BALTIMORE COUNTY PUBLIC SCHOOLS S. Dallas Dance Superintendent 6901 Charles Street Towson, MD 21204 ADDENDUM NUMBER 5 DATE: 05 January 2015 BID NAME: Westowne Elementary School BID NUMBER: MWE-809-15 DUE DATE: 13 January 2015 (Revised) DUE TIME: 2:00 PM EDT PUBLIC OPENING: 13 January 2015, 2:10 PM EDT (Revised) TOTAL PAGES: 19 The following revisions and responses to questions are made to the original bid document. This addendum forms a part of the Contract Documents and modifies the Original Bidding Documents accordingly and as noted below. The project schedule has been updated and is included as an attachment to this document. Acknowledge receipt of this Addendum in the space provided on the Bid "Addenda" form. GENERAL 1. Revision: See revised Section 00 1000 Notice to Contractors – Revised Due Date included. 2. Revision: See revised Construction Schedule included. 3. Question: The answer to question 8 in Addendum #4 states that the 2A Bidder is to assume 24” of undercut for the entire slab on grade area. The answer does not define if the material is to be hauled offsite and haul in suitable fill or if the area is to be undercut and recompacted using the same material. This is a significant cost difference so please clarify. It also states that the 2A bidder is to provide a unit rate for undercut, however, there is not a location in the bid form to do so. Please provide an updated bid form for this requirement. Answer: 2A Bidder is to assume that 24” of undercut for the entire slab on grade area. All undercut material is to be properly removed from the site and suitable material brought in and properly compacted on site. The undercut/removal/backfill is all to be included in the base bid. Any required additional undercut and subsequent backfill or in the case of acceptable site soils deletion of undercutting will be properly defined in the field and paid for as a Unit Price that was previously defined in Addenda No. 2. 4. Question: 2A Scope under Geothermal System (Note 5) says for the mechanical contractor to tie in to the header provided by this subcontractor. Please advise as the mechanical subcontractor typically provides this structure and would make more sense for them to provide/install. Answer: The geothermal contractor is responsible for the stub up through the building slab to the HDPE to Steel adapter as indicated on the Mechanical Detail Sheet M7.2, Detail #7 “Typical Geothermal Heat Pump Water Supply and Return Stub-Outs (Floor Penetrations) Detail”. The

Upload: others

Post on 30-Nov-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

BALTIMORE COUNTY PUBLIC SCHOOLS

S. Dallas Dance Superintendent 6901 Charles Street Towson, MD 21204

ADDENDUM NUMBER 5 DATE: 05 January 2015 BID NAME: Westowne Elementary School BID NUMBER: MWE-809-15 DUE DATE: 13 January 2015 (Revised) DUE TIME: 2:00 PM EDT PUBLIC OPENING: 13 January 2015, 2:10 PM EDT (Revised) TOTAL PAGES: 19 The following revisions and responses to questions are made to the original bid document. This addendum forms a part of the Contract Documents and modifies the Original Bidding Documents accordingly and as noted below. The project schedule has been updated and is included as an attachment to this document. Acknowledge receipt of this Addendum in the space provided on the Bid "Addenda" form.

GENERAL 1. Revision: See revised Section 00 1000 Notice to Contractors – Revised Due Date

included. 2. Revision: See revised Construction Schedule included. 3. Question: The answer to question 8 in Addendum #4 states that the 2A Bidder is to

assume 24” of undercut for the entire slab on grade area. The answer does not define if the material is to be hauled offsite and haul in suitable fill or if the area is to be undercut and recompacted using the same material. This is a significant cost difference so please clarify. It also states that the 2A bidder is to provide a unit rate for undercut, however, there is not a location in the bid form to do so. Please provide an updated bid form for this requirement.

Answer: 2A Bidder is to assume that 24” of undercut for the entire slab on grade area. All undercut material is to be properly removed from the site and suitable material brought in and properly compacted on site. The undercut/removal/backfill is all to be included in the base bid. Any required additional undercut and subsequent backfill or in the case of acceptable site soils deletion of undercutting will be properly defined in the field and paid for as a Unit Price that was previously defined in Addenda No. 2.

4. Question: 2A Scope under Geothermal System (Note 5) says for the mechanical

contractor to tie in to the header provided by this subcontractor. Please advise as the mechanical subcontractor typically provides this structure and would make more sense for them to provide/install.

Answer: The geothermal contractor is responsible for the stub up through the building slab to the HDPE to Steel adapter as indicated on the Mechanical Detail Sheet M7.2, Detail #7 “Typical Geothermal Heat Pump Water Supply and Return Stub-Outs (Floor Penetrations) Detail”. The

Page 2: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

mechanical contractor shall pick up and continue the geothermal piping at the steel adapter.

5. Question: 2A Scope under Geothermal System (Note 6.) says this contractor shall remobilize to install the glycol. Again, wouldn't it make more sense for the 15A contractor to install this as to keep remobilization costs, etc. down. (the total volume of piping for the exterior geothermal system is 16,400 gallons)

Answer: The geothermal system for this project does not require any glycol. Freeze protection for the geothermal water piping is achieved by the boilers and a plate heat exchanger when required.

6. Question: The revised schedule via addendum shows (40) working days for the

geothermal system to be installed. Please note this is a very tight schedule and may not be completed within this duration. While the scope states (2) rigs are mandatory, at (1) hole/day per rig x 5days/week = 10wells/week divided by 144/bores = 14 total weeks. Please extended the duration to accommodate a longer duration.

