impact disturbed land

but not vegetation;

• Does not impact water

(surface or

groundwater);

• Does not harm fauna;

and

• Can be easily cleaned

up.

Moderate uncontrolled spill

or release of materials

contained within bunded or

contained area that may:

• Has minor impacts on

soil, fauna and flora but

not priority flora/fauna

or significant species;

and

• Minor impacts to

surface or groundwater.

Uncontained spill or

release of materials

that may:

• Has impact, fauna

and flora and is

uncontrolled and

extensive in its

release;

• Impacts on native

vegetation including

priority / rare flora;

• Moderate impacts

on soil requiring soil

treatment or

replacement

• Has moderate

impacts on low

value surface /

groundwater

sources; and

• Has reasonable

probability of being

detrimental to

fauna.

Major uncontained spill or

release of materials that

may:

• Has impact on fauna

and flora and is major,

uncontrolled and time

extensive in its

release;

• Impact soil, requiring

significant treatment

and soil replacement;

• Major impacts on

surface and/or

groundwater sources;

• Impacts on vegetation

over an extensive

area that causes loss

of priority / rare flora;

• Results in fauna

deaths of rare / priority

species; and

• Has a reasonable

probability of being

detrimental to public

health.

* Contained area can include: concrete bunds; plastic lined bunds; concrete pads; and spill trays.

12.6 Prevention

The following are some simple techniques that shall be adopt and implemented on the Project to

prevent spillages and leaks from occurring:

• No tanks are to be filled prior to checking available tank volume;

• Tank filling and dispensing procedures shall be carried out only by appropriately trained

personnel and within designated and bunded area;

• The main outlet valve on tanks will be locked shut when unattended;

Page 156: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 156 301012-02135-EMP-003 Rev 1 : 3 February 2017

• Each tank/storage facility will be gauged and monitored daily;

• All chemical and hazardous materials are contained in bunded areas with an appropriate

holding capacity;

• Bunded compound shall be lined with low permeability (less than 10 - 9 m/s) material that is

not adversely affected by contact with the stored chemicals. It should be constructed in such

a way that permits full recovery of contents spilt from tanks and ensures that the lining

material is not damaged. The bund itself should be constructed of waterproof membrane,

reinforced concrete or an approved equivalent;

• The bunded compound shall have a minimum capacity of 110% of the capacity of the largest

tank. The compound shall also have sufficient capacity to retain spilt chemicals and not be

affected during extreme rainfall events;

• After a rainfall event, pumping should be used to empty the compound, provided the water is

not contaminated. The water should be checked by a suitably qualified and experienced

person;

• Under no circumstances shall contaminated water be allowed to discharge to the

environment, but shall be pumped into a tanker for appropriate disposal;

• Emptying of the compound should not be achieved through a valved (i.e. gravity flow) outlet

as this may be inadvertently be left open;

• Vehicle refueling and maintenance will only be conducted in the designated Vehicle

Maintenance and Refueling areas;

• Tanks; vehicles and equipment will be regularly inspected and maintained as per the required

specifications;

• The network of storm water drains, diversion ditches and drains will be regularly inspected to

ensure there are no blockages;

• All spills and leaks will be cleaned up immediately and reported to the TL Cement Mine

Manager;

• Shovels, drip pans and absorbent materials will be strategically located throughout the Project

site; and

• Ensure that all chemical and hazardous materials are stored appropriately. Substances may

escape from storage facilities through various means, including, but not limited to:

o Absence of containment facilities;

o Poor construction or deterioration of containment facilities;

o Inappropriate equipment maintenance operations; and

o Poor ‘house-keeping’ practices.

12.7 Safety Data Sheets (SDS)

Before a contractor can bring a chemical onto site, they must inform and receive approval from the TL

Cement HSE Department / Environmental Manager.

Page 157: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 157 301012-02135-EMP-003 Rev 1 : 3 February 2017

All chemicals which have been approved for use on site by the TL Cement HSE Department/

Environment Manager will be stored in accordance with the SDS and in a designated bunded /

contained area.

12.8 Spill Response

In the event of a spill and/or leak TL Cement shall adopted the following ‘3C Response Policy’:

• Control;

• Contain; and

• Clean-up.

The following sections provide an outline of the ‘3C Response Policy’.

12.8.1 Control

The ‘Control’ aspect of the response policy includes, but is not limited to; the following steps for all

spills / leaks (i.e. Minor to Major):

• Identification of the source and material involved of the spill / leak.

• If required, get help / advice from the TL Cement Safety and Quality Officer.

• Ensure the appropriate personal protective equipment (PPE) is used.

• If it is safe to do so, control the spill / leak at the source by:

o Shut off valves;

o Stop the pump process;

o Upright the container.

• Clear the area of people and equipment not directly involved in the clean-up process.

• Complete the appropriate Form estimating the quantity spilled and submit to the TL

Cement Safety and Quality Officer.

12.8.2 Contain

The ‘Contain’ aspect of the response policy includes, but is not limited to; the following steps for all

spills / leaks (i.e. Minor to Major):

• For land spills, sand, rags or other like materials should be used.

• Block or divert the flow of the spill / leak from entering any stormwater drain.

• Place appropriate spill kit material over the body of the spill to ensure it does not

disperse further.

12.8.3 Clean Up

The ‘Clean Up’ aspect of the response policy includes, but is not limited to; the following steps:

• Ensuring that the appropriate PPE is in place; spills / leaks should be cleaned up using

appropriate absorbent materials which should then be disposed of to a suitably labelled

Page 158: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 158 301012-02135-EMP-003 Rev 1 : 3 February 2017

“Contaminated Material Bin” for storage and eventual transportation via a licenced

contractor to a licenced disposal facility.

• Any equipment used from spill kits must be recorded and the TL Cement Environment

Manager / Environment Officer is to ensure the spill kit is restocked.

• For spills on soil, they may be either remediated in-situ or the contaminated soil may

need to be removed for appropriate disposal.

12.9 Equipment

12.9.1 Spill Response

The following spill response equipment will be stored in the fuel and other chemical storage areas:

• 55 gallon drum of absorbent granules;

• 100 absorbent pads;

• 30 metres of absorbent pigs;

• Shovels;

• Two (2) empty 55-gallon drums (steel) for collecting used absorbent;

• A hand pump and 10 metres of plastic hose;

• All PPE to safely handle spills (e.g. gloves and eye protection).

In the case of soil contaminated by a fuel or chemical spill, the soil should be excavated and taken to

the volatilisation pad, before being disposed of in the approved solid waste landfill. This also applies

to any sorbent material used to clean up spills.

12.9.2 First Aid Facilit ies and Personal Protective Equipment (PPE)

First aid facilities will be located in every site office and work vehicle. The location of first aid kits in

the site offices will be clearly displayed. The first aid kits will be kept clean and restocked on a three

monthly basis.

TL Cement will provide all employees with the necessary PPE, including but not limited to:

• Ear plugs;

• Eye protection; and

• Gloves.

12.9.3 Fire Fighting Equipment

Firefighting equipment (i.e. extinguishers) will be located in every site office and work vehicle. The

extinguishers will be easily accessible and clearly displayed. All employees will be provided with the

necessary training on the appropriate usage of extinguishers.

Page 159: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 159 301012-02135-EMP-003 Rev 1 : 3 February 2017

The firefighting equipment will be tested and tagged by a competent person every six months. Used

or expired extinguishers will be removed from site and will be immediately replaced.

12.10 Training

All personnel will receive environmental training as part of a mandatory induction for the Project. The

environmental induction will include as a minimum the requirements of this EP.

All personnel will be trained in the use of the spill response kit and fire fighting equipment required for

the implementation of this EP.

Environmental notices will be developed and placed on the Project site notice boards on a regular

basis and in response to non-compliance and environmental incidents.

The training register will be kept onsite in an easily accessible location for inspection and auditing.

Page 160: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 160 301012-02135-EMP-003 Rev 1 : 3 February 2017

13 DECOMMISSIONING PLAN

Sections 7 and 9 of this EMP contains details of the mitigation and monitoring requirements for the

Decommissioning Phase of the Project.

TL Cement’s vision for closure is to:

• Ensure a self-sustaining vegetation cover on areas disturbed by mining activities where this is

appropriate;

• Provide sustainable end land uses in keeping with the needs of local communities; and

• Ensure economic sustainability for affected communities (Holtec, 2015).

A draft Mine Closure Plan has been produced by Holtec (2015). The draft success criteria are

presented in Figure 13-1 below, together with the measurement and monitoring requirements post-

closure.

13.1 Preliminary Decommissioning Plan

In order to meet the vision for closure, a preliminary decommissioning plan has been outlined below,

including impacts of the project and mitigation and monitoring measures to be undertaken during the

decommissioning phase of the project (Holtec 2015).

Sections 7 and 9 of this EMP also contain details of the mitigation and monitoring requirements for

the Decommissioning Phase of the Project.

Ecology and Biodiversity

Aspect / Impact Mitigation Measures

Re-establishment of habitats or creation of new

habitats via rehabilitation

Sequential reclamation and rehabilitation is proposed;

Afforestation by plantation is proposed to be carried out;

The top soil stored separately during the operation phase shall be used for afforestation and plantation only. Local species shall be planted in the area;

The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers. The area shall be brought to its original state.

Introduction of alien invasive flora and fauna Invasive alien species control programme implemented as a component of the EMP,

Page 161: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 161 301012-02135-EMP-003 Rev 1 : 3 February 2017

Ecology and Biodiversity

Aspect / Impact Mitigation Measures including adaptive management measures;

EMP should be reviewed every five years with emphasis on control of alien invasive flora and fauna;

All invasive alien species control measures

specified in the EMP must be implemented.

