Batesville High SchoolBatesville Middle School
Master PlanJanuary 21, 2019
2012 Admin/Guidance.
1998 Academic Wing
1998 Music
Non-Colored Areas are Original 1967 Construction
BHS Master PlanAge of Construction
2
2013 Finishes
``
2017 SAC (not shown)
N
2013 FINISHES
2011ARTS
2011ITE
1998 Academic Wing
2011LABS
BHS Master PlanAge of Construction
Non-Colored Areas are Orig. 1967 Construction
3
2017 SAC (not shown)
N
2013 FINISHES
First Floor
BHS Master Plan
4
Must Priority Scope: Tier 1
Door Monitoring/Security New Mechanical Controls throughoutSelective HVAC Equipment Replacement
N
Must Priority Scope: Tier 1
Second Floor
BHS Master Plan
5
N
Re-Roof
Auditorium & Student CommonsRoof is 30+ yrs. of Age
Original Academic Area Roof is 30+ yrs. of Age
BHS Master Plan
6
Must Priority Scope: Tier 1
N
BHS Master Plan
Remodel 1998 Finishes and open up for flexible use and connection to Student Commons
Cafeteria
7
Must Priority Scope: Tier 1
N
BHS Master Plan
8
Must Priority Scope: Tier 1
Expand & reconfigure South Parking Area to 110 Cars, aNet increase of 44 Cars
N
BHS Master Plan
Remodel 1967 Restrooms by Cafeteria
Cafeteria
9
Must Priority Scope: Tier 2
Restrooms
N
1998 Music
CARPET TILE IN CLASSROOMS (9)
BHS Master Plan
10
Must Priority Scope: Tier 2
N
CARPET TILE IN CLASSROOMS (18)
BHS Master Plan
11
Must Priority Scope: Tier 2
N
First Floor
Locker Room
BHS Master Plan
12
Must Priority Scope: Tier 2Complete Shelled out
Locker from last Project
N
Batesville Middle School
13
First Floor
Old Gym
BMS Master Plan
14
Cafeteria
Gymnasium
Main Entry
N
Age of Construction1998 Gym
Non-Colored Areas are Original 1974 Construction
1998 Academic Wing
First Floor
BMS Master Plan
15
Must Priority Scope: Tier 1
Door Monitoring/Security New Mechanical Controls throughoutSelective HVAC Equipment Replacement
Cafeteria
Gymnasium
Main Entry
N
Media Center
Must Priority Scope: Tier 2
BMS Master PlanSite Plan
16
Re-Roof Old GymRoof is 30+ yrs. of Age
N
First Floor
New Construction
Band
Music Admin
Choir
Corridor
Old Gym
BMS Master Plan
17
Must Priority Scope: Tier 1
N
Music and Administration Expansion with Link to Old Gymnasium (Security)
Media Center
Cafeteria
Gymnasium
Main Entry
BMS Master PlanSite Plan
Locker Room
Support
Music and Admin Addition
18
New Construction
Cafeteria/Serving Expansion
Renovation/Right size Choir
First Floor
Band
Music Admin
ExpandCafeteria
Choir
Corridor
Old Gym
New Corridor
Expand Food Service
BMS Master Plan
19
High Priority Scope: Tiers 3 & 4
N
Future
Media Center
Gymnasium
Main Entry
First Floor
Carpet Tile in Classrooms (19)
C̀arpet Tile in Corridors
`
BMS Master Plan
20
Must Priority Scope: Tier 2
Cafeteria
Gymnasium
Main Entry
N
Media Center
Second Floor
Carpet Tile in Corridors
Carpet Tile in Academics (10)
BMS Master Plan
21
Must Priority Scope: Tier 2
N
First Floor
Secured Media Center
Old Gym
Media Center
New Wall/Doors
BMS Master Plan
22
Cafeteria
Gymnasium
Main Entry
N
Must Priority Scope: Tier 1
First Floor
Window Wall
Renovate to Student Commons
Remodel
Old Gym
Media Center
Open Student Collaboration
New Connecting Corridor
Comm.Room
STEMLab
BMS Master Plan
23
High Priority Scope: Tier 2
Cafeteria
Gymnasium
Main Entry
N
Future
Batesville High SchoolBatesville Middle School
Master Plan
24