Answer: Schedule for geothermal wells MUST be adhered to.

7. Question: 2A Scope under Geothermal System (Note 3) says to furnish and install a quantity of 180 wells at 450 vertical linear feet deep, while the Mechanical Site Plan (MS0.1) shows (144) wells at a revised depth of 475/LF. Please confirm the quantity is (144) wells and not (180).

Answer: The exact amount and linear footage of well is shown on the Contract Drawings.

8. Question: Please confirm that casing may be pulled from the borehole and not abandoned in place. This is a lot of money to leave in the ground when it is not needed.

Answer: Were deemed acceptable, casing can be pulled as long as the installed geothermal piping is not damaged. Refer to note 13 within detail 5 on Drawing M7.2 as well as the revised Form Of Proposal Bid Sheet included.

9. Question: Please provide a detail for the bollards.

Answer: See sketch SKC-06 included and refer to detail 15 on drawing E6.1 for bollards associated with the transformer.

10. Question: In reference to the fences and gates scope, please provide an updated plan showing the fence for the generator and trash area as stated in item # 1 with details.

Answer: See sketch SKC-07 for clarification to fencing associated with the generator. No fencing will be provided for trash area.

11. Question: Please provide drawing P6.4 as noted in Fence and gates scope item 3. Answer: See Sketch SKP-01 for fencing details associated with the building gas

meter assembly.

12. Question: Please provide a location and detail for the fire access road gate noted in item 5 of the fence and gates scope.

Page 3: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

Answer: Delete item 5 within scope of work Unit 2A – Sitework, Fences and Gates.

13. Question: How would you like us to determine the total bid? It is difficult to determine the total number of containers that will be needed on a construction project since it will be contingent how the containers are loaded and how much is diverted. I can guestimate a total based on a predetermined number of containers needed, but that may fluctuate depending on what the crew on site needs. Also, you require a bid bond that is a percentage of the total. Since its difficult to determine total amount would you accept a bid bond for $10,000 or $20,000 instead of a percentage?

Answer: The total amount of containers is indicated on the revised Construction and Demolition Waste Proposal Rate Form included.

14. Question: You would like us to submit a flat rate. How many tons do you want us to

include in the flat rate for general C&D? Answer: Please see the revised C&D Waste Proposal Rate Form included.

15. Question: There will be rebates for all metal loads taken from your site. Do you want us to include details about the recycling? If so, do you want us to add the details about container in the blank space under Rates/Extension?

Answer: Any rebate would be for the contractor to take in consideration when they prepare their bid. No details would be required.

DRAWINGS

16. Drawing C-5 • ADD: Pipe Bollard Detail # 4 included with sketch SKC-06.

17. Drawing C-7 • ADD: 10’ High Chain Link Fence around Generator area as indicated with

sketch SKC-07 List of Attachments:

18. Section 00 1000 Notice to Contractors – Revised Due Date included (1 page) 19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21. Revised Construction and Demolition Waste Proposal Rate Form (1 page) 22. Civil Sketches SKC-06 & SKC-07 dated 1/05/15 (2 pages) 23. Plumbing Sketch SKP-01 dated 12/10/14 (1 page)

Melanie L. Webster, Purchasing Agent BCPS - Office of Purchasing cc: Bid file Melanie Webster Gannett Fleming GWWO

Creating a Culture of Deliberate Excellence

Page 4: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

BALTIMORE COUNTY PUBLIC SCHOOLS S. Dallas Dance, Ph.D. Superintendent 6901 Charles Street Towson, Maryland 21204-3711

SECTION 00 1000 – NOTICE TO CONTRACTORS – REVISED DUE DATE The Board of Education of Baltimore County invites Trade Contractors to bid on the REPLACEMENT OF WESTOWNE ELEMENTARY SCHOOL, Solicitation Number MWE-809-15. Commodity Codes: 912-44; 907-83; 909-76. Procurement questions can be emailed to Melanie Webster at [email protected] , or they may be faxed to 410-887-7831. Verbal questions will not be taken. Contractors proposing to bid may obtain solicitation documents beginning at 2:00 pm on Thursday, November 20, 2014. Visit website: http://www.bcps.org/offices/purchasing/ and click onto "Bid Board", then click onto "Invitation to Bid”. Solicitation documents can be ordered electronically or picked-up in person from Gardens Reprographics (419 Saint Paul Place, Baltimore, MD 21202. Hours: Monday through Friday 8 – 5. Phone: 410-539-2763). A pre-bid meeting is scheduled for December 2, 2014 at 12:30 P.M. at BCPS Office of Purchasing, Conference Room # 123, 6901 N. Charles Street, Building E, Towson, Maryland 21204. Sealed bids will be received until 2:00 P.M., January 13, 2015 in the Office of Purchasing at Baltimore County Public Schools, located at 6901 Charles Street, Building "E", 1st Floor, Towson, Maryland 21204. A public bid opening will be held in conference room #114 approximately 10 minutes after the due date and time for this solicitation. All bidders for the 2A package shall be pre-qualified by Baltimore County Department of Public Works (BCDPW), Contracts Division. 2A bidders shall hold Category “B” Grading prior to the date of bid opening. Certified Minority Business Enterprises are encouraged to respond to this solicitation notice. The contractor or supplier who provides materials, supplies, equipment and/or services for this construction project shall attempt to achieve the specific overall MBE goal established for their portion of the project. All prime contractors, including certified MBE firms, when submitting bids or proposals as general or prime contractors, are required to attempt to achieve this goal from certified MBE firms. The subgoals established for this project are listed below. The bidder or offeror is required to submit with its bid or proposal a completed Attachment A - Certified MBE Utilization and Fair Solicitation Affidavit and Attachment B - MBE Participation Schedule, as described in the solicitation documents.