Loss or disturbance of fauna species of special

concern due to collisions and noise disturbance

Sequential rehabilitation to be conducted as soon as possible at the completion of operation;

Reclamation and rehabilitation of the area to restore the area in natural, pre- construction condition;

Environmental education training program, including refresher sessions, for all employees, contractors and their families;

EMP should be reviewed every five years.

Increased hunting/ poaching of wildlife and loss

of habitats for crop production

No fauna are to be hunted or destroyed by any project personnel;

Effective penalties (e.g. fines) must be imposed for the hunting or harm to fauna by any employee of TL Cement;

The locals should be encouraged to utilize the cash income, during employment for investments that will assist with increasing productivity of the local agricultural sector;

An environmental education programme to be developed and implemented for all TLC employees, their families and villages within the concession.

Water Resources

Aspect / Impact Mitigation Measures

Chemical contamination of surface water

resulting from accidental spills during

transportation and handling and seepage from

Emergency contaminant and mitigation measures must be developed to minimize impacts should accidental spillages occur along the transport routes;

Page 162: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 162 301012-02135-EMP-003 Rev 1 : 3 February 2017

waste

Equip all trucks and equipment carrying fuels or oil with spill response materials and train personnel in the use of such materials;

Store all potential sources of contamination in secure facilities with appropriate Storm Water management systems in place to ensure that contaminants are not released to the water resource through Storm Water runoff.

Sedimentation of surface water resulting from

erosion and runoff from exposed surfaces and

roads

Minimize disturbance of soil and vegetation;

Implement rehabilitation and re-vegetation as soon as possible;

Refer to dust and erosion suppression measures

listed above.

Contamination of groundwater resulting from

seepage from hazardous materials and waste

Manage waste in accordance with Waste Management Plan;

Waste Management

Aspect / Impact Mitigation Measures

Generation of debris from p r o j e c t

infrastructure

The buildings shall be dismantled. The machinery shall be sold to other industries for use or to authorized scrap dealers;

The office equipment like table, chairs, computers etc. can be donated or auctioned for its use;

The debris generated from dismantling of building shall be used in backfilling of exploited pits.

Socio-economic Impacts

Aspect / Impact Mitigation Measures

Direct impacts on project employees and

their families

Communication with internal stakeholders i.e. employees to discuss the implications of closure;

Phased programme of retrenchments and retirements to ensure that the full impact of reduction in employment is spread over several years to ensure that the impact is absorbed as far as possible;

Page 163: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 163 301012-02135-EMP-003 Rev 1 : 3 February 2017

Socio-economic Impacts

Aspect / Impact Mitigation Measures

Career counselling and capacity building;

Development of a skills register and dissemination of the register to alternative employers, government etc.

Loss of economic benefits to the project supply

chain

Early communication with stakeholders i.e. service providers including local service providers, bulk service providers and the business community to discuss the implications of closure;

Liaison with other industries to discuss opportunities for service providers within their supply chain.

Loss of support to the local government and

other government levels with respect to taxes

and royalty incomes

Timely engagement of local, regional and national government to advise of closure and the implications this will have on the government revenue from taxes and royalties;

Gradual transfer/return of responsibilities to local government with respect to service provision where the project has played an active role in service provision.

Loss of community benefits in the form of

project funded community development

programme

Early engagement of stakeholders to discuss and scenario plan the transfer of usable assets to the community, local government and other stakeholders;

Provision of information on the maintenance and management costs of assets and typical maintenance programme;

Capacity building for asset management.

Loss of Employment and Income due to

retrenchment

Develop the TLC grievance procedure to capture and address grievances arising due to retrenchments and downscaling for the employees;

If practical, shift the employees to other businesses of the group company;

Compliance with IFC’s Performance Standard 2 “Labour and Working Conditions”;

Page 164: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 164 301012-02135-EMP-003 Rev 1 : 3 February 2017

Socio-economic Impacts

Aspect / Impact Mitigation Measures Actively promoting the development of different economic sectors from an early stage e.g. through incentivizing other industries to locate in the area, and promoting an increase and diversity of skills in the local population;

Develop a decommissioning and closure plan which is updated every five years increasing in detail as closure approaches, and actively engaging with a range of stakeholders throughout the life-of-project to discuss potential consequences of decommissioning and possible mitigation.

Eco-system Services

Aspect / Impact Mitigation Measures

Reduced quality of natural resources and

ecosystem services to local communities due

to emissions to air, water or soil

To minimize impacts, the project must comply with best pract ice for air emissions, water (storm water and effluent) discharge quality and solid waste disposal.

Soils, land capacity and land use

Aspect / Impact Mitigation Measures

Remediation of contaminated soils and

demolition of project infrastructure, resulting in

re- establishment of baseline soil characteristics

and land capability

The contaminated soils during de-commissioning and closure should be excavated and disposed of;

Infrastructure like buildings, access roads etc. having potential post mining benefit, if desired shall be handed over to stakeholders;

The areas not required by stakeholders shall be decommissioned and the area will be rehabilitated by replacing soils and adding nutrients, if necessary;

Air Quality

Aspect / Impact Mitigation Measures

Page 165: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 165 301012-02135-EMP-003 Rev 1 : 3 February 2017

Increase in PM10 and PM2.5 emissions resulting

from land clearing, earthworks and vehicular

movement

Continuous water spraying on roads used routinely by vehicles;

Set speed limits to minimize the creation of fugitive dust within the project boundary;

Continue with the routine air quality monitoring program;

Minimize the disturbed footprint as far as practically possible;

Revegetate and landscape disturbed areas as soon as possible.

Visual Impacts

Aspect / Impact Mitigation Measures

Dust generation and site disturbance due to

earth moving and removal of infrastructure,

affecting the visual character for communities

Minimize the disturbed footprint as far as practically possible;

Revegetate and landscape disturbed areas as soon as possible to reflect the surrounding topography and vegetation as much as possible;

Re-establishment of baseline visual character

due to rehabilitation of the site and removal of

project infrastructure

Landscaping and re-vegetation in accordance with the surrounding vegetation and topography

Page 166: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 166 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 13-1: Mine Closure Plan Success Criteria (Holtec, 2015a)

Page 167: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 167 301012-02135-EMP-003 Rev 1 : 3 February 2017

14 CAPACITY DEVELOPMENT AND TRAINING

Training is essential for ensuring that the provisions of the EMP are implemented efficiently and

effectively. Training needs will be identified based on the existing and available capacity of the site

and Project personnel (including the proponent, contractors and subcontractors) to undertake the

required management actions and monitoring activities. A training program will be presented in this

section of the EMP. The training program will be developed and delivered by suitably qualified

personnel, in a language and medium understood by workers and/or employees.

A training needs analysis will be conducted by TL Cement as part of the resource planning for the

Project implementation. The training needs analysis will consider:

• Practical training via instruction;

• Formal vocational training;

• Success and completion criteria;

• Delivery method;

• Certification and recognition system; and

• Training refreshers and frequency.

During the life of the Project, the following EMP training will be provided to relevant personnel:

• Field sampling and sample handling techniques;

• Data collection and collation;

• Emergency response procedures (e.g. spills);

• Management of exceedances (e.g. dust levels); and

• Roles and responsibilities for EMP implementation.

Page 168: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 168 301012-02135-EMP-003 Rev 1 : 3 February 2017

15 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

WorleyParsons and TL Cement have undertaken a process of consultation with the people who may

be affected by the Project and the Project stakeholders. WorleyParsons and TL Cement have made

efforts to ensure that the public, including affected people, women and vulnerable groups, have the

opportunity to participate fully in the consultation process. Consultations have taken place on a

continuous basis, starting as early as possible in the EIA process. This section describes the public

consultation conducted to date.

Consultation was undertaken during the development of the EIS. During this consultation, aspects

pertaining to the management and mitigation measures for the Project were raised. These details are

included in this component to illustrate that both TL Cement and WorleyParsons have undertaken

consultation around the EMP.

15.1 Purpose of the consultation during the preparation of the EMP

The public consultation process for the environmental assessment is carried out in accordance with

the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and

Requirements during the Environmental Assessment Process” dated 22 April 2014.

The EMP was referenced in the final consultation session undertaken on 11 December 2015.

15.2 Methodology and Approach

15.2.1 Identif ied Stakeholders

The following table lists the identified stakeholders consulted during the environmental assessment

process.

Table 5: Identified stakeholders consulted during the EIS process

Governments

President of Republic Democratic of Timor-Leste

• President of RDTL

Prime Minister of Republic Democratic of Timor-Leste

• Prime Minister of RDTL

Ministry of Commerce, Industry, and Environment

• Minister of CIE

• National Directorate for Pollution Control and Environmental Impact

Page 169: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 169 301012-02135-EMP-003 Rev 1 : 3 February 2017

• General Director for Environment

• Nacional Director for Industries and Manufacturing

Ministry of Petroleum and Mineral Resources

• Minister of PMR

• National Directorate of Minerals

• Institute of Petroleum and Geology (IPG)

Ministry of Justice

• Secretary of State for Land and Property

Ministry of Finance

• Minister of Finance

Ministry of Planning and Strategic Investment

• Minister of PSI

Ministry of Public Works, Transport and Communications

• Minister of PWTC

• Directorate of Ports/APORTIL

• National Directorate for Water Quality and Control

Ministry of Tourism, Arts and Culture

• Secretary of State for Arts and Culture

Secretary of State for Employment Policy and Vocational Training

• Secretary of State for EPVT

Municipality (District) Government

Baucau Municipality (formerly Baucau District Administration)

Baucau Administrative Post (formerly Baucau Sub-District Administration)

PNTL Baucau Municipality

PNTL Baucau Administrative Post

BOP Baucau Municipality

F-FDTL Baucau Municipality

Page 170: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 170 301012-02135-EMP-003 Rev 1 : 3 February 2017

Baucau Municipality Directorate of Land, Property and Cadastral Services

Baucau Municipality Directorate of Pollution Control and Environmental Impact

Baucau Municipality Health Directorate

Baucau Municipality SEPFOPE

Baucau Municipality Public Works

Baucau Municipality Social Directorate

Baucau Municipality Agriculture Directorate

Baucau Municipality Water and Sanitation Directorate

Baucau Municipality Electricity Directorate

Local Government

Suco Council Tirilolo

Suco Council Triloca

Suco Council Caibada

Suco Council Bahu,

Suco Council Bucoli

Local Community

Chefes de Aldeia

Lia’nain

Local Youth Organizations

Local Women’s Organizations

Local Fishermen’s Organization

Baucau Parish – Old Town

Baucau Parish – New Town

Baucau Bishop

Civil Society/Local NGOs

La’o Hamutuk

Luta Hamutuk

Page 171: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 171 301012-02135-EMP-003 Rev 1 : 3 February 2017

Haburas

Rede ba Rai

Belun

Kapeliwa (Local NGO)

Other Organizations

International Finance Corporation (IFC)

Conservation International

BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program

Presidente CCI Baucau

15.2.2 Mechanism for Public Consultation

The public consultation conducted for the EIS and EMP engaged affected communities, general

public, non-governmental organizations, government agencies, and others.

The consultation took different forms, depending on the purpose; including, but not limited to:

• One on one meetings;

• Public information meetings and presentations;

• Site visits;

• Development and distribution of a Non-Technical Summary document; and

• Questionnaire completion with stakeholders and community members.

All public consultation sessions were advertised 7 days in advance by local TV transmissions and by

notices placed strategic locations; and were also advertised though local radio stations such Radio

Popular Coulelemai Bucoli and Radio Komunidade Lian Matebian in Baucau. A copy of the public

notice was also posted on TL Cement’s website.

Additionally, the notices were displayed at local government offices including Baucau Municipality,

Baucau Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all

notices was provided to the NDPCEI.

15.3 Summary of consultation activities carried out

The formal consultation activities undertaken between February 2015 and December 2015 are

detailed below. Ongoing consultation with key stakeholders has taken place in addition to the formal

sessions.

Page 172: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 172 301012-02135-EMP-003 Rev 1 : 3 February 2017

Table 6: Summary of consultation session completed during the EIS process

Date Type of Consultation Key components

June 2014 TL Cement conducted consultation with the

Tirilolo community and Youth group

The meeting was used to discuss the land

use and crop types in the area, in relation

to the location of the proposed project.

July 2014 TL Cement met with members of the Casido

Traditional Council, Suco Council and

Government of Timor Leste to coordinate

activities for a cultural ceremony.

Prior to TL Cement construction and

production activities it is important to hold

a cultural ceremony.

October 2014 TL Cement met with the Lia-Nain of Suco

Ostico

The meeting was used to discuss the

proposed project and the land use in the

area.

November 2014 TL Cement met the communities from Suco’s

Bucoli Adeia Macadai, Lulihen and Land

owners Mr Virgillio G Antonio, Mr Oscar Da

Silva and Mr Jose’ Da Silva

The meeting was used to discuss the

proposed project and the land use in the

area. The community was supportive of

industry being established in Baucau.

February 2015 TL Cement and WorleyParsons conducted

consultation in the local community during a

site visit with the Lian Nian (Traditional

Leaders)

The locals in general were enthusiastic

about the project and had queries about

the development activities for the locals

that TL Cement would initiate as well as

the employment opportunities the project

would generate for the locals.

May 2015 TL cement and WorleyParsons with the

community representatives :

• Chefe Suco Trololo: Ricardo Ernesto

Belo (RB)

• Chief of Community Police in Suco

Trilolo: Norberta Belo (NB)

• Chefe Aldeia Lia Lailesu: Cipriano Belo

(CB)

• Chefe Aldeia Parlamentu: Manuel Belo

(MB)

• Chief of Traditional Practice (Lia Nain):

Duarte Belo (DUB)

• Secretary of Suco Trilolo: Zeca Belo

These meetings were set up to discuss

the field work surveys that would be

undertaken for the EIS

Page 173: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 173 301012-02135-EMP-003 Rev 1 : 3 February 2017

(ZB)

August 2015 Community Questionnaire

WP Timor Leste office staff visited four (4)

most affected aldeias in Suco Tirilolo; aldeia lia

lailesu, Parlamentu, Caisido-Kotalali and

Osso-wa.

The objective was to meet the community

who are unable to attend the previous

meeting and hear their opinions and

suggestions as well as improve their

awareness of the project.

Most of them were well aware of the

project and showed their enthusiasm for

the project; however, they are worried

about the impact of the project on their

cultural heritage, land and lifestyle.

3 September

2015

Public Consultation on the draft TOR was

conducted in Caisido, Baucau Municipality.

WorleyParsons presented some

preliminary findings as described in the

TOR and Project Documents.

11 December

2015

TL Cement and WPTL organized a public

meeting in Caisido, Baucau Municipality, to

discuss the proposed project and the draft EIS

and EMP. The date, venue, and time of this

public meeting were coordinated with the

relevant Administrator, Chefes do Suco and

Chefes da Aldeia.

WorleyParsons presented a description of

the project, explained the EIS process,

and provided a brief summary of the study

findings to date. Following the

presentation, two information tables were

set up with maps, diagrams and pictures

of a similar cement plant in Indonesia.

The tables were staffed by

representatives of WorleyParsons and TL

Cement who provided more detailed

explanations of project details and answer

questions. The community members

were invited to observe, ask questions

and/or provide recommendations to the

Project team.

07 January 2016 TL Cement and Worley Parsons met with the

NGO group Lao Hamutuk to update them on

preliminary EIS findings

WorleyParsons description of the project,

explained the EIS process, and provided

a brief summary of the study findings to

date. Lao Hamutuk stated that

resettlement and compensation need to

be carefully addressed. Lessons learnt

from the Suai Supply base should also be

taken into consideration.

07 January 2016 TL Cement and Worley Parsons met with

Foundação Haburas to update them on

WorleyParsons description of the project,

explained the EIS process, and provided

Page 174: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 174 301012-02135-EMP-003 Rev 1 : 3 February 2017

preliminary EIS findings a brief summary of the study findings to

date. Foundação Haburas stated that a

Resettlement/relocation and Groundwater

Management Plans should be developed.

13 January 2016 TL Cement and Worley Parsons met with

Direcção Nacional Controla Qualidade Agua

(DNCQA)to update them on preliminary EIS

findings

WorleyParsons description of the project,

explained the EIS process, and provided

a brief summary of the study findings to

date. DNCQA stated that that

resettlement and compensation need to

be carefully addressed. Groundwater,

Dust and Noise management plans

should be developed.

13 January 2016 TL Cement and Worley Parsons met with NGO

group Luta Hamutuk (LH) to update them on

preliminary EIS findings

WorleyParsons description of the project,

explained the EIS process, and provided

a brief summary of the study findings to

date. LH stated that that resettlement and

compensation need to be carefully

addressed. Government strategies to

maintain and enhance subsistence

farming strategies need to be

implemented. They recommended

contributions towards the health and

education sectors.

Page 175: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 175 301012-02135-EMP-003 Rev 1 : 3 February 2017

15.4 Summary of main comments received from the public, community leaders, NGOs, local officials, other stakeholders

The EMP has been developed to take into account the concerns raised in the Community

Consultation sessions. In order to ensure that they are included in the EMP, the key aspect is

identified below in relation to the question or comment and the management measure or mitigation

measure is detailed below the key aspect.

# (Unique

number

Retained

from

Questions

database)

Aspect &

Environmental

Management and

Mitigation

Measure

Questions from

Public Consultation

Proponent’s Response

3 Air quality

Air Quality and

Dust mitigation

measures

Noise

Jaime (school

teacher), Suco

Parlamento; Claudio

(student); Agustinho

da Costa Belo,

Aldeia Osso-ua;

Joao Freitas, Suco

Caisido

What are the impacts

from the cement plant

and limestone mine to the

surrounding

environment? What are

the measures taken to

mitigate these impacts?

What is the level of air

pollution emitted from the

plant and mine (including

when transporting from

mine to plant)?

What will be the

mitigation towards noise

pollution (from machinery,

heavy equipment,

blasting)?

James Rhee:

Air pollution mainly will

come from power

generation and dust.

Dust will mainly be

released during

transportation of

material from mine to

plant and from/to jetty

using conveyor belt. The

amount of air pollution

can be mitigated by

using solar and wind

power to generate

electricity whereas dust

from the conveyor belt

will be well contained

using a closed system.

In addition, company will

build new road from

mine to plant as a

mitigation measure to

reduce dust.

Regarding noise

pollution, since it is low

risk, hence no mitigation

Page 176: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 176 301012-02135-EMP-003 Rev 1 : 3 February 2017

measure required.

4 Cultural Heritage

Cultural Heritage

Management Plan

Jaime (school

teacher), Suco

Parlamento; Joao

Freitas, Suco

Caisido; Tomas

Freitas,

Administrative Post

of Vemasse

What is the position of TL

Cement regarding any

sacred site and/or

cemetery found within the

project site?

TL Cement respects all

cultural heritages

including evidence of

ancient human

habitation found within

the project site. In fact, a

Cultural Heritage

Management Plan will

be prepared in

coordination with the

community and the

Secretariat of Arts and

Culture to conduct

procedures and/or

traditional rituals

required relocating

sacred site and/or

tombs including the

management and

protection of new and

known sites during the

project life.

During a field study on

the project site and its

vicinity, some antique

materials from ancient

civilization (spanning the

last ca 30,000 years)

were found and

documented.

5 Groundwater

Water

Management Plan

Francisco Hero

(PNTL)

Where is the location to

drill borewells for water

supply? Will the amount

withdraw from the well

affect the spring located

in Osso-ua?

Water requirement for

mining and plant

operation is to be

abstracted from

groundwater through the

drilling of borewells at

the Uaidei River.