Division

Overall Certified MBE Subcontract Participation

Subgoal African American - Owned Businesses

Subgoal Asian American - Owned Businesses

1A Waste Management 0% 0% 0%

1B Testing & Inspection 5% 0% 0%

2A Site Prep 27% 7% 0%

The Board of Education of Baltimore County reserves the right to reject any or all proposals and to waive informalities.

By Order of the Board of Education of Baltimore County Richard Gay, Manager, Office of Purchasing

END OF SECTION

Creating a Culture of Deliberate Excellence

Page 5: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

WESTOWNE ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load $ $Initial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

TOTAL BID

(COMPANY NAME)

(SIGNATURE)

(DATE)

CONSTRUCTION AND DEMOLITION WASTE PROPOSAL RATE FORM

Concrete, Recycled - Clean no re-bar, asphalt, dirt or oversized slabs of three feet or higher.

200 20 Yd. Containers

30 20 Yd. Containers

Metal, Recylced-Delivered to local metal recycling facility. Rebate retained by the hauler.

35 30 Yd. Containers

General Construction & Demolition (C&D), Processed Material - Waste Containers

175 30 Yd. Containers

Asphaltic Concrete, Recycled - Mixed may contain re-bar, asphalt, dirt and brick.

$__________________

Page 6: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

1 PRECONSTRUCTION 70 days 11/20/14 2/26/15

2 ADVERTISE 8 days 11/20/14 12/1/14

4 PRE-BID MEETING 1 day 12/2/14 12/2/14

5 BIDS DUE 29 days 12/3/14 1/13/15

6 BIDS TO BOARD OF EDUCATION 25 days 1/14/15 2/17/15

7 NOTICE TO PROCEED 5 days 2/18/15 2/24/15

8 GRADING PERMIT 40 days 11/20/14 1/15/15

9 BUILDING PERMIT 40 days 11/20/14 1/15/15

3 SPRINKLER PERMIT 30 days 1/16/15 2/26/15

10 CRITICAL SUBMITTALS 30 days 2/25/15 4/4/15

11 STORM DRAINAGE, WATER & SEWER UTILITES 10 days 2/25/15 3/10/15

12 CONCRETE FOUNDATION MIX DESIGN 10 days 2/25/15 3/10/15

13 REBAR 15 days 2/25/15 3/17/15

14 CMU, MORTAR & ACCESSORIES 15 days 2/25/15 3/17/15

15 STRUCTURAL STEEL 20 days 2/25/15 3/24/15

16 HM DOORS & FRAMES 20 days 2/25/15 3/24/15

17 CONCRETE PLANK 30 days 2/25/15 4/4/15

18 ELEVATOR 20 days 2/25/15 3/24/15

19 WINDOWS 30 days 2/25/15 4/4/15

20 SUBMITTAL REVIEW 35 days 3/11/15 4/22/15

21 STORM DRAINAGE, WATER & SEWER UTILITES 10 days 3/11/15 3/24/15

22 CONCRETE FOUNDATION MIX DESIGN 15 days 3/11/15 3/30/15

23 REBAR 15 days 3/18/15 4/4/15

24 CMU, MORTAR & ACCESSORIES 15 days 3/18/15 4/4/15

25 STRUCTURAL STEEL 15 days 3/25/15 4/10/15

26 HM DOORS & FRAMES 15 days 3/25/15 4/10/15

27 CONCRETE PLANK 15 days 4/6/15 4/22/15

28 ELEVATOR 15 days 3/25/15 4/10/15

29 WINDOWS 15 days 4/6/15 4/22/15

30 FABRICATION / MANUFACTURING LEAD TIME 105 days 3/25/15 7/27/15

31 STORM DRAINAGE, WATER & SEWER UTILITES 15 days 3/25/15 4/10/15

32 REBAR 10 days 4/6/15 4/16/15

33 CMU, MORTAR & ACCESSORIES 10 days 4/6/15 4/16/15

34 STRUCTURAL STEEL 30 days 4/11/15 5/15/15

35 HM DOORS & FRAMES 20 days 4/11/15 5/4/15

36 CONCRETE PLANK 30 days 4/23/15 5/28/15

37 ELEVATOR 30 days 4/11/15 5/15/15

38 WINDOWS 80 days 4/23/15 7/27/15

39 PHASE 1 SITEWORK 330 days 2/25/15 3/26/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

1

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 7: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