A feasibility study will be

conducted prior to

Page 177: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 177 301012-02135-EMP-003 Rev 1 : 3 February 2017

finalize the decision on

drilling. The location of

the proposed drilling site

and the Osso-Ua Spring

are quite far separated

and thus there will be no

impact to Ossu-Ua

Spring.

6 Land Use and

Tenure

Relocation and

Compensation

Plan

Manuel Azevedo Has the company

identified properties that

may be found within the

project site? What will be

the negotiation regarding

these properties?

TL Cement is currently

working with the

Directorate of Land,

Property and Cadastral

Services (DLPCS) to

map affected

households, farmland,

and other property.

Once TL Cement has

secured the mining and

environmental licenses

required for the project,

we will enter into

discussions with those

affected households and

property owners. Based

on the mapping and

negotiations, TL Cement

will prepare a

Resettlement Plan. This

Resettlement Plan will

provide greater detail on

the monitoring and

reporting requirements

in relation to the

potential social and

economic impacts

associated with the

development of the

project

7 Agustinho da Costa

Belo, Aldeia Osso-ua

If the properties (Farm

land, house etc) are taken

by the company, will there

Yes.

Page 178: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 178 301012-02135-EMP-003 Rev 1 : 3 February 2017

be compensation to the

owners?

10 Groundwater

Water Quality

Management Plan

Duarte Xavier Recommendation:

Management plan for

local reservoir/spring so

to avoid waste water

contamination from the

plant.

Noted

11 Air Quality

Air Quality

Management Plan

Duarte Xavier It is mentioned that traffic

will increase from 3 to 71

passenger cars in a day

during construction and

operation. What will be

the mitigation measure

towards dust caused by

this high traffic?

Dust suppression using

water.

13 Waste

Waste

Management Plan

Herminio Belo Where will the waste

water from the plant be

discharged? Is there any

treatment plan for waste

water?

The volume of waste

water from plant to be

discharged is very low

and thus will have

negligible detrimental

impact to the

environment. In

addition, all chemicals

used on site are to be

stored, handled and

disposed of in

accordance with a

Waste Management

Plan.

14 Economic

Resettlement Plan

Felipe Belmiro Belo Recommendation: There

should be compensation

for community whose

properties are directly

affected by the project.

Yes

21 Tenure and Land

Use

Cultural Heritage

Eusebio Assis

(Youth

Representative),

Suco Tirilolo

When will the affected

community be gathered to

discuss property lost and

cultural heritage- related

TL Cement will proceed

with compensation

negotiations following

receipt of project

Page 179: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 179 301012-02135-EMP-003 Rev 1 : 3 February 2017

Resettlement Plan

Cultural Heritage

Management Plan

issues before proceeding

with construction of the

plant and/or limestone

extraction?

approvals.

22 Economic

Training needs

analysis

Training Plan

Eusebio Assis

(Youth

Representative),

Suco Tirilolo

When will the training for

local workers begin?

Once the company has

obtained the

Environmental License

and other project

approvals.

15.5 Identify how those comments were taken into account

These comments were taken into account by ensuring that any recommended mitigation measures

were populated in the EMP. Key items which were raised by the community which have been

incorporated are:

• Water quality impacts from the Limestone Mine have been addressed through mitigation

measures and a monitoring programme;

• Cultural Heritage impacts through clearing have been addressed by incorporating mitigation

measures;

• Abstraction impact from water supply on the springs at Osso-ua and Caisido requiring regular

monitoring; and

• Dust and Air Quality impacts requiring air quality monitoring and reporting.

15.6 Details of public participation activities

The public consultation and community engagement process has been detailed extensively in the EIS

and the reader is referred to this document which includes the minutes and photographs.

A summary of the consultation sessions is contained in Table 6 in Section 15.3.

15.7 Summarize the public acceptance or opinions on the proposed Project

Key comments from community members are extracted below:

Lian Nian (Traditional Leaders) said “The locals in general were enthusiastic about the project and

had queries about the development activities for the locals that TL Cement would initiate as well as

the employment opportunities the project would generate for the locals”

Casido Community leaders “are 100% willing to accept the cement plant project in their area”

Chief of Suco “Time of development has come. Community to ignore any rumours [that project will

destroy livelihood]”

Page 180: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 180 301012-02135-EMP-003 Rev 1 : 3 February 2017

Director of Environmental Department, GoTL said that many community concerns around air quality

will be addressed by “technology used in Australia which does not produce smog to a level harmful to

the nearby community”.

Overall the response to the project is positive and the majority (more than 90%) of the local

community supports the project.

15.8 Related materials or activities

Newspaper readership is low in Baucau and thus other advertising methods are better suited to

encourage broad public consultation. Therefore, all notices associated with the EIS public

consultation were advertised on national television (TVTL) in Dili on the 4th to 10

th of December 2015.

Notices were also advertised though local radio stations such Radio Popular Coulelemai Bucoli and

Radio Komunidade Lian Matebian in Baucau commencing on the 27th of November to 4

th of

December, 2015. A copy of the public notice was also posted on TL Cement’s website. Additionally,

the notices were displayed at local government offices including Baucau Municipality, Baucau

Administrative Post, Chief of Village, and PNTL Baucau Municipality. Lastly, a copy of all notices was

provided to the NDPCEI.

Prior to the consultation in December 2015 a Non-Technical Summary document was prepared and

translated into Tetun and made available at the following locations:

• TL Cement Office;

• Baucau Municipality Office;

• The NDPCEI Dili Office;

• The NDPCEI Baucau municipality office;

• Baucau church;

• PNTL Vemasse HQ;

• Vemasse Administrative Post;

• Baucau Municipality SEPFOPE Directorate; and

• Tirilolo Suco Hall.

The document was made available for viewing during normal business hours and made available free

of charge.

A copy of the document was made available at a local school, church, or other public facility (Figure

5) near the proposed project and available outside of normal work hours.

The document was also posted on TL Cement’s public website at http://www.tlcement.net/

Page 181: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 181 301012-02135-EMP-003 Rev 1 : 3 February 2017

15.9 Recommendations for future consultations

TL Cement is committed to ensuring continued, open and transparent consultation with all Project

stakeholders and interested and affected parties. Consultation will continue through the life cycle of

the Project.

Page 182: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 182 301012-02135-EMP-003 Rev 1 : 3 February 2017

16 COMPLAINTS AND GRIEVANCES MECHANISM

The Project Proponent will establish a Complaints and Grievances Mechanism (CGM) related to

environmental and social issues arising during the pre-construction, construction, operation and

decommissioning, and post-closure phases of the Project.

The Complaints and Grievance Mechanism shall be developed to ensure that concerns and potential

conflicts arising during the various phases of the Project can be satisfactorily addressed.

WorleyParsons has developed this grievance mechanism framework for discussion with stakeholders

(including government) to refine the procedure to meet stakeholder needs through consultation. .

Once refined, project staff (comprising a representative who will receive grievances at each Project

site’s grievance office, and a Dili office representative) should be provided with training. These staff

will accept and log incoming grievances and, if the grievance is directly related to the Project’s

actions, follow a prioritisation process to identify the required remedial action.

Figure 16-1 illustrates a suggested procedure for managing and resolving complaints during the

feasibility stage. The procedure is equally relevant during the development stage of the Project with

responsibility for resolution defined between the Project Proponent and the construction contractor. It

is important to ensure the following values are upheld throughout the grievance process:

• Awareness;

• Accessibility;

• Transparency; and

• Expediency.

Stakeholder awareness of the existence of the CGM will mean that when an issue arises, community

members will know where to go to address and resolve the issue. This will encourage the issue to be

dealt with through the appropriate mechanism and will improve expediency of resolution and good will

with the community. Therefore, when engaging with the villages and other stakeholders they should

be made aware of the grievance mechanism and where or whom they should contact to access the

mechanism.

Accessibility to the CGM will also enable stakeholders to air their complaints directly thereby avoiding

other forums such as the media. Typically, the earlier the Proponent becomes aware of potential

issues, the more efficiently these can be mitigated and contained. Furthermore early detection of

potential issues can prevent problems arising later in the Project lifecycle. It will be essential to break

down barriers to accessibility which, based on baseline investigations, include, geographic location,

literacy levels, language and cultural appropriateness, and distrust in government or corporate

structures. Recommended strategies to overcome these barriers include:

• Establishing a grievance office at Dili, surrounding sucos and the Cement Plant site where

grievances might be heard, namely Caisido and Baucau.

• Upon request, remote locations and vulnerable individuals (e.g. elderly and disabled) should

be visited by a representative of the project on a regular basis who will disseminate

Page 183: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 183 301012-02135-EMP-003 Rev 1 : 3 February 2017

information regarding the Project and receive complaints from stakeholders at their village or

residence. This will promote accessibility of the grievance procedure and help build a

relationship with communities and encourage dialogue.

• Complaints should be able to be registered via a toll-free mobile telephone number to be

established by the Proponent in cooperation with local telecom provider to allow direct access

to each individual to the grievance mechanism. Another option is to provide a pre-paid mobile

phone to each village chief to be exclusively used for lodging grievances. The mobile phone

would allow the chief to send a message to the nearest grievance office requesting the

grievance officer to visit the village and record the grievance. The pre-paid mobile option

needs to be further investigated in consultation with village chiefs.

• Representatives should be instructed to note down complaints where the individual is unable

or unwilling to write the complaint themselves.

• Local people fluent in the relevant languages should be engaged as representatives.

• Locals should be consulted regarding the cultural appropriateness of the complaints process.

• Complainants should be given the option of maintaining anonymity throughout the complaints

process.

Transparency of process cultivates trust and ensures expectations among the stakeholders are set at

an appropriate level. Elements of the grievance procedure which will encourage transparency include

explaining the process and timescales associated with processing a complaint, providing the

complainant with a copy of the complaint when it has been submitted and ensuring the complainant is

kept informed of developments in processing their complaint. Written complaints should be held at the

respective grievance offices where the complainant (or a designated advocate) should be allowed

access.

Expediency will enable efficient processing of complaints. In order to encourage expediency the

project should set deadlines for processing complaints and a case management approach should be

established among the relevant staff, with oversight from a senior individual who should be assigned

responsibility for management of the grievance mechanism.

As well as committing to the values mentioned here, the project will work to International Finance

Corporation (IFC) guidelines (IFC, 2011) regarding grievance mechanisms.

Page 184: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 184 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 16-1: Grievance resolution framework

Page 185: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 185 301012-02135-EMP-003 Rev 1 : 3 February 2017

17 WORK PLAN AND IMPLEMENTATION SCHEDULE

The following sections details the work plan and implementation schedule for the various phases of the Project.

Page 186: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 186 301012-02135-EMP-003 Rev 1 : 3 February 2017

Figure 17-1 Overall work plan and implementation schedule

Post project approval 2016 - 2017 *1 2018 2019 - 2055 2055 - 2060

Tasks to implement EMP Tender and Detailed Design Phase Preconstruction Construction Operations Decommissioning

Surface Water Quality Baseline Studies ●

Project Approvals ●

Stream gauges installed ●

Monitoring boreholes installed ●

Relocation of people and heritage sites (w here required) ●

Groundw ater Study ●

Flora and Fauna Pre-Clearance Validation ●

Relocation of affected landholders ●

Heritage pre-clearance activities ●

Complaints and grievances mechanism ●

Fauna counts and tracking ●

Water monitoring ● ● ● ●

Weed management and control of invasive species ● ● ● ●

Fauna counts and tracking ●

Traffic assessment (4 w eeks monitoring at start of phase) ● ● ● ●

Install Automated Weather Station and commence climate recording ●

Annual air quality monitoring ● ● ● ●

6-monthly groundw ater monitoring ●

Annual groundw ater monitoring ● ● ●

Accident Emergency Response Review ● ● ● ●

Review Biodiversity Action Plan ● ●

Annual Environmental Reporting to the GoTL ● ● ●

Finalise Closure Plan ●

Monitoring and reporting of f lora species abundance and coverage 5 years after mine closure ●

Record and monitor total area of re-vegetation and the species used for rehabilitation ●

5 years post closure assessment of rehabilitation success and soil health ●

Page 187: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 187 301012-02135-EMP-003 Rev 1 : 3 February 2017

Table 7 Detailed work plan and implementation schedule

Activity Tender and Detailed

Design Phase

Preconstruction Construction Operations Decommissioning

Post project approval 2016 - 2017 2018 2019 - 2055 2055 - 2060

Clearing and earthworks

movement of heavy

machinery

Surface Water Quality Baseline

Studies

Project Approvals

Stream gauges installed

Monitoring boreholes installed

Relocation of people and

heritage sites (where required)

Flora and Fauna Pre-

Clearance Validation

Relocation of affected

landholders

Heritage pre-clearance

activities

Complaints and grievances

mechanism

N/A N/A Accident Emergency Response

Review

Review Biodiversity Action

Plan

Water monitoring

Complaints and grievances

mechanism

Weed management and control

of invasive species

Annual Environmental

Reporting to the GoTL

Construction of

infrastructure

Fauna counts and tracking

Water monitoring

Complaints and grievances

mechanism

N/A N/A

Page 188: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 188 301012-02135-EMP-003 Rev 1 : 3 February 2017

Weed management and

control of invasive species

Fauna counts and tracking

Movement of vehicles

and people causing dust

and noise

Generate electricity

through Power Station or

diesel generators

N/A Traffic assessment (4 weeks

monitoring at start of phase)

Install Automated Weather

Station and commence climate

recording

Annual air quality monitoring

Traffic assessment (4

weeks monitoring at start of

phase)

Undertake daily climate

measurements

Annual air quality

monitoring

Traffic assessment (4

weeks at start of phase)

Undertake daily climate

measurements

Annual air quality

monitoring

Traffic assessment (4 weeks

at start of phase)

Undertake daily climate

measurements

Annual air quality monitoring

Dewatering of Mine area Groundwater Study 6-monthly groundwater

monitoring

Annual groundwater

monitoring

Annual groundwater

monitoring

Annual groundwater monitoring

Operation of

infrastructure & Mining

activities

N/A N/A N/A Accident Emergency

Response Review

Review Biodiversity Action

Plan

Water monitoring

Complaints and grievances

mechanism

N/A

Page 189: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 189 301012-02135-EMP-003 Rev 1 : 3 February 2017

Weed management and

control of invasive species

Fauna counts and tracking

Annual Environmental

Reporting to the GoTL

Decommissioning of

infrastructure and

revegetation of habitat

Biodiversity Action Plan

Closure Plan

Water monitoring

Annual air quality

monitoring

Traffic assessment (4

weeks at start of phase)

Monitoring and reporting of

flora species abundance

and coverage 5 years after

mine closure

Complaints and grievances

mechanism

Record and monitor total

Page 190: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 190 301012-02135-EMP-003 Rev 1 : 3 February 2017

area of re-vegetation and

the species used for

rehabilitation for a period of

5 years following

decommissioning.

5 years post closure

assessment of rehabilitation

success and soil health

Undertake daily climate

measurements

Notes:

1. This start date is only possible if TL Cement receives the necessary project approval permits on time and based on type of financing structure in

place for the project.

Page 191: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 191

18 COST ESTIMATES

For the purpose of the cost estimate, the following assumptions are key:

• This estimate covers both the EMP for the Cement Plant, Jetty and Other Associated

Infrastructure and the EMP for the Limestone Mine

• The duration of the Project phases are:

o Pre-construction = 6 months;

o Construction = 2 years and 6 months; and

o Operations and Decommissioning = 55 years.

• Replacement and maintenance costs for monitoring equipment are excluded.

• All reporting and data interpretation for Construction, Operations and Decommissioning

phases are undertaken by Company technical specialists. External consultant costs have not

been allowed.

• The responsibility for the costs are aligned with the Company responsibility matrix in Section

8

• CPIX Inflation has not been accounted for.

• Costs associated with infrastructure development recommended as a mitigation measure

have been excluded.

Table 18-1 EMP Implementation cost estimate

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Air Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Automated Weather Station setup and installation Monthly data download and interpretation

$150,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Monthly data download and interpretation

$24,000

Operating the quarry/mining

Operation Monthly data download, 6-monthly interpretation

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Monthly data download, 6-monthly interpretation

$24,000

Page 192: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 192

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Noise Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Twice per year measurements at receptors

$10,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Twice per year measurements at receptors

$20,000

Operating the quarry/mining

Operation Annual measurements at receptors

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Twice per year measurements at receptors

$20,000

Water Quality Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Baseline Marine Water Quality survey (coral health, risk from ballast) Monthly sampling at 5 locations, interpretation 4x per year

$124,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Monthly sampling at 5 locations, interpretation 4x per year

$48,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Operation Monthly sampling at 5 locations, interpretation 4x per year

$1,300,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Monthly sampling at 5 locations, interpretation 4x per year

$48,000

Page 193: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 193

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Water Quantity (flows instreams, springs)

Earthworks Heavy machinery movement Vehicles, buses and cars movement Dewatering of work areas

Pre-construction Detailed hydrological model and 2x monitoring boreholes in the Limestone (Mine area) Flow meters and stream gauging units x4 Measurement and interpretation monthly and interpretation 4x per year

$400,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Dewatering of work areas

Construction Measurement and interpretation monthly and interpretation 4x per year

$20,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Dewatering of work areas

Operation Measurement and interpretation monthly and interpretation 4x per year

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement Dewatering of work areas

Decommissioning Measurement and interpretation monthly and interpretation 4x per year

$20,000

Flora Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Pre-clearance vegetation distribution mapping Post clearance area survey

$80,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Post clearance area survey Ongoing capture of clearing area information

$20,000

Operating the quarry/mining Dewatering

Operation Progressive rehabilitation costs (material and equipment) Post operations vegetation survey Rehabilitation success survey (post closure)

$5,500,000

Page 194: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 194

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement Dewatering

Decommissioning Post rehabilitation area survey Ongoing capture of rehabilitation area information

$20,000

Fauna Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Fauna relocation expert – standby for pre- construction duration

$100,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Fauna management records as required Annual environmental reporting

$20,000

Operating the quarry/mining Dewatering

Operation Fauna management records as required Annual environmental reporting

$550,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Fauna management records as required Annual environmental reporting

$20,000

Traffic Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Traffic monitoring equipment (1 unit) Traffic census (1 instance)

$20,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Traffic census (1 instance) $10,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Operation Traffic census (5 instance) $50,000

Page 195: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 195

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Traffic census (1 instance) $10,000

Community Clearing of land Relocation and resettlement Earthworks Heavy machinery movement Vehicles, buses and cars movement

Pre-construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Corporate social responsibility support and implementation

$120,000

$250,000

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Construction Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Training of local people # development costs in Section 19.1 below

$480,000

Mining operations Blasting Drilling Trucks moving Rock breaking

Operation Annual community engagement events Quarterly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation Training of local people (over the life of operations – 58 years)# development costs in Section 19.1 below

$1,100,000

Page 196: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 196

Aspect Activity Project Phase Mitigation and monitoring measures

Cost Estimate (USD)

Earthworks Heavy machinery movement Vehicles, buses and cars movement

Decommissioning Monthly community engagement events Monthly grievances committee review and reporting Community engagement survey (1 instance) Community awareness programmes Corporate social responsibility support and implementation

$480,000

Total cost mitigation and monitoring implementation # $15,758,000

Page 197: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 197

18.1 Infrastructure costs

Item Cost (USD) Waste water treatment plant $ 340,000 Training centre (20 years) $22,000,000 Drainage system (bunds and drains) $ 900,000 PPE $ 20,000 Fire response system $ 840,000 Raised Conveyor system $ 5,000,000 Instrumentation $ 150,000 Water supply borehole and infrastructure $ 120,000 Total – All infrastructure for mitigation $29,370,000

Page 198: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 198

19 REVIEW OF THE EMP

The Limestone Mine EMP will be reviewed at the following key project milestones:

• Completion of the pre-construction phase and additional specialist studies;

• Completion of the construction phase;

• Award of the Operations contract to incorporate operator-specific information; and

• Every 5 years at minimum during Operations phase;

The Limestone Mine EMP will be reviewed following the events where:

• Equipment or procedural changes result in a positive or negative change to the project

environmental and social risks;

• Monitoring results indicate that a change to the mitigation and monitoring regime is required

to manage the project impacts;

• Legislative changes in country require update to the EMP; and

• There is a change to the responsibility matrix for EMP implementation.