40 MOBILIZATION 15 days 2/25/15 3/17/15

41 BALTIMORE COUNTY SEDIMENT CONTROL MEETING

1 day 3/18/15 3/18/15

42 RELOCATE CLASSROOM TRAILERS 6 days 4/3/15 4/9/15

43 TEMPORARY PARKING LOT 2 days 3/19/15 3/20/15

44 LOCATE / MARK EXISTING UTILITIES 2 days 3/18/15 3/19/15

45 TEMPORARY FENCE AT LOD 3 days 3/23/15 3/25/15

46 CONSTRUCTION ENTRANCE 3 days 3/23/15 3/25/15

47 SEDIMENT CONTROLS 6 days 3/26/15 4/1/15

48 SITE DEMOLITION 6 days 4/2/15 4/8/15

49 SEDIMENT TRAP #1 2 days 4/9/15 4/10/15

50 TEMPORARY STORM DRAIN FROM EXISTING 1-2 TO EXISTING 1-3

2 days 4/11/15 4/13/15

51 REMOVE STORM DRAIN BETWEEN EXISTING 1-3 & EXISTING 1-4

2 days 4/14/15 4/15/15

52 SITE GRADING 15 days 4/16/15 5/2/15

53 RETAINING WALL 15 days 4/28/15 5/14/15

54 WATER UTILITIES 14 days 5/14/15 5/30/15

55 STORM DRAIN UTILITIES 7 days 5/29/15 6/5/15

56 SEWER UTILITIES 7 days 5/1/15 5/8/15

57 GREASE INTERECPTOR 2 days 5/6/15 5/7/15

58 BIORETENTION SYSTEM 10 days 6/6/15 6/17/15

59 GEOTHERMAL SYSTEM 40 days 6/25/15 8/11/15

60 SITE ELECTRIC 10 days 6/3/15 6/13/15

61 INSTALL 2ND SCE WITH GATE & TEMPORARY ROAD 5 days 4/2/15 4/7/15

62 BASE PAVING 5 days 8/12/15 8/17/15

63 CURB & GUTTER (sawcut asphalt, box out, pour & backfill) 10 days 1/18/16 1/28/16

64 SIDEWALKS 20 days 1/29/16 2/20/16

65 TOPSOIL 10 days 2/22/16 3/3/16

66 LANDSCAPING 10 days 3/4/16 3/15/16

67 SEEDING 5 days 3/16/16 3/21/16

68 ATHLETIC EQUIPMENT 5 days 2/22/16 2/26/16

69 WOOD BENCHES 5 days 2/22/16 2/26/16

70 SITE RAILINGS 5 days 2/22/16 2/26/16

71 SITE SIGNAGE 5 days 2/22/16 2/26/16

72 TEMPORARY STRIPING 2 days 3/16/16 3/17/16

73 REMOVE SEDIMENT CONTROLS 5 days 3/22/16 3/26/16

74

75 UTILITY CONNECTIONS 121 days 3/18/15 8/8/15

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

2

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 8: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

76 TEMPORARY POWER 20 days 3/18/15 4/10/15

77 CONNECTION TO EXISTING SEWER MAIN 1 day 5/9/15 5/9/15

78 WATER METER 1 day 6/1/15 6/1/15

79 PERMANENT POWER 1 day 8/8/15 8/8/15

107

108 BUILDING SHELL - WEST 226 days 6/9/15 3/3/16

109 FOOTINGS 10 days 6/9/15 6/19/15

110 FOUNDATION WALLS 10 days 6/20/15 7/1/15

111 SLAB ON GRADE PREP 12 days 8/11/15 8/24/15

112 SLAB ON GRADE POUR 2 days 8/25/15 8/26/15

113 HM DOOR FRAMES 5 days 8/27/15 9/1/15

114 BEARING WALLS 35 days 9/2/15 10/13/15

115 STEEL ERECTION 5 days 10/14/15 10/19/15

116 JOIST / DECK ERECTION / DETAILING 7 days 10/20/15 10/27/15

117 BRICK VENEER 30 days 10/14/15 11/17/15

118 NON-BEARING WALLS 21 days 10/14/15 11/6/15

119 ROOF BLOCKNG 5 days 10/28/15 11/2/15

120 BUILT UP ROOF 10 days 11/3/15 11/13/15

121 METAL ROOF 10 days 11/3/15 11/13/15

122 VEGETATED ROOF 5 days 11/3/15 11/7/15

123 ROOF DECK 5 days 11/14/15 11/19/15

124 STOREFRONT 10 days 11/18/15 11/30/15

125 WINDOWS 3 days 12/3/15 12/5/15

126 METAL CANOPY 10 days 2/22/16 3/3/16

80

81 BUILDING SHELL - EAST 1ST FLOOR 164 days 6/20/15 1/2/16

82 FOOTINGS 15 days 6/20/15 7/8/15

83 FOUNDATION WALLS 10 days 7/9/15 7/20/15

84 SLAB ON GRADE PREP 12 days 8/19/15 9/1/15

85 SLAB ON GRADE POUR 2 days 9/2/15 9/3/15

86 STEEL ERECTION 5 days 9/4/15 9/10/15

87 HM DOOR FRAMES 5 days 9/4/15 9/10/15

88 BEARING WALLS 35 days 9/11/15 10/21/15

89 PRE-CAST PLANK 5 days 10/22/15 10/27/15

90 NON-BEARING WALLS 21 days 10/28/15 11/20/15

91 BRICK VENEER 30 days 10/22/15 11/25/15

92 STOREFRONT 30 days 11/27/15 1/2/16

93 WINDOWS 5 days 11/27/15 12/2/15

94

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

3

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 9: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