The review will follow standard QA/QC document management and review processes with the

Approver being technically responsible for the content.

The EMP will be reviewed where the changes in the EMP have influenced the following key factors

(Section 3):

• Displacement / Resettlement;

• Cultural Heritage;

• Traffic;

• Water; and

• Legally responsible person.

Page 199: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 199

20 NON-TECHNICAL SUMMARY

The Non-Technical Summary which was used as a component of the Consultation phase, is included

below.

20.1 Introduction

TL Cement LDA, a privately-owned company, proposes to construct a new cement manufacturing

plant in Baucau Municipality, Timor-Leste. In accordance with Decree Law 05/2011, Environmental

Licensing Law (ELL), the TL Cement LDA has submitted an Application for Environmental License for

this project to the National Directorate of the Environment (NDE). The Baucau Cement overall Project

will consist of:

1. Cement Plant, Marine Jetty, Belt Conveyor, and associated infrastructure

2. Limestone Mine

The NDE has classified the project as a “Category A” project, and must go through the environmental

assessment process, including preparation of an Environmental Impact Statement (EIS).

20.1.1 Purpose of this document

This document is a Non-Technical Summary (NTS) of the EIS for the Limestone Mine. This NTS

presents the assessment of the potential environmental and social impacts, proposed control

measures to mitigate and manage the impacts, and remaining impacts of the project.

20.1.2 Benefits of the project

The benefits of the project include direct employment with 1000 permanent jobs expected during

operations. The project aims to develop local capacity and will develop a training centre. Other

benefits include indirect employment to local community members, through the multiplier effect due to

downstream socio-economic benefits and consequent improvement in the living conditions of local

population in the project area. It is estimated that at least 2000 more jobs can be created through

indirect activities during operations with local business opportunity creation in supplying goods and

services to TL Cement and its employees. The location of the Baucau Cement Project and its

components can be seen in Figure 20-1 below.

Page 200: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 200

Figure 20-1: Location of Baucau Cement Project Limestone Mine

Page 201: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 201

20.1.3 Key project characteristics

The key project characteristics are listed in Table 2.

Table 2: Summary of Baucau Cement Project Characteristics

Element Description

Project life Limestone reserves for 50 years at full production capacity

Investment $400 million USD

Largest industrial project undertaken in Timor-Leste to date

List of major

project

components

Limestone mine (up to 5.76 km2)

Area of

disturbance

Limestone mine – 244 ha

Power Supply 30 Mega Watt Biomes and Recycle Power Generation power plant

3-5 Mega Watt Solar Power Plant

Water Supply Groundwater from borewells at the Uaidei River

• 0.35 ML/day for construction

• 3.15 ML/day for operation

Number of jobs of

all project

components

3000 jobs during peak of construction

1000 permanent jobs during operations

20.1.4 Operations

When in operation, limestone will be mined from the ground in an open pit and will be taken to the

Cement Plant for processing. Some other cement components will be shipped to the Marine Jetty

and put on a fully enclosed Pipe Conveyor Belt and taken to the Cement Plant to be processed along

with the limestone and turned into Portland cement clinker. Portland cement clinker is small lumps

that are the basic ingredient of cement. The Portland cement clinker will then be taken by the same

full enclosed Pipe Conveyor Belt from the cement plant to the Port where it will be loaded onto ships

from a Marine Jetty. A similar example of a conveyor and marine jetty can be seen in Figure 20-2.

Page 202: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 202

Figure 20-2: The Baucau Cement Plant Project once in operation

Page 203: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 203

20.2 Project Phases

The project will have four phases: Pre-construction (18 months), Construction (2 years), Operations

(over 35 - 50 years) and Decommissioning (5 years). A summary of the activities to be undertaken

during each phase and potential impacts are presented in Table 3. In addition, the potential impacts

that could occur as a result of the activities during each phase have been outlined below. Of these,

key impacts have been identified as either a ‘Medium’ or ‘High’ risk, and have been discussed further

in Section 20.3, along with identified mitigation measures to manage and reduce the impacts.

Page 204: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 204

Table 3: Summary of Baucau Cement Project phase characteristics and potential impacts

Phase Activities Potential Impacts (risk)

Pre-construction

(Duration of

approximately 18 months)

• Clearing of fence lines & Installing fences

• Clearing of access roads internal to the project area

• Establishment of Laydown areas and preliminary office infrastructure such as

portable toilets and shipping containers for storage

• Relocation of people and animals within the project area

• Exploratory water source drilling and installation of water supply wells.

• Installation of power supply infrastructure corridors via clearing, excavation

and pegging

• Geological studies including bore drilling and pit surveys

• Weir installation in streams

• Establishment of exclusion zones around, boreholes and springs (known

impact, appropriation of natural asset)

• Clearing of natural vegetation (Low)

• Displacement of people (High)

• Exclusion of people from, boreholes

and springs (Low)

• Increased traffic and transport (Low)

• Increased noise and increase in air

pollution (Low)

• Disturbance of heritage sites (Low)

• Increased groundwater usage (Low)

• Disturbance of cultural heritage at the

mine site (High)

Construction

(Duration of

approximately 2 years)

• Building structures in concrete and steel

• Establishment of bunds, hauling roads, drainage areas and mine stope

markers ahead of mining commencing

• Construction of internal access roads and haul roads

• Clearing of natural vegetation (Low)

• Displacement of people (High)

• Visual impact (High)

Page 205: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 205

• Discharge into landfill – solid and liquid waste • Increased noise, increased air

pollution (Low)

• Increased traffic and transport (Low)

• Increased light and heavy vehicle

interaction with pedestrians and

motorbikes (Medium)

• Increased groundwater usage (Low)

• Increase in waste (Low)

• Clearing of coral (Low)

Operation

Duration of approximately

35-50 years)

• Mining 12 hours a day, 7 days a week

• Blasting

• Truck hauling

• Discharge to landfill – solid waste

• Increased traffic and transport

(Medium)

• Increased noise, increased air

pollution (Low)

• Disturbance to community from

blasting (Medium)

• Increased light and heavy vehicle

interaction with pedestrians and

motorbikes (Medium)

• Increased groundwater usage

(Medium)

Page 206: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 206

• Increased pollution (waste water

outfall) (Low)

De-Commissioning

(Duration of

approximately 5 year)

• Mine Closure and Rehabilitation • Reduction in employment levels

• Continued employment during

rehabilitation and closure of the mine

• Negative impact on local economy

Page 207: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 207

20.3 Key Potential Impacts and Mitigation Measures

There are a number of aspects to the project that have the potential to cause 'environmental and

social impacts during different phases of the project. Of these, key aspects and their impacts have

been identified to be a ‘Medium’ or ‘High’ risk. These key aspects, along with mitigation measures

identified to manage and reduce the impacts, and monitoring and reporting to ensure compliance,

have been outlined in Table 4 below.

Page 208: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 208

Table 4: Key Potential Impacts, Mitigation Measures and Monitoring and Reporting

Aspect Mitigation Measures

Displacement / Resettlement

Local people will be displaced and will require

relocation in order for this project land to be

acquired.

During pre-construction the people who live on

the land zone for the project will need to be

relocated and compensated for their loss of land.

This NTS and EIS does not address the issue of

resettlement, and is currently being addressed via

another process

This can cause a Medium to High level of impact

on local people.

TL Cement is currently working with the Directorate of Land, Property and Cadastral

Services (DLPCS) to map affected households, farmland, and other property. Once

TL Cement has secured the mining license and environmental licenses required for

the project, they will enter into discussions with those affected households and

property owners. Based on the mapping and negotiations, TL Cement will prepare a

Resettlement Plan.

An alternative to outright sale of the land may be for TL Cement to rather lease the

land from the locals. This rent system prevents local landowners from losing their

rights to the land if the project should cease operations. The leasehold system would

also allow local to retain their identification with their place of origin and territorial

identity (BBS, 2015d).

The development of a Resettlement Action Plan will provide greater detail on the

monitoring and reporting requirements in relation to the potential social and economic

impacts associated with the development of the project.

Cultural Heritage

Impacts of the mine on Cultural Heritage for the

local area results in a number of sacred heritage

sites directly impacted by clearing and activities

within the project footprint. Local area sites will be

A Cultural Heritage Management Plan will be prepared in coordination with the

community and the Secretariat of Arts and Culture that documents the process and

procedures to be followed during the project, including the management and

protection of new and known sites during the project life.

Access to the sites during the life of the project should be considered in the context of

Page 209: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 209

Aspect Mitigation Measures

permanently impacted causing a Medium impact. the importance of the sites to the local community and the broader Timorese culture.

Where safe access cannot be guaranteed, those sites which are located adjacent to

the project should be fenced off, access restricted for the project life or relocated, in

consultation with the community.

Where a site is located inside the location of the proposed mine pit and the impact is

unavoidable, the impact should be documented, exhumation of bones (where

applicable) and relocated in consultation with the local community.

Traffic

• During operation there is predicted to be a

significant increase in vehicles using the

local roads

• During operation, heavy vehicles (25 tonne

trucks) will be transporting cement to Baucau

for local sale, which will lead to up to 12

heavy vehicles per day on the roads, which

is a significant increase from the 2.4

currently using the local roads per day.

An increase in heavy vehicle numbers and

movements is likely to cause damage to the

condition of the local road network and also

poses a Moderate safety risk for the local road

Traffic impacts associated with the development of the project can be adequately

managed if the following mitigation measures are adopted and implemented for the

life of the project:

• Minimising vehicle movement – good planning and scheduling can limit the

number of vehicle movements required which will reduce the likely impacts to

the condition of the roads and public safety. Transporting workers in buses will

reduce individual vehicle traffic. Having a camp within the plant site is additional

mitigation

• Limit vehicle reversing, as it is major cause of fatal accidents. Implementation of

one-way systems, ensuring reversing sensor/alarms are installed on all vehicles

and mobile equipment and signage in reversing areas can reduce the risk of

reversing accidents.

• Traffic signage – all traffic signage should be clearly and prominently displayed

in well-lit areas. Signage should be posted to indicate speed limits, restricted

Page 210: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 210

Aspect Mitigation Measures

users and pedestrians. access, visitor parking, headroom, and other route hazards.

• Speed limits should be implemented and enforced.

• Road widening may be required as a minimum road width of 6.5 meters is

recommended for heavy vehicles (BBS, 2015c).

• Limit vehicle idling time and keep vehicles well maintained to minimise

particulate and gaseous emissions (Holtec, 2015a).

• Where appropriate, pedestrian crossing points should be provided in the mist

visible and obvious pedestrian routes. The crossing points should be

appropriately sign posted.

• Regular review, maintenance and repair of road pavement and drainage should

be undertaken.

• A management plan for dealing with the health and safety implications for all

vehicle incidents and recommending improvement should be developed and

updated annually

Water

All water for the operation of the mine is to be

abstracted from groundwater through the drilling

of borewells at the Uaidei River. During operation

this will be 3.15 ML/day. Impacts on the local

ecosystem and the local users are expected to be

• Implementation of a Groundwater Management Plan

• Monitoring boreholes should be drilled at strategic locations around the

infrastructure to monitor the background water quality as well as provide an

indication of the presence of contaminants in the surrounding aquifer.

• Groundwater modelling for the water supply should be undertaken to determine

Page 211: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

301012-02135-EMP-003

Rev 0 : 3 February 2017 Page 211

Aspect Mitigation Measures

Moderate. the radius of influence of the drawdown in the local aquifers. This will enable the

project to manage abstraction and dewatering to minimise impact on the

vegetation and river base flow.

• Ground water extraction can be minimized with the use of sea water for power

plant cooling and further optimized by closed circuit water condensers to recycle

the water

• Contamination of the aquifer from the project should be mitigated through a Spill

Management Plan and all spills immediately cleaned up and disposed of

appropriately.

• All chemicals used on site are to be stored, handled and disposed of in

accordance with a Waste Management Plan.

Page 212: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 212 301012-02135-EMP-003 Rev 1 : 3 February 2017

20.4 Stakeholder Engagement Process

This project has involved consultation with people who may be affected by the project and other

project stakeholders. This includes the public, such as those who will be directly affected, women and

vulnerable groups. As can be seen by Figure 20-3, public engagement consultation is a continuous

process throughout the EIA process and has already been initiated.

The public consultation process for the environmental assessment is being carried out in accordance

with the Draft Ministerial Diploma for the “Regulation on the Public Consultation Procedures and

Requirements during the Environmental Assessment Process” dated 22 April 2014.

Figure 20-3: Stakeholder Engagement and Consultation

The stakeholder consultation list to date is shown in Table 5.

Table 5: Consultation Summary

Stakeholder

Government Ministries

Ministry of Commerce, Industry, and Environment

• National Directorate for Environment

Ministry of Petroleum and Mineral Resources

• National Directorate of Mines and Minerals

• Institute of Petroleum and Geology

Ministry of Justice

• National Directorate of Land, Property and Cadastral Services

Ministry of Finance

Ministry of Planning and Strategic Investment

Page 213: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 213 301012-02135-EMP-003 Rev 1 : 3 February 2017

Ministry of Public Works, Transport and Communications

• Directorate of Roads, Bridges, and Flood Control

• Directorate of Ports/APORTIL

Ministry of Tourism, Arts and Culture

State Secretariat of Arts and Culture

Municipality (District) Government

Baucau Municipality (formerly Baucau District Administration)

Baucau Administrative Post (formerly Baucau Sub-District Administration)

Baucau Municipality Police District

Baucau Municipality Directorate of Land, Property and Cadastral Services

Baucau Municipality Directorate of Environment

Vemasse Administrative Post

Local Government

Suco Council Tirilolo

Suco Council Triloca

Suco Council Vemasse-Vila

Suco Council Caibada

Suco Council Bahu

Suco Council Wailili

Suco Council Bucoli

Suco Council Fatumaca

TL Cement and Worley Parsons conducted follow up consultation

in the local community during site visits in February 2015 and May

2015.

These meetings were attended by the following community

members:

• Chefe Suco Tirilolo: Ricardo Ernesto Belo (RB)

• Chief of Community Police in Suco Tirilolo: Norberta Belo

(NB)

• Chefe Aldeia Lialailesu: Cipriano Belo (CB)

• Chefe Aldeia Parlamentu: Manuel Belo (MB)

• Chief of Traditional Practice (Lia-Nain): Duarte Belo (DUB)

• Secretary of Suco Tirilolo: Zeca Belo (ZB)

Representative of youth of Suco Tirilolo: Damião Belo (DB)

Local Communities

Chefes de Aldeia

Lia-Nain

Local Youth Organizations

Page 214: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 214 301012-02135-EMP-003 Rev 1 : 3 February 2017

Local Women’s Organizations

Local Fishermen’s Organization

Baucau Parish

Civil Society/Local NGOs

Lao Hamutuk

Luta Hamutuk

Haburas

Rede ba Rai

Belun

Kapeliwa

Other Organizations

International Finance Corporation

Conservation International

BESIK (Bee, Saneamentu no Ijiene iha Komunidade) Rural Water Program

*****************end of non technical summary************************

Page 215: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 215 301012-02135-EMP-003 Rev 1 : 3 February 2017

21 REFERENCES

Advisian (2016). Baucau Cement Project: Surface Water Impact Assessment Report. Unpublished

report for WorleyParsons, Feb 2016.

BBS (2015a). Air Quality Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste.

Final Draft Report No: 15.3380-DR-002 Rev B, Oct 2015.

BBS (2015b) Noise Impact Assessment study of Clinker Cement Project Baucau – Timor-Leste. Final

Draft Report No: 15.3380-FDR-002 Rev B, Oct 2015.

BBS (2015c). Traffic Impact Assessment Study of Clinker Cement Project Baucau-Timor-Leste. Final

Draft Report No:15.3380-FD-002, Rev B, Oct 2015.

BBS (2015d). Social Impact Assessment Study of Clinker Cement Project Baucau – Timor-Leste.

Final Draft Report No: 15.3380-DR-002, Rev. C, Oct 2015.

BOM (2015). What are El Niño and La Niña events? Online publication of the Australian Bureau of

Meteorology (BOM) [Accessed 3 Dec 2015] http://www.bom.gov.au/climate/enso/history/ln-2010-

12/ENSO-what.shtml

CDU (2009) The Timor-Leste Coastal / Marine Habitat Mapping for Tourism and Fisheries

Development Project. A joint research project by Charles Darwin University, Northern Territory

Government, Republica Democratica de Timor-Leste, Australian National University, the Australian

Government and the Australian Institute of Marine Science.

http://www.cdu.edu.au/sites/default/files/research/docs/36091-executive-summary-secured-final.pdf

Conservation International (2013). A Marine Rapid Assessment (MRAP) of Timor-Leste, 14-23

August 2012. Report prepared by Conservation International, Edited by MV Erdmann and C Mohan.

Cowie, I. 2006. Assessment of floristic values of the proposed Jaco-Tutuala-Lore National Park,

TimorLeste (East Timor). . Northern Territory Herbarium, Darwin.

CSIRO (2010). Climate change in Timor-Leste. A brief overview on future climate projections.

Prepared by the CSIRO.

CSIRO (2011). Current and future climate of Timor-Leste, International Climate Change Adaption

Initiative. A report for the Pacific Climate Change Science Program partners [Accessed online 3

December 2015] http://www.pacificclimatechangescience.org/wp-

content/uploads/2013/06/5_PCCSP_East_Timor_8pp.pdf

Dethmers K, Chatto R, Meekan M, Amaral A, de Cunha C, de Carvalho N, Edyvane K (2012) Marine

Megafauna Surveys in Timor Leste Coastal-Marine Habitat Mapping, Tourism and Fisheries

Development Project. Ministry of Agriculture & Fisheries, Government of Timor Leste.

DotE (2015) Lead. Online database for the Australian Department of the Environment. [Accessed 10

December 2015] https://www.environment.gov.au/protection/chemicals-management/lead

Page 216: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 216 301012-02135-EMP-003 Rev 1 : 3 February 2017

Edyvane K, McWilliam A, Quintas J, Turner A, Penny S, Teixeira I, Pereira C, Tibirica Y, Birtles A.

(2009) Coastal and Marine Ecotourism Values, Issues & Opportunities on the North Coast of Timor

Leste – Final Report. Ministry of Agriculture and Fisheries, National Directorate of Tourism,

Government of Timor Leste.

EPA (2015a). National Ambient Air Quality Standards (NAAQS). Online database for the US

Environmental Protection Authority. [Accessed 9 December 2015, last updated 10 July 2015]

http://www3.epa.gov/ttn/naaqs/criteria.html

EPA (2015b) Particulate Matter. Online database for the US Environmental Protection Agency.