95 BUILDING SHELL - EAST 2ND FLOOR 93 days 10/22/15 2/10/16

96 BEARING WALLS 35 days 10/22/15 12/2/15

97 JOIST / DECK ERECTION / DETAILING 7 days 12/3/15 12/10/15

102 CLERESTORY FRAMING 10 days 12/3/15 12/14/15

103 ROOF BLOCKING 5 days 12/3/15 12/8/15

104 BUILT UP ROOF 15 days 12/9/15 12/26/15

98 BRICK VENEER 30 days 12/11/15 1/16/16

99 TOPPING SLAB 5 days 12/11/15 12/16/15

100 HM DOOR FRAMES 5 days 12/17/15 12/22/15

105 METAL ROOF 5 days 12/28/15 1/2/16

101 NON-BEARING WALLS 21 days 1/18/16 2/10/16

106 WINDOWS 6 days 1/18/16 1/23/16

127

128 ELEVATORS 119 days 7/2/15 11/19/15

130 ELEVATOR CMU INBEDS DELIVERY 1 day 7/2/15 7/2/15

131 ELEVATOR CAR & HOIST 15 days 7/4/15 7/21/15

129 WHEELCHAIR LIFT 5 days 11/14/15 11/19/15

132

133 METAL STAIRS 32 days 11/7/15 12/15/15

135 METAL STAIRS E - WEST 5 days 11/7/15 11/12/15

134 METAL STAIRS A, B, C & D EAST 20 days 11/21/15 12/15/15

136

137 ROOFTOP EQUIPMENT 6 days 12/28/15 1/4/16

138 SET ROOF CURBS 3 days 12/28/15 12/30/15

139 SET ROOFTOP EQUIPMENT 3 days 12/31/15 1/4/16

216

217 MECHANICAL / ELECTRICAL / PLUMBING WEST 254 days 7/2/15 4/28/16

223

224 PLUMBING 254 days 7/2/15 4/28/16

225 UNDERGROUND PLUMBING ROUGH IN 18 days 7/2/15 7/23/15

226 STORM PIPING & RISERS 45 days 11/18/15 1/12/16

227 PLUMBING ROUGH IN 45 days 12/21/15 2/12/16

228 PIPE TESTING 5 days 2/13/16 2/18/16

229 PIPE INSULATION 15 days 2/19/16 3/7/16

230 PLUMBING FIXTURES 15 days 4/12/16 4/28/16

231

232 MECHANICAL 244 days 7/2/15 4/16/16

233 UNDERGROUND HYDRONIC PIPING 15 days 7/2/15 7/20/15

237 MECHANICAL EQUIPMENT SET 15 days 11/14/15 12/2/15

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

4

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 10: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

235 HVAC DUCT 30 days 12/3/15 1/8/16

234 ATC ROUGH IN 45 days 12/21/15 2/12/16

236 HYDRONIC PIPING 45 days 12/21/15 2/12/16

238 DUCT TESTING 10 days 1/9/16 1/20/16

239 DUCT INSULATION 30 days 1/21/16 2/24/16

241 EQUIPMENT START UP 15 days 2/13/16 3/1/16

242 BALANCING 20 days 3/2/16 3/24/16

240 HVAC TRIM 15 days 3/19/16 4/5/16

243 COMMISSIONING 20 days 3/25/16 4/16/16

218 SPRINKLER 125 days 10/28/15 3/24/16

219 SPRINKLER ROUGH IN 15 days 10/28/15 11/13/15

220 SPRINKLER DROPS 10 days 11/14/15 11/25/15

221 SPRINKLER HYDRO 5 days 11/27/15 12/2/15

222 SPRINKLER TRIM 5 days 3/19/16 3/24/16

244

245 ELECTRICAL 221 days 7/24/15 4/11/16

246 UNDERGROUND ELECTRIC 15 days 7/24/15 8/10/15

247 POWER POUGH IN 45 days 10/28/15 12/19/15

248 SET ELECTRIC PANEL BOXES 10 days 10/28/15 11/7/15

249 INSTALL IT EQUIPMENT 15 days 11/14/15 12/2/15

250 LIGHTING ROUGH IN 45 days 10/28/15 12/19/15

251 FIRE ALARM ROUGH IN 45 days 10/28/15 12/19/15

252 DATA, VOICE VIDEO & SECURITY SYSTEM ROUGHIN

45 days 11/14/15 1/8/16

253 EMERGIZE HVAC EQUIPMENT 15 days 12/21/15 1/8/16

254 LIGHT FIXTURES 20 days 3/19/16 4/11/16

140

141 MECHANICAL / ELECTRICAL / PLUMBING - EAST 1ST

FLOOR268 days 7/15/15 5/26/16

148

149 PLUMBING 238 days 7/15/15 4/21/16

150 UNDERGROUND PLUMBING PIPING 15 days 7/15/15 7/31/15

151 STORM PIPING & RISERS 18 days 10/28/15 11/17/15

152 PLUMBING ROUGH IN 45 days 10/28/15 12/19/15

153 PIPE TESTING 5 days 12/21/15 12/26/15

154 PIPE INSULATION 20 days 12/28/15 1/20/16

155 PLUMBING FIXTURES 15 days 4/5/16 4/21/16

156

157 MECHANICAL 268 days 7/15/15 5/26/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

5

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 11: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

158 UNDERGROUND HYDRONIC PIPING 15 days 7/15/15 7/31/15

159 ATC ROUGH IN 45 days 10/28/15 12/19/15

160 HVAC DUCT 30 days 10/28/15 12/2/15

161 HYDRONIC PIPING 45 days 10/28/15 12/19/15

162 MECHANICAL EQUIPMENT SET 15 days 12/28/15 1/14/16

163 DUCT TESTING 10 days 12/3/15 12/14/15

164 DUCT INSULATION 30 days 12/15/15 1/20/16

165 HVAC TRIM 15 days 3/24/16 4/9/16

166 EQUIPMENT START UP 15 days 1/15/16 2/1/16

167 BALANCING 20 days 4/11/16 5/3/16

168 COMMISSIONING 20 days 5/4/16 5/26/16

142

143 SPRINKLER 35 days 11/21/15 1/4/16

144 SPRINKLER ROUGH IN 15 days 11/21/15 12/9/15

145 SPRINKLER DROPS 10 days 12/10/15 12/21/15

146 SPRINKLER HYDRO 5 days 12/22/15 12/28/15

147 SPRINKLER TRIM 5 days 12/29/15 1/4/16

169

170 ELECTRICAL 218 days 8/1/15 4/15/16

171 UNDERGROUND ELECTRIC 15 days 8/1/15 8/18/15

172 POWER ROUGH IN 45 days 10/28/15 12/19/15

173 SET ELECTRIC PANEL BOXES 10 days 10/28/15 11/7/15

174 INSTALL IT EQUIPMENT 15 days 1/4/16 1/20/16

175 LIGHTING ROUGH IN 45 days 10/28/15 12/19/15

176 FIRE ALARM ROUGH IN 45 days 10/28/15 12/19/15

177 DATA, VOICE, VIDEO & SECURITY SYSTEMS ROUGH IN

45 days 1/4/16 2/24/16

178 ENERGIZE HVAC EQUIPMENT 15 days 12/21/15 1/8/16

179 LIGHT FIXTURES 20 days 3/24/16 4/15/16

180

181 MECHANICAL / ELECTRICAL / PLUMBING EAST 2ND

FLOOR140 days 12/3/15 5/16/16

187

188 PLUMBING 133 days 12/11/15 5/16/16

189 STORM PIPING & RISERS 18 days 12/11/15 1/2/16

190 PLUMBING ROUGH IN 45 days 12/21/15 2/12/16

191 PIPE TESTING 5 days 2/13/16 2/18/16

192 PIPE INSULATION 20 days 2/19/16 3/12/16

193 PLUMBING FIXTURES 15 days 4/29/16 5/16/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

6

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 12: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

194

195 MECHANICAL 140 days 12/3/15 5/16/16

197 HVAC DUCT 30 days 12/3/15 1/8/16

196 ATC ROUGH IN 45 days 12/9/15 2/1/16

198 HYDRONIC PIPING 45 days 12/15/15 2/6/16

200 DUCT TESTING 10 days 1/9/16 1/20/16

199 MECHANICAL EQUIPMENT SET 15 days 1/15/16 2/1/16

201 DUCT INSULATION 30 days 2/8/16 3/12/16

204 BALANCING 20 days 3/14/16 4/5/16

202 HVAC TRIM 15 days 3/31/16 4/16/16

203 EQUIPMENT START UP 15 days 4/6/16 4/22/16

205 COMMISSIONING 20 days 4/23/16 5/16/16

182 SPRINKLER 99 days 12/10/15 4/5/16

183 SPRINKLER ROUGH IN 15 days 12/10/15 12/28/15

184 SPRINKLER DROPS 10 days 12/29/15 1/9/16

185 SPRINKLER HYDRO 5 days 1/11/16 1/15/16

186 SPRINKLER TRIM 5 days 3/31/16 4/5/16

206

207 ELECTRICAL 113 days 12/11/15 4/22/16

208 POWER ROUGH IN 45 days 12/11/15 2/3/16

209 SET ELECTRIC PANEL BOXES 10 days 12/11/15 12/22/15

210 INSTALL IT EQUIPMENT 15 days 1/4/16 1/20/16

211 LIGHTING ROUGH IN 45 days 12/11/15 2/3/16

212 FIRE ALARM ROUGH IN 45 days 12/11/15 2/3/16

213 DATA, VOICE, VIDEO & SECURITY SYSTEM ROUGH IN

45 days 1/4/16 2/24/16

214 ENERGIZE HVAC EQUIPMENT 15 days 2/4/16 2/20/16

215 LIGHT FIXTURES 20 days 3/31/16 4/22/16

305

306 FINISHES - WEST 181 days 11/13/15 6/15/16

311 PAINT STAIRS 5 days 11/13/15 11/18/15

307 PRIME COAT / BLOCK FILL 15 days 12/7/15 12/23/15

310 PAINTED EXPOSED STRUCTURE 15 days 12/7/15 12/23/15

326 DOORS & HARDWARE 20 days 12/24/15 1/18/16

312 CEILING & BULKHEAD FRAMING 10 days 3/2/16 3/12/16

308 CEILING GRID 10 days 3/8/16 3/18/16

313 DRYWALL 10 days 3/8/16 3/18/16

314 CAFETERIA & GYM COMMONS CEILING 10 days 3/14/16 3/24/16

309 CEILING TILE 10 days 3/19/16 3/30/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

7

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 13: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