[Accessed 9 December 2015. Last updated 9 November 2015] http://www3.epa.gov/pm/

EPA (2015c) Nitrogen Oxides (NOx) Control Regulations. Online database for the US Enironmental

Protection Authority [Accessed 9 December 2015, last updated 12 September 2015]

http://www3.epa.gov/region1/airquality/nox.html

EMEP-MSC-W (1995) Status of the development of the multilayer Eulerian model: a) Model

description; b) A new method of calculating mixing heights; c) Model results for sulphur transport and

deposition in Europe for 1992 in the 50 km grid. http://www.atmos-chem-phys.net/12/7825/2012/acp-

12-7825-2012.pdf

European Commission (2015) Air Quality Standards. Website on Environmental Air Quality

Standards. Available at: http://ec.europa.eu/environment/air/quality/standards.htm. Accessed 13

October 2015

Fabricius KE & Alderslade P (2001) Soft Corals and Sea Fans: A comprehensive guide to the tropical

shallow water genera of the central-west Pacific, the Indian Ocean and the Red Sea. Australian

Institute of Marine Science, Townsville. 264 pp. ISBN: 0 642 322104.

FAO (2015) Food and Agriculture Organisation (FAO) of the United Nations. Fishery and Aquaculture

Country Profiles (The Democratic Republic of Timor-Leste). Available online at:

http://www.fao.org/fishery/facp/TLS/en#CountrySector-PostHarvest . Accessed 13 October 2015

Goines, L and Hagler, L (2007). Noise Pollution: A Modern Plague. Southern Medical Journal, vol.

100, issue 3, pgs 287-294 [http://www.medscape.com/viewarticle/554566_3]

Grantham HS, Watson JEM, Mendes M, Santana F, Fernandez G, Pinto P, Ribeiro LM and da Cunha

Barreto C (2010) National Ecological Gap Assessment for Timor-Leste 2010. CNRM Solutions report

for the Department of Protected Areas and National Parks of Timor-Leste, National Directorate of

Forestry, Ministry of Agriculture and Fisheries.

[file:///C:/Users/katherine.swain/Downloads/tl_nega_final%20(2).pdf]

Holtec. 2015a. Mine Closure Plan for Bucoli Limestone Deposit – Block I-1, Baucau District, Timor-

Leste. September 2015.

Jocson, J. M. U., Jenson, J. W. & Contractor, D. N. (2002) Recharge and aquifer response: northern

Guam lens aquifer, Guam, Mariana Islands. J. Hydrol. 260, 231–254.

Page 217: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 217 301012-02135-EMP-003 Rev 1 : 3 February 2017

MAFF (2004) Ministry of Agriculture, Forestry and Fisheries website. [Accessed 11 December 2015,

last updated 2004] http://gov.east-timor.org/MAFF/index.htm

Monk KA, Y De Fretes, and G Reksodinharjo-Lilley (1997). The Ecology of Nusa Tenggara and

Maluku. Periplus Editions, Singapore.

Oliveira NV (2015). Baucau Cement Plant, Assessing the Impact on Archaelogical and Cultural

Heritage Sites. Unpublished report for WorleyParsons, August 2015

Rong Y, Park J, Duggan D, Mahdyiar M and Bazzuro P (2012). Probabilistic Seismic Hazard

Assessment for the Pacific Island Counties. 15 WCEE, Lisboa 2012

[http://www.iitk.ac.in/nicee/wcee/article/WCEE2012_2521.pdf]

Royal Hakoning DHV (2015). Report on TL Cement Jetty Facilities, for TL Cement LDA, Ref. No.

M&WSA1071R001F01, August 2015.

The World Bank (2015). Reducing the Risk of Disasters and Climate Variability in the Pacific Islands:

Timor-Leste Country Assessment. A Report by the Global Facility for Disaster Reduction and

Recovery, The World Bank and SOPAC. Washington DC [Accessed 4 December 2015]

http://siteresources.worldbank.org/INTPACIFICISLANDS/Resources/TIMOR_LESTE_ASSESSMENT.

pdf

Trainor, C. R. 2010. Timor’s fauna: the influence of scale, history and land-use on faunal patterning. .

Faculty of Education, Health and Science. Charles Darwin University, Darwin.

Trainor, C. & Easton, B. (2015). Baucau Cement Clinker Plant Vegetation and Fauna Survey Report.

Prepared for WorleyParsons, August 2015.

Trainor, C. (2015) Baucau Cement Clinker Plant, Mine I-2 and II-1 Desktop study of vegetation and

fauna. Report to WorleyParsons, September 2015.

UNDP (2010). Disaster Risk and Hazard Map Analysis for Timor-Leste: An overview of existing risk

maps. Disaster Risk Management Institutional and Operations Systems Development in Timor-Leste

Project, UNDP. United Nations Disaster Planning, published on the Global Risk Information Platform,

January 2010

[http://www.gripweb.org/gripweb/sites/default/files/Hazard_and_Risk_Map_Analysis_for_Timor_Jan'1

0_Ver_4_(3).pdf]

US DOT (2014). Lane Width. Mitigation Strategies for Design Exceptions. Website for the US

Department of Transport, Federal Highway Administration. [Accessed 21 December 2015, last

updated 15 October 2014]

http://safety.fhwa.dot.gov/geometric/pubs/mitigationstrategies/chapter3/3_lanewidth.cfm

Valdivieso L M (2001). East Timor: Macroeconomic Management on the Road to Independence but

cant work it out. See here http://www.highbeam.com/doc/1G1-73849042.html.

WHO (1999) Guidelines on Community Noise. A publication of the World Health Organization

[http://www.who.int/docstore/peh/noise/guidelines2.html]

Page 218: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 218 301012-02135-EMP-003 Rev 1 : 3 February 2017

WHO (2005) WHO Air Quality Guidelines for Particulate Matter, Ozone, Nitrogen Dioxide and Sulphur

Dioxide, Global update for the World Health Organization, 2005

Wikramanayake E, E Dinerstein, C J Loucks, D Olson, J Morrison, J Lamoreux, M McKnight and P

Hedao. (2002a). Terrestrial Ecoregions of the Indo-Pacific: A Conservation Assessment. Island Press.

Wikramanayake E, E Dinerstein, G. Loucks, D. Olson, J. Morrison, J. Lamoreux, M. McKnight, and P.

Hedao. 2002b. Ecoregions in ascendance: reply to Jepson and Whittaker. Conservation Biology

16:238-243.

WorleyParsons (2015a) Coastal Processes Desktop Study - Marine Facilities, Unpublished report

301012-02135 – CS-REP-0001) for TL Cement LDA, 23 September 2015

WorleyParsons (2015b), Baucau Cement Plant Marine Jetty, Benthic Habitat Survey and Fisheries

Assessment Report. Unpublished report for WorleyParsons, October 2015.

WorleyParsons (2015c) Timor-Leste Cement Project : Preliminary Groundwater Environmental Impact

Assessment.

Page 219: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 219 301012-02135-EMP-003 Rev 1 : 3 February 2017

22 ACRONYMS / ABBREVIATIONS

$ United States dollar

% Percentage

< Less than

µg/L Microgram per litre

µg/m3 Micrograms per cubic meter

µg/m3 Micrograms per cubic meter

ADB Asian Development Bank

AWS Automated Weather Station

BAP Biodiversity Action Plan

BAT Best Available Technologies

CEMP Construction Environmental Management Plan

CFB Circulating Fluidized Bed

CGM Complaints and Grievances Mechanism

CHMP Cultural Heritage Management Plan

CO Carbon monoxide

CPIX Consumer Price Index

dB Decibels

DBRFC Directorate of Bridges, Roads, and Flood Control

DLPCS Directorate of Land, Property and Cadastral Services

DWRQC Directorate of Water Resources and Quality Control

EA Environmental Assessment

EBL Environment Basic Law

EIS Environmental Impact Statement

ELL Environmental Licensing Law

EMF Environmental Management Framework

EMP Environmental Management Plan

Page 220: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 220 301012-02135-EMP-003 Rev 1 : 3 February 2017

EMS Environmental Management System

ERP Emergency Response Plan

EP Emergency Plan

GPS Global positioning satellite

ha Hectares

hr hour

HSE Health, Safety and Environment

IFC International Finance Corporation

IAAQS International Ambient Air Quality Standards

IPG Institute of Petroleum and Geology

km Kilometre

m/s Metres per seconds

mg/L Milligram per litre

ML Mega liters

ml Millilitres

MOF Materials Offloading Facility

MOPW Ministry of Public Works

MOU Memorandum of Understanding

Mtpa Million tonnes per annum

MW Megawatt

N/A Not Applicable

NDPCEI National Directorate for Pollution Control and Environmental Impact

NGOs Non-Government Organisations

NO2 Nitrogen dioxide

OEMP Operational Environmental Management Plan

PM10 and

PM2.5

Particulate matter

PPE Personal Protective Equipment

Page 221: Baucau Cement Project - La'o Hamutuk · 2020. 7. 9. · PROJECT 301012-02135 - BAUCAU CEMENT PROJECT REV DESCRIPTION ORIG REVIEW WORLEY- PARSONS APPROVA L DATE CLIENT APPROVAL DATE

TL CEMENT, LDA

BAUCAU CEMENT PROJECT

LIMESTONE MINE ENVIRONMENTAL MANAGEMENT PLAN

Page 221 301012-02135-EMP-003 Rev 1 : 3 February 2017

ppm Part per million

RDTL Republic Democratic of Timor-Leste

SDS Safety Data Sheet

SEP Stakeholder Engagement Plan

SO2 Sulphur dioxide

UNTAET United Nations Transitional Administration in East Timor

USD United States Dollar

WHO World Health Organisation