315 PAINT FINISH COAT CLASSROOMS 10 days 3/19/16 3/30/16

316 VCT 15 days 3/31/16 4/16/16

317 EPOXY FLOOR 10 days 3/31/16 4/11/16

318 WOOD FLOOR (STAGE) 5 days 3/31/16 4/5/16

319 CERAMIC TILE 10 days 3/31/16 4/11/16

320 PAINT FINISH COAT CORRIDORS 10 days 3/31/16 4/11/16

321 CASEWORK 5 days 3/31/16 4/5/16

322 KITCHEN EQUIPMENT 15 days 3/31/16 4/16/16

323 VISUAL DISPLAY BOARDS 10 days 3/31/16 4/11/16

327 WINDOW TREATMENTS 10 days 3/31/16 4/11/16

329 ACOUSTICAL PANELS (CAFETERIA, MAIN STAIRS & GYM)

10 days 3/31/16 4/11/16

330 STAGE CURTAINS 5 days 3/31/16 4/5/16

331 OPERABLE PARTITIONS 5 days 3/31/16 4/5/16

332 GYM EQUIPMENT 5 days 3/31/16 4/5/16

324 TOILET PARTITIONS 5 days 4/12/16 4/16/16

325 LOCKERS 2 days 4/12/16 4/13/16

328 SIGNAGE 5 days 4/12/16 4/16/16

333 FINAL CLEANING 20 days 4/29/16 5/21/16

334 PUNCHLIST 20 days 5/23/16 6/15/16

255

256 FINISHES - EAST 1ST FLOOR 161 days 12/18/15 6/25/16

278 PAINT STAIRS 15 days 12/18/15 1/6/16

258 PAINT EXPOSED STRUCTURE 10 days 1/25/16 2/4/16

260 DRYWALL 10 days 1/25/16 2/4/16

259 CEILING & BULKHEAD FRAMING 15 days 2/25/16 3/12/16

280 PRIME COAT / BLOCK FILL 15 days 2/24/16 3/11/16

261 KINDERGARDEN COMMONS CEILING 10 days 3/14/16 3/24/16

262 FIRST GRADE COMMONS CEILING 10 days 3/14/16 3/24/16

263 SECOND GRADE COMMONS CEILING 10 days 3/14/16 3/24/16

279 CEILING GRID 15 days 3/7/16 3/23/16

264 PAINT FINISH COAT CLASSROOMS 10 days 3/12/16 3/23/16

273 DOORS & HARDWARE 10 days 3/12/16 3/23/16

257 CELING TILE 15 days 3/24/16 4/9/16

265 VCT 20 days 3/24/16 4/15/16

266 EPOXY FLOOR 10 days 3/24/16 4/4/16

267 CERAMIC TILE 10 days 3/24/16 4/4/16

268 CASEWORK 15 days 3/24/16 4/9/16

269 PAINT FINISH COAT CORRIDORS 10 days 3/24/16 4/4/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

8

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 14: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

270 VISUAL DISPLAY BOARDS 10 days 3/24/16 4/4/16

274 WINDOW TREATMENTS 10 days 3/24/16 4/4/16

271 TOILET PARTITIONS 5 days 4/5/16 4/9/16

275 SIGNAGE 5 days 4/5/16 4/9/16

272 LOCKERS 10 days 4/16/16 4/27/16

276 FINAL CLEANING 20 days 5/21/16 6/14/16

277 PUNCHLIST 20 days 6/3/16 6/25/16

281

282 FINISHES- EAST 2ND FLOOR 130 days 1/25/16 6/24/16

283 PRIME COAT / BLOCK FILL 15 days 1/25/16 2/10/16

300 DOORS & HARDWARE 10 days 2/11/16 2/22/16

284 CEILING GRID 15 days 3/14/16 3/30/16

286 CEILING & BULKHEAD FRAMING 15 days 3/14/16 3/30/16

285 CEILING TILE 15 days 3/31/16 4/16/16

287 DRYWALL 10 days 3/31/16 4/11/16

288 THIRD GRADE COMMONS CEILING 10 days 3/31/16 4/11/16

289 FOURTH GRADE COMMONS CEILING 10 days 3/31/16 4/11/16

290 FIFTH GRADE COMMONS CEILING 10 days 4/12/16 4/22/16

291 PAINT FINISH COAT CLASSROOMS 10 days 4/12/16 4/22/16

292 VCT 20 days 4/23/16 5/16/16

293 EPOXY FLOOR 5 days 4/23/16 4/28/16

294 CERAMIC TILE 5 days 4/23/16 4/28/16

295 CASEWORK 15 days 4/23/16 5/10/16

296 PAINT FINISH COAT CORRIDORS 10 days 4/23/16 5/4/16

297 VISUAL DISPLAY BOARDS 10 days 4/23/16 5/4/16

301 WINDOW TREATMENTS 10 days 4/23/16 5/4/16

298 TOILET PARTITIONS 5 days 4/29/16 5/4/16

299 LOCKERS 15 days 5/5/16 5/21/16

302 SIGNAGE 5 days 5/5/16 5/10/16

303 FINAL CLEANING 20 days 5/14/16 6/7/16

304 PUNCHLIST 20 days 6/2/16 6/24/16

335

336 INSPECTIONS 69 days 4/6/16 6/25/16

343 SPRINKLER FINAL 1 day 4/6/16 4/6/16

338 HEALTH DEPARTMENT FINAL 1 day 4/18/16 4/18/16

341 FIRE ALARM FINAL 1 day 4/23/16 4/23/16

344 ELEVATOR 3RD PARTY INSPECTION 30 days 4/25/16 5/28/16

340 ELECTRICAL FINAL 1 day 4/23/16 4/23/16

339 PLUMBING FINAL 1 day 5/17/16 5/17/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

9

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 15: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

ID Task

Mode

Task Name Duration Start Finish

337 ELEVATOR STATE INSPECTION 1 day 5/31/16 5/31/16

342 USE & OCCUPANCY / SUBSTANTIAL COMPLETION 1 day 6/25/16 6/25/16

345

346 PHASE 2 SITEWORK 33 days 6/27/16 8/4/16

347 BALTIMORE COUNTY SEDIMENT CONTROL MEETING

1 day 6/27/16 6/27/16

348 LOCATE / MARK EXISTING UTILITIES 2 days 6/28/16 6/29/16

349 TEMPORARY FENCE AT LOD 3 days 6/30/16 7/2/16

350 CUT, CAP & MAKE SAFE UTILITES 3 days 7/5/16 7/7/16

351 SEDIMENT CONTROLS 7 days 7/8/16 7/15/16

352 HAZMAT ABATEMENT 15 days 6/30/16 7/18/16

353 BUILDING DEMOLITION 15 days 7/19/16 8/4/16

354

355 PHASE 3 SITEWORK 103 days 8/5/16 12/5/16

356 BALTIMORE COUNTY SEDIMENT CONTROL MEETING

1 day 8/5/16 8/5/16

357 LOCATE / MARK EXISTING UTILITIES 2 days 8/6/16 8/8/16

358 TEMPORARY FENCE AT LOD 5 days 8/9/16 8/13/16

359 CUT, CAP & MAKE SAFE UTILITES 3 days 8/15/16 8/17/16

360 SEDIMENT CONTROLS 5 days 8/18/16 8/23/16

361 SITE GRADING 7 days 8/24/16 8/31/16

362 BALL FIELD 15 days 11/11/16 11/29/16

363 REMOVE PHASE 1 TEMPORARY PARKING 1 day 8/6/16 8/6/16

364 STORM DRAIN UTILITIES 10 days 9/1/16 9/13/16

365 BIORETENTION SYSTEMS 15 days 9/14/16 9/30/16

366 SITE ELECTRIC 15 days 9/14/16 9/30/16

367 CURB & GUTTER NEAR HARLEM LANE 5 days 10/1/16 10/6/16

368 PHASE 3 CURB & GUTTER 10 days 10/1/16 10/12/16

369 BASE PAVING 10 days 10/13/16 10/24/16

370 SIDEWALKS 15 days 10/25/16 11/10/16

371 TOPSOIL 5 days 11/11/16 11/16/16

372 LANDSCAPING 5 days 11/17/16 11/22/16

373 SEEDING 5 days 11/23/16 11/29/16

374 SITE SIGNAGE 5 days 11/11/16 11/16/16

375 TOP COAT PAVING PHASE 1 & PHASE 3 5 days 11/17/16 11/22/16

376 STRIPING 2 days 11/23/16 11/24/16

377 REMOVE SEDIMENT CONTROLS 5 days 11/30/16 12/5/16

O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

Half 2, 2014 Half 1, 2015 Half 2, 2015 Half 1, 2016 Half 2, 2016 Half 1, 2017

Task

Milestone

Summary

Project Summary

Manual Summary Rollup

Critical

Critical Split

Progress

WESTOWNE ELEMENTARY SCHOOL

10

Project: Westowne Elementary School

Six day work week

Date: 1/5/15

Page 16: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

WESTOWNE ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load $ $Initial delivery of the container to the site $ $

Fuel Surcharge $ $

Qty. Rates ExtensionHaul rate per load $ $

Additional disposal/processing per ton over 5 tons per load N/A N/AInitial delivery of the container to the site $ $

Fuel Surcharge $ $

TOTAL BID

(COMPANY NAME)

(SIGNATURE)

(DATE)

CONSTRUCTION AND DEMOLITION WASTE PROPOSAL RATE FORM

Concrete, Recycled - Clean no re-bar, asphalt, dirt or oversized slabs of three feet or higher.

200 20 Yd. Containers

30 20 Yd. Containers

Metal, Recylced-Delivered to local metal recycling facility. Rebate retained by the hauler.

35 30 Yd. Containers

General Construction & Demolition (C&D), Processed Material - Waste Containers

175 30 Yd. Containers

Asphaltic Concrete, Recycled - Mixed may contain re-bar, asphalt, dirt and brick.

$__________________

Page 17: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

4 01/05/15 5

Page 18: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

24’

4 01/05/15 5

Page 19: BALTIMORE COUNTY PUBLIC SCHOOLSbids.urbanzink.com/westownees/Addendum 5.pdf19. Revised Form Of Proposal (1 page) 20. Revised Construction Schedule dated 1/5/15 (10) 11x17 pages) 21

SKP - 01

1402

WESTOWNE ELEMENTARY SCHOOL

INCOMING GAS SERVICE DETAIL

REV # DATE

DRAWING:

PROJECT: SCALE:

JOB NO.

SKETCH NO.

GWWO INC.

800 WYMAN PARK DRIVE, SUITE 300

BALTIMORE, MARYLAND 21211, 410-332-1009

C 2013 GWWO INC.

ADDENDUM NO.

05

004 12-10-